Commission Information Collection Activities, Proposed Collection; Comment Request; Submitted for OMB Review, 34280-34281 [E8-13533]

Download as PDF 34280 Federal Register / Vol. 73, No. 117 / Tuesday, June 17, 2008 / Notices Electronic Access to This Document: You can view this document, as well as all other documents of this Department published in the Federal Register, in text or Adobe Portable Document Format (PDF) on the Internet at the following site: https://www.ed.gov/news/ fedregister. To use PDF you must have Adobe Acrobat Reader, which is available free at this site. If you have questions about using PDF, call the U.S. Government Printing Office (GPO), toll free, at 1– 888–293–6498; or in the Washington, DC, area at (202) 512–1530. Note: The official version of this document is the document published in the Federal Register. Free Internet access to the official edition of the Federal Register and the Code of Federal Regulations is available on GPO Access at: https://www.gpoaccess.gov/nara/ index.html. Dated: June 12, 2008. Tracy R. Justesen, Assistant Secretary for Special Education and Rehabilitative Services. [FR Doc. E8–13645 Filed 6–16–08; 8:45 am] BILLING CODE 4000–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. IC08–512–001, FERC–512] Commission Information Collection Activities, Proposed Collection; Comment Request; Submitted for OMB Review June 10, 2008. Federal Energy Regulatory Commission. ACTION: Notice. AGENCY: SUMMARY: In compliance with the requirements of section 3507 of the Paperwork Reduction Act of 1995, 44 U.S.C. 3507, the Federal Energy Regulatory Commission (Commission) has submitted the information collection described below to the Office of Management and Budget (OMB) for review of this information collection requirement. Any interested person may file comments directly with OMB and should address a copy of those comments to the Commission as explained below. The Commission received no comments in response to an earlier Federal Register notice of March 13, 2008 (73 FR 13536–13537), and has made this notation in its submission to OMB. DATES: Comments on the collection of information are due by July 10, 2008. ADDRESSES: Address comments on the collection of information to the Office of Management and Budget, Office of Information and Regulatory Affairs, Attention: Federal Energy Regulatory Commission Desk Officer. Comments to OMB should be filed electronically, c/o oiralsubmission@omb.eop.gov and include the OMB Control No. (1902– 0073) as a point of reference. The Desk Officer may be reached by telephone at 202–395–7345. A copy of the comments should also be sent to the Federal Energy Regulatory Commission, Office of the Executive Director, ED–34, Attention: Michael Miller, 888 First Street, NE., Washington, DC 20426. Comments may be filed either in paper format or electronically. Those persons filing electronically do not need to make a paper filing. For paper filings, such comments should be submitted to the Secretary of the Commission, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426 and should refer to Docket No. IC08– 512–001. Documents filed electronically via the Internet must be prepared in an acceptable filing format and in compliance with the Federal Energy Regulatory Commission submission guidelines. Complete filing instructions and acceptable filing formats are available at (https://www.ferc.gov/help/ submission-guide/electronic-media.asp). To file the document electronically, access the Commission’s Web site and click on Documents & Filing, E-Filing (https://www.ferc.gov/docs-filing/ efiling.asp), and then follow the instructions for each screen. First time users will have to establish a user name and password. The Commission will send an automatic acknowledgement to the sender’s e-mail address upon receipt of comments. All comments may be viewed, printed or downloaded remotely via the Internet through FERC’s homepage using the ‘‘eLibrary’’ link. For user assistance, contact fercolinesupport@ferc.gov or toll-free at (866) 208–3676 or for TTY, contact (202) 502–8659. FOR FURTHER INFORMATION CONTACT: Michael Miller may be reached by telephone at (202) 502–8415, by fax at (202) 273–0873, and by e-mail at michael.miller@ferc.gov. SUPPLEMENTARY INFORMATION: Abstract: The information collected under the requirements of FERC–512, ‘‘Application for Preliminary Permit’’ (OMB No. 1902–0073) is used by the Commission to implement the statutory provisions of sections 4(f), 5 and 7 of the Federal Power Act (FPA), 16 U.S.C. sections 797, 798 & 800. The purpose of obtaining a preliminary permit is to maintain priority of the application for a license for a hydropower facility while the applicant conducts surveys to prepare maps, plans, specifications and estimates; conducts engineering, economic and environmental feasibility studies; and making financial arrangements. The conditions under which the priority will be maintained are set forth in each permit. During the term of the permit, no other application for a preliminary permit or application for a license submitted by another party can be accepted. The term of the permit is three years. The information collected under the designation FERC–512 is in the form of a written application for a preliminary permit which is used by Commission staff to determine an applicant’s qualifications to hold a preliminary permit, review the proposed hydro development for feasibility and to issue a notice of the application in order to solicit public and agency comments. The Commission implements these mandatory filing requirements in the Code of Federal Regulations (CFR) under 18 CFR 4.31– 33, 4.81–.83. Action: The Commission is requesting a three-year extension of the current expiration date, with no changes to the existing collection of data. Burden Statement: Public reporting burden for this collection is estimated as: Annual responses per respondent Average burden hours per response Total annual burden hours (1) jlentini on PROD1PC65 with NOTICES No. of respondents (2) (3) (1) × (2) × (3) 200 1 37 7,400 VerDate Aug<31>2005 17:02 Jun 16, 2008 Jkt 214001 PO 00000 Frm 00035 Fmt 4703 Sfmt 4703 E:\FR\FM\17JNN1.SGM 17JNN1 Federal Register / Vol. 73, No. 117 / Tuesday, June 17, 2008 / Notices jlentini on PROD1PC65 with NOTICES Estimated cost burden to respondents is $508,000; (i.e., 7 hours @$200 an hour (legal) + 30 hours @$39 an hour (technical) × 200) per year equals $514,000). The reporting burden includes the total time, effort, or