Blue Light Power, LLC; Notice of Application Accepted for Filing and Soliciting Motions To Intervene, Protests, and Comments, 26090-26091 [E8-10199]
Download as PDF
mstockstill on PROD1PC66 with NOTICES
26090
Federal Register / Vol. 73, No. 90 / Thursday, May 8, 2008 / Notices
feet mean sea level (msl), (3) a proposed
lower reservoir having a surface area of
164 acres, with storage capacity of
21,900 acre-feet and normal water
surface elevation of 926 feet msl located
within the East Pit of the inactive Eagle
Mountain Mine, (4) proposed intake and
outlet structures for both reservoirs, (5)
a proposed upper ‘‘low head’’ pressure
4,400-foot-long, 35-foot-diameter tunnel
and a lower tunnel 1,500 feet in length
and 35 feet in diameter, which will
extend to a penstock manifold. These
two tunnels will be joined by a 35-footdiameter vertical shaft 1,333-foot deep,
(6) a proposed powerhouse containing
four generating units having a total
installed capacity of 1,300 megawatts,
(7) a proposed 6,835-foot-long, 35-footdiameter tailrace tunnel, (8) a proposed
46-mile-long, 500 kilovolt transmission
line, (9) a desalination facility, and (10)
appurtenant facilities.
k. Location of Applications: A copy of
the application is available for
inspection and reproduction at the
Commission in the Public Reference
Room or may be viewed on the
Commission’s Web site at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, call toll-free 1–866–208–
3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY,
call (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item g
above.
l. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
m. Competing Preliminary Permit—
Anyone desiring to file a competing
application for preliminary permit for a
proposed project must submit the
competing application itself, or a notice
of intent to file such an application, to
the Commission on or before the
specified comment date for the
particular application (see 18 CFR 4.36).
Submission of a timely notice of intent
allows an interested person to file the
competing preliminary permit
application no later than 30 days after
the specified comment date for the
particular application. A competing
preliminary permit application must
conform with 18 CFR 4.30 and 4.36.
n. Competing Development
Application—Any qualified
development applicant desiring to file a
competing development application
must submit to the Commission, on or
before a specified comment date for the
particular application, either a
competing development application or a
VerDate Aug<31>2005
17:22 May 07, 2008
Jkt 214001
notice of intent to file such an
application. Submission of a timely
notice of intent to file a development
application allows an interested person
to file the competing application no
later than 120 days after the specified
comment date for the particular
application. A competing license
application must conform with 18 CFR
4.30 and 4.36.
o. Notice of Intent—A notice of intent
must specify the exact name, business
address, and telephone number of the
prospective applicant, and must include
an unequivocal statement of intent to
submit, if such an application may be
filed, either a preliminary permit
application or a development
application (specify which type of
application). A notice of intent must be
served on the applicant(s) named in this
public notice.
p. Proposed Scope of Studies Under
Permit—A preliminary permit, if issued,
does not authorize construction. The
term of the proposed preliminary permit
would be 36 months. The work
proposed under the preliminary permit
would include economic analysis,
preparation of preliminary engineering
plans, and a study of environmental
impacts. Based on the results of these
studies, the Applicant would decide
whether to proceed with the preparation
of a development application to
construct and operate the project.
q. Comments, Protests, or Motions to
Intervene—Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
r. Filing and Service of Responsive
Documents—Any filings must bear in
all capital letters the title
‘‘COMMENTS’’, ‘‘NOTICE OF INTENT
TO FILE COMPETING APPLICATION’’,
‘‘COMPETING APPLICATION’’,
‘‘PROTEST’’, or ‘‘MOTION TO
INTERVENE’’, as applicable, and the
Project Number of the particular
application to which the filing refers.
Any of the above-named documents
must be filed by providing the original
and the number of copies provided by
the Commission’s regulations to: The
Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE.,
PO 00000
Frm 00017
Fmt 4703
Sfmt 4703
Washington, DC 20426. An additional
copy must be sent to Director, Division
of Hydropower Administration and
Compliance, Federal Energy Regulatory
Commission, at the above-mentioned
address. A copy of any notice of intent,
competing application or motion to
intervene must also be served upon each
representative of the Applicant
specified in the particular application.
s. Agency Comments—Federal, State,
and local agencies are invited to file
comments on the described application.
