Davis Hydro, LLC.; Notice of Application for Preliminary Permit Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests, 46610 [E8-18376]

Download as PDF 46610 Federal Register / Vol. 73, No. 155 / Monday, August 11, 2008 / Notices Scoping Meetings Commission staff will hold two scoping meetings in the vicinity of the project at the time and place noted below. The daytime meeting will focus on resource agency, Indian tribes, and non-governmental organization concerns, while the evening meeting is primarily for receiving input from the public. We invite all interested individuals, organizations, and agencies to attend one or both of the meetings, and to assist staff in identifying particular study needs, as well as the scope of environmental issues to be addressed in the environmental document. The times and locations of these meetings are as follows: Daytime Scoping Meeting Date: Thursday, September 11, 2008. Time: 9 a.m. to 12 noon (CST). Location: Central Alabama Community College, Betty Carol Graham Center at Alexander City Campus, 1675 Cherokee Road, Alexander City, AL 35010. Phone: (205) 257–2211. rmajette on PRODPC74 with NOTICES Evening Scoping Meeting Date: Thursday, September 11, 2008. Time: 6 p.m. to 8 p.m. (CST). Location: Central Alabama Community College, Betty Carol Graham Center at Alexander City Campus, 1675 Cherokee Road, Alexander City, AL 35010. Phone: (205) 257–2211. Scoping Document 1 (SD1), which outlines the subject areas to be addressed in the environmental document, was mailed to the individuals and entities on the Commission’s mailing list. Copies of SD1 will be available at the scoping meetings, or may be viewed on the Web at https://www.ferc.gov, using the ‘‘eLibrary’’ link. Follow the directions for accessing information in paragraph n. Based on all oral and written comments, a Scoping Document 2 (SD2) may be issued. SD2 may include a revised process plan and schedule, as well as a list of issues, identified through the scoping process. Site Visit The potential applicant and Commission staff will conduct a site visit of the project on Wednesday, September 10, 2008, starting at 9 a.m. (CST). All participants should meet at the parking lot for the Martin Dam powerhouse, located at 675 Overlook Drive, Dadeville, AL 36853. All participants are responsible for their own transportation to the powerhouse site. Anyone with questions about the site visit should contact Viki Pate, VerDate Aug<31>2005 15:22 Aug 08, 2008 Jkt 214001 Alabama Power Company at (205) 257– 2211 on or before September 3, 2008. Meeting Objectives At the scoping meetings, staff will: (1) Initiate scoping of the issues; (2) review and discuss existing conditions and resource management objectives; (3) review and discuss existing information and identify preliminary information and study needs; (4) review and discuss the process plan and schedule for prefiling activity that incorporates the time frames provided for in Part 5 of the Commission’s regulations and, to the extent possible, maximizes coordination of federal, state, and tribal permitting and certification processes; and (5) discuss the appropriateness of any federal or state agency or Indian tribe acting as a cooperating agency for development of an environmental document. Meeting participants should come prepared to discuss their issues and/or concerns. Please review the PAD in preparation for the scoping meetings. Directions on how to obtain a copy of the PAD and SD1 are included in item n. of this document. Meeting Procedures The meetings will be recorded by a stenographer and will become part of the formal record of the Commission proceeding on the project. Kimberly D. Bose, Secretary. [FR Doc. E8–18471 Filed 8–8–08; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission P–13174–000] Davis Hydro, LLC.; Notice of Application for Preliminary Permit Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests August 4, 2008. On April 16, 2008, Davis Hydro LLC. filed an application, pursuant to section 4(f) of the Federal Power Act (FPA), to study the feasibility of Boca Power Project. The proposed project would be located on the Little Truckee River in Nevada County, California. The existing facilities are owned and operated by the Bureau of Reclamation. The proposed project using the existing Bureau of Reclamation Boca Power Project would consist of: (1) A proposed approximately eight-foot-long PO 00000 Frm 00029 Fmt 4703 Sfmt 4703 50-inch diameter penstock, (2) a proposed powerhouse, containing one generating unit with an installed capacity of 1.125 megawatts, (3) a proposed 2,000-foot-long, 12 kilovolt transmission line, and (4) appurtenant facilities. The proposed project would have an average annual generation of 5 gigawatt-hours and be sold to a local utility. Applicant Contact: Richard D. Ely, Principal, Davis Hydro LLC., 27264 Meadowbrook Drive, Davis, California 95618, (530) 753–8864, Dick@davishydro.com. FERC Contact: Jake Tung, (202) 502– 8757. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. If unable to be filed electronically, documents may be paperfiled. To paper-file, an original and eight copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For more information on how to submit these types of filings please go to the Commission’s Web site located at https://www.ferc.gov/filingcomments.asp. More information about this project can be viewed or printed on the ‘‘eLibrary’’ link of the Commission’s Web site at https://www.ferc.gov/docsfiling/elibrary.asp. Enter the docket number (P–13177) in the docket number field to access the document. For assistance, call toll-free 1–866–208– 3372. Kimberly D. Bose, Secretary. [FR Doc. E8–18376 Filed 8–8–08; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\11AUN1.SGM 11AUN1

Agencies

[Federal Register Volume 73, Number 155 (Monday, August 11, 2008)]
[Notices]
[Page 46610]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-18376]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

P-13174-000]


Davis Hydro, LLC.; Notice of Application for Preliminary Permit 
Accepted for Filing and Soliciting Comments, Motions To Intervene, and 
Protests

August 4, 2008.
    On April 16, 2008, Davis Hydro LLC. filed an application, pursuant 
to section 4(f) of the Federal Power Act (FPA), to study the 
feasibility of Boca Power Project. The proposed project would be 
located on the Little Truckee River in Nevada County, California. The 
existing facilities are owned and operated by the Bureau of 
Reclamation.
    The proposed project using the existing Bureau of Reclamation Boca 
Power Project would consist of: (1) A proposed approximately eight-
foot-long 50-inch diameter penstock, (2) a proposed powerhouse, 
containing one generating unit with an installed capacity of 1.125 
megawatts, (3) a proposed 2,000-foot-long, 12 kilovolt transmission 
line, and (4) appurtenant facilities. The proposed project would have 
an average annual generation of 5 gigawatt-hours and be sold to a local 
utility.
    Applicant Contact: Richard D. Ely, Principal, Davis Hydro LLC., 
27264 Meadowbrook Drive, Davis, California 95618, (530) 753-8864, 
Dick@davishydro.com.
    FERC Contact: Jake Tung, (202) 502-8757.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Comments, motions to intervene, notices of intent, and competing 
applications may be filed electronically via the Internet. See 18 CFR 
385.2001(a)(1)(iii) and the instructions on the Commission's Web site 
under the ``e-Filing'' link. If unable to be filed electronically, 
documents may be paper-filed. To paper-file, an original and eight 
copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For 
more information on how to submit these types of filings please go to 
the Commission's Web site located at https://www.ferc.gov/filing-
comments.asp. More information about this project can be viewed or 
printed on the ``eLibrary'' link of the Commission's Web site at http:/
/www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number (P-
13177) in the docket number field to access the document. For 
assistance, call toll-free 1-866-208-3372.

Kimberly D. Bose,
Secretary.
 [FR Doc. E8-18376 Filed 8-8-08; 8:45 am]
BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.