Public Service Company of Colorado; Notice of Application Tendered for Filing With the Commission and Establishing Procedural Schedule for Licensing and Deadline for Submission of Final Amendments, 40558-40559 [E8-16047]

Download as PDF 40558 Federal Register / Vol. 73, No. 136 / Tuesday, July 15, 2008 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. P–400–051] Public Service Company of Colorado; Notice of Application Tendered for Filing With the Commission and Establishing Procedural Schedule for Licensing and Deadline for Submission of Final Amendments July 8, 2008. Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: New Major License. b. Project No.: P–400–051. c. Date Filed: June 26, 2008. d. Applicant: Public Service Company of Colorado. e. Name of Project: Ames Hydroelectric Project. f. Location: The existing project is located on Lake Fork, Howard Fork, and South Fork of the San Miguel River, in San Miguel County, about 6 miles north of Telluride, Colorado. The Ames Project occupies 99 acres of the Uncompahgre National Forest. g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)–825(r) h. Applicant Contact: Randy Rhodes, Public Service Company of Colorado, 4653 Table Mountain Drive, Golden Colorado 80403; telephone (720) 497– 2123. i. FERC Contact: David Turner (202) 502–6091 or via e-mail at david.turner@ferc.gov. j. This application is not ready for environmental analysis at this time. k. Project Description: The existing project uses water that originates in two separate subbasins (Lake Fork and Howard’s Fork) of the South Fork San Miguel River. The existing project, from upstream to downstream along Lake Fork and Howard’s Fork, respectively, consists of the following: (1) A 44-acre reservoir (Hope Lake) that has 2,000 acre-feet of active storage capacity at a normal maximum water surface elevation of 11,910 feet; (2) a 150-footlong, 20-foot high rock-filled, timber dam (Hope Lake dam), with a 816-footlong, 5-foot-wide, and 6-foot-high rock tunnel that releases water from Hope Lake to Lake Fork Creek; (3) a 138-acre reservoir (Trout Lake) with 2,500 acrefeet of active storage capacity at a normal maximum water surface elevation of 9,700 feet; (4) a 570-footlong, 30-foot-high earth-filled dam (Trout Lake dam) with a 42-inchdiameter, concrete encased steel pipe outlet that extends through the embankment; (5) a 12,650-foot-long, 42inch to 26-inch-diameter steel pipe penstock that conveys water from Trout Lake to the Ames powerhouse; (6) a 260foot-long, 6-foot-high earth-filled and timber crib diversion dam on the Howards Fork, with a concrete inlet structure, which diverts water from a sluiceway constructed through the embankment via a manually-operated 9foot-wide steel slide gate at the downstream end of the sluiceway; (7) a 4,500-foot-long, 36-inch-diameter welded steel penstock; (8) a 2,000-footlong, 18-inch-diameter steel penstock; (9) the 44-foot-long, 54-foot-wide, stone masonry Ames powerhouse that contains one 3.6 megawatt (MW) generating unit; and (10) appurtenant facilities. The project is operated both as a base-load plant and a peaking plant depending on the time of the year; the applicant does not propose any changes to project operations. The applicant is proposing new recreation facilities at Trout Lake, along with additions and deletions to the project boundary due to new land surveys and easements l. Locations of the Application: A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov or tollfree at (866) 208–3676, or for TTY, (202) 502–8659. A copy is also available for inspection and reproduction at the address in item (h) above. m. You may also register online at https://www.ferc.gov/esubscribenow.htm to be notified via e-mail of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. n. Procedural Schedule: The application will be processed according to the following Hydro Licensing Schedule. Revisions to the schedule may be made as appropriate. For example, issuance of the Ready for Environmental Analysis Notice is based on the assumption that there will be no additional information. Date Application Deficiency Determination Letter and Issuance of Additional Information Requests (AIRs) .......................................... Notice of Acceptance/Notice of Ready for Environmental Analysis ................................................................................................ Filing of Interventions, Recommendations, Terms and Conditions, and Fishway Prescriptions ..................................................... Reply Comments Due ...................................................................................................................................................................... Issuance of Draft EA ........................................................................................................................................................................ Comments on Draft EA Due ............................................................................................................................................................. Filing of Modified Terms and Conditions .......................................................................................................................................... Issuance of Final EA ........................................................................................................................................................................ mstockstill on PROD1PC66 with NOTICES Milestone July 2008. August 2008. October 2008. December 2008. January 2009. February 2009. April 2009. July 2009. VerDate Aug<31>2005 15:01 Jul 14, 2008 Jkt 214001 PO 00000 Frm 00080 Fmt 4703 Sfmt 4703 E:\FR\FM\15JYN1.SGM 15JYN1 Federal Register / Vol. 73, No. 136 / Tuesday, July 15, 2008 / Notices o. Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis. Kimberly D. Bose, Secretary. [FR Doc. E8–16047 Filed 7–14–08; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. P–12589–001] Public Service Company of Colorado; Notice of Application Tendered for Filing With the Commission and Establishing Procedural Schedule for Licensing and Deadline for Submission of Final Amendments July 8, 2008. Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: New Major License. b. Project No.: P–12589–001. c. Date Filed: June 25, 2008. d. Applicant: Public Service Company of Colorado. e. Name of Project: Tacoma Hydroelectric Project. f. Location: The existing project is located on Cascade Creek, Little Cascade Creek and Elbert Creek in La Plata and San Juan Counties, Colorado. The Tacoma Project occupies 221 acres of the San Juan National Forest. g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Randy Rhodes, Public Service Company of Colorado, 4653 Table Mountain Drive, Golden Colorado 80403; telephone (720) 497– 2123. i. FERC Contact: David Turner (202) 502–6091 or via e-mail at david.turner@ferc.gov. j. This application is not ready for environmental analysis at this time. k. Project Description: The existing project consists of the following: (1) A 30-foot-long, 10-foot-high concrete diversion dam on Cascade Creek; (2) a 4,200-foot-long, 10-foot-diameter, semicircular, elevated wooden flume; (3) a 1,400-foot-long, 60-inch-diameter steel inverted siphon; (4) a 14,500-foot-long, 64-inch-diameter steel pipeline; (5) the open channel of Little Cascade Creek; (6) a 0.5-mile-long, 5-foot-deep lake (Columbine Lake) formed by a small, partially breached timber dam on Little Cascade Creek; (7) the open channel of Little Cascade Creek downstream of Columbine Lake; (8) the 4-acre Aspaas Lake; (9) a 274-foot-long, 27-foot-high, earth-filled Aspaas dam; (10) a 14-footwide, rock-cut open diversion channel that diverts flow from Aspaas Lake to Electra Lake; (11) the 800-acre Electra Lake; (12) a 140-foot-long, 20-foot-high, rock-filled, timber crib dam (Stagecoach dam) serving as the spillway for Electra Lake; (13) a 1,270-foot-long, 62-foothigh, rock-filled dam (Terminal dam), with an impermeable asphalt membrane on the upstream face and an asphaltpaved crest; (14) a 429-foot-long, 54inch-diameter steel pipe intake under the Terminal dam that leads project flows from Electra Lake to a valve vault; (15) the valve vault; (16) a 9,590-footlong, 66-inch-diameter welded steel penstock, with a 12-foot-diameter, 116foot-high surge tank; (17) a bifurcated penstock structure that diverts flow to a 2,050-foot-long, 30-inch-diameter welded steel penstock that enters the powerhouse and a 2,050-foot-long, 54inch diameter welded steel penstock that branches to a 46-inch diameter pipe immediately prior to entering the power house; (18) a 108-foot-long, 64-footwide, steel frame, brick powerhouse 40559 containing three generating units with a total installed capacity of 8 megawatts (MW); (19) a 44 kV substation adjacent to the powerhouse; and (20) appurtenant facilities. The project is operated both as a base-load plant and a peaking plant depending on the time of the year. The applicant proposes the following changes to project facilities: (1) project boundary modifications to reflect lands needed for project operations; (2) rehabilitation and addition of the 6-foot-high Canyon Creek diversion to supply potable water, emergency cooling water, and fire protection; (3) the addition of 4 MW turbine-generator (Unit 4); and (4) several recreation and environmental measures. l. Locations of the Application: A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov or tollfree at (866) 208–3676, or for TTY, (202) 502–8659. A copy is also available for inspection and reproduction at the address in item (h) above. m. You may also register online at https://www.ferc.gov/esubscribenow.htm to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. n. Procedural Schedule: The application will be processed according to the following Hydro Licensing Schedule. Revisions to the schedule may be made as appropriate. For example, issuance of the Ready for Environmental Analysis Notice is based on the assumption that there will be no additional information. Date Application Deficiency Determination Letter and Issuance of Additional Information Requests (AIRs) .......................................... Notice of Acceptance/Notice of Ready for Environmental Analysis ................................................................................................ Filing of Interventions, Recommendations, Terms and Conditions, and Fishway Prescriptions ..................................................... Reply Comments Due ...................................................................................................................................................................... Issuance of Draft EA ........................................................................................................................................................................ Comments on Draft EA Due ............................................................................................................................................................. Filing of Modified Terms and Conditions .......................................................................................................................................... Issuance of Final EA ........................................................................................................................................................................ mstockstill on PROD1PC66 with NOTICES Milestone July 2008. August 2008. October 2008. December 2008. January 2009. February 2009. April 2009. July 2009. VerDate Aug<31>2005 15:01 Jul 14, 2008 Jkt 214001 PO 00000 Frm 00081 Fmt 4703 Sfmt 4703 E:\FR\FM\15JYN1.SGM 15JYN1

Agencies

[Federal Register Volume 73, Number 136 (Tuesday, July 15, 2008)]
[Notices]
[Pages 40558-40559]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-16047]