A copy of the application may be
obtained by agencies directly from the
Applicant. If an agency does not file
comments within the time specified for
filing comments, it will be presumed to
have no comments. One copy of an
agency’s comments must also be sent to
the Applicant’s representatives.
Kimberly D. Bose,
Secretary.
[FR Doc. E8–10129 Filed 5–7–08; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13055–000]
Blue Light Power, LLC; Notice of
Application Accepted for Filing and
Soliciting Motions To Intervene,
Protests, and Comments
May 1, 2008.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Preliminary
Permit.
b. Project No.: 13055–000.
c. Date filed: November 6, 2007.
d. Applicant: Blue Light Power, LLC.
e. Name of Project: Chatfield Dam
Hydroelectric Project.
f. Location: Nevada Ditch and Platte
River in Arapahoe County, Colorado.
The project would use the U.S. Army
Corps of Engineers’ Chatfield Dam.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Mr. Mike Zink,
Blue Light Power, LLC, 1648 S. Adams,
Denver, CO 80210, (303) 568–9640.
i. FERC Contact: Henry Woo, (202)
502–8872.
j. Deadline for filing motions to
intervene, protests, and comments: 60
days from the issuance date of this
notice.
All documents (original and eight
copies) should be filed with: Kimberly
D. Bose, Secretary, Federal Energy
E:\FR\FM\08MYN1.SGM
08MYN1
mstockstill on PROD1PC66 with NOTICES
Federal Register / Vol. 73, No. 90 / Thursday, May 8, 2008 / Notices
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
Comments, protests, and interventions
may be filed electronically via the
Internet in lieu of paper; see 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under the
‘‘eFiling’’ link. The Commission
strongly encourages electronic filings.
Please include the project number (P–
13055–000) on any comments or
motions filed.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person in the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
k. Description of Project: The
proposed project, using the U.S. Army
Corps of Engineers’ Chatfield Dam,
would consist of: (1) An intake
structure; (2) a new powerhouse
containing a generating unit with a total
installed capacity of 250 kilowatts; (3) a
new 500-foot long, 480-volt
transmission line; and (4) appurtenant
facilities. The proposed Chatfield Dam
Hydroelectric Project would have an
average annual generation of 1.3
gigawatt-hours, which would be sold to
a local utility.
l. Locations of Applications: A copy of
the application is available for
inspection and reproduction at the
Commission in the Public Reference
Room, located at 888 First Street, NE.,
Room 2A, Washington DC 20426, or by
calling (202) 502–8371. This filing may
also be viewed on the Commission’s
Web site at https://www.ferc.gov using
the ‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, call toll-free
1–866–208–3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY,
call (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item h
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Competing Preliminary Permit—
Anyone desiring to file a competing
application for preliminary permit for a
proposed project must submit the
competing application itself, or a notice
of intent to file such an application, to
the Commission on or before the
specified comment date for the
VerDate Aug<31>2005
17:22 May 07, 2008
Jkt 214001
particular application (see 18 CFR 4.36).
Submission of a timely notice of intent
allows an interested person to file the
competing preliminary permit
application no later than 30 days after
the specified comment date for the
particular application. A competing
preliminary permit application must
conform with 18 CFR 4.30 and 4.36.
o. Competing Development
Application—Any qualified
development applicant desiring to file a
competing development application
must submit to the Commission, on or
before a specified comment date for the
particular application, either a
competing development application or a
notice of intent to file such an
application. Submission of a timely
notice of intent to file a development
application allows an interested person
to file the competing application no
later than 120 days after the specified
comment date for the particular
application. A competing license
application must conform with 18 CFR
4.30 and 4.36.
p. Notice of Intent—A notice of intent
must specify the exact name, business
address, and telephone number of the
prospective applicant, and must include
an unequivocal statement of intent to
submit, if such an application may be
filed, either a preliminary permit
application or a development
application (specify which type of
application). A notice of intent must be
served on the applicant(s) named in this
public notice.
