Eastland Power LLC; Notice of Issuance of Order, 24588 [E8-9776]

Download as PDF 24588 Federal Register / Vol. 73, No. 87 / Monday, May 5, 2008 / Notices placed on the building between the utility transformer and the building’s existing service entrance switchgear. The facility is located at 2800 Raleigh Road, NE, Suite B, Wilson NC 27896. This qualifying interconnects with Wilson Energy’s electric distribution system. The facility will provide standby power and occasionally supplementary power to Farm Fresh. A notice of self-certification does not institute a proceeding regarding qualifying facility status; a notice of selfcertification provides notice that the entity making the filing has determined the Facility meets the applicable criteria to be a qualifying facility. Any person seeking to challenge such qualifying facility status may do so by filing a motion pursuant to 18 CFR 292.207(d)(iii). This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Kimberly D. Bose, Secretary. [FR Doc. E8–9793 Filed 5–2–08; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket Nos. ER08–665–000; ER08–665– 001] Eastland Power LLC; Notice of Issuance of Order rfrederick on PROD1PC67 with NOTICES April 25, 2008. Eastland Power LLC (Eastland Power) filed an application for market-based rate authority, with an accompanying rate schedule. The proposed marketbased rate schedule provides for the sale of energy and capacity. Eastland Power also requested waivers of various Commission regulations. In particular, Eastland Power requested that the Commission grant blanket approval under 18 CFR Part 34 of all future issuances of securities and assumptions of liability by Eastland Power. On April 24, 2008, pursuant to delegated authority, the Director, Division of Tariffs and Market VerDate Aug<31>2005 15:16 May 02, 2008 Jkt 214001 Development-West, granted the requests for blanket approval under Part 34 (Director’s Order). The Director’s Order also stated that the Commission would publish a separate notice in the Federal Register establishing a period of time for the filing of protests. Accordingly, any person desiring to be heard concerning the blanket approvals of issuances of securities or assumptions of liability by Eastland Power should file a protest with the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure. 18 CFR 385.211, 385.214 (2004). The Commission encourages the electronic submission of protests using the FERC Online link at https:// www.ferc.gov. Notice is hereby given that the deadline for filing protests is May 27, 2008. Absent a request to be heard in opposition to such blanket approvals by the deadline above, Eastland Power is authorized to issue securities and assume obligations or liabilities as a guarantor, indorser, surety, or otherwise in respect of any security of another person; provided that such issuance or assumption is for some lawful object within the corporate purposes of Eastland Power, compatible with the public interest, and is reasonably necessary or appropriate for such purposes. The Commission reserves the right to require a further showing that neither public nor private interests will be adversely affected by continued approvals of Eastland Power’s issuance of securities or assumptions of liability. Copies of the full text of the Director’s Order are available from the Commission’s Public Reference Room, 888 First Street, NE., Washington, DC 20426. The Order may also be viewed on the Commission’s Web site at https://www.ferc.gov, using the eLibrary link. Enter the docket number excluding the last three digits in the docket number filed to access the document. Comments, protests, and interventions may be filed electronically via the Internet in lieu of paper. See, 18 CFR 385.2001(a) (1) (iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. The Commission strongly encourages electronic filings. Kimberly D. Bose, Secretary. [FR Doc. E8–9776 Filed 5–2–08; 8:45 am] BILLING CODE 6717–01–P PO 00000 Frm 00059 Fmt 4703 Sfmt 4703 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. ER08–649–000] EFS Parlin Holdings LLC; Notice of Issuance of Order April 25, 2008. EFS Parlin Holding LLC (Parlin) filed an application for market-based rate authority, with an accompanying tariff. The proposed market-based rate tariff provides for the sale of energy, capacity and ancillary services at market-based rates. Parlin also requested waivers of various Commission regulations. In particular, Parlin requested that the Commission grant blanket approval under 18 CFR Part 34 of all future issuances of securities and assumptions of liability by Parlin. On April 23, 2008, pursuant to delegated authority, the Director, Division of Tariffs and Market Development-West, granted the request for blanket approval under Part 34 (Director’s Order). The Director’s Order also stated that the Commission would publish a separate notice in the Federal Register establishing a period of time for the filing of protests. Accordingly, any person desiring to be heard concerning the blanket approvals of issuances of securities or assumptions of liability by Parlin, should file a protest with the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure, 18 CFR 385.211, 385.214 (2007). The Commission encourages the electronic submission of protests using the FERC Online link at https://www.ferc.gov. Notice is hereby given that the deadline for filing protests is May 23, 2008. Absent a request to be heard in opposition to such blanket approvals by the deadline above, Parlin is authorized to issue securities and assume obligations or liabilities as a guarantor, indorser, surety, or otherwise in respect of any security of another person; provided that such issuance or assumption is for some lawful object within the corporate purposes of Parlin, compatible with the public interest, and is reasonably necessary or appropriate for such purposes. The Commission reserves the right to require a further showing that neither public nor private interests will be adversely affected by continued approvals of Parlin’s issuance of securities or assumptions of liability. E:\FR\FM\05MYN1.SGM 05MYN1

