Twin Lakes Canal Company; Notice of Application Accepted for Filing and Soliciting Motions To Intervene, Protests, and Comments, 20274-20275 [E8-7922]

Download as PDF jlentini on PROD1PC65 with NOTICES 20274 Federal Register / Vol. 73, No. 73 / Tuesday, April 15, 2008 / Notices ‘‘e-Filing’’ link. The Commission strongly encourages electronic filings. Please include the project number (P– 13138–000) on any comments or motions filed. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person in the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. Description of Project: The proposed project would consist of: (1) An existing 200-foot-long, 9-foot-high Stoughton Dam, (2) an existing impoundment having a surface area of 11 acres, with a storage capacity of 80 acre-feet and normal water surface elevation of 841.5 feet mean sea level, (3) an existing 200-foot-long power canal, (4) a proposed power house containing two generating units having a total installed capacity of 192 kilowatts, (5) a proposed 350-foot-long transmission line, and (6) appurtenant facilities. The proposed project would have an estimated average annual generation of 450 megawatt-hours, which would be sold to a local utility. l. Location of Application: This filing is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, call toll-free 1–866–208– 3676 or e-mail FERCONLINESUPPORT@FERC.GOV. For TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item h above. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Competing Preliminary Permit— Anyone desiring to file a competing application for preliminary permit for a proposed project must submit the competing application itself, or a notice of intent to file such an application, to the Commission on or before the specified comment date for the particular application (see 18 CFR 4.36). Submission of a timely notice of intent allows an interested person to file the competing preliminary permit application no later than 30 days after the specified comment date for the VerDate Aug<31>2005 17:31 Apr 14, 2008 Jkt 214001 particular application. A competing preliminary permit application must conform with 18 CFR 4.30(b) and 4.36. o. Competing Development Application—Any qualified development applicant desiring to file a competing development application must submit to the Commission, on or before a specified comment date for the particular application, either a competing development application or a notice of intent to file such an application. Submission of a timely notice of intent to file a development application allows an interested person to file the competing application no later than 120 days after the specified comment date for the particular application. A competing license application must conform with 18 CFR 4.30(b) and 4.36. p. Notice of Intent—A notice of intent must specify the exact name, business address, and telephone number of the prospective applicant, and must include an unequivocal statement of intent to submit, if such an application may be filed, either a preliminary permit application or a development application (specify which type of application). A notice of intent must be served on the applicant(s) named in this public notice. q. Proposed Scope of Studies Under Permit—A preliminary permit, if issued, does not authorize construction. The term of the proposed preliminary permit would be 36 months. The work proposed under the preliminary permit would include economic analysis, preparation of preliminary engineering plans, and a study of environmental impacts. Based on the results of these studies, the Applicant would decide whether to proceed with the preparation of a development application to construct and operate the project. r. Comments, Protests, or Motions to Intervene—Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. s. Filing and Service of Responsive Documents—Any filings must bear in all capital letters the title ‘‘COMMENTS’’, ‘‘NOTICE OF INTENT TO FILE COMPETING APPLICATION’’, PO 00000 Frm 00033 Fmt 4703 Sfmt 4703 ‘‘COMPETING APPLICATION’’, ‘‘PROTEST’’, and ‘‘MOTION TO INTERVENE’’, as applicable, and the Project Number of the particular application to which the filing refers. Any of the above-named documents must be filed by providing the original and the number of copies provided by the Commission’s regulations to: The Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. An additional copy must be sent to Director, Division of Hydropower Administration and Compliance, Federal Energy Regulatory Commission, at the above-mentioned address. A copy of any notice of intent, competing application or motion to intervene must also be served upon each representative of the Applicant specified in the particular application. t. Agency Comments—Federal, state, and local agencies are invited to file comments on the described application. A copy of the application may be obtained by agencies directly from the Applicant. If an agency does not file comments within the time specified for filing comments, it will be presumed to have no comments. One copy of an agency’s comments must also be sent to the Applicant’s representatives. Kimberly D. Bose, Secretary. [FR Doc. E8–7925 Filed 4–14–08; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 12486–002] Twin Lakes Canal Company; Notice of Application Accepted for Filing and Soliciting Motions To Intervene, Protests, and Comments April 8, 2008. Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Type of Application: Preliminary Permit. b. Project No.: 12486–002. c. Date filed: February 5, 2008. d. Applicant: Twin Lakes Canal Company. e. Name of Project: Bear River Narrows Project. f. Location: On the Bear River, in Franklin County, Idaho. