Download as PDF 44244 Federal Register / Vol. 73, No. 147 / Wednesday, July 30, 2008 / Notices Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission’s final order. Motions to intervene, protests and comments may be filed electronically via the Internet in lieu of paper; see, 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. The Commission strongly encourages electronic filings. Comment Date: August 13, 2008. Kimberly D. Bose, Secretary. [FR Doc. E8–17396 Filed 7–29–08; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings July 24, 2008. mstockstill on PROD1PC66 with NOTICES Take notice that the Commission has received the following Natural Gas Pipeline Rate and Refund Report filings: Docket Numbers: RP08–371–001. Applicants: Texas Gas Transmission, LLC. Description: Texas Gas Transmission, LLC submits Original Sheet 74B of its FERC Gas Tariff, Second Revised Volume 1 effective 7/1/08. Filed Date: 07/23/2008. Accession Number: 20080723–0239. Comment Date: 5 p.m. Eastern Time on Monday, August 04, 2008. Docket Numbers: RP08–452–000. Applicants: Northwest Pipeline GP. Description: Northwest Pipeline, GP request that the Commission grant a waiver of Section 25.2(c) of the General Terms and Conditions of FERC Gas Tariff, etc. Filed Date: 07/23/2008. Accession Number: 20080724–0021. Comment Date: 5 p.m. Eastern Time on Monday, August 04, 2008. Any person desiring to intervene or to protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214) on or before 5 p.m. Eastern time on the specified comment date. It is not necessary to separately intervene again in a subdocket related to a compliance filing if you have previously intervened in the same docket. Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. VerDate Aug<31>2005 23:06 Jul 29, 2008 Jkt 214001 Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. In reference to filings initiating a new proceeding, interventions or protests submitted on or before the comment deadline need not be served on persons other than the Applicant. The Commission encourages electronic submission of protests and interventions in lieu of paper, using the FERC Online links at https:// www.ferc.gov. To facilitate electronic service, persons with Internet access who will eFile a document and/or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. Persons unable to file electronically should submit an original and 14 copies of the intervention or protest to the Federal Energy Regulatory Commission, 888 First St. NE., Washington, DC 20426. The filings in the above proceedings are accessible in the Commission’s eLibrary system by clicking on the appropriate link in the above list. They are also available for review in the Commission’s Public Reference Room in Washington, DC. There is an eSubscription link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed dockets(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov. or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. E8–17434 Filed 7–29–08; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP08–207–000] Transcontinental Gas Pipe Line Corporation; Notice of Intent To Prepare an Environmental Assessment for the Proposed Hester Storage Field Retirement Project and Request for Comments on Environmental Issues July 23, 2008. The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of PO 00000 Frm 00034 Fmt 4703 Sfmt 4703 Transcontinental Gas Pipe Line Corporation’s (Transco) Hester Storage Field Retirement Project (Project) involving abandonment, construction, and temporary operation of facilities by Transco in St. James Parish, Louisiana. This notice announces the opening of the scoping process we will use to gather input from the public and interested agencies on the project. Your input will help the Commission staff determine which issues need to be evaluated in the EA. Please note that the scoping period will close on August 22, 2008. This notice is being sent to affected landowners; federal, state, and local government representatives and agencies; environmental and public interest groups; Native American tribes; other interested parties in this proceeding; and local libraries and newspapers. We encourage government representatives to notify their constituents of this planned project and encourage them to comment on their areas of concern. A fact sheet prepared by the FERC entitled ‘‘An Interstate Natural Gas Facility On My Land? What Do I Need To Know?’’ was attached to the project notice Transco provided to landowners. This fact sheet addresses a number of typically asked questions, including how to participate in the Commission’s proceedings. It is available for viewing on the FERC Internet Web site (https:// www.ferc.gov). Summary of the Proposed Project The proposed project would involve temporary compression and minor modification and installation of yard pipeline at Compressor Station 64 to support the final withdrawal of base gas from the Hester Storage field; eventual removal and capping of 5 wells of the Hester Storage Field; closure of Compressor Station 64, and the abandonment in place of 4.75 miles of pipeline lateral. Specifically, Transco proposes to: • Temporarily install one 630 horsepower engine/compressor unit associated yard pipes at Compressor Station 64; • Remove gathering lines between Compressor Station 64 and 5 injection/ withdrawal wells, 1 monitoring well, and 3 water wells; • Abandon the 12-inch pipeline lateral from Compressor station 64 (milepost 8.66) to the interconnect with Occidental Chemical Corporation (milepost 3.91); • Abandon and cap 5 injection/ withdrawal wells, 1 monitoring well, and 3 water wells; and E:\FR\FM\30JYN1.SGM 30JYN1 Federal Register / Vol. 73, No. 147 / Wednesday, July 