Agencies

[Federal Register Volume 73, Number 87 (Monday, May 5, 2008)]
[Notices]
[Page 24588]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-9776]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. ER08-665-000; ER08-665-001]


Eastland Power LLC; Notice of Issuance of Order

April 25, 2008.
    Eastland Power LLC (Eastland Power) filed an application for 
market-based rate authority, with an accompanying rate schedule. The 
proposed market-based rate schedule provides for the sale of energy and 
capacity. Eastland Power also requested waivers of various Commission 
regulations. In particular, Eastland Power requested that the 
Commission grant blanket approval under 18 CFR Part 34 of all future 
issuances of securities and assumptions of liability by Eastland Power.
    On April 24, 2008, pursuant to delegated authority, the Director, 
Division of Tariffs and Market Development-West, granted the requests 
for blanket approval under Part 34 (Director's Order). The Director's 
Order also stated that the Commission would publish a separate notice 
in the Federal Register establishing a period of time for the filing of 
protests. Accordingly, any person desiring to be heard concerning the 
blanket approvals of issuances of securities or assumptions of 
liability by Eastland Power should file a protest with the Federal 
Energy Regulatory Commission, 888 First Street, NE., Washington, DC 
20426, in accordance with Rules 211 and 214 of the Commission's Rules 
of Practice and Procedure. 18 CFR 385.211, 385.214 (2004). The 
Commission encourages the electronic submission of protests using the 
FERC Online link at https://www.ferc.gov.
    Notice is hereby given that the deadline for filing protests is May 
27, 2008.
    Absent a request to be heard in opposition to such blanket 
approvals by the deadline above, Eastland Power is authorized to issue 
securities and assume obligations or liabilities as a guarantor, 
indorser, surety, or otherwise in respect of any security of another 
person; provided that such issuance or assumption is for some lawful 
object within the corporate purposes of Eastland Power, compatible with 
the public interest, and is reasonably necessary or appropriate for 
such purposes.
    The Commission reserves the right to require a further showing that 
neither public nor private interests will be adversely affected by 
continued approvals of Eastland Power's issuance of securities or 
assumptions of liability.
    Copies of the full text of the Director's Order are available from 
the Commission's Public Reference Room, 888 First Street, NE., 
Washington, DC 20426. The Order may also be viewed on the Commission's 
Web site at https://www.ferc.gov, using the eLibrary link. Enter the 
docket number excluding the last three digits in the docket number 
filed to access the document. Comments, protests, and interventions may 
be filed electronically via the Internet in lieu of paper. See, 18 CFR 
385.2001(a) (1) (iii) and the instructions on the Commission's Web site 
under the ``e-Filing'' link. The Commission strongly encourages 
electronic filings.

Kimberly D. Bose,
Secretary.
 [FR Doc. E8-9776 Filed 5-2-08; 8:45 am]
BILLING CODE 6717-01-P