Download as PDF Federal Register / Vol. 73, No. 166 / Tuesday, August 26, 2008 / Notices Information Relay Service (FIRS) at 1–800–877–8339. FOR FURTHER INFORMATION CONTACT: BILLING CODE 4000–01–P Bryan Whitener, Telephone: (202) 566– 3100. * * * * * ELECTION ASSISTANCE COMMISSION Alice Miller, Chief Operating Officer, U.S. Election Assistance Commission. [FR Doc. E8–19855 Filed 8–22–08; 4:15 pm] [FR Doc. E8–19700 Filed 8–25–08; 8:45 am] BILLING CODE 6820–KF–P Sunshine Act Notice United States Election Assistance Commission (EAC). * * * * * AGENCY: DEPARTMENT OF ENERGY Notice of Virtual Public Forum for EAC Board of Advisors. ACTION: Thursday, September 11, 2008, 9 a.m. EDT through Monday, September 15, 2008, 5 p.m. EDT. DATE AND TIME: EAC Board of Advisors Virtual Meeting Room at https://www.eac.gov. Once at the main page of EAC’s Web site, viewers should click the link to the Board of Advisors Virtual Meeting Room. The virtual meeting room will open on Thursday, September 11, 2008 at 9 a.m. EDT and will close on Monday, September 15, 2008, at 5 p.m. EDT. The site will be available 24 hours per day during that 5-day period. sroberts on PROD1PC76 with NOTICES PLACE: PURPOSE: The EAC Board of Advisors will review and provide comment on a draft of the independent evaluation plan. The draft contains a plan for evaluating the EAC’s $10M Election Data Collection Grant Program. The EAC Board of Advisors Virtual Meeting Room was established to enable the Board of Advisors to conduct business in an efficient manner in a public forum, including being able to review and discuss draft documents, when it is not feasible for an in-person board meeting. The Board of Advisors will not take any votes or propose any resolutions during the 5-day forum of September 11–September 15, 2008. Members will post comments about the draft evaluation plan. This activity is open to the public. The public may view the Proceedings of this special forum by visiting the EAC Board of Advisors virtual meeting room at https://www.eac.gov. At any time between Thursday, September 11, 2008, 9 a.m. EDT and Monday, September 15, 2008, 5 p.m. EDT. The public may file written statements to the EAC Board of Advisors at boardofadvisors@eac.gov. Data on EAC’s Web site is accessible to visitors with disabilities and meets the requirements of Section 508 of the Rehabilitation Act. VerDate Aug<31>2005 00:53 Aug 26, 2008 Jkt 214001 Federal Energy Regulatory Commission [Project No. 8118–034] Lake George Hydro, LLC; Notice of Application for Surrender of License and Soliciting Comments, Motions To Intervene, and Protests August 19, 2008. Take notice that the following application has been filed with the Commission and is available for public inspection: a. Application Type: Surrender of License. b. Project No.: 8118–034. c. Date Filed: August 6, 2008. d. Applicant: Lake George Hydro, LLC. e. Name of Project: Jerry Buckley. f. Location: The project is located on Clear Creek, in Clear Creek County, Colorado, and occupies 0.8 acre of U.S. Bureau of Land Management lands. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a–825r. h. Applicant Contact: Mr. Dennis W. Pungitore, Lake George Hydro, LLC, 9748 Clairtone Lane, Littleton, CO 80126. Telephone: (303) 475–6149. i. FERC Contact: Mr. Vedula Sarma, Telephone (202) 502–6190, and e-mail vedula.sarma@ferc.gov. j. Deadline for filing comments and/ or motions: September 19, 2008. All documents (original and eight copies) should be filed with: Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. Comments, protests, and interventions may be filed electronically via the Internet in lieu of paper; see 18 CFR 385.2001(a)(1)(iii) and instructions on the Commission’s Web site under the ‘‘e-filing’’ link. The Commission strongly encourages electronic filings. Please include the project number P– 8118–034 on any comments or motions filed. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of those documents on each person whose name appears on the PO 00000 Frm 00015 Fmt 4703 Sfmt 4703 50313 official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of those documents on that resource agency. A copy of any motion to intervene must also be served upon each representative of the Applicant specified in the particular application. k. Description of Request: The licensee filed an application to surrender its license. The licensee agreed to sell the project to the City of Black Hawk, Colorado, (City) and the surrender of license is a condition precedent to the purchase and sale of the project. The City intends to purchase the assets of the project and remove the penstock and generating equipment and sell the property as a real estate transaction. l. Locations of the Application: A copy of the application is available for inspection and reproduction at the Commission’s Public Reference Room, located at 888 First Street, NE., Room 2A, Washington, DC 20426, or by calling (202) 502–8371. This filing may also be viewed on the Commission’s Web site at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1–866–208–3372 or e-mail FERCOnlineSupport@ferc.gov. For TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item (h) above. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions To Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, and .