q. Proposed Scope of Studies under
Permit—A preliminary permit, if issued,
does not authorize construction. The
term of the proposed preliminary permit
would be 36 months. The work
proposed under the preliminary permit
would include economic analysis,
preparation of preliminary engineering
plans, and a study of environmental
impacts. Based on the results of these
studies, the Applicant would decide
whether to proceed with the preparation
of a development application to
construct and operate the project.
r. Comments, Protests, or Motions To
Intervene—Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
PO 00000
Frm 00018
Fmt 4703
Sfmt 4703
26091
comment date for the particular
application.
s. Filing and Service of Responsive
Documents—Any filings must bear in
all capital letters the title
‘‘COMMENTS’’, ‘‘NOTICE OF INTENT
TO FILE COMPETING APPLICATION’’,
‘‘COMPETING APPLICATION’’,
‘‘PROTEST’’, or ‘‘MOTION TO
INTERVENE’’, as applicable, and the
Project Number of the particular
application to which the filing refers.
Any of the above-named documents
must be filed by providing the original
and the number of copies provided by
the Commission’s regulations to: The
Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington, DC 20426. An additional
copy must be sent to Director, Division
of Hydropower Administration and
Compliance, Federal Energy Regulatory
Commission, at the above-mentioned
address. A copy of any motion to
intervene must also be served upon each
representative of the Applicant
specified in the particular application.
Comments, protests, and
interventions may be filed electronically
via the Internet in lieu of paper; see 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site under the ‘‘eFiling’’ link. The
Commission strongly encourages
electronic filings.
t. Agency Comments—Federal, State,
and local agencies are invited to file
comments on the described application.
A copy of the application may be
obtained by agencies directly from the
Applicant. If an agency does not file
comments within the time specified for
filing comments, it will be presumed to
have no comments. One copy of an
agency’s comments must also be sent to
the Applicant’s representatives.
Kimberly D. Bose,
Secretary.
[FR Doc. E8–10199 Filed 5–7–08; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\08MYN1.SGM
08MYN1
Agencies
[Federal Register Volume 73, Number 90 (Thursday, May 8, 2008)]
[Notices]
[Pages 26090-26091]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-10199]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 13055-000]
Blue Light Power, LLC; Notice of Application Accepted for Filing
and Soliciting Motions To Intervene, Protests, and Comments
May 1, 2008.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Application: Preliminary Permit.
b. Project No.: 13055-000.
c. Date filed: November 6, 2007.
d. Applicant: Blue Light Power, LLC.
e. Name of Project: Chatfield Dam Hydroelectric Project.
f. Location: Nevada Ditch and Platte River in Arapahoe County,
Colorado. The project would use the U.S. Army Corps of Engineers'
Chatfield Dam.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Mr. Mike Zink, Blue Light Power, LLC, 1648 S.
Adams, Denver, CO 80210, (303) 568-9640.
i. FERC Contact: Henry Woo, (202) 502-8872.
j. Deadline for filing motions to intervene, protests, and
comments: 60 days from the issuance date of this notice.
All documents (original and eight copies) should be filed with:
Kimberly D. Bose, Secretary, Federal Energy
[[Page 26091]]
Regulatory Commission, 888 First Street, NE., Washington, DC 20426.
Comments, protests, and interventions may be filed electronically via
the Internet in lieu of paper; see 18 CFR 385.2001(a)(1)(iii) and the
instructions on the Commission's Web site under the ``eFiling'' link.
The Commission strongly encourages electronic filings. Please include
the project number (P-13055-000) on any comments or motions filed.
The Commission's Rules of Practice and Procedure require all
intervenors filing documents with the Commission to serve a copy of
that document on each person in the official service list for the
project. Further, if an intervenor files comments or documents with the
Commission relating to the merits of an issue that may affect the
responsibilities of a particular resource agency, they must also serve
a copy of the document on that resource agency.
k. Description of Project: The proposed project, using the U.S.
