Grays Harbor Ocean Energy Company, LLC; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests, 26093-26094 [E8-10169]
Download as PDF
mstockstill on PROD1PC66 with NOTICES
Federal Register / Vol. 73, No. 90 / Thursday, May 8, 2008 / Notices
adequate flow for full operation of the
Project powerhouses. During the
summer months, the available base flow
water is augmented by water releases
from Round Valley and Philbrook
reservoirs.
During the fall months, Project
powerhouses are operated at reduced
capacities due to low stream flows.
Water releases from Round Valley
reservoir flow down the West Branch
Feather River, and water releases from
Philbrook reservoir pass down natural
channels of Philbrook Creek and the
West Branch Feather River about 8
miles to Hendricks Head dam. Then
water is conveyed in the Hendricks
canal, through Toadtown Powerhouse,
then into the Toadtown canal. From this
point, the water is conveyed in the Butte
Creek canal to DeSabla Forebay then
discharged into Butte Creek. Water flow
is then diverted into the Lower
Centerville canal to the Centerville
header box, through the Centerville
Powerhouse, and finally discharged to
Butte Creek.
PG&E proposes to continue operating
the Project with no change to Project
generation facilities or features other
than adoption of resource management
measures and the deletion of five feeder
diversions.
l. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
202–502–8659. A copy is also available
for inspection and reproduction at the
address in item h above.
Register online at https://
www.ferc.gov/esubscribenow.htm to be
notified via e-mail of new filings and
issuances related to this or other
pending projects. For assistance, contact
FERC Online Support.
m. Anyone may submit comments, a
protest, or a motion to intervene in
accordance with the requirements of
Rules of Practice and Procedure, 18 CFR
385.210, .211, .214. In determining the
appropriate action to take, the
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
on or before the specified comment date
for the particular application.
VerDate Aug<31>2005
17:22 May 07, 2008
Jkt 214001
All filings must (1) Bear in all capital
letters the title ‘‘PROTEST’’, ‘‘MOTION
TO INTERVENE’’, ‘‘COMMENTS,’’
‘‘REPLY COMMENTS,’’
‘‘RECOMMENDATIONS,’’
‘‘PRELIMINARY TERMS AND
CONDITIONS,’’ or ‘‘PRELIMINARY
FISHWAY PRESCRIPTIONS;’’ (2) set
forth in the heading the name of the
applicant and the project number of the
application to which the filing
responds; (3) furnish the name, address,
and telephone number of the person
protesting or intervening; and (4)
otherwise comply with the requirements
of 18 CFR 385.2001 through 385.2005.
All comments, recommendations, terms
and conditions or prescriptions must set
forth their evidentiary basis and
otherwise comply with the requirements
of 18 CFR 4.34(b). Agencies may obtain
copies of the application directly from
the applicant. A copy of any protest or
motion to intervene must be served
upon each representative of the
applicant specified in the particular
application. A copy of all other filings
in reference to this application must be
accompanied by proof of service on all
persons listed in the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
4.34(b) and 385.2010.
n. Procedural Schedule:
The application will be processed
according to the following revised
Hydro Licensing Schedule. Revisions to
the schedule may be made as
appropriate.
Milestone
Filing of recommendations, preliminary
terms and conditions, and preliminary fishway prescriptions.
Commission issues
Draft EA.
Comments on Draft
EA.
Modified Terms and
Conditions.
Commission Issues
Final EA.
Target Date
June 30, 2008.
December 27, 2008.
January 26, 2009.
March 27, 2009.
June 25, 2009.
o. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of this notice.
p. A license applicant must file no
later than 60 days following the date of
issuance of the notice of acceptance and
ready for environmental analysis
provided for in § 5.22: (1) A copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
PO 00000
Frm 00020
Fmt 4703
Sfmt 4703
26093
evidence of waiver of water quality
certification.
Kimberly D. Bose,
Secretary.
[FR Doc. E8–10195 Filed 5–7–08; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13058–000]
Grays Harbor Ocean Energy Company,
LLC; Notice of Application Accepted
for Filing and Soliciting Comments,
Motions To Intervene, and Protests
April 30, 2008.