30, 2008 / Notices • Remove all aboveground buildings and equipment at Compressor Station 64, including, but not limited to the compressor building, office/shop, air compressor building, utility shed, meter building, condensate and wastewater tanks, gas coolers, glycol units, gas scrubbers, 2 existing engine/compressor units, and associated piping. The location of the project facilities is shown in Appendix 1.1 Nonjurisdictional Facilities There are no non-jurisdictional facilities associated with this project. Land Requirements for Construction Construction of the proposed temporary facilities would be contained within the existing Compressor Station 64 fence line, existing well pads and existing pipeline right-of-way. Approximately 14.06 acres of land would be disturbed during the temporary installation of compression and the abandonment of wells and pipeline. Following construction, the use of the pipeline lateral right-of-way would revert to the landowner while the compressor station property would either be donated to the community or sold. The EA Process mstockstill on PROD1PC66 with NOTICES The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental impacts that could result from an action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. NEPA also requires us to discover and address concerns the public may have about proposals. This process is referred to as ‘‘scoping.’’ The main goal of the scoping process is to focus the analysis in the EA on the important environmental issues. By this Notice of Intent, the Commission staff requests public comments on the scope of the issues to address in the EA. All comments received are considered during the preparation of the EA. State and local government representatives are encouraged to notify their constituents of this proposed action and encourage them to comment on their areas of concern. 1 The appendices referenced in this notice are not being printed in the Federal Register. Copies of all appendices, other than Appendix 1 (maps), are available on the Commission’s Web site at the ‘‘eLibrary’’ link or from the Commission’s Public Reference Room, 888 First Street, NE., Washington, DC 20426, or call (202) 502–8371. For instructions on connecting to eLibrary refer to the last page of this notice. Copies of the appendices were sent to all those receiving this notice in the mail. VerDate Aug<31>2005 23:06 Jul 29, 2008 Jkt 214001 In the EA we 2 will discuss impacts that could occur as a result of the construction and operation of the proposed project under these general headings: • Geology and soils. • Land use. • Water resources, fisheries, and wetlands. • Cultural resources. • Vegetation and wildlife. • Air quality and noise. • Endangered and threatened species. • Hazardous waste. • Public safety. We will also evaluate reasonable alternatives to the proposed project or portions of the project, and make recommendations on how to lessen or avoid impacts on the various resource areas. Our independent analysis of the issues will be in the EA. Depending on the comments received during the scoping process, the EA may be published and mailed to federal, state, and local agencies, public interest groups, interested individuals, affected landowners, newspapers, libraries, and the Commission’s official service list for this proceeding. A comment period will be allotted for review if the EA is published. We will consider all comments on the EA before we make our recommendations to the Commission. To ensure your comments are considered, please carefully follow the instructions in the public participation section below. Currently Identified Environmental Issues We have already identified issues that we think deserve attention based on a preliminary review of the proposed facilities and the environmental information provided by Transco. This preliminary list of issues may be changed based on your comments and our analysis. • The project may have air emissions and noise impacts. • Safety of the storage field after abandonment. Public Participation You can make a difference by providing us with your specific comments or concerns about the Hester Storage Field Abandonment Project. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. 2 ‘‘We’’, ‘‘us’’, and ‘‘our’’ refer to the environmental staff of the Office of Energy Projects (OEP). PO 00000 Frm 00035 Fmt 4703 Sfmt 4703 44245 The more specific your comments, the more useful they will be. To ensure that your comments are timely and properly recorded, please send in your comments so that they will be received in Washington, DC on or before August 22, 2008. For your convenience, there are three methods which you can use to submit your comments to the Commission. In all instances please reference the project docket number CP08–207–000 with your submission. The docket number can be found on the front of this notice. The Commission encourages electronic filing of comments and has dedicated eFiling expert staff available to assist you at 202–502–8258 or efiling@ferc.gov. (1) You may file your comments electronically by using the Quick Comment feature, which is located on the Commission’s internet Web site at https://www.ferc.gov under the link to Documents and Filings. A Quick Comment is an easy method for interested persons to submit text-only comments on a project; (2) You may file your comments electronically by using the eFiling feature, which is located on the Commission’s internet Web site at https://www.ferc.gov under the link to Documents and Filings. eFiling involves preparing your submission in the same manner as you would if filing on paper, and then saving the file on your computer’s hard drive. You will attach that file as your submission. New eFiling users must first create an account by clicking on ‘‘Sign up’’ or ‘‘eRegister.’’ You will be asked to select the type of filing you are making. A comment on a particular project is considered a ‘‘Comment on a Filing;’’ or (3) You may file your comments via mail to the Commission by sending an original and two copies of your letter to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First St., NE., Room 1A, Washington, DC 20426. Label one copy of the comments for the attention of Gas Branch 3, PJ11.3. Environmental Mailing List An effort is being made to send this notice to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed project. This includes all landowners whose property may be used temporarily for project purposes, who have existing easements from the pipeline, or who own homes within distances defined in the Commission’s regulations of certain aboveground facilities. By this notice we are also asking governmental agencies, E:\FR\FM\30JYN1.SGM 30JYN1 44246 Federal Register / Vol. 73, No. 147 / Wednesday, July 30, 2008 / Notices especially those in Appendix 2, to express their interest in becoming cooperating agencies for the preparation of the EA. If you do not want to send comments at this time but still want to remain on our mailing list, please return the Information Request (Appendix 3). If you do not return the Information Request, you will be taken off the mailing list. mstockstill on PROD1PC66 with NOTICES Becoming an Intervenor In addition to involvement in the EA scoping process, you may want to become an official party to the proceeding known as an ‘‘intervenor.’’ Intervenors play a more formal role in the process. Among other things, intervenors have the right to receive copies of case-related Commission documents and filings by other intervenors. Likewise, each intervenor must send one electronic copy (using the Commission’s eFiling system) or 14 paper copies of its filings to the Secretary of the Commission and must send a copy of its filings to all other parties on the Commission’s service list for this proceeding. If you want to become an intervenor you must file a motion to intervene according to Rule 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.214). Only intervenors have the right to seek rehearing of the Commission’s decision. The Notice of Application for this proposed project issued on May 6, 2008 identified the date for the filing of interventions as May 28, 2008. However, affected landowners and parties with environmental concerns may be granted late intervenor status upon showing good cause by stating that they have a clear and direct interest in this proceeding which would not be adequately represented by any other parties. You do not need intervenor status to have your environmental comments considered. Availability of Additional Information Additional information about the project is available from the Commission’s Office of External Affairs, at 1–866–208–FERC or on the FERC Internet Web site (https://www.ferc.gov) using the eLibrary link. Click on the eLibrary link, click on ‘‘General Search’’ and enter the docket number excluding the last three digits in the Docket Number field. Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at 1–866–208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the VerDate Aug<31>2005 23:06 Jul 29, 2008 Jkt 214001 texts of formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission now offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries and direct links to the documents. Go to https:// www.ferc.gov/esubscribenow.htm. Finally, public meetings or site visits will be posted on the Commission’s calendar located at https://www.ferc.gov/ EventCalendar/EventsList.aspx along with other related information. Kimberly D. Bose, Secretary. [FR Doc. E8–17404 Filed 7–29–08; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5 p.m. Eastern Time on August 13, 2008. Federal Energy Regulatory Commission Kimberly D. Bose, Secretary. [FR Doc. E8–17397 Filed 7–29–08; 8:45 am] [Docket No. EF08–2011–000] BILLING CODE 6717–01–P Bonneville Power Administration; Notice of Filing DEPARTMENT OF ENERGY July 23, 2008. Take notice that on July 14, 2008, the Bonneville Power Administration (BPA) filed its proposed Average system Cost Methodology (2008 ASCM) for the Commission’s review and approval on an interim basis, effective October 1, 2008, vested in the Commission by Pacific Northwest Electric Power Planning and Conservation Act, under section 5(c)(7), and Commission regulations, 16 U.S.C. section 839c(c)(7). BPA also requests the Commission to revise its regulations at 18 CFR section 301.1 to reflect BPA’s 2008 ASCM once it is approved. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the comment date. On or before the comment date, it is not necessary to serve motions to intervene or protests on persons other than the Applicant. PO 00000 Frm 00036 Fmt 4703 Sfmt 4703 Federal Energy Regulatory Commission [Docket No. EF08–2021–000] Bonneville Power Administration; Notice of Filing July 23, 2008. Take notice that on July 17, 2008, Bonneville Power Administration, filed its 2009 Wind Integration—Within-Hour Balancing Service rate schedule for the Commission’s confirmation and approval on an interim basis by September 30, 2008 and final approval effective October 1, 2008 through September 30, 2008, vested in the Commission by Pacific Northwest Electric Power Planning and Conservation Act, under sections 7(a)(2) and 7(i)(6), and Commission regulations, 16 U.S.C. 839e(a)(2) and 839e(i)(6), and Subpart B of Part 300, 18 CFR part 300. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to E:\FR\FM\30JYN1.SGM 30JYN1