Army Corps of Engineers' Chatfield Dam, would consist of: (1) An intake
structure; (2) a new powerhouse containing a generating unit with a
total installed capacity of 250 kilowatts; (3) a new 500-foot long,
480-volt transmission line; and (4) appurtenant facilities. The
proposed Chatfield Dam Hydroelectric Project would have an average
annual generation of 1.3 gigawatt-hours, which would be sold to a local
utility.
l. Locations of Applications: A copy of the application is
available for inspection and reproduction at the Commission in the
Public Reference Room, located at 888 First Street, NE., Room 2A,
Washington DC 20426, or by calling (202) 502-8371. This filing may also
be viewed on the Commission's Web site at https://www.ferc.gov using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. For
assistance, call toll-free 1-866-208-3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY, call (202) 502-8659. A copy is
also available for inspection and reproduction at the address in item h
above.
m. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
n. Competing Preliminary Permit--Anyone desiring to file a
competing application for preliminary permit for a proposed project
must submit the competing application itself, or a notice of intent to
file such an application, to the Commission on or before the specified
comment date for the particular application (see 18 CFR 4.36).
Submission of a timely notice of intent allows an interested person to
file the competing preliminary permit application no later than 30 days
after the specified comment date for the particular application. A
competing preliminary permit application must conform with 18 CFR 4.30
and 4.36.
o. Competing Development Application--Any qualified development
applicant desiring to file a competing development application must
submit to the Commission, on or before a specified comment date for the
particular application, either a competing development application or a
notice of intent to file such an application. Submission of a timely
notice of intent to file a development application allows an interested
person to file the competing application no later than 120 days after
the specified comment date for the particular application. A competing
license application must conform with 18 CFR 4.30 and 4.36.
p. Notice of Intent--A notice of intent must specify the exact
name, business address, and telephone number of the prospective
applicant, and must include an unequivocal statement of intent to
submit, if such an application may be filed, either a preliminary
permit application or a development application (specify which type of
application). A notice of intent must be served on the applicant(s)
named in this public notice.
q. Proposed Scope of Studies under Permit--A preliminary permit, if
issued, does not authorize construction. The term of the proposed
preliminary permit would be 36 months. The work proposed under the
preliminary permit would include economic analysis, preparation of
preliminary engineering plans, and a study of environmental impacts.
Based on the results of these studies, the Applicant would decide
whether to proceed with the preparation of a development application to
construct and operate the project.
r. Comments, Protests, or Motions To Intervene--Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214. In determining the appropriate action to take, the Commission
will consider all protests or other comments filed, but only those who
file a motion to intervene in accordance with the Commission's Rules
may become a party to the proceeding. Any comments, protests, or
motions to intervene must be received on or before the specified
comment date for the particular application.
s. Filing and Service of Responsive Documents--Any filings must
bear in all capital letters the title ``COMMENTS'', ``NOTICE OF INTENT
TO FILE COMPETING APPLICATION'', ``COMPETING APPLICATION'',
``PROTEST'', or ``MOTION TO INTERVENE'', as applicable, and the Project
Number of the particular application to which the filing refers. Any of
the above-named documents must be filed by providing the original and
the number of copies provided by the Commission's regulations to: The
Secretary, Federal Energy Regulatory Commission, 888 First Street, NE.,
Washington, DC 20426. An additional copy must be sent to Director,
Division of Hydropower Administration and Compliance, Federal Energy
Regulatory Commission, at the above-mentioned address. A copy of any
motion to intervene must also be served upon each representative of the
Applicant specified in the particular application.
Comments, protests, and interventions may be filed electronically
via the Internet in lieu of paper; see 18 CFR 385.2001(a)(1)(iii) and
the instructions on the Commission's Web site under the ``eFiling''
link. The Commission strongly encourages electronic filings.
t. Agency Comments--Federal, State, and local agencies are invited
to file comments on the described application. A copy of the
application may be obtained by agencies directly from the Applicant. If
an agency does not file comments within the time specified for filing
comments, it will be presumed to have no comments. One copy of an
agency's comments must also be sent to the Applicant's representatives.
Kimberly D. Bose,
Secretary.
[FR Doc. E8-10199 Filed 5-7-08; 8:45 am]