Take notice that the following
hydroelectric applications have been
filed with the Commission and are
available for public inspection:
a. Type of Application: Preliminary
Permit.
b. Project No.: P–13058–000.
c. Date Filed: November 5, 2007.
d. Applicant: Grays Harbor Ocean
Energy Company, LLC.
e. Name of the Project: Grays Harbor
Ocean Energy Project
f. Location: The project would be
located in the Pacific Ocean in Grays
Harbor County, Washington. The project
uses no dam or impoundment.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r.
h. Applicant Contact: Mr. W. Burton
Hamner, President, Grays Harbor Ocean
Energy Company, LLC, 5534 30th
Avenue, NE., Seattle, WA 98105, 206/
491–0945.
i. FERC Contact: Patricia W. Gillis,
(202) 502–8735.
j. Deadline for filing comments,
protests, and motions to intervene: 60
days from the issuance date of this
notice.
All documents (original and eight
copies) should be filed with: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
Comments, protests, and interventions
may be filed electronically via the
Internet in lieu of paper; see 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under the
‘‘e-Filing’’ link. The Commission
strongly encourages electronic filings.
Please include the project number (P–
13058–000) on any comments or
motions filed.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
E:\FR\FM\08MYN1.SGM
08MYN1
mstockstill on PROD1PC66 with NOTICES
26094
Federal Register / Vol. 73, No. 90 / Thursday, May 8, 2008 / Notices
each person in the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
k. Description of Project: The
proposed project would consist of: (1)
12 proposed generating units having a
total installed capacity of 6-megawatts;
(2) a proposed transmission line; and (4)
appurtenant facilities. The project
would have an average annual
generation of 316-gigawatt-hours and be
sold to a local utility.
l. Location of Application: A copy of
the application is available for
inspection and reproduction at the
Commission in the Public Reference
Room, located at 888 First Street, NE.,
Room 2A, Washington, DC 20426, or by
calling (202) 502–8371. This filing may
also be viewed on the Commission’s
Web site at https://www.ferc.gov using
the ‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, call toll-free
1–866–208–3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY,
call (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item h
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Competing Preliminary Permit—
Anyone desiring to file a competing
application for preliminary permit for a
proposed project must submit the
competing application itself, or a notice
of intent to file such an application, to
the Commission on or before the
specified comment date for the
particular application (see 18 CFR 4.36).
Submission of a timely notice of intent
allows an interested person to file the
competing preliminary permit
application no later than 30 days after
the specified comment date for the
particular application. A competing
preliminary permit application must
conform with 18 CFR 4.30 and 4.36.
o. Competing Development
Application—Any qualified
development applicant desiring to file a
competing development application
must submit to the Commission, on or
before a specified comment date for the
particular application, either a
competing development application or a
notice of intent to file such an
application. Submission of a timely
notice of intent to file a development
application allows an interested person
VerDate Aug<31>2005
17:22 May 07, 2008
Jkt 214001
to file the competing application no
later than 120 days after the specified
comment date for the particular
application. A competing license
application must conform with 18 CFR
4.30 and 4.36.
p. Notice of Intent—A notice of intent
must specify the exact name, business
address, and telephone number of the
prospective applicant, and must include
an unequivocal statement of intent to
submit, if such an application may be
filed, either a preliminary permit
application or a development
application (specify which type of
application). A notice of intent must be
served on the applicant(s) named in this
public notice.
q. Proposed Scope of Studies Under
Permit—A preliminary permit, if issued,
does not authorize construction. The
term of the proposed preliminary permit
would be 36 months. The work
proposed under the preliminary permit
would include economic analysis,
preparation of preliminary engineering
plans, and a study of environmental
impacts. Based on the results of these
studies, the Applicant would decide
whether to proceed with the preparation
of a development application to
construct and operate the project.
r. Comments, Protests, or Motions to
Intervene—Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
Comments, protests and interventions
may be filed electronically via the
Internet in lieu of paper. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site at
https://www.ferc.gov under the ‘‘eFiling’’ link.
s. Filing and Service of Responsive
Documents—Any filings must bear in
all capital letters the title
‘‘COMMENTS’’, ‘‘NOTICE OF INTENT
TO FILE COMPETING APPLICATION’’,
‘‘COMPETING APPLICATION’’,
‘‘PROTEST’’, and ‘‘MOTION TO
INTERVENE’’, as applicable, and the
Project Number of the particular
application to which the filing refers.