financial resources expended to generate, maintain, retain, or disclose or provide the information including: (1) Reviewing instructions; (2) developing, acquiring, installing, and utilizing technology and systems for the purposes of collecting, validating, verifying, processing, maintaining, disclosing and providing information; (3) adjusting the existing ways to comply with any previously applicable instructions and requirements; (4) training personnel to respond to a collection of information; (5) searching data sources; (6) completing and reviewing the collection of information; and (7) transmitting, or otherwise disclosing the information. The estimate of cost for respondents is based upon salaries for professional and clerical support, as well as direct and indirect overhead costs. Direct costs include all costs directly attributable to providing this information, such as administrative costs and the cost for information technology. Indirect or overhead costs are costs incurred by an organization in support of its mission. These costs apply to activities which benefit the whole organization rather than anyone particular function or activity. Comments are invited on: (1) Whether the proposed collection of information is necessary for the proper performance of the functions of the Commission, including whether the information will have practical utility; (2) the accuracy of the agency’s estimate of the burden of the proposed collection of information, including the validity of the methodology and assumptions used; (3) ways to enhance the quality, utility and clarity of the information to be collected; and (4) ways to minimize the burden of the collection of information on those who are to respond, including the use of appropriate automated, electronic, mechanical, or other technological collection techniques or other forms of information technology, e.g., permitting electronic submission of responses. Kimberly D. Bose, Secretary. [FR Doc. E8–13533 Filed 6–16–08; 8:45 am] BILLING CODE 6717–01–P VerDate Aug<31>2005 16:10 Jun 16, 2008 Jkt 214001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2266–096] Nevada Irrigation District; Notice of Intent To File License Application, Filing of Pre-Application Document, Commencement of Licensing Proceeding and Scoping; Request for Comments on the Pad and Scoping Document, and Identification of Issues and Associated Study Requests June 10, 2008. a. Type of Filing: Notice of Intent to File License Application for a New License and Commencing Licensing Proceeding. b. Project No.: 2266–096. c. Dated Filed: April 11, 2008. d. Submitted By: Nevada Irrigation District. e. Name of Project: Yuba-Bear Project. f. Location: The Yuba-Bear Project is located on the west slope of the Sierra Nevada on the Middle Yuba River, Canyon Creek, Fall Creek, Rucker Creek and Bear River, in Nevada, Placer and Sierra counties, California. A large portion of the project is located on the Tahoe National Forest. Some of the project is located on federally-owned land managed by the Bureau of Land Management as part of the Sierra Resource Management Area. The project consists of four developments—Bowman, Dutch Flat, Chicago Park, and Rollins—which, in total, include: 13 main dams with a combined gross storage capacity of 207,865 acre-feet of water; four water conduits; five diversion dams; four powerhouses with a combined installed capacity of 79.32 megawatts; one 9.0mile-long, 60-kilovolt transmission line; and appurtenant facilities and structures, including recreation facilities. g. Filed Pursuant to: 18 CFR Part 5 of the Commission’s Regulations. h. Applicant Contact: Ron Nelson, General Manager, Nevada Irrigation District, 1036 West Main Street, Grass Valley, CA 95945, (530) 271–6824 or email nelson@nid.dst.ca.us. i. FERC Contact: John Mudre at 202– 502–8902 or e-mail john.mudre@ferc.gov. j. We are asking federal, state, local, and tribal agencies with jurisdiction and/or special expertise with respect to environmental issues to cooperate with us in the preparation of the environmental document. Agencies who would like to request cooperating status should follow the instructions for filing comments described in paragraph o PO 00000 Frm 00036 Fmt 4703 Sfmt 4703 34281 below. Cooperating agencies should note the Commission’s policy that agencies that cooperate in the preparation of the environmental document cannot also intervene. See, 94 FERC ¶ 61,076 (2001). k. With this notice, we are initiating informal consultation with: (a) The U.S. Fish and Wildlife Service and/or NOAA Fisheries under section 7 of the Endangered Species Act and the joint agency regulations thereunder at 50 CFR, Part 402 and (b) the State Historic Preservation Officer, as required by section 106, National Historical Preservation Act, and the implementing regulations of the Advisory Council on Historic Preservation at 36 CFR 800.2. l. With this notice, we are designating Nevada Irrigation District as the Commission’s non-federal representative for carrying out informal consultation, pursuant to section 7 of the Endangered Species Act and section 106 of the National Historic Preservation Act. m. Nevada Irrigation District filed a Pre-Application Document (PAD; including a proposed process plan and schedule) with the Commission, pursuant to 18 CFR 5.6 of the Commission’s regulations. n. A copy of the PAD is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site (https:// www.ferc.gov), using the ‘‘eLibrary’’ link. Enter the docket number, excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support at FERCONlineSupport@ferc.gov or toll free at 1–866–208–3676, of for TTY, (202) 502–8659. A copy is also available for inspection and reproduction at the address in paragraph h. Register online at https://ferc.gov/ esubscribenow.htm to be notified via email of new filing and issuances related to this or other pending projects. For assistance, contact FERC Online Support. o. With this notice, we are soliciting comments on the PAD and Scoping Document 1 (SD1), as well as study requests. All comments on the PAD and SD1, and study requests should be sent to the address above in paragraph h. In addition, all comments on the PAD and SD1, study requests, requests for cooperating agency status, and all communications to and from Commission staff related to the merits of the potential application (original and eight copies) must be filed with the Commission at the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 E:\FR\FM\17JNN1.SGM 17JNN1

