Regional Transmission Organizations; Bangor Hydro-Electric Company, et al.; New York Independent System Operator, Inc., et al.; PJM Interconnection, L.L.C., et al.; PJM Interconnection, L.L.C.; ISO New England, Inc.; New York Independent System Operator, Inc.; Notice of Filing, 23221-23222 [E8-9300]
Download as PDF
sroberts on PROD1PC70 with NOTICES
Federal Register / Vol. 73, No. 83 / Tuesday, April 29, 2008 / Notices
where feasible, and planted with native
vegetation. WGC will implement BMPs
to minimize adverse environmental
impacts during construction of road
crossings. WGC has prepared and
submitted a Federal Section 404
Authorization permit for water
resources impacts, including wetlands
impacts, and a State Section 401 permit
under the Clean Water Act issued by
USACE and WVDEP, respectively. DOE
estimated that 0.26 acre of wetlands will
be potentially impacted at the proposed
power plant site by service roads,
stockpile areas, and water supply lines.
Under one option a cooling water
intake structure, pump house, and
pipeline would be used to withdraw
water from Meadow River. WGC is
currently looking at the best locations
for these facilities to minimize
disturbance of wetlands and
floodplains. Prior to construction of a
permanent intake structure WGC must
obtain a Section 404 Authorization
permit from the USACE and Section 401
permit from the WVDEP. The Section
404 Authorization permit is required as
a result of water resources impacts,
including wetlands impacts. The Water
Quality 401 Certification is required to
ensure that the project will not violate
the state’s water quality standards or
stream designated uses. Depending
upon the final plant design and location
of the water supply line from the sewage
treatment plant, up to one additional
acre of wetlands and 120 linear feet
‘‘waters of the U.S.’’ could be impacted.
WGC is in the process of consulting
with the USACE concerning the wetland
permitting process to identify wetland
impacts and methods for avoiding and
minimizing impacts and developing
suitable forms of wetland mitigation.
Under all options for the transmission
line corridor from the proposed WGC
power plant to the Grassy Falls
substation, construction activities
would be temporary and localized and
would not result in permanent impacts
to existing 100-year floodplains. Where
the transmission line corridor would
cross a stream, new power line poles
would be situated at maximum
distances so as to not obstruct flood
flows. Construction and operation of the
transmission line could impact
approximately three acres of wetlands,
of which 0.38 acres could be
permanently impacted as discussed
above in Biological Resources.
No floodplain or wetland impacts are
expected as a result of the fuel recovery
efforts that would occur at the Anjean,
Donegan, Green Valley, and Joe Knob
coal refuse sites to be used for fuel
supply to the project.
VerDate Aug<31>2005
21:01 Apr 28, 2008
Jkt 214001
23221
Any structures located within the
floodplain would be designed in
accordance with the National Flood
Insurance Program (NFIP) requirements
for nonresidential buildings and
structures located in special flood
hazard areas. The NFIP regulations
require vulnerable structures to be
constructed above the 100-year flood
elevation or to be watertight. In
accordance with 10 CFR part 1022, DOE
will ensure through the cooperative
agreement that WGC implements
measures to mitigate the adverse
impacts of actions in a floodplain or
wetlands, including but not limited to,
minimum grading requirements, runoff
controls, design and construction
constraints. Whenever possible, WGC
will avoid disturbing floodplains and
wetlands and will minimize impacts to
the extent practicable, if avoidance is
not possible. Impacts to floodplains and
wetlands will be minimized through the
implementation of engineering design
standards and BMPs (as described above
under Mitigation, these measures are
contained in Appendix M (Volume 2) of
the EIS). In addition, WGC will comply
with state and Federal wetlands
permits, which may require additional
mitigation as well as compensatory
wetland replacement.
public inspection. The Draft EA may
also be viewed on the Commission’s
Web site at https://www.ferc.gov using
the ‘‘eLibrary’’ link. Enter the docket
number (P–1864) excluding the last
three digits in the docket number field
to access the document. For assistance,
contact FERC Online Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659.
Any comments should be filed by
May 27, 2008, and should be addressed
to the Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Room 1–A, Washington, DC
20426. Please reference the project name
and project number (P–1864) on all
comments. Comments may be filed
electronically via Internet in lieu of
paper. The Commission strongly
encourages electronic filings. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site under the ‘‘eFiling’’ link. For further
information, contact Monica Maynard at
(202) 502–6013.
Issued in Washington, DC, on this 23rd day
of April, 2008.
James A. Slutz,
Acting Principal Deputy Assistant Secretary,
Office of Fossil Energy.
[FR Doc. E8–9329 Filed 4–28–08; 8:45 am]
DEPARTMENT OF ENERGY
BILLING CODE 6450–01–P
DEPARTMENT OF ENERGY
Kimberly D. Bose,
Secretary.