Any of the above-named documents
must be filed by providing the original
and the number of copies provided by
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
the Commission’s regulations to: The
Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington, DC 20426. An additional
copy must be sent to Director, Division
of Hydropower Administration and
Compliance, Federal Energy Regulatory
Commission, at the above-mentioned
address. A copy of any notice of intent,
competing application or motion to
intervene must also be served upon each
representative of the Applicant
specified in the particular application.
t. Agency Comments—Federal, State,
and local agencies are invited to file
comments on the described application.
A copy of the application may be
obtained by agencies directly from the
Applicant. If an agency does not file
comments within the time specified for
filing comments, it will be presumed to
have no comments. One copy of an
agency’s comments must also be sent to
the Applicant’s representatives.
Kimberly D. Bose,
Secretary.
[FR Doc. E8–10169 Filed 5–7–08; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13123–000]
Eagle Crest Energy Company; Notice
of Application Accepted for Filing and
Soliciting Comments, Protests, and
Motions To Intervene
April 30, 2008.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Preliminary
Permit.
b. Project No.: 13123–000.
c. Date filed: March 3, 2008.
d. Applicant: Eagle Crest Energy
Company.
e. Name and Location of Project: The
proposed Eagle Mountain Pumped
Storage Project would be located in
Riverside County, California. The
project would use federal land managed
by the U.S. Bureau of Land Management
(BLM).
f. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
g. Applicant contact: Mr. Arthur W.
Lowe, 1 El Paseo West, Suite 204, 74199
El Paseo, Palm Desert, CA 92260, (760)
779–0040, and Mr. Donald H. Clarke,
Esq., Law Offices of GKRSE, 1500 K St.,
NW., Suite 330, Washington, DC 20005,
(202) 408–5400.
E:\FR\FM\08MYN1.SGM
08MYN1
Agencies
[Federal Register Volume 73, Number 90 (Thursday, May 8, 2008)]
[Notices]
[Pages 26093-26094]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-10169]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 13058-000]
Grays Harbor Ocean Energy Company, LLC; Notice of Application
Accepted for Filing and Soliciting Comments, Motions To Intervene, and
Protests
April 30, 2008.
Take notice that the following hydroelectric applications have been
filed with the Commission and are available for public inspection:
a. Type of Application: Preliminary Permit.
b. Project No.: P-13058-000.
c. Date Filed: November 5, 2007.
d. Applicant: Grays Harbor Ocean Energy Company, LLC.
e. Name of the Project: Grays Harbor Ocean Energy Project
f. Location: The project would be located in the Pacific Ocean in
Grays Harbor County, Washington. The project uses no dam or
impoundment.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
h. Applicant Contact: Mr. W. Burton Hamner, President, Grays Harbor
Ocean Energy Company, LLC, 5534 30th Avenue, NE., Seattle, WA 98105,
206/491-0945.
i. FERC Contact: Patricia W. Gillis, (202) 502-8735.
j. Deadline for filing comments, protests, and motions to
intervene: 60 days from the issuance date of this notice.
All documents (original and eight copies) should be filed with:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426. Comments, protests, and
interventions may be filed electronically via the Internet in lieu of
paper; see 18 CFR 385.2001(a)(1)(iii) and the instructions on the
Commission's Web site under the ``e-Filing'' link. The Commission
strongly encourages electronic filings. Please include the project
number (P-13058-000) on any comments or motions filed.