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. C:\FR\FM\26AUN1.SGM 26AUN1 50314 Federal Register / Vol. 73, No. 166 / Tuesday, August 26, 2008 / Notices o. Any filings must bear in all capital letters the title ‘‘COMMENTS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’, as applicable, and the Project Number of the particular application to which the filing refers. p. Agency Comments: Federal, state, and local agencies are invited to file comments on the described application. A copy of the application may be obtained by agencies directly from the Applicant. If an agency does not file comments within the time specified for filing comments, it will be presumed to have no comments. One copy of an agency’s comments must also be sent to the Applicant’s representatives. Kimberly D. Bose, Secretary. [FR Doc. E8–19692 Filed 8–25–08; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 459–230] Ameren/UE; Notice of Application for Amendment of License and Soliciting Comments, Motions to Intervene, and Protests sroberts on PROD1PC76 with NOTICES August 19, 2008. a. Type of Application: Non-project use of project lands and waters. b. Project Number: 459–230. c. Date Filed: July 14, 2008. Supplemented August 12, 2008. d. Applicant: Ameren/UE. e. Name of Project: Osage Hydroelectric Project. f. Location: The project is located at the Mission Bay development near mile marker 32.1 of the main channel of the Lake of the Ozarks, in Camden County, Missouri. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a) 825(r) and 799 and 801. h. Applicant Contact: Mr. Jeff Green, Shoreline Supervisor, Ameren/UE, P.O. Box 993, Lake Ozark, MO 65049, (573) 365–9214. i. FERC Contact: Any questions on this notice should be addressed to Christopher Yeakel at (202) 502–8132, or e-mail address: christopher.yeakel@ferc.gov. j. Deadline for filing comments and or motions: September 19, 2008. k. Description of Request: Ameren/UE requests approval to permit EC Development, LLC, to construct 8 new multi-slip boat docks at the Mission Bay development. The docks would have a total of 104 boat slips ranging from 12 VerDate Aug<31>2005 00:53 Aug 26, 2008 Jkt 214001 feet long and 12 feet wide to 56 feet long and 14 feet wide and would include central walkways 4 feet wide. The docks would be available to the residents of the Mission Bay development. The shoreline within the project boundary is currently occupied by a new seawall but is otherwise undeveloped. No dredging, fuel dispensing, or sewage pumping facilities are proposed. l. Locations of the Application: A copy of the application is available for inspection and reproduction at the Commission’s Public Reference Room, located at 888 First Street, NE., Room 2A, Washington, DC 20426, or by calling (202) 502–8371. This filing may also be viewed on the Commission’s Web site at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field (p-459) to access the document. You may also register online at https://www.ferc.gov/ docs-filing/esubscription.asp to be notified via e-mail of new filings and issuances related to this or other pending projects. For assistance, call 1–866–208–3372 or e-mail FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item (h) above. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene—Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Responsive Documents—Any filings must bear in all capital letters the title ‘‘COMMENTS’’, ‘‘RECOMMENDATIONS FOR TERMS AND CONDITIONS’’, ‘‘PROTEST’’, OR ‘‘MOTION TO INTERVENE’’, as applicable, and the Project Number of the particular application to which the filing refers (p-459–230). All documents (original and eight copies) should be filed with: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington DC PO 00000 Frm 00016 Fmt 4703 Sfmt 4703 20426. A copy of any motion to intervene must also be served upon each representative of the Applicant specified in the particular application. p. Agency Comments—Federal, state, and local agencies are invited to file comments on the described application. A copy of the application may be obtained by agencies directly from the Applicant. If an agency does not file comments within the time specified for filing comments, it will be presumed to have no comments. One copy of an agency’s comments must also be sent to the Applicant’s representatives. q. Comments, protests and interventions may be filed electronically via the Internet in lieu of paper. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site at https://www.ferc.gov under the ‘‘e-Filing’’ link. Kimberly D. Bose, Secretary. [FR Doc. E8–19690 Filed 8–25–08; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13190–000] Ceresco Power and Light; Notice of Application for Preliminary Permit Accepted for Filing and Soliciting Comments, Motions to Intervene, and Protests August 19, 2008. On April 18, 2008, Ceresco Power and Light filed an application, pursuant to section 4(f) of the Federal Power Act (FPA), to study the feasibility of Ceresco Hydroelectric Project. The proposed project would be located on the Kalamazoo River in Calhoun County, Michigan. The existing Ceresco Dam is owned by the applicant. No lands of the United States are within the proposed project boundary. The proposed project using the existing Ceresco Dam would consist of: (1) A proposed powerhouse, containing four turbine-generator units, switchgears, circuit breakers, transformers, and a control panel; (2) a proposed service building; and (3) appurtenant facilities. The proposed project would have a total installed capacity of 800 kilowatts and an average annual generation of 2.6 gigawatt-hours, to be sold to a local utility, Consumers Energy, or the City of Battle Creek, MI. Applicant Contact: William Morris, 544 West Columbia Avenue, Suite B, C:\FR\FM\26AUN1.SGM 26AUN1