[[Page 40558]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

 [Project No. P-400-051]


Public Service Company of Colorado; Notice of Application 
Tendered for Filing With the Commission and Establishing Procedural 
Schedule for Licensing and Deadline for Submission of Final Amendments

July 8, 2008.
    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: New Major License.
    b. Project No.: P-400-051.
    c. Date Filed: June 26, 2008.
    d. Applicant: Public Service Company of Colorado.
    e. Name of Project: Ames Hydroelectric Project.
    f. Location: The existing project is located on Lake Fork, Howard 
Fork, and South Fork of the San Miguel River, in San Miguel County, 
about 6 miles north of Telluride, Colorado. The Ames Project occupies 
99 acres of the Uncompahgre National Forest.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r)
    h. Applicant Contact: Randy Rhodes, Public Service Company of 
Colorado, 4653 Table Mountain Drive, Golden Colorado 80403; telephone 
(720) 497-2123.
    i. FERC Contact: David Turner (202) 502-6091 or via e-mail at 
david.turner@ferc.gov.
    j. This application is not ready for environmental analysis at this 
time.
    k. Project Description: The existing project uses water that 
originates in two separate subbasins (Lake Fork and Howard's Fork) of 
the South Fork San Miguel River. The existing project, from upstream to 
downstream along Lake Fork and Howard's Fork, respectively, consists of 
the following: (1) A 44-acre reservoir (Hope Lake) that has 2,000 acre-
feet of active storage capacity at a normal maximum water surface 
elevation of 11,910 feet; (2) a 150-foot-long, 20-foot high rock-
filled, timber dam (Hope Lake dam), with a 816-foot-long, 5-foot-wide, 
and 6-foot-high rock tunnel that releases water from Hope Lake to Lake 
Fork Creek; (3) a 138-acre reservoir (Trout Lake) with 2,500 acre-feet 
of active storage capacity at a normal maximum water surface elevation 
of 9,700 feet; (4) a 570-foot-long, 30-foot-high earth-filled dam 
(Trout Lake dam) with a 42-inch-diameter, concrete encased steel pipe 
outlet that extends through the embankment; (5) a 12,650-foot-long, 42-
inch to 26-inch-diameter steel pipe penstock that conveys water from 
Trout Lake to the Ames powerhouse; (6) a 260-foot-long, 6-foot-high 
earth-filled and timber crib diversion dam on the Howards Fork, with a 
concrete inlet structure, which diverts water from a sluiceway 
constructed through the embankment via a manually-operated 9-foot-wide 
steel slide gate at the downstream end of the sluiceway; (7) a 4,500-
foot-long, 36-inch-diameter welded steel penstock; (8) a 2,000-foot-
long, 18-inch-diameter steel penstock; (9) the 44-foot-long, 54-foot-
wide, stone masonry Ames powerhouse that contains one 3.6 megawatt (MW) 
generating unit; and (10) appurtenant facilities. The project is 
operated both as a base-load plant and a peaking plant depending on the 
time of the year; the applicant does not propose any changes to project 
operations. The applicant is proposing new recreation facilities at 
Trout Lake, along with additions and deletions to the project boundary 
due to new land surveys and easements
    l. Locations of the Application: A copy of the application is 
available for review at the Commission in the Public Reference Room or 
may be viewed on the Commission's Web site at https://www.ferc.gov using 
the ``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. For 
assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov 
or toll-free at (866) 208-3676, or for TTY, (202) 502-8659. A copy is 
also available for inspection and reproduction at the address in item 
(h) above.
    m. You may also register online at https://www.ferc.gov/
esubscribenow.htm to be notified via e-mail of new filings and 
issuances related to this or other pending projects. For assistance, 
contact FERC Online Support.
    n. Procedural Schedule: The application will be processed according 
to the following Hydro Licensing Schedule. Revisions to the schedule 
may be made as appropriate. For example, issuance of the Ready for 
Environmental Analysis Notice is based on the assumption that there 
will be no additional information.

------------------------------------------------------------------------
                Milestone                              Date
------------------------------------------------------------------------
Application Deficiency Determination      July 2008.
 Letter and Issuance of Additional
 Information Requests (AIRs).
Notice of Acceptance/Notice of Ready for  August 2008.
 Environmental Analysis.
Filing of Interventions,                  October 2008.
 Recommendations, Terms and Conditions,
 and Fishway Prescriptions.
Reply Comments Due......................  December 2008.
Issuance of Draft EA....................  January 2009.
Comments on Draft EA Due................  February 2009.
Filing of Modified Terms and Conditions.  April 2009.
Issuance of Final EA....................  July 2009.
------------------------------------------------------------------------


[[Page 40559]]

    o. Final amendments to the application must be filed with the 
Commission no later than 30 days from the issuance date of the notice 
of ready for environmental analysis.

Kimberly D. Bose,
Secretary.
[FR Doc. E8-16047 Filed 7-14-08; 8:45 am]
BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.