Twin Lakes Canal Company; Notice Dismissing Request for Rehearing, 26103 [E8-10198]
Download as PDF
Federal Register / Vol. 73, No. 90 / Thursday, May 8, 2008 / Notices
intervention to the Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on May 20, 2008.
Kimberly D. Bose,
Secretary.
[FR Doc. E8–10196 Filed 5–7–08; 8:45 am]
The Secretary’s March 10, 2008 notice
dismissed PacifiCorp’s motion only to
the extent that it sought cancellation of
Twin Lakes’ permit. It took no action
with respect to the other arguments
raised by PacifiCorp in its filing, which
remain in the public record of Project
No. 12486 and will be considered in the
context of the ILP.2
Accordingly, because PacifiCorp does
not raise any issues or arguments
relating to the mootness of its request to
cancel the initial preliminary permit in
Project No. 12486, its request for
rehearing of the March 10, 2008 notice
is dismissed.
This notice constitutes final agency
action. Requests for rehearing of this
dismissal notice must be filed within 30
days of the date of issuance of this
notice, pursuant to 18 CFR 385.713
(2007).
Kimberly D. Bose,
Secretary.
[FR Doc. E8–10198 Filed 5–7–08; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
BILLING CODE 6717–01–P
Federal Energy Regulatory
Commission
DEPARTMENT OF ENERGY
[Project No. 12486–003]
Federal Energy Regulatory
Commission
Twin Lakes Canal Company; Notice
Dismissing Request for Rehearing
[Docket No. CP08–8–000]
mstockstill on PROD1PC66 with NOTICES
May 1, 2008.
On March 10, 2008, the Secretary
issued a notice dismissing as moot a
motion filed by PacifiCorp on October
24, 2007, seeking, inter alia, to cancel a
preliminary permit issued to Twin
Lakes Canal Company (Twin Lakes) for
the proposed Bear River Narrows Project
No. 12486, to be located on the Bear
River in Franklin County, Idaho. The
notice explained that the request to
cancel the preliminary permit was moot
because the permit had expired. On
April 3, 2008, PacifiCorp filed a request
for rehearing of the Secretary’s notice.
On rehearing, PacifiCorp does not
allege error with the conclusion that the
request to cancel the permit was
rendered moot when the permit expired.
Instead, PacifiCorp argues, as it did in
its October 24, 2007 motion, that Twin
Lakes’ preparation of a license
application using the Commission’s
Integrated Licensing Process (ILP)
should be terminated because Twin
Lakes’ project would impermissibly
conflict with PacifiCorp’s upstream
licensed Bear River Project No. 20.1
1 The ILP is set forth in Part 5 of the
Commission’s regulations, 18 CFR Part 5 (2007).
Twin Lakes initiated an ILP by filing a notice of
intention and preliminary application document for
the Bear River Narrows Project on February 23,
2007.
VerDate Aug<31>2005
17:22 May 07, 2008
Jkt 214001
Leaf River Energy Center LLC; Notice
of Availability of the Environmental
Assessment for the Proposed Leaf
River Storage Project
April 30, 2008.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) has prepared an
environmental assessment (EA) on the
natural gas pipeline facilities proposed
by Leaf River Energy Center LLC (Leaf
River) in the above-referenced docket.
The EA was prepared to satisfy the
requirements of the National
Environmental Policy Act. The FERC
staff concludes that approval of the
proposed project, with appropriate
mitigating measures, would not
constitute a major federal action
significantly affecting the quality of the
human environment.
The U.S. Army Corps of Engineers is
a federal cooperating agency for the
development of this EA. A federal
2 In addition, on February 5, 2008, Twin Lakes
filed an application for second preliminary permit
for the Bear River Narrows Project (docketed Project
No. 12486–002). Notice of the application was
issued on April 8, 2008, and established June 9,
2008, as the deadline for filing comments, protest,
and motions to intervene. If PacifiCorp has
concerns regarding Twin Lake’s second preliminary
permit application, it should raise them in that
proceeding.
PO 00000
Frm 00030
Fmt 4703
Sfmt 4703
26103
cooperating agency has jurisdiction by
law or special expertise with respect to
the proposed action and participates in
the NEPA analysis.