The Commission's Rules of Practice and Procedure require all
intervenors filing documents with the Commission to serve a copy of
that document on
[[Page 26094]]
each person in the official service list for the project. Further, if
an intervenor files comments or documents with the Commission relating
to the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
k. Description of Project: The proposed project would consist of:
(1) 12 proposed generating units having a total installed capacity of
6-megawatts; (2) a proposed transmission line; and (4) appurtenant
facilities. The project would have an average annual generation of 316-
gigawatt-hours and be sold to a local utility.
l. Location of Application: A copy of the application is available
for inspection and reproduction at the Commission in the Public
Reference Room, located at 888 First Street, NE., Room 2A, Washington,
DC 20426, or by calling (202) 502-8371. This filing may also be viewed
on the Commission's Web site at https://www.ferc.gov using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. For
assistance, call toll-free 1-866-208-3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY, call (202) 502-8659. A copy is
also available for inspection and reproduction at the address in item h
above.
m. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
n. Competing Preliminary Permit--Anyone desiring to file a
competing application for preliminary permit for a proposed project
must submit the competing application itself, or a notice of intent to
file such an application, to the Commission on or before the specified
comment date for the particular application (see 18 CFR 4.36).
Submission of a timely notice of intent allows an interested person to
file the competing preliminary permit application no later than 30 days
after the specified comment date for the particular application. A
competing preliminary permit application must conform with 18 CFR 4.30
and 4.36.
o. Competing Development Application--Any qualified development
applicant desiring to file a competing development application must
submit to the Commission, on or before a specified comment date for the
particular application, either a competing development application or a
notice of intent to file such an application. Submission of a timely
notice of intent to file a development application allows an interested
person to file the competing application no later than 120 days after
the specified comment date for the particular application. A competing
license application must conform with 18 CFR 4.30 and 4.36.
p. Notice of Intent--A notice of intent must specify the exact
name, business address, and telephone number of the prospective
applicant, and must include an unequivocal statement of intent to
submit, if such an application may be filed, either a preliminary
permit application or a development application (specify which type of
application). A notice of intent must be served on the applicant(s)
named in this public notice.
q. Proposed Scope of Studies Under Permit--A preliminary permit, if
issued, does not authorize construction. The term of the proposed
preliminary permit would be 36 months. The work proposed under the
preliminary permit would include economic analysis, preparation of
preliminary engineering plans, and a study of environmental impacts.
Based on the results of these studies, the Applicant would decide
whether to proceed with the preparation of a development application to
construct and operate the project.
r. Comments, Protests, or Motions to Intervene--Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214. In determining the appropriate action to take, the Commission
will consider all protests or other comments filed, but only those who
file a motion to intervene in accordance with the Commission's Rules
may become a party to the proceeding. Any comments, protests, or
motions to intervene must be received on or before the specified
comment date for the particular application.
Comments, protests and interventions may be filed electronically
via the Internet in lieu of paper. See 18 CFR 385.2001(a)(1)(iii) and
the instructions on the Commission's Web site at https://www.ferc.gov
under the ``e-Filing'' link.
s. Filing and Service of Responsive Documents--Any filings must
bear in all capital letters the title ``COMMENTS'', ``NOTICE OF INTENT
TO FILE COMPETING APPLICATION'', ``COMPETING APPLICATION'',
``PROTEST'', and ``MOTION TO INTERVENE'', as applicable, and the
Project Number of the particular application to which the filing
refers. Any of the above-named documents must be filed by providing the
original and the number of copies provided by the Commission's
regulations to: The Secretary, Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC 20426. An additional copy must be
sent to Director, Division of Hydropower Administration and Compliance,
Federal Energy Regulatory Commission, at the above-mentioned address. A
copy of any notice of intent, competing application or motion to
intervene must also be served upon each representative of the Applicant
specified in the particular application.
t. Agency Comments--Federal, State, and local agencies are invited
to file comments on the described application. A copy of the
application may be obtained by agencies directly from the Applicant. If
an agency does not file comments within the time specified for filing
comments, it will be presumed to have no comments. One copy of an
agency's comments must also be sent to the Applicant's representatives.
Kimberly D. Bose,
Secretary.
[FR Doc. E8-10169 Filed 5-7-08; 8:45 am]
BILLING CODE 6717-01-P