Agencies

[Federal Register Volume 73, Number 117 (Tuesday, June 17, 2008)]
[Notices]
[Pages 34280-34281]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-13533]


=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. IC08-512-001, FERC-512]


Commission Information Collection Activities, Proposed 
Collection; Comment Request; Submitted for OMB Review

June 10, 2008.
AGENCY: Federal Energy Regulatory Commission.

ACTION: Notice.

-----------------------------------------------------------------------

SUMMARY: In compliance with the requirements of section 3507 of the 
Paperwork Reduction Act of 1995, 44 U.S.C. 3507, the Federal Energy 
Regulatory Commission (Commission) has submitted the information 
collection described below to the Office of Management and Budget (OMB) 
for review of this information collection requirement. Any interested 
person may file comments directly with OMB and should address a copy of 
those comments to the Commission as explained below. The Commission 
received no comments in response to an earlier Federal Register notice 
of March 13, 2008 (73 FR 13536-13537), and has made this notation in 
its submission to OMB.

DATES: Comments on the collection of information are due by July 10, 
2008.

ADDRESSES: Address comments on the collection of information to the 
Office of Management and Budget, Office of Information and Regulatory 
Affairs, Attention: Federal Energy Regulatory Commission Desk Officer. 
Comments to OMB should be filed electronically, c/o oira_
submission@omb.eop.gov and include the OMB Control No. (1902-0073) as a 
point of reference. The Desk Officer may be reached by telephone at 
202-395-7345. A copy of the comments should also be sent to the Federal 
Energy Regulatory Commission, Office of the Executive Director, ED-34, 
Attention: Michael Miller, 888 First Street, NE., Washington, DC 20426. 
Comments may be filed either in paper format or electronically. Those 
persons filing electronically do not need to make a paper filing. For 
paper filings, such comments should be submitted to the Secretary of 
the Commission, Federal Energy Regulatory Commission, 888 First Street, 
NE., Washington, DC 20426 and should refer to Docket No. IC08-512-001. 
Documents filed electronically via the Internet must be prepared in an 
acceptable filing format and in compliance with the Federal Energy 
Regulatory Commission submission guidelines. Complete filing 
instructions and acceptable filing formats are available at (https://
www.ferc.gov/help/submission-guide/electronic-media.asp). To file the 
document electronically, access the Commission's Web site and click on 
Documents & Filing, E-Filing (https://www.ferc.gov/docs-filing/
efiling.asp), and then follow the instructions for each screen. First 
time users will have to establish a user name and password. The 
Commission will send an automatic acknowledgement to the sender's e-
mail address upon receipt of comments.
    All comments may be viewed, printed or downloaded remotely via the 
Internet through FERC's homepage using the ``eLibrary'' link. For user 
assistance, contact fercolinesupport@ferc.gov or toll-free at (866) 
208-3676 or for TTY, contact (202) 502-8659.

