Hydrodynamics, Inc.; Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Terms and Conditions, Recommendations, and Prescriptions, 49665-49666 [E8-19472]
Download as PDF
Federal Register / Vol. 73, No. 164 / Friday, August 22, 2008 / Notices
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceedings. Any
comments, protests, or motions to
intervene must be received on or before
the specified comment date for the
particular application.
All filings must (1) Bear in all capital
letters the title ‘‘PROTEST’’, ‘‘MOTION
TO INTERVENE’’, ‘‘NOTICE OF
INTENT TO FILE COMPETING
APPLICATION’’, ‘‘COMPETING
APPLICATION’’, ‘‘COMMENTS’’,
‘‘REPLY COMMENTS’’,
‘‘RECOMMENDATIONS’’, ‘‘TERMS
AND CONDITIONS’’, or
‘‘PRESCRIPTIONS’’; (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person protesting or
intervening; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. All
comments, recommendations, terms and
conditions or prescriptions must set
forth their evidentiary basis and
otherwise comply with the requirements
of 18 CFR 4.34(b). Agencies may obtain
copies of the applications directly from
the applicant. A copy of any protest or
motion to intervene must be served
upon each representative of the
applicant specified in the particular
application. A copy of all other filings
in reference to these applications must
be accompanied by proof of service on
all persons listed in the service lists
prepared by the Commission in these
proceedings, in accordance with 18 CFR
4.34(b) and 385.2010.
o. A license applicant must file no
later than 60 days following the date of
issuance of this notice: (1) A copy of the
water quality certification(s); (2) a copy
of the request(s) for certification,
including proof of the date on which the
certifying agency received the
request(s); or (3) evidence of waiver(s) of
water quality certification.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. E8–19471 Filed 8–21–08; 8:45 am]
jlentini on PROD1PC65 with NOTICES
BILLING CODE 6717–01–P
VerDate Aug<31>2005
17:12 Aug 21, 2008
Jkt 214001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 12548–002]
Hydrodynamics, Inc.; Notice of
Application Accepted for Filing,
Soliciting Motions To Intervene and
Protests, Ready for Environmental
Analysis, and Soliciting Comments,
Terms and Conditions,
Recommendations, and Prescriptions
August 14, 2008.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Minor
unconstructed project.
b. Project No.: 12548–002.
c. Date filed: April 1, 2008.
d. Applicant: Hydrodynamics, Inc.
e. Name of Project: Greenfield.
f. Location: On the Greenfields Main
Canal, part of the U.S. Bureau of
Reclamation’s existing Sun River
Irrigation Project, in Teton County,
Montana, near Fairfield, Montana.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Roger Kirk,
Hydrodynamics, Inc., P.O. Box 1136,
Bozeman, MT 59771, (406) 587–5086.
i. FERC Contact: Dianne Rodman,
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426; telephone (202) 502–6077 or by
e-mail at dianne.rodman@ferc.gov.
j. Deadline for filing motions to
intervene and protests, comments, terms
and conditions, recommendations, and
prescriptions: 60 days from the issuance
of this notice. All reply comments must
be filed with the Commission within
105 days from the date of this notice.
All documents (original and eight
copies) should be filed with: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
Motions to intervene, protests,
comments, terms and conditions,
recommendations, and prescriptions
may be filed electronically via the
Internet in lieu of paper. The
PO 00000
Frm 00024
Fmt 4703
Sfmt 4703
49665
Commission strongly encourages
electronic filings. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site (https://
www.ferc.gov) under the ‘‘e-Filing’’ link.
k. This application has been accepted
for filing and is now ready for
environmental analysis.
l. The proposed Greenfield Project
would be built at the Greenfields Main
Canal’s Greenfield drop structure. The
applicant proposes to construct: (1) An
inflatable weir spanning the width of
the canal; (2) an intake structure with
trash rack and radial gate or stop-log
shut off; (3) a buried, 60-inch-diameter,
530-foot-long steel or polyethylene
penstock; (4) a powerhouse containing
one Francis or propeller (Reaction)
turbine and one generator with a rated
output of 600 kilowatts; (5) a tailrace
returning flows to the canal; (6) a
switchyard; and (7) a 512-foot-long, 12kilovolt transmission line
interconnecting with an existing
powerline. Average annual generation
would be 1.5 gigawatt hours.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number, excluding the last three digits,
in the docket number field to access the
document. For assistance, contact FERC
Online Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in item h above.
Register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Any qualified applicant desiring to
file a competing application must
submit to the Commission, on or before
the specified intervention deadline date,
a competing development application,
or a notice of intent to file such an
application. Submission of a timely
notice of intent allows an interested
person to file the competing
development application no later than
120 days after the specified intervention
deadline date. Applications for
preliminary permits will not be
accepted in response to this notice.