[FR Doc. E8–9298 Filed 4–28–08; 8:45 am]
BILLING CODE 6717–01–P
Federal Energy Regulatory
Commission
[RT01–99–000, RT01–99–001, RT01–99–002
and RT01–99–003; RT01–86–000, RT01–86–
001 and RT01–86–002; RT01–95–000, RT01–
95–001 and RT01–95–002; RT01–2–000,
RT01–2–001, RT01–2–002 and RT01–2–003;
RT01–98–000; RT02–3–000]
Upper Peninsula Power Company;
Notice of Availability of Environmental
Assessment
Regional Transmission Organizations;
Bangor Hydro-Electric Company, et al.;
New York Independent System
Operator, Inc., et al.; PJM
Interconnection, L.L.C., et al.; PJM
Interconnection, L.L.C.; ISO New
England, Inc.; New York Independent
System Operator, Inc.; Notice of Filing
April 22, 2008.
April 21, 2008.
In accordance with the National
Environmental Policy Act of 1969 and
the Federal Energy Regulatory
Commission’s regulations, 18 CFR Part
380 (Order No. 486, 52 FR 47879), the
Office of Energy Projects has reviewed
the proposed lake level amendment for
the bond Falls Project, located in the
Ontonagon River Basin in Ontonagon
and Gogebic Counties, Michigan and
Vilas County, Wisconsin, and has
prepared a Draft Environmental
Assessment (Draft EA).
A copy of the Draft EA is on file with
the Commission and is available for
Take notice that PJM Interconnection,
L.L.C., New York Independent System
Operator, Inc. and ISO New England,
Inc. have posted on their internet Web
sites information updating their
progress on the resolution of RTO
seams.
Any person desiring to file comments
on this information should file with the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426, in accordance with Rules 211
and 214 of the Commission’s Rules of
Practice and Procedure (18 CFR 385.211
and 385.214). All such comments
Federal Energy Regulatory
Commission
[Project No. 1864–079–MI & WI]
PO 00000
Frm 00044
Fmt 4703
Sfmt 4703
E:\FR\FM\29APN1.SGM
29APN1
23222
Federal Register / Vol. 73, No. 83 / Tuesday, April 29, 2008 / Notices
should be filed on or before the
comment date. Comments may be filed
electronically via the Internet in lieu of
paper; see 18 CFR 385.2001(a)(1)(iii)
and the instructions on the
Commission’s Web site under the ‘‘eFiling’’ link. The Commission strongly
encourages electronic filings.
Comment Date: May 13, 2008.
Kimberly D. Bose,
Secretary.
[FR Doc. E8–9300 Filed 4–28–08; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. EL08–56–000]
New Brunswick Power Transmission
Corp., New Brunswick System
Operator, Northern Maine Independent
System Administrator, Inc.,
Complainants v. ISO New England,
Inc., Respondent; Notice of Complaint
sroberts on PROD1PC70 with NOTICES
April 21, 2008.
Take notice that on April 18, 2008,
New Brunswick Power Transmission
Corporation, New Brunswick System
Operator, and Northern Maine
Independent System Administrator, Inc.
(collectively, Complainants), pursuant
to sections 206 and 306 of the Federal
Power Act, 16 U.S.C. 824e, 825e, and
Rule 206 of Practice and Procedures of
the Commission’s regulations, 18 CFR
385.206, hereby file this complaint
against ISO New England, Inc. (ISO–
NE). Complainants state that this
complaint is in response to the ISO–NE
unilateral decision to arbitrarily limit
the transfer capabilities at the New
Brunswick/New England external
interface, which, for the reasons set
forth in the complaint, is unjust,
unreasonable and unduly
discriminatory.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. The Respondent’s answer
and all interventions, or protests must
be filed on or before the comment date.
The Respondent’s answer, motions to
intervene, and protests must be served
on the Complainants.
VerDate Aug<31>2005
21:01 Apr 28, 2008
Jkt 214001
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on May 8, 2008.
Kimberly D. Bose,
Secretary.
[FR Doc. E8–9301 Filed 4–28–08; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
in the oil pipeline proxy group. These
trends have made the MLP issue one of
particular concern to the Commission
and are the reason that the Commission
issued the Proposed Policy Statement.2
2. After review of an extensive record
developed in this proceeding, the
Commission concludes: (1) MLPs
should be included in the ROE proxy
group for both oil and gas pipelines; (2)
there should be no cap on the level of
distributions included in the
Commission’s current DCF
methodology; (3) the Institutional
Brokers Estimated System (IBES)
forecasts should remain the basis for the
short-term growth forecast used in the
DCF calculation; (4) there should be an
adjustment to the long-term growth rate
used to calculate the equity cost of
capital for an MLP; and (5) there should
be no modification to the current
respective two-thirds and one-third
weightings of the short- and long-term
growth factors. Moreover, the
Commission will not explore other
methods for determining a pipeline’s
equity cost of capital at this time. The
Commission also concludes that this
Policy Statement should govern all gas
and oil rate proceedings involving the
establishment of ROE that are now
pending before the Commission,
whether at hearing or in a decisional
phase at the Commission.