The EA assesses the potential
environmental effects of the
construction and operation of Leaf
River’s proposed Leaf River Storage
(LRS) Project. The LRS Project would
involve construction of the following
facilities in Smith, Jasper, and Clarke
Counties, Mississippi:
• Four storage wells and caverns with
a total working gas capacity of 32 billion
cubic feet (Bcf);
• Seven 4,800-horsepower gas driven
reciprocating compressor units at its
proposed compressor station/gas
handling facility along with gas
dehydration equipment;
• Four water supply wells and four
deep saltwater disposal wells, and
construct a 16-inch-diameter water
supply pipeline and a 16-inch-diameter
saltwater disposal pipeline to these
wells;
• 6.6 miles of dual bi-directional 24inch-diameter natural gas pipelines
called the Dome Lateral;
• The West-East Lateral which
consists of a single 6.9 mile 24-inchdiameter natural gas pipeline to the
west of the junction with the Dome
Lateral and 30.2 miles of dual 24-inchdiameter natural gas pipelines to the
east of the junction which would follow
the corridor to be occupied by Gulf
South Pipeline Company, LP’s
Southeast Expansion Project currently
under construction;
• A fiber optic cable communication
system from the gas handling facility
along the header system to the
interconnect locations to the cavern
wells to transmit communications to
operate the storage facility;
• A fiber optic cable from the gas
handling facility to the water supply
wells and salt water disposal wells and
to the cavern wells to transmit
communications to develop the cavern
wells; and
• Four meter and regulator stations
and five interstate gas transmission
pipeline interconnections.
The purpose of the project is to
provide high-deliverability, multi-cycle
natural gas storage services to multiple
interstate gas transmission systems.
The EA has been placed in the public
files of the FERC. A limited number of
copies of the EA are available for
distribution and public inspection at:
Federal Energy Regulatory Commission,
Public Reference Room, 888 First Street,
NE., Room 2A, Washington, DC 20426,
(202) 502–8371.
Copies of the EA have been mailed to
federal, state, and local agencies, public
E:\FR\FM\08MYN1.SGM
08MYN1
Agencies
[Federal Register Volume 73, Number 90 (Thursday, May 8, 2008)]
[Notices]
[Page 26103]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-10198]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 12486-003]
Twin Lakes Canal Company; Notice Dismissing Request for Rehearing
May 1, 2008.
On March 10, 2008, the Secretary issued a notice dismissing as moot
a motion filed by PacifiCorp on October 24, 2007, seeking, inter alia,
to cancel a preliminary permit issued to Twin Lakes Canal Company (Twin
Lakes) for the proposed Bear River Narrows Project No. 12486, to be
located on the Bear River in Franklin County, Idaho. The notice
explained that the request to cancel the preliminary permit was moot
because the permit had expired. On April 3, 2008, PacifiCorp filed a
request for rehearing of the Secretary's notice.
On rehearing, PacifiCorp does not allege error with the conclusion
that the request to cancel the permit was rendered moot when the permit
expired. Instead, PacifiCorp argues, as it did in its October 24, 2007
motion, that Twin Lakes' preparation of a license application using the
Commission's Integrated Licensing Process (ILP) should be terminated
because Twin Lakes' project would impermissibly conflict with
PacifiCorp's upstream licensed Bear River Project No. 20.\1\
---------------------------------------------------------------------------
\1\ The ILP is set forth in Part 5 of the Commission's
regulations, 18 CFR Part 5 (2007). Twin Lakes initiated an ILP by
filing a notice of intention and preliminary application document
for the Bear River Narrows Project on February 23, 2007.
---------------------------------------------------------------------------
The Secretary's March 10, 2008 notice dismissed PacifiCorp's motion
only to the extent that it sought cancellation of Twin Lakes' permit.
It took no action with respect to the other arguments raised by
PacifiCorp in its filing, which remain in the public record of Project
No. 12486 and will be considered in the context of the ILP.\2\
---------------------------------------------------------------------------
\2\ In addition, on February 5, 2008, Twin Lakes filed an
application for second preliminary permit for the Bear River Narrows
Project (docketed Project No. 12486-002). Notice of the application
was issued on April 8, 2008, and established June 9, 2008, as the
deadline for filing comments, protest, and motions to intervene. If
PacifiCorp has concerns regarding Twin Lake's second preliminary
permit application, it should raise them in that proceeding.
---------------------------------------------------------------------------
Accordingly, because PacifiCorp does not raise any issues or
arguments relating to the mootness of its request to cancel the initial
preliminary permit in Project No. 12486, its request for rehearing of
the March 10, 2008 notice is dismissed.
This notice constitutes final agency action. Requests for rehearing
of this dismissal notice must be filed within 30 days of the date of
issuance of this notice, pursuant to 18 CFR 385.713 (2007).
Kimberly D. Bose,
Secretary.
[FR Doc. E8-10198 Filed 5-7-08; 8:45 am]