Agencies

[Federal Register Volume 73, Number 147 (Wednesday, July 30, 2008)]
[Notices]
[Pages 44244-44246]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-17404]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP08-207-000]


Transcontinental Gas Pipe Line Corporation; Notice of Intent To 
Prepare an Environmental Assessment for the Proposed Hester Storage 
Field Retirement Project and Request for Comments on Environmental 
Issues

July 23, 2008.
    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of Transcontinental Gas Pipe Line 
Corporation's (Transco) Hester Storage Field Retirement Project 
(Project) involving abandonment, construction, and temporary operation 
of facilities by Transco in St. James Parish, Louisiana.
    This notice announces the opening of the scoping process we will 
use to gather input from the public and interested agencies on the 
project. Your input will help the Commission staff determine which 
issues need to be evaluated in the EA. Please note that the scoping 
period will close on August 22, 2008.
    This notice is being sent to affected landowners; federal, state, 
and local government representatives and agencies; environmental and 
public interest groups; Native American tribes; other interested 
parties in this proceeding; and local libraries and newspapers. We 
encourage government representatives to notify their constituents of 
this planned project and encourage them to comment on their areas of 
concern.
    A fact sheet prepared by the FERC entitled ``An Interstate Natural 
Gas Facility On My Land? What Do I Need To Know?'' was attached to the 
project notice Transco provided to landowners. This fact sheet 
addresses a number of typically asked questions, including how to 
participate in the Commission's proceedings. It is available for 
viewing on the FERC Internet Web site (https://www.ferc.gov).