FOR FURTHER INFORMATION CONTACT: Michael Miller may be reached by 
telephone at (202) 502-8415, by fax at (202) 273-0873, and by e-mail at 
michael.miller@ferc.gov.

SUPPLEMENTARY INFORMATION:
    Abstract: The information collected under the requirements of FERC-
512, ``Application for Preliminary Permit'' (OMB No. 1902-0073) is used 
by the Commission to implement the statutory provisions of sections 
4(f), 5 and 7 of the Federal Power Act (FPA), 16 U.S.C. sections 797, 
798 & 800. The purpose of obtaining a preliminary permit is to maintain 
priority of the application for a license for a hydropower facility 
while the applicant conducts surveys to prepare maps, plans, 
specifications and estimates; conducts engineering, economic and 
environmental feasibility studies; and making financial arrangements. 
The conditions under which the priority will be maintained are set 
forth in each permit. During the term of the permit, no other 
application for a preliminary permit or application for a license 
submitted by another party can be accepted. The term of the permit is 
three years. The information collected under the designation FERC-512 
is in the form of a written application for a preliminary permit which 
is used by Commission staff to determine an applicant's qualifications 
to hold a preliminary permit, review the proposed hydro development for 
feasibility and to issue a notice of the application in order to 
solicit public and agency comments. The Commission implements these 
mandatory filing requirements in the Code of Federal Regulations (CFR) 
under 18 CFR 4.31-33, 4.81-.83.
    Action: The Commission is requesting a three-year extension of the 
current expiration date, with no changes to the existing collection of 
data.
    Burden Statement: Public reporting burden for this collection is 
estimated as:

----------------------------------------------------------------------------------------------------------------
                                Annual  responses per      Average burden hours  per
     No. of respondents               respondent                   response            Total annual burden hours
(1)                                            (2)                          (3)             (1) x (2) x (3)
----------------------------------------------------------------------------------------------------------------
                  200                            1                           37                       7,400
----------------------------------------------------------------------------------------------------------------


[[Page 34281]]

    Estimated cost burden to respondents is $508,000; (i.e., 7 hours 
@$200 an hour (legal) + 30 hours @$39 an hour (technical) x 200) per 
year equals $514,000).
    The reporting burden includes the total time, effort, or financial 
resources expended to generate, maintain, retain, or disclose or 
provide the information including: (1) Reviewing instructions; (2) 
developing, acquiring, installing, and utilizing technology and systems 
for the purposes of collecting, validating, verifying, processing, 
maintaining, disclosing and providing information; (3) adjusting the 
existing ways to comply with any previously applicable instructions and 
requirements; (4) training personnel to respond to a collection of 
information; (5) searching data sources; (6) completing and reviewing 
the collection of information; and (7) transmitting, or otherwise 
disclosing the information.
    The estimate of cost for respondents is based upon salaries for 
professional and clerical support, as well as direct and indirect 
overhead costs. Direct costs include all costs directly attributable to 
providing this information, such as administrative costs and the cost 
for information technology. Indirect or overhead costs are costs 
incurred by an organization in support of its mission. These costs 
apply to activities which benefit the whole organization rather than 
anyone particular function or activity.
    Comments are invited on: (1) Whether the proposed collection of 
information is necessary for the proper performance of the functions of 
the Commission, including whether the information will have practical 
utility; (2) the accuracy of the agency's estimate of the burden of the 
proposed collection of information, including the validity of the 
methodology and assumptions used; (3) ways to enhance the quality, 
utility and clarity of the information to be collected; and (4) ways to 
minimize the burden of the collection of information on those who are 
to respond, including the use of appropriate automated, electronic, 
mechanical, or other technological collection techniques or other forms 
of information technology, e.g., permitting electronic submission of 
responses.

Kimberly D. Bose,
Secretary.
 [FR Doc. E8-13533 Filed 6-16-08; 8:45 am]