A notice of intent must specify the
exact name, business address, and
telephone number of the prospective
applicant, and must include an
unequivocal statement of intent to
submit a development application. A
E:\FR\FM\22AUN1.SGM
22AUN1
jlentini on PROD1PC65 with NOTICES
49666
Federal Register / Vol. 73, No. 164 / Friday, August 22, 2008 / Notices
notice of intent must be served on the
applicant named in this public notice.
Anyone may submit comments, a
protest, or a motion to intervene in
accordance with the requirements of
Rules of Practice and Procedure, 18 CFR
385.210, 385.211, and 385.214. In
determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
All filings must (1) bear in all capital
letters the title ‘‘PROTEST’’, ‘‘MOTION
TO INTERVENE’’, ‘‘NOTICE OF
INTENT TO FILE COMPETING
APPLICATION’’, ‘‘COMPETING
APPLICATION’’, ‘‘COMMENTS’’,
‘‘REPLY COMMENTS’’,
‘‘RECOMMENDATIONS’’, ‘‘TERMS
AND CONDITIONS’’, or
‘‘PRESCRIPTIONS’’; (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person protesting or
intervening; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. All
comments, recommendations, terms and
conditions or prescriptions must set
forth their evidentiary basis and
otherwise comply with the requirements
of 18 CFR 4.34(b). Agencies may obtain
copies of the application directly from
the applicant. A copy of any protest or
motion to intervene must be served
upon each representative of the
applicant specified in the particular
application. A copy of all other filings
in reference to this application must be
accompanied by proof of service on all
persons listed in the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
4.34(b) and 385.2010.
o. License applicant must file no later
than 60 days following the date of
issuance of this notice: (1) A copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. E8–19472 Filed 8–21–08; 8:45 am]
BILLING CODE 6717–01–P
VerDate Aug<31>2005
17:12 Aug 21, 2008
Jkt 214001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP08–454–000]
Liberty Gas Storage, LLC; Notice of
Application
August 14, 2008.
Take notice that on July 31, 2008,
Liberty Gas Storage, LLC (Liberty Gas),
101 Ash Street, San Diego, CA 92101,
filed in the above referenced docket an
application pursuant to section 7(c) of
the Natural Gas Act (NGA), for an order
granting a certificate of public
convenience to construct new natural
gas storage, comprised of three existing
salt dome caverns and the development
of a new salt dome cavern, pipeline and
appurtenant facilities. The new facilities
will be located in Cameron and
Calcasieu Parishes, Louisiana, all as
more fully set forth in the application
which is on file with the Commission
and open to public inspection. The
filing may also be viewed on the Web
at https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, please contact
FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at (866) 208–3676, or TTY, contact
(202) 502–8659.
Any questions concerning this
application may be directed to William
Rapp, Liberty Gas Storage, 101 Ash
Street, San Diego, CA 92101 or by phone
at (619) 699–5050.
Liberty Gas’ new storage project has
been designed to provide approximately
18.9 billion cubic feet (Bcf) of working
gas capacity with a maximum injection
rate of up to 600 million cubic feet (Mcf)
per day and a maximum withdrawal
rate of up to 1.2 Bcf per day.
Additionally, Liberty Gas intends to
construct 5.1 miles of 36-inch diameter
pipeline to deliver the natural gas to
Cameron Interstate Pipeline, LLC, as
well as one 18,940 horsepower
compressor station, a 4.0 mile brine
disposal pipeline and water supply
facilities necessary to develop the
proposed new cavern.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
PO 00000
Frm 00025
Fmt 4703
Sfmt 4703
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below, file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
14 copies of filings made with the
Commission and must mail a copy to
the applicant and to every other party in
the proceeding. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commentors will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
E:\FR\FM\22AUN1.SGM
22AUN1
Agencies
[Federal Register Volume 73, Number 164 (Friday, August 22, 2008)]
[Notices]
[Pages 49665-49666]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-19472]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 12548-002]
Hydrodynamics, Inc.; Notice of Application Accepted for Filing,
Soliciting Motions To Intervene and Protests, Ready for Environmental
Analysis, and Soliciting Comments, Terms and Conditions,
Recommendations, and Prescriptions
August 14, 2008.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Minor unconstructed project.
b. Project No.: 12548-002.
c. Date filed: April 1, 2008.
d. Applicant: Hydrodynamics, Inc.
e. Name of Project: Greenfield.
f. Location: On the Greenfields Main Canal, part of the U.S. Bureau
of Reclamation's existing Sun River Irrigation Project, in Teton
County, Montana, near Fairfield, Montana.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Roger Kirk, Hydrodynamics, Inc., P.O. Box
1136, Bozeman, MT 59771, (406) 587-5086.
i. FERC Contact: Dianne Rodman, Federal Energy Regulatory
Commission, 888 First Street, NE., Washington, DC 20426; telephone
(202) 502-6077 or by e-mail at dianne.rodman@ferc.gov.
j. Deadline for filing motions to intervene and protests, comments,
terms and conditions, recommendations, and prescriptions: 60 days from
the issuance of this notice. All reply comments must be filed with the
Commission within 105 days from the date of this notice.