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Nicholas Josten, Twin Lakes Canal Company Authority, E:\FR\FM\15APN1.SGM 15APN1 jlentini on PROD1PC65 with NOTICES Federal Register / Vol. 73, No. 73 / Tuesday, April 15, 2008 / Notices C/O GeoSense, 2742 Saint Charles Avenue, Idaho Falls, ID 83404, (208) 528–6152. i. FERC Contact: Robert Bell, (202) 502–6062. j. Deadline for filing comments, protests, and motions to intervene: 60 days from the issuance date of this notice. All documents (original and eight copies) should be filed with: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. Comments, protests, and interventions may be filed electronically via the Internet in lieu of paper; see 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. The Commission strongly encourages electronic filings. Please include the project number (P– 12486–002) on any comments or motions filed. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person in the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. Description of Project: The proposed project would consist of: (1) A proposed 700-foot-long, 108-foot-high embankment dam, (2) a proposed reservoir having a surface area of 420 acres, having a storage capacity of 17,300 acre-feet and normal water surface elevation of 4,734 feet above mean sea level, (3) a proposed powerhouse containing two generating units with a total installed capacity of 11 megawatts, (4) a proposed 0.8-milelong transmission line, and (5) appurtenant facilities. The applicant estimates that the average annual generation would be 51 gigawatt-hours, which would be sold to a local utility. l. This filing is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, call toll-free 1–866–208– 3676 or e-mail FERCONLINESUPPORT@FERC.GOV. For TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item h above. VerDate Aug<31>2005 17:31 Apr 14, 2008 Jkt 214001 m. Competing Preliminary Permit— Anyone desiring to file a competing application for preliminary permit for a proposed project must submit the competing application itself, or a notice of intent to file such an application, to the Commission on or before the specified comment date for the particular application (see 18 CFR 4.36). Submission of a timely notice of intent allows an interested person to file the competing preliminary permit application no later than 30 days after the specified comment date for the particular application. A competing preliminary permit application must conform with 18 CFR 4.30(b) and 4.36. n. Competing Development Application—Any qualified development applicant desiring to file a competing development application must submit to the Commission, on or before a specified comment date for the particular application, either a competing development application or a notice of intent to file such an application. Submission of a timely notice of intent to file a development application allows an interested person to file the competing application no later than 120 days after the specified comment date for the particular application. A competing license application must conform with 18 CFR 4.30(b) and 4.36. o. Notice of Intent—A notice of intent must specify the exact name, business address, and telephone number of the prospective applicant, and must include an unequivocal statement of intent to submit, if such an application may be filed, either a preliminary permit application or a development application (specify which type of application). A notice of intent must be served on the applicant(s) named in this public notice. p. Proposed Scope of Studies Under Permit—A preliminary permit, if issued, does not authorize construction. The term of the proposed preliminary permit would be 36 months. The work proposed under the preliminary permit would include economic analysis, preparation of preliminary engineering plans, and a study of environmental impacts. Based on the results of these studies, the Applicant would decide whether to proceed with the preparation of a development application to construct and operate the project. q. Comments, Protests, or Motions to Intervene—Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all PO 00000 Frm 00034 Fmt 4703 Sfmt 4703 20275 protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. r. Filing and Service of Responsive Documents—Any filings must bear in all capital letters the title ‘‘COMMENTS’’, ‘‘NOTICE OF INTENT TO FILE COMPETING APPLICATION’’, ‘‘COMPETING APPLICATION’’, ‘‘PROTEST’’, and ‘‘MOTION TO INTERVENE’’, as applicable, and the Project Number of the particular application to which the filing refers. Any of the above-named documents must be filed by providing the original and the number of copies provided by the Commission’s regulations to: The Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. An additional copy must be sent to Director, Division of Hydropower Administration and Compliance, Federal Energy Regulatory Commission, at the above-mentioned address. A copy of any notice of intent, competing application or motion to intervene must also be served upon each representative of the Applicant specified in the particular application. s. Agency Comments—Federal, state, and local agencies are invited to file comments on the described application. A copy of the application may be obtained by agencies directly from the Applicant. If an agency does not file comments within the time specified for filing comments, it will be presumed to have no comments. One copy of an agency’s comments must also be sent to the Applicant’s representatives. Kimberly D. Bose, Secretary. [FR Doc. E8–7922 Filed 4–14–08; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No.: 2232–522] Duke Energy Carolinas, LLC; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions April 7, 2008. Take notice that the following hydroelectric application has been filed E:\FR\FM\15APN1.SGM 15APN1

