Public Service Company of Colorado; Notice of Application Tendered for Filing With the Commission and Establishing Procedural Schedule for Licensing and Deadline for Submission of Final Amendments, 40558-40559 [E8-16047]
Download as PDF
40558
Federal Register / Vol. 73, No. 136 / Tuesday, July 15, 2008 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. P–400–051]
Public Service Company of Colorado;
Notice of Application Tendered for
Filing With the Commission and
Establishing Procedural Schedule for
Licensing and Deadline for
Submission of Final Amendments
July 8, 2008.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: P–400–051.
c. Date Filed: June 26, 2008.
d. Applicant: Public Service Company
of Colorado.
e. Name of Project: Ames
Hydroelectric Project.
f. Location: The existing project is
located on Lake Fork, Howard Fork, and
South Fork of the San Miguel River, in
San Miguel County, about 6 miles north
of Telluride, Colorado. The Ames
Project occupies 99 acres of the
Uncompahgre National Forest.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r)
h. Applicant Contact: Randy Rhodes,
Public Service Company of Colorado,
4653 Table Mountain Drive, Golden
Colorado 80403; telephone (720) 497–
2123.
i. FERC Contact: David Turner (202)
502–6091 or via e-mail at
david.turner@ferc.gov.
j. This application is not ready for
environmental analysis at this time.
k. Project Description: The existing
project uses water that originates in two
separate subbasins (Lake Fork and
Howard’s Fork) of the South Fork San
Miguel River. The existing project, from
upstream to downstream along Lake
Fork and Howard’s Fork, respectively,
consists of the following: (1) A 44-acre
reservoir (Hope Lake) that has 2,000
acre-feet of active storage capacity at a
normal maximum water surface
elevation of 11,910 feet; (2) a 150-footlong, 20-foot high rock-filled, timber
dam (Hope Lake dam), with a 816-footlong, 5-foot-wide, and 6-foot-high rock
tunnel that releases water from Hope
Lake to Lake Fork Creek; (3) a 138-acre
reservoir (Trout Lake) with 2,500 acrefeet of active storage capacity at a
normal maximum water surface
elevation of 9,700 feet; (4) a 570-footlong, 30-foot-high earth-filled dam
(Trout Lake dam) with a 42-inchdiameter, concrete encased steel pipe
outlet that extends through the
embankment; (5) a 12,650-foot-long, 42inch to 26-inch-diameter steel pipe
penstock that conveys water from Trout
Lake to the Ames powerhouse; (6) a 260foot-long, 6-foot-high earth-filled and
timber crib diversion dam on the
Howards Fork, with a concrete inlet
structure, which diverts water from a
sluiceway constructed through the
embankment via a manually-operated 9foot-wide steel slide gate at the
downstream end of the sluiceway; (7) a
4,500-foot-long, 36-inch-diameter
welded steel penstock; (8) a 2,000-footlong, 18-inch-diameter steel penstock;
(9) the 44-foot-long, 54-foot-wide, stone
masonry Ames powerhouse that
contains one 3.6 megawatt (MW)
generating unit; and (10) appurtenant
facilities. The project is operated both as
a base-load plant and a peaking plant
depending on the time of the year; the
applicant does not propose any changes
to project operations. The applicant is
proposing new recreation facilities at
Trout Lake, along with additions and
deletions to the project boundary due to
new land surveys and easements
l. Locations of the Application: A
copy of the application is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s Web site at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or tollfree at (866) 208–3676, or for TTY, (202)
502–8659. A copy is also available for
inspection and reproduction at the
address in item (h) above.
m. You may also register online at
https://www.ferc.gov/esubscribenow.htm
to be notified via e-mail of new filings
and issuances related to this or other
pending projects. For assistance, contact
FERC Online Support.
n. Procedural Schedule: The
application will be processed according
to the following Hydro Licensing
Schedule. Revisions to the schedule
may be made as appropriate. For
example, issuance of the Ready for
Environmental Analysis Notice is based
on the assumption that there will be no
additional information.
Date
Application Deficiency Determination Letter and Issuance of Additional Information Requests (AIRs) ..........................................
Notice of Acceptance/Notice of Ready for Environmental Analysis ................................................................................................
Filing of Interventions, Recommendations, Terms and Conditions, and Fishway Prescriptions .....................................................
Reply Comments Due ......................................................................................................................................................................
Issuance of Draft EA ........................................................................................................................................................................
Comments on Draft EA Due .............................................................................................................................................................
Filing of Modified Terms and Conditions ..........................................................................................................................................
Issuance of Final EA ........................................................................................................................................................................
mstockstill on PROD1PC66 with NOTICES
Milestone
July 2008.
August 2008.
October 2008.
December 2008.
January 2009.
February 2009.
April 2009.
July 2009.
VerDate Aug<31>2005
15:01 Jul 14, 2008
Jkt 214001
PO 00000
Frm 00080
Fmt 4703
Sfmt 4703
E:\FR\FM\15JYN1.SGM
15JYN1
Federal Register / Vol. 73, No. 136 / Tuesday, July 15, 2008 / Notices
o. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
Kimberly D. Bose,
Secretary.