Agencies

[Federal Register Volume 73, Number 166 (Tuesday, August 26, 2008)]
[Notices]
[Pages 50313-50314]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-19692]


=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 8118-034]


Lake George Hydro, LLC; Notice of Application for Surrender of 
License and Soliciting Comments, Motions To Intervene, and Protests

August 19, 2008.
    Take notice that the following application has been filed with the 
Commission and is available for public inspection:
    a. Application Type: Surrender of License.
    b. Project No.: 8118-034.
    c. Date Filed: August 6, 2008.
    d. Applicant: Lake George Hydro, LLC.
    e. Name of Project: Jerry Buckley.
    f. Location: The project is located on Clear Creek, in Clear Creek 
County, Colorado, and occupies 0.8 acre of U.S. Bureau of Land 
Management lands.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
    h. Applicant Contact: Mr. Dennis W. Pungitore, Lake George Hydro, 
LLC, 9748 Clairtone Lane, Littleton, CO 80126. Telephone: (303) 475-
6149.
    i. FERC Contact: Mr. Vedula Sarma, Telephone (202) 502-6190, and e-
mail vedula.sarma@ferc.gov.
    j. Deadline for filing comments and/or motions: September 19, 2008.
    All documents (original and eight copies) should be filed with: 
Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., 
Washington, DC 20426. Comments, protests, and interventions may be 
filed electronically via the Internet in lieu of paper; see 18 CFR 
385.2001(a)(1)(iii) and instructions on the Commission's Web site under 
the ``e-filing'' link. The Commission strongly encourages electronic 
filings. Please include the project number P-8118-034 on any comments 
or motions filed.
    The Commission's Rules of Practice and Procedure require all 
intervenors filing documents with the Commission to serve a copy of 
those documents on each person whose name appears on the official 
service list for the project. Further, if an intervenor files comments 
or documents with the Commission relating to the merits of an issue 
that may affect the responsibilities of a particular resource agency, 
they must also serve a copy of those documents on that resource agency. 
A copy of any motion to intervene must also be served upon each 
representative of the Applicant specified in the particular 
application.
    k. Description of Request: The licensee filed an application to 
surrender its license. The licensee agreed to sell the project to the 
City of Black Hawk, Colorado, (City) and the surrender of license is a 
condition precedent to the purchase and sale of the project. The City 
intends to purchase the assets of the project and remove the penstock 
and generating equipment and sell the property as a real estate 
transaction.
    l. Locations of the Application: A copy of the application is 
available for inspection and reproduction at the Commission's Public 
Reference Room, located at 888 First Street, NE., Room 2A, Washington, 
DC 20426, or by calling (202) 502-8371. This filing may also be viewed 
on the Commission's Web site at https://www.ferc.gov using the 
``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. You may also 
register online at https://www.ferc.gov/docs-filing/esubscription.asp to 
be notified via e-mail of new filings and issuances related to this or 
other pending projects. For assistance, call 1-866-208-3372 or e-mail 
FERCOnlineSupport@ferc.gov. For TTY, call (202) 502-8659. A copy is 
also available for inspection and reproduction at the address in item 
(h) above.
    m. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    n. Comments, Protests, or Motions To Intervene: Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
and .214. In determining the appropriate action to take, the Commission 
will consider all protests or other comments filed, but only those who 
file a motion to intervene in accordance with the Commission's Rules 
may become a party to the proceeding. Any comments, protests, or 
motions to intervene must be received on or before the specified 
comment date for the particular application.

[[Page 50314]]

    o. Any filings must bear in all capital letters the title 
``COMMENTS'', ``PROTEST'', or ``MOTION TO INTERVENE'', as applicable, 
and the Project Number of the particular application to which the 
filing refers.
    p. Agency Comments: Federal, state, and local agencies are invited 
to file comments on the described application. A copy of the 
application may be obtained by agencies directly from the Applicant. If 
an agency does not file comments within the time specified for filing 
comments, it will be presumed to have no comments. One copy of an 
agency's comments must also be sent to the Applicant's representatives.

Kimberly D. Bose,
Secretary.
 [FR Doc. E8-19692 Filed 8-25-08; 8:45 am]
BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.