Summary of the Proposed Project

    The proposed project would involve temporary compression and minor 
modification and installation of yard pipeline at Compressor Station 64 
to support the final withdrawal of base gas from the Hester Storage 
field; eventual removal and capping of 5 wells of the Hester Storage 
Field; closure of Compressor Station 64, and the abandonment in place 
of 4.75 miles of pipeline lateral.
    Specifically, Transco proposes to:
     Temporarily install one 630 horsepower engine/compressor 
unit associated yard pipes at Compressor Station 64;
     Remove gathering lines between Compressor Station 64 and 5 
injection/withdrawal wells, 1 monitoring well, and 3 water wells;
     Abandon the 12-inch pipeline lateral from Compressor 
station 64 (milepost 8.66) to the interconnect with Occidental Chemical 
Corporation (milepost 3.91);
     Abandon and cap 5 injection/withdrawal wells, 1 monitoring 
well, and 3 water wells; and

[[Page 44245]]

     Remove all aboveground buildings and equipment at 
Compressor Station 64, including, but not limited to the compressor 
building, office/shop, air compressor building, utility shed, meter 
building, condensate and wastewater tanks, gas coolers, glycol units, 
gas scrubbers, 2 existing engine/compressor units, and associated 
piping.
    The location of the project facilities is shown in Appendix 1.\1\
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice are not being 
printed in the Federal Register. Copies of all appendices, other 
than Appendix 1 (maps), are available on the Commission's Web site 
at the ``eLibrary'' link or from the Commission's Public Reference 
Room, 888 First Street, NE., Washington, DC 20426, or call (202) 
502-8371. For instructions on connecting to eLibrary refer to the 
last page of this notice. Copies of the appendices were sent to all 
those receiving this notice in the mail.
---------------------------------------------------------------------------

Nonjurisdictional Facilities

    There are no non-jurisdictional facilities associated with this 
project.

Land Requirements for Construction

    Construction of the proposed temporary facilities would be 
contained within the existing Compressor Station 64 fence line, 
existing well pads and existing pipeline right-of-way. Approximately 
14.06 acres of land would be disturbed during the temporary 
installation of compression and the abandonment of wells and pipeline. 
Following construction, the use of the pipeline lateral right-of-way 
would revert to the landowner while the compressor station property 
would either be donated to the community or sold.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and Necessity. NEPA also requires us 
to discover and address concerns the public may have about proposals. 
This process is referred to as ``scoping.'' The main goal of the 
scoping process is to focus the analysis in the EA on the important 
environmental issues. By this Notice of Intent, the Commission staff 
requests public comments on the scope of the issues to address in the 
EA. All comments received are considered during the preparation of the 
EA. State and local government representatives are encouraged to notify 
their constituents of this proposed action and encourage them to 
comment on their areas of concern.
    In the EA we \2\ will discuss impacts that could occur as a result 
of the construction and operation of the proposed project under these 
general headings:
---------------------------------------------------------------------------

    \2\ ``We'', ``us'', and ``our'' refer to the environmental staff 
of the Office of Energy Projects (OEP).
---------------------------------------------------------------------------

     Geology and soils.
     Land use.
     Water resources, fisheries, and wetlands.
     Cultural resources.
     Vegetation and wildlife.
     Air quality and noise.
     Endangered and threatened species.
     Hazardous waste.
     Public safety.
    We will also evaluate reasonable alternatives to the proposed 
project or portions of the project, and make recommendations on how to 
lessen or avoid impacts on the various resource areas.
    Our independent analysis of the issues will be in the EA. Depending 
on the comments received during the scoping process, the EA may be 
published and mailed to federal, state, and local agencies, public 
interest groups, interested individuals, affected landowners, 
newspapers, libraries, and the Commission's official service list for 
this proceeding. A comment period will be allotted for review if the EA 
is published. We will consider all comments on the EA before we make 
our recommendations to the Commission.
    To ensure your comments are considered, please carefully follow the 
instructions in the public participation section below.

Currently Identified Environmental Issues

    We have already identified issues that we think deserve attention 
based on a preliminary review of the proposed facilities and the 
environmental information provided by Transco. This preliminary list of 
issues may be changed based on your comments and our analysis.
     The project may have air emissions and noise impacts.
     Safety of the storage field after abandonment.