[FR Doc. E8–16047 Filed 7–14–08; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. P–12589–001]
Public Service Company of Colorado;
Notice of Application Tendered for
Filing With the Commission and
Establishing Procedural Schedule for
Licensing and Deadline for
Submission of Final Amendments
July 8, 2008.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: P–12589–001.
c. Date Filed: June 25, 2008.
d. Applicant: Public Service Company
of Colorado.
e. Name of Project: Tacoma
Hydroelectric Project.
f. Location: The existing project is
located on Cascade Creek, Little Cascade
Creek and Elbert Creek in La Plata and
San Juan Counties, Colorado. The
Tacoma Project occupies 221 acres of
the San Juan National Forest.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Randy Rhodes,
Public Service Company of Colorado,
4653 Table Mountain Drive, Golden
Colorado 80403; telephone (720) 497–
2123.
i. FERC Contact: David Turner (202)
502–6091 or via e-mail at
david.turner@ferc.gov.
j. This application is not ready for
environmental analysis at this time.
k. Project Description: The existing
project consists of the following: (1) A
30-foot-long, 10-foot-high concrete
diversion dam on Cascade Creek; (2) a
4,200-foot-long, 10-foot-diameter, semicircular, elevated wooden flume; (3) a
1,400-foot-long, 60-inch-diameter steel
inverted siphon; (4) a 14,500-foot-long,
64-inch-diameter steel pipeline; (5) the
open channel of Little Cascade Creek;
(6) a 0.5-mile-long, 5-foot-deep lake
(Columbine Lake) formed by a small,
partially breached timber dam on Little
Cascade Creek; (7) the open channel of
Little Cascade Creek downstream of
Columbine Lake; (8) the 4-acre Aspaas
Lake; (9) a 274-foot-long, 27-foot-high,
earth-filled Aspaas dam; (10) a 14-footwide, rock-cut open diversion channel
that diverts flow from Aspaas Lake to
Electra Lake; (11) the 800-acre Electra
Lake; (12) a 140-foot-long, 20-foot-high,
rock-filled, timber crib dam (Stagecoach
dam) serving as the spillway for Electra
Lake; (13) a 1,270-foot-long, 62-foothigh, rock-filled dam (Terminal dam),
with an impermeable asphalt membrane
on the upstream face and an asphaltpaved crest; (14) a 429-foot-long, 54inch-diameter steel pipe intake under
the Terminal dam that leads project
flows from Electra Lake to a valve vault;
(15) the valve vault; (16) a 9,590-footlong, 66-inch-diameter welded steel
penstock, with a 12-foot-diameter, 116foot-high surge tank; (17) a bifurcated
penstock structure that diverts flow to a
2,050-foot-long, 30-inch-diameter
welded steel penstock that enters the
powerhouse and a 2,050-foot-long, 54inch diameter welded steel penstock
that branches to a 46-inch diameter pipe
immediately prior to entering the power
house; (18) a 108-foot-long, 64-footwide, steel frame, brick powerhouse
40559
containing three generating units with a
total installed capacity of 8 megawatts
(MW); (19) a 44 kV substation adjacent
to the powerhouse; and (20)
appurtenant facilities. The project is
operated both as a base-load plant and
a peaking plant depending on the time
of the year. The applicant proposes the
following changes to project facilities:
(1) project boundary modifications to
reflect lands needed for project
operations; (2) rehabilitation and
addition of the 6-foot-high Canyon
Creek diversion to supply potable water,
emergency cooling water, and fire
protection; (3) the addition of 4 MW
turbine-generator (Unit 4); and (4)
several recreation and environmental
measures.
l. Locations of the Application: A
copy of the application is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s Web site at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or tollfree at (866) 208–3676, or for TTY, (202)
502–8659. A copy is also available for
inspection and reproduction at the
address in item (h) above.
m. You may also register online at
https://www.ferc.gov/esubscribenow.htm
to be notified via email of new filings
and issuances related to this or other
pending projects. For assistance, contact
FERC Online Support.
n. Procedural Schedule: The
application will be processed according
to the following Hydro Licensing
Schedule. Revisions to the schedule
may be made as appropriate. For
example, issuance of the Ready for
Environmental Analysis Notice is based
on the assumption that there will be no
additional information.
Date
Application Deficiency Determination Letter and Issuance of Additional Information Requests (AIRs) ..........................................
Notice of Acceptance/Notice of Ready for Environmental Analysis ................................................................................................
Filing of Interventions, Recommendations, Terms and Conditions, and Fishway Prescriptions .....................................................
Reply Comments Due ......................................................................................................................................................................
Issuance of Draft EA ........................................................................................................................................................................
Comments on Draft EA Due .............................................................................................................................................................
Filing of Modified Terms and Conditions ..........................................................................................................................................
Issuance of Final EA ........................................................................................................................................................................
mstockstill on PROD1PC66 with NOTICES
Milestone
July 2008.
August 2008.
October 2008.
December 2008.
January 2009.