Agencies

[Federal Register Volume 73, Number 73 (Tuesday, April 15, 2008)]
[Notices]
[Pages 20274-20275]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-7922]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 12486-002]


Twin Lakes Canal Company; Notice of Application Accepted for 
Filing and Soliciting Motions To Intervene, Protests, and Comments

April 8, 2008.
    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Type of Application: Preliminary Permit.
    b. Project No.: 12486-002.
    c. Date filed: February 5, 2008.
    d. Applicant: Twin Lakes Canal Company.
    e. Name of Project: Bear River Narrows Project.
    f. Location: On the Bear River, in Franklin County, Idaho.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: Nicholas Josten, Twin Lakes Canal Company 
Authority,

[[Page 20275]]

C/O GeoSense, 2742 Saint Charles Avenue, Idaho Falls, ID 83404, (208) 
528-6152.
    i. FERC Contact: Robert Bell, (202) 502-6062.
    j. Deadline for filing comments, protests, and motions to 
intervene: 60 days from the issuance date of this notice.
    All documents (original and eight copies) should be filed with: 
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 
First Street, NE., Washington, DC 20426. Comments, protests, and 
interventions may be filed electronically via the Internet in lieu of 
paper; see 18 CFR 385.2001(a)(1)(iii) and the instructions on the 
Commission's Web site under the ``e-Filing'' link. The Commission 
strongly encourages electronic filings. Please include the project 
number (P-12486-002) on any comments or motions filed.
    The Commission's Rules of Practice and Procedure require all 
intervenors filing documents with the Commission to serve a copy of 
that document on each person in the official service list for the 
project. Further, if an intervenor files comments or documents with the 
Commission relating to the merits of an issue that may affect the 
responsibilities of a particular resource agency, they must also serve 
a copy of the document on that resource agency.
    k. Description of Project: The proposed project would consist of: 
(1) A proposed 700-foot-long, 108-foot-high embankment dam, (2) a 
proposed reservoir having a surface area of 420 acres, having a storage 
capacity of 17,300 acre-feet and normal water surface elevation of 
4,734 feet above mean sea level, (3) a proposed powerhouse containing 
two generating units with a total installed capacity of 11 megawatts, 
(4) a proposed 0.8-mile-long transmission line, and (5) appurtenant 
facilities. The applicant estimates that the average annual generation 
would be 51 gigawatt-hours, which would be sold to a local utility.
    l. This filing is available for review at the Commission in the 
Public Reference Room or may be viewed on the Commission's Web site at 
https://www.ferc.gov using the ``eLibrary'' link. Enter the docket 
number excluding the last three digits in the docket number field to 
access the document. For assistance, call toll-free 1-866-208-3676 or 
e-mail FERCONLINESUPPORT@FERC.GOV. For TTY, call (202) 502-8659. A copy 
is also available for inspection and reproduction at the address in 
item h above.
    m. Competing Preliminary Permit--Anyone desiring to file a 
competing application for preliminary permit for a proposed project 
must submit the competing application itself, or a notice of intent to 
file such an application, to the Commission on or before the specified 
comment date for the particular application (see 18 CFR 4.36). 
Submission of a timely notice of intent allows an interested person to 
file the competing preliminary permit application no later than 30 days 
after the specified comment date for the particular application. A 
competing preliminary permit application must conform with 18 CFR 
4.30(b) and 4.36.
    n. Competing Development Application--Any qualified development 
applicant desiring to file a competing development application must 
submit to the Commission, on or before a specified comment date for the 
particular application, either a competing development application or a 
notice of intent to file such an application. Submission of a timely 
notice of intent to file a development application allows an interested 
person to file the competing application no later than 120 days after 
the specified comment date for the particular application. A competing 
license application must conform with 18 CFR 4.30(b) and 4.36.
     o. Notice of Intent--A notice of intent must specify the exact 
name, business address, and telephone number of the prospective 
applicant, and must include an unequivocal statement of intent to 
submit, if such an application may be filed, either a preliminary 
permit application or a development application (specify which type of 
application). A notice of intent must be served on the applicant(s) 
named in this public notice.
    p. Proposed Scope of Studies Under Permit--A preliminary permit, if 
issued, does not authorize construction. The term of the proposed 
preliminary permit would be 36 months. The work proposed under the 
preliminary permit would include economic analysis, preparation of 
preliminary engineering plans, and a study of environmental impacts. 
Based on the results of these studies, the Applicant would decide 
whether to proceed with the preparation of a development application to 
construct and operate the project.
    q. Comments, Protests, or Motions to Intervene--Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214. In determining the appropriate action to take, the Commission 
will consider all protests or other comments filed, but only those who 
file a motion to intervene in accordance with the Commission's Rules 
may become a party to the proceeding. Any comments, protests, or 
motions to intervene must be received on or before the specified 
comment date for the particular application.
    r. Filing and Service of Responsive Documents--Any filings must 
bear in all capital letters the title ``COMMENTS'', ``NOTICE OF INTENT 
TO FILE COMPETING APPLICATION'', ``COMPETING APPLICATION'', 
``PROTEST'', and ``MOTION TO INTERVENE'', as applicable, and the 
Project Number of the particular application to which the filing 
refers. Any of the above-named documents must be filed by providing the 
original and the number of copies provided by the Commission's 
regulations to: The Secretary, Federal Energy Regulatory Commission, 
888 First Street, NE., Washington, DC 20426. An additional copy must be 
sent to Director, Division of Hydropower Administration and Compliance, 
Federal Energy Regulatory Commission, at the above-mentioned address. A 
copy of any notice of intent, competing application or motion to 
intervene must also be served upon each representative of the Applicant 
specified in the particular application.
    s. Agency Comments--Federal, state, and local agencies are invited 
to file comments on the described application. A copy of the 
application may be obtained by agencies directly from the Applicant. If 
an agency does not file comments within the time specified for filing 
comments, it will be presumed to have no comments. One copy of an 
agency's comments must also be sent to the Applicant's representatives.

Kimberly D. Bose,
Secretary.
 [FR Doc. E8-7922 Filed 4-14-08; 8:45 am]
BILLING CODE 6717-01-P