I. Background
[Docket No: PL07–2–000]
A. The DCF Model
Composition of Proxy Groups for
Determining Gas and Oil Pipeline
Return on Equity; Policy Statement
3. The Supreme Court has stated that
‘‘the return to the equity owner should
be commensurate with the return on
investments in other enterprises having
corresponding risks. That return,
moreover, should be sufficient to assure
confidence in the financial integrity of
the enterprise, so as to maintain its
credit and to attract capital.’’ 3 Since the
1980s, the Commission has used the
DCF model to develop a range of returns
earned on investments in companies
with corresponding risks for purposes of
determining the ROE to be awarded
natural gas and oil pipelines.
4. The DCF model was originally
developed as a method for investors to
estimate the value of securities,
including common stocks. It is based on
Issued April 17, 2008.
Before Commissioners: Joseph T. Kelliher,
Chairman; Suedeen G. Kelly, Marc Spitzer,
Philip D. Moeller, and Jon Wellinghoff.
1. On July 19, 2007, the Commission
issued a proposed policy statement
concerning the composition of the proxy
groups used to determine gas and oil
pipelines’ return on equity (ROE) under
the Discounted Cash Flow (DCF)
model.1 Historically, in determining the
proxy group, the Commission required
that pipeline operations constitute a
high proportion of the business of any
firm included in the proxy group.
However, in recent years, there have
been fewer gas pipeline corporations
that meet that standard, in part because
of the greater trend toward Master
Limited Partnerships (MLPs) in the gas
pipeline industry. Additionally, there
are no oil corporations available for use
1 Composition of Proxy Groups for Determining
Gas and Oil Pipeline Return on Equity, 120 FERC
¶ 61,068 (2007) (Proposed Policy Statement).
PO 00000
Frm 00045
Fmt 4703
Sfmt 4703
2 After an initial round of comments and reply
comments, the Commission concluded that it
required additional comment on the issue of the
growth rates of MLPs. After notice to this effect and
the receipt of a round of initial and reply
comments, staff held a technical conference
involving an eight member panel on January 23,
2008 that was transcribed for the record. Comments
and reply comments were filed thereafter.
3 FPC v. Hope Natural Gas Co., 320 U.S. 591
(1944). Bluefield Water Works & Improvement Co.
v. Public Service Comm’n, 262 U.S. 679 (1923).
E:\FR\FM\29APN1.SGM
29APN1
Agencies
[Federal Register Volume 73, Number 83 (Tuesday, April 29, 2008)]
[Notices]
[Pages 23221-23222]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-9300]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[RT01-99-000, RT01-99-001, RT01-99-002 and RT01-99-003; RT01-86-000,
RT01-86-001 and RT01-86-002; RT01-95-000, RT01-95-001 and RT01-95-002;
RT01-2-000, RT01-2-001, RT01-2-002 and RT01-2-003; RT01-98-000; RT02-3-
000]
Regional Transmission Organizations; Bangor Hydro-Electric
Company, et al.; New York Independent System Operator, Inc., et al.;
PJM Interconnection, L.L.C., et al.; PJM Interconnection, L.L.C.; ISO
New England, Inc.; New York Independent System Operator, Inc.; Notice
of Filing
April 21, 2008.
Take notice that PJM Interconnection, L.L.C., New York Independent
System Operator, Inc. and ISO New England, Inc. have posted on their
internet Web sites information updating their progress on the
resolution of RTO seams.
Any person desiring to file comments on this information should
file with the Federal Energy Regulatory Commission, 888 First Street,
NE., Washington, DC 20426, in accordance with Rules 211 and 214 of the
Commission's Rules of Practice and Procedure (18 CFR 385.211 and
385.214). All such comments
[[Page 23222]]
should be filed on or before the comment date. Comments may be filed
electronically via the Internet in lieu of paper; see 18 CFR
385.2001(a)(1)(iii) and the instructions on the Commission's Web site
under the ``e-Filing'' link. The Commission strongly encourages
electronic filings.
Comment Date: May 13, 2008.
Kimberly D. Bose,
Secretary.
[FR Doc. E8-9300 Filed 4-28-08; 8:45 am]
BILLING CODE 6717-01-P