Public Participation

    You can make a difference by providing us with your specific 
comments or concerns about the Hester Storage Field Abandonment 
Project. Your comments should focus on the potential environmental 
effects, reasonable alternatives, and measures to avoid or lessen 
environmental impacts. The more specific your comments, the more useful 
they will be. To ensure that your comments are timely and properly 
recorded, please send in your comments so that they will be received in 
Washington, DC on or before August 22, 2008.
    For your convenience, there are three methods which you can use to 
submit your comments to the Commission. In all instances please 
reference the project docket number CP08-207-000 with your submission. 
The docket number can be found on the front of this notice. The 
Commission encourages electronic filing of comments and has dedicated 
eFiling expert staff available to assist you at 202-502-8258 or 
efiling@ferc.gov.
    (1) You may file your comments electronically by using the Quick 
Comment feature, which is located on the Commission's internet Web site 
at https://www.ferc.gov under the link to Documents and Filings. A Quick 
Comment is an easy method for interested persons to submit text-only 
comments on a project;
    (2) You may file your comments electronically by using the eFiling 
feature, which is located on the Commission's internet Web site at 
https://www.ferc.gov under the link to Documents and Filings. eFiling 
involves preparing your submission in the same manner as you would if 
filing on paper, and then saving the file on your computer's hard 
drive. You will attach that file as your submission. New eFiling users 
must first create an account by clicking on ``Sign up'' or 
``eRegister.'' You will be asked to select the type of filing you are 
making. A comment on a particular project is considered a ``Comment on 
a Filing;'' or
    (3) You may file your comments via mail to the Commission by 
sending an original and two copies of your letter to: Kimberly D. Bose, 
Secretary, Federal Energy Regulatory Commission, 888 First St., NE., 
Room 1A, Washington, DC 20426.
    Label one copy of the comments for the attention of Gas Branch 3, 
PJ11.3.

Environmental Mailing List

    An effort is being made to send this notice to all individuals, 
organizations, and government entities interested in and/or potentially 
affected by the proposed project. This includes all landowners whose 
property may be used temporarily for project purposes, who have 
existing easements from the pipeline, or who own homes within distances 
defined in the Commission's regulations of certain aboveground 
facilities. By this notice we are also asking governmental agencies,

[[Page 44246]]

especially those in Appendix 2, to express their interest in becoming 
cooperating agencies for the preparation of the EA.
    If you do not want to send comments at this time but still want to 
remain on our mailing list, please return the Information Request 
(Appendix 3). If you do not return the Information Request, you will be 
taken off the mailing list.

Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want 
to become an official party to the proceeding known as an 
``intervenor.'' Intervenors play a more formal role in the process. 
Among other things, intervenors have the right to receive copies of 
case-related Commission documents and filings by other intervenors. 
Likewise, each intervenor must send one electronic copy (using the 
Commission's eFiling system) or 14 paper copies of its filings to the 
Secretary of the Commission and must send a copy of its filings to all 
other parties on the Commission's service list for this proceeding.
    If you want to become an intervenor you must file a motion to 
intervene according to Rule 214 of the Commission's Rules of Practice 
and Procedure (18 CFR 385.214). Only intervenors have the right to seek 
rehearing of the Commission's decision.
    The Notice of Application for this proposed project issued on May 
6, 2008 identified the date for the filing of interventions as May 28, 
2008. However, affected landowners and parties with environmental 
concerns may be granted late intervenor status upon showing good cause 
by stating that they have a clear and direct interest in this 
proceeding which would not be adequately represented by any other 
parties. You do not need intervenor status to have your environmental 
comments considered.

Availability of Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at 1-866-208-FERC or on the 
FERC Internet Web site (https://www.ferc.gov) using the eLibrary link. 
Click on the eLibrary link, click on ``General Search'' and enter the 
docket number excluding the last three digits in the Docket Number 
field. Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
FercOnlineSupport@ferc.gov or toll free at 1-866-208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission now offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries and direct links to 
the documents. Go to https://www.ferc.gov/esubscribenow.htm.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at https://www.ferc.gov/EventCalendar/
EventsList.aspx along with other related information.

Kimberly D. Bose,
Secretary.
[FR Doc. E8-17404 Filed 7-29-08; 8:45 am]