All documents (original and eight copies) should be filed with:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
Motions to intervene, protests, comments, terms and conditions,
recommendations, and prescriptions may be filed electronically via the
Internet in lieu of paper. The Commission strongly encourages
electronic filings. See 18 CFR 385.2001(a)(1)(iii) and the instructions
on the Commission's Web site (https://www.ferc.gov) under the ``e-
Filing'' link.
k. This application has been accepted for filing and is now ready
for environmental analysis.
l. The proposed Greenfield Project would be built at the
Greenfields Main Canal's Greenfield drop structure. The applicant
proposes to construct: (1) An inflatable weir spanning the width of the
canal; (2) an intake structure with trash rack and radial gate or stop-
log shut off; (3) a buried, 60-inch-diameter, 530-foot-long steel or
polyethylene penstock; (4) a powerhouse containing one Francis or
propeller (Reaction) turbine and one generator with a rated output of
600 kilowatts; (5) a tailrace returning flows to the canal; (6) a
switchyard; and (7) a 512-foot-long, 12-kilovolt transmission line
interconnecting with an existing powerline. Average annual generation
would be 1.5 gigawatt hours.
m. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number, excluding the last three digits, in the
docket number field to access the document. For assistance, contact
FERC Online Support at FERCOnlineSupport@ferc.gov or toll-free at 1-
866-208-3676, or for TTY, (202) 502-8659. A copy is also available for
inspection and reproduction at the address in item h above.
Register online at https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via e-mail of new filings and
issuances related to this or other pending projects. For assistance,
contact FERC Online Support.
n. Any qualified applicant desiring to file a competing application
must submit to the Commission, on or before the specified intervention
deadline date, a competing development application, or a notice of
intent to file such an application. Submission of a timely notice of
intent allows an interested person to file the competing development
application no later than 120 days after the specified intervention
deadline date. Applications for preliminary permits will not be
accepted in response to this notice.
A notice of intent must specify the exact name, business address,
and telephone number of the prospective applicant, and must include an
unequivocal statement of intent to submit a development application. A
[[Page 49666]]
notice of intent must be served on the applicant named in this public
notice.
Anyone may submit comments, a protest, or a motion to intervene in
accordance with the requirements of Rules of Practice and Procedure, 18
CFR 385.210, 385.211, and 385.214. In determining the appropriate
action to take, the Commission will consider all protests or other
comments filed, but only those who file a motion to intervene in
accordance with the Commission's Rules may become a party to the
proceeding. Any comments, protests, or motions to intervene must be
received on or before the specified comment date for the particular
application.
All filings must (1) bear in all capital letters the title
``PROTEST'', ``MOTION TO INTERVENE'', ``NOTICE OF INTENT TO FILE
COMPETING APPLICATION'', ``COMPETING APPLICATION'', ``COMMENTS'',
``REPLY COMMENTS'', ``RECOMMENDATIONS'', ``TERMS AND CONDITIONS'', or
``PRESCRIPTIONS''; (2) set forth in the heading the name of the
applicant and the project number of the application to which the filing
responds; (3) furnish the name, address, and telephone number of the
person protesting or intervening; and (4) otherwise comply with the
requirements of 18 CFR 385.2001 through 385.2005. All comments,
recommendations, terms and conditions or prescriptions must set forth
their evidentiary basis and otherwise comply with the requirements of
18 CFR 4.34(b). Agencies may obtain copies of the application directly
from the applicant. A copy of any protest or motion to intervene must
be served upon each representative of the applicant specified in the
particular application. A copy of all other filings in reference to
this application must be accompanied by proof of service on all persons
listed in the service list prepared by the Commission in this
proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
o. License applicant must file no later than 60 days following the
date of issuance of this notice: (1) A copy of the water quality
certification; (2) a copy of the request for certification, including
proof of the date on which the certifying agency received the request;
or (3) evidence of waiver of water quality certification.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. E8-19472 Filed 8-21-08; 8:45 am]
BILLING CODE 6717-01-P