South Carolina Electric and Gas Company; Notice of Availability of Environmental Assessment, 43744 [E8-17170]
Download as PDF
43744
Federal Register / Vol. 73, No. 145 / Monday, July 28, 2008 / Notices
A copy of the draft EIS is available for
review in the Commission’s Public
Reference Branch, Room 2A, located at
888 First Street, NE., Washington, DC
20426. The final EIS also may be viewed
on the Commission’s Web site at
https://www.ferc.gov under the eLibrary
link. Enter the docket number excluding
the last three digits in the docket
number field to access the document.
For assistance, contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
e-mail of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
For further information, contact Blake
Condo at (202) 502–8914 or
blake.condo@ferc.gov.
Kimberly D. Bose,
Secretary.
[FR Doc. E8–17176 Filed 7–25–08; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Lighthouse’s development proposal.
The EA finds that approval of SCE&G’s
application would not constitute a
major federal action significantly
affecting the quality of the human
environment.
A copy of the EA is on file with the
Commission and is available for public
inspection. The EA may also be viewed
on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number (P–516) excluding the last three
digits in the docket number field to
access the document. For assistance,
contact FERC Online Support at
FERCOnlineSupport@ferc.gov,or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659.
Any comments should be filed by July
31, 2008, and should be addressed to
the Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE.,
Room 1–A, Washington, DC 20426.
Please reference the project name and
project number (P–2686) on all
comments. Comments may be filed
electronically via the Internet in lieu of
paper. The Commission strongly
encourages electronic filings. See18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under the
‘‘eFiling’’ link. For further information,
contact Brian Romanek at (202) 502–
6175.
Southeast Gas Storage, LLC; Notice of
Intent To Prepare an Environmental
Assessment for the Proposed Black
Warrior Storage Project and Request
for Comments on Environmental
Issues
would consist of new natural gas
pipeline, abandonment by removal of
existing pipeline, new existing
injection/withdrawal wells, new
gathering pipelines, a new salt water
disposal pipeline, conversion of existing
gas wells to observation wells, a new
salt water disposal well, a new
compressor station and a new meter
station. This EA will be used by the
Commission in its decision-making
process to determine whether the
project is in the public convenience and
necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the project.
Your input will help determine which
issues need to be evaluated in the EA.
Please note that the scoping period will
close on August 20, 2008. Details on
how to submit comments are provided
in the Public Participation section of
this notice.
If you are a landowner receiving this
notice, you may be contacted by a
pipeline company representative about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The pipeline
company would seek to negotiate a
mutually acceptable agreement.
However, if the project is approved by
the Commission, that approval conveys
with it the right of eminent domain.
Therefore, if easement negotiations fail
to produce an agreement, the pipeline
company could initiate condemnation
proceedings in accordance with state
law.
A fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ was attached to the project
notice Southwest provided to
landowners. This fact sheet addresses a
number of typically asked questions,
including the use of eminent domain
and how to participate in the
Commission’s proceedings. It is
available for viewing on the FERC
Internet Web site (www.ferc.gov).
July 21, 2008.
Summary of the Proposed Project
[Project No. 516–452]
South Carolina Electric and Gas
Company; Notice of Availability of
Environmental Assessment
Kimberly D. Bose,
Secretary.
[FR Doc. E8–17170 Filed 7–25–08; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
jlentini on PROD1PC65 with NOTICES
July 18, 2008.
In accordance with the National
Environmental Policy Act of 1969 and
the Federal Energy Regulatory
Commission’s regulations, 18 CFR part
380 (Order No. 486, 52 FR 47879), the
Office of Energy Projects has prepared
an environmental assessment (EA) for
an application filed by South Carolina
Electric and Gas Company (SCE&G)
(licensee) on January 17, 2008, for a
non-project use of project lands and
waters at the Saluda Hydroelectric
Project (FERC Project No.516).
Specifically, the licensee requests
authorization to issue a permit to
Lighthouse Developments, Inc.
(Lighthouse) to install a community
dock that would accommodate 84
watercraft, a boat launch ramp, and
parking lot. The proposed facilities
would provide boating access to the
project’s reservoir (Lake Murray) for
homeowners in a new residential
development known as Paradise Cove.
The EA evaluates the environmental
impacts that would likely result from
VerDate Aug<31>2005
18:35 Jul 25, 2008
Jkt 214001
Federal Energy Regulatory
Commission
[Docket No. CP08–418–000]
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Black Warrior Storage Project
involving construction and operation of
facilities by Southeast Gas Storage, LLC
(Southeast) in Monroe and Lowndes
Counties, Mississippi.1 These facilities
1 Southwest’s application was filed with the
Commission under section 7 of the Natural Gas Act
and Part 157 of the Commission’s regulations.
PO 00000
Frm 00070
Fmt 4703
Sfmt 4703
Southeast proposes to convert a
nearly depleted oil and gas reservoir
into a high-deliverability natural gas
storage facility approximately 3.5 miles
northwest of Caledonia in Monroe and
Lowndes Counties, Mississippi. The
purpose of this project is to provide 24.7
billion cubic feet of working gas
capacity to customers in the region.
Southeast would achieve this capacity
by drilling new withdrawal/injection
wells, converting, reworking or plugging
existing wells, constructing lateral and
E:\FR\FM\28JYN1.SGM
28JYN1
Agencies
[Federal Register Volume 73, Number 145 (Monday, July 28, 2008)]
[Notices]
[Page 43744]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-17170]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 516-452]
South Carolina Electric and Gas Company; Notice of Availability
of Environmental Assessment
July 18, 2008.
In accordance with the National Environmental Policy Act of 1969
and the Federal Energy Regulatory Commission's regulations, 18 CFR part
380 (Order No. 486, 52 FR 47879), the Office of Energy Projects has
prepared an environmental assessment (EA) for an application filed by
South Carolina Electric and Gas Company (SCE&G) (licensee) on January
17, 2008, for a non-project use of project lands and waters at the
Saluda Hydroelectric Project (FERC Project No.516). Specifically, the
licensee requests authorization to issue a permit to Lighthouse
Developments, Inc. (Lighthouse) to install a community dock that would
accommodate 84 watercraft, a boat launch ramp, and parking lot. The
proposed facilities would provide boating access to the project's
reservoir (Lake Murray) for homeowners in a new residential development
known as Paradise Cove. The EA evaluates the environmental impacts that
would likely result from Lighthouse's development proposal. The EA
finds that approval of SCE&G's application would not constitute a major
federal action significantly affecting the quality of the human
environment.
A copy of the EA is on file with the Commission and is available
for public inspection. The EA may also be viewed on the Commission's
Web site at https://www.ferc.gov using the ``eLibrary'' link. Enter the
docket number (P-516) excluding the last three digits in the docket
number field to access the document. For assistance, contact FERC
Online Support at FERCOnlineSupport@ferc.gov,or toll-free at 1-866-208-
3676, or for TTY, (202) 502-8659.
Any comments should be filed by July 31, 2008, and should be
addressed to the Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Room 1-A, Washington, DC 20426. Please reference the
project name and project number (P-2686) on all comments. Comments may
be filed electronically via the Internet in lieu of paper. The
Commission strongly encourages electronic filings. See18 CFR
385.2001(a)(1)(iii) and the instructions on the Commission's Web site
under the ``eFiling'' link. For further information, contact Brian
Romanek at (202) 502-6175.
Kimberly D. Bose,
Secretary.
[FR Doc. E8-17170 Filed 7-25-08; 8:45 am]
BILLING CODE 6717-01-P