February 2009.
April 2009.
July 2009.
VerDate Aug<31>2005
15:01 Jul 14, 2008
Jkt 214001
PO 00000
Frm 00081
Fmt 4703
Sfmt 4703
E:\FR\FM\15JYN1.SGM
15JYN1
Agencies
[Federal Register Volume 73, Number 136 (Tuesday, July 15, 2008)]
[Notices]
[Pages 40558-40559]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-16047]
[[Page 40558]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. P-400-051]
Public Service Company of Colorado; Notice of Application
Tendered for Filing With the Commission and Establishing Procedural
Schedule for Licensing and Deadline for Submission of Final Amendments
July 8, 2008.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
b. Project No.: P-400-051.
c. Date Filed: June 26, 2008.
d. Applicant: Public Service Company of Colorado.
e. Name of Project: Ames Hydroelectric Project.
f. Location: The existing project is located on Lake Fork, Howard
Fork, and South Fork of the San Miguel River, in San Miguel County,
about 6 miles north of Telluride, Colorado. The Ames Project occupies
99 acres of the Uncompahgre National Forest.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r)
h. Applicant Contact: Randy Rhodes, Public Service Company of
Colorado, 4653 Table Mountain Drive, Golden Colorado 80403; telephone
(720) 497-2123.
i. FERC Contact: David Turner (202) 502-6091 or via e-mail at
david.turner@ferc.gov.
j. This application is not ready for environmental analysis at this
time.
k. Project Description: The existing project uses water that
originates in two separate subbasins (Lake Fork and Howard's Fork) of
the South Fork San Miguel River. The existing project, from upstream to
downstream along Lake Fork and Howard's Fork, respectively, consists of
the following: (1) A 44-acre reservoir (Hope Lake) that has 2,000 acre-
feet of active storage capacity at a normal maximum water surface
elevation of 11,910 feet; (2) a 150-foot-long, 20-foot high rock-
filled, timber dam (Hope Lake dam), with a 816-foot-long, 5-foot-wide,
and 6-foot-high rock tunnel that releases water from Hope Lake to Lake
Fork Creek; (3) a 138-acre reservoir (Trout Lake) with 2,500 acre-feet
of active storage capacity at a normal maximum water surface elevation
of 9,700 feet; (4) a 570-foot-long, 30-foot-high earth-filled dam
(Trout Lake dam) with a 42-inch-diameter, concrete encased steel pipe
outlet that extends through the embankment; (5) a 12,650-foot-long, 42-
inch to 26-inch-diameter steel pipe penstock that conveys water from
Trout Lake to the Ames powerhouse; (6) a 260-foot-long, 6-foot-high
earth-filled and timber crib diversion dam on the Howards Fork, with a
concrete inlet structure, which diverts water from a sluiceway
constructed through the embankment via a manually-operated 9-foot-wide
steel slide gate at the downstream end of the sluiceway; (7) a 4,500-
foot-long, 36-inch-diameter welded steel penstock; (8) a 2,000-foot-
long, 18-inch-diameter steel penstock; (9) the 44-foot-long, 54-foot-
wide, stone masonry Ames powerhouse that contains one 3.6 megawatt (MW)
generating unit; and (10) appurtenant facilities. The project is
operated both as a base-load plant and a peaking plant depending on the
time of the year; the applicant does not propose any changes to project
operations. The applicant is proposing new recreation facilities at
Trout Lake, along with additions and deletions to the project boundary
due to new land surveys and easements
l. Locations of the Application: A copy of the application is
available for review at the Commission in the Public Reference Room or
may be viewed on the Commission's Web site at https://www.ferc.gov using
the ``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. For
assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov
or toll-free at (866) 208-3676, or for TTY, (202) 502-8659. A copy is
also available for inspection and reproduction at the address in item
(h) above.
m. You may also register online at https://www.ferc.gov/
esubscribenow.htm to be notified via e-mail of new filings and
issuances related to this or other pending projects. For assistance,
contact FERC Online Support.
n. Procedural Schedule: The application will be processed according
to the following Hydro Licensing Schedule. Revisions to the schedule
may be made as appropriate. For example, issuance of the Ready for
Environmental Analysis Notice is based on the assumption that there
will be no additional information.
------------------------------------------------------------------------
Milestone Date
------------------------------------------------------------------------
Application Deficiency Determination July 2008.
Letter and Issuance of Additional
Information Requests (AIRs).
Notice of Acceptance/Notice of Ready for August 2008.
Environmental Analysis.
Filing of Interventions, October 2008.
Recommendations, Terms and Conditions,
and Fishway Prescriptions.
Reply Comments Due...................... December 2008.
Issuance of Draft EA.................... January 2009.
Comments on Draft EA Due................ February 2009.
Filing of Modified Terms and Conditions. April 2009.
Issuance of Final EA.................... July 2009.
------------------------------------------------------------------------
[[Page 40559]]
o. Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Kimberly D. Bose,
Secretary.
[FR Doc. E8-16047 Filed 7-14-08; 8:45 am]
BILLING CODE 6717-01-P