Alabama Power Company; Notice of Application for Amendment of License and Soliciting Comments, Motions To Intervene, and Protests, 15503-15504 [E8-5832]

Download as PDF mstockstill on PROD1PC66 with NOTICES Federal Register / Vol. 73, No. 57 / Monday, March 24, 2008 / Notices an unequivocal statement of intent to submit, if such an application may be filed, either a preliminary permit application or a development application (specify which type of application). A notice of intent must be served on the applicant(s) named in this public notice. p. Proposed Scope of Studies Under Permit—A preliminary permit, if issued, does not authorize construction. The term of the proposed preliminary permit would be 36 months. The work proposed under the preliminary permit would include economic analysis, preparation of preliminary engineering plans, and a study of environmental impacts. Based on the results of these studies, the Applicant would decide whether to proceed with the preparation of a development application to construct and operate the project. q. Comments, Protests, or Motions to Intervene—Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. r. Filing and Service of Responsive Documents—Any filings must bear in all capital letters the title ‘‘COMMENTS’’, ‘‘NOTICE OF INTENT TO FILE COMPETING APPLICATION’’, ‘‘COMPETING APPLICATION’’, ‘‘PROTEST’’, and ‘‘MOTION TO INTERVENE’’, as applicable, and the Project Number of the particular application to which the filing refers. Any of the above-named documents must be filed by providing the original and the number of copies provided by the Commission’s regulations to: The Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. An additional copy must be sent to Director, Division of Hydropower Administration and Compliance, Federal Energy Regulatory Commission, at the above-mentioned address. A copy of any notice of intent, competing application or motion to intervene must also be served upon each representative of the Applicant specified in the particular application. s. Agency Comments—Federal, state, and local agencies are invited to file comments on the described application. A copy of the application may be VerDate Aug<31>2005 16:33 Mar 21, 2008 Jkt 214001 obtained by agencies directly from the Applicant. If an agency does not file comments within the time specified for filing comments, it will be presumed to have no comments. One copy of an agency’s comments must also be sent to the Applicant’s representatives. Kimberly D. Bose, Secretary. [FR Doc. E8–5845 Filed 3–21–08; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 618–175] Alabama Power Company; Notice of Application for Amendment of License and Soliciting Comments, Motions To Intervene, and Protests March 14, 2008. Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Type of Application: Request for Temporary Variance of Minimum Flow Requirement. b. Project No.: 618–175. c. Date Filed: March 13, 2008. d. Applicant: Alabama Power Company. e. Name of Project: Jordan Dam. f. Location: On the Coosa River, in Elmore, Chilton, and Coosa Counties, Alabama. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a–825r. h. Applicant Contact: Barry Lovett, Alabama Power Company, 600 N. 18th Street, P.O. Box 2641, Birmingham, AL 35291, (205) 257–1258. i. FERC Contact: Peter Yarrington, peter.yarrington@ferc.gov, (202) 502– 6129. j. Deadline for filing comments, motions to intervene and protests: March 28, 2008. All documents (original and eight copies) should be filed with: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person whose name appears on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must PO 00000 Frm 00031 Fmt 4703 Sfmt 4703 15503 also serve a copy of the document on that resource agency. A copy of any motion to intervene must also be served upon each representative of the Applicant specified in the particular application. k. Description of Request: Alabama Power Company (APC) is requesting a temporary variance of the Jordan Dam Project’s minimum flow requirements due to continuing drought conditions in the southeast, and to ensure, to the extent possible, that there will be sufficient water available in the Coosa River to support both reservoir and downstream environmental, municipal and industrial water supply and navigation needs. Beginning April 1, the project license requires a continuous minimum base flow of 4,000 cubic feet per second (cfs) for 18 hours per day and a pulse flow release for 6 hours per day. During June, the base and pulse flows are ramped down in daily increments, to a continuous 2,000 cfs, which is required up to March 31. APC is requesting a variance to release from Jordan Dam no less than a continuous flow of 2,000 cfs (± 5 percent) from April 1 through December 31, 2008, unless further reduction in flows becomes necessary to address emergency operating conditions. Any reduction in flows would be achieved by ramping down flows by no more than 66.7 cfs per day. The licensee is also proposing to conduct weekly conference calls with the resource agencies to discuss project releases and operations to address drought related issues. l. Location of the Application: The filing is available for inspection and reproduction at the Commission’s Public Reference Room, located at 888 First Street, NE., Room 2A, Washington, DC 20426 or by calling (202) 502–8371, or by calling (202) 502–8371. This filing may also be viewed on the Commission’s Web site at https://ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number (P–618) in the docket number field to access the document. You may also register online at https:// www.ferc.gov/docsfiling/ esubscription.asp to be notified via email or new filings and issuances related to this or other pending projects. For assistance, call 1–866–208–3676 or e-mail FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item (h) above. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene: Anyone may submit E:\FR\FM\24MRN1.SGM 24MRN1 15504 Federal Register / Vol. 73, No. 57 / Monday, March 24, 2008 / Notices comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Any filings must bear in all capital letters the title ‘‘COMMENTS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’, as applicable, and the Project Number of the particular application to which the filing refers. p. Agency Comments: Federal, state, and local agencies are invited to file comments on the described application. A copy of the application may be obtained by agencies directly from the Applicant. If an agency does not file comments within the time specified for filing comments, it will be presumed to have no comments. One copy of an agency’s comments must also be sent to the Applicant’s representatives. q. Comments, protests and interventions may be filed electronically via the Internet in lieu of paper. See, 18 CFR 385.2001(a)(I)(iii) and the instructions on the Commission’s Web site at https://www.ferc.gov under the ‘‘eFiling’’ link. Kimberly D. Bose, Secretary. [FR Doc. E8–5832 Filed 3–21–08; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 12991–000] Kentucky Hydro 2, LLC; Notice of Application Accepted for Filing and Soliciting Motions To Intervene, Protests, and Comments mstockstill on PROD1PC66 with NOTICES March 17, 2008. Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Type of Application: Preliminary Permit. b. Project No.: 12991–000. c. Date filed: September 10, 2007. d. Applicant: Kentucky Hydro 2, LLC. e. Name of Project: Kentucky River Lock and Dam #2 Hydroelectric Project. VerDate Aug<31>2005 16:33 Mar 21, 2008 Jkt 214001 f. Location: Kentucky River in Henry County, Kentucky. It would use the U.S. Army Corps of Engineers’ Kentucky River Lock and Dam #2. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Mr. Brent L. Smith, COO, Symbiotics, LLC, P.O. Box 535, Rigby, ID 83442, (208) 745–0834. i. FERC Contact: Robert Bell, (202) 502–4126. j. Deadline for filing comments, protests, and motions to intervene: 60 days from the issuance date of this notice. All documents (original and eight copies) should be filed with: Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. Comments, protests, and interventions may be filed electronically via the Internet in lieu of paper; see 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. The Commission strongly encourages electronic filings. Please include the project number (P–12991–000) on any comments or motions filed. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person in the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. Description of Project: The proposed project using the U.S. Army Corps of Engineers’ Kentucky River Lock and Dam #2 and operated in a runof-river mode would consist of: (1) A new powerhouse and switchyard; (2) two turbine/generator units with a combined installed capacity of 13 megawatts; (3) a new 3-mile-long above ground 25-kilovolt transmission line extending from the switchyard to an interconnection point with the local utility’s distribution system; and (4) appurtenant facilities. The proposed Kentucky River Lock and Dam #2 Project would have an average annual generation of 39 gigawatt-hours. l. This filing is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, call toll-free 1–866–208– 3676 or e-mail FERCONLINESUPPORT@FERC.GOV. PO 00000 Frm 00032 Fmt 4703 Sfmt 4703 For TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item h above. m. Competing Preliminary Permit— Anyone desiring to file a competing application for preliminary permit for a proposed project must submit the competing application itself, or a notice of intent to file such an application, to the Commission on or before the specified comment date for the particular application (see 18 CFR 4.36). Submission of a timely notice of intent allows an interested person to file the competing preliminary permit application no later than 30 days after the specified comment date for the particular application. A competing preliminary permit application must conform with 18 CFR 4.30 and 4.36. n. Competing Development Application—Any qualified development applicant desiring to file a competing development application must submit to the Commission, on or before a specified comment date for the particular application, either a competing development application or a notice of intent to file such an application. Submission of a timely notice of intent to file a development application allows an interested person to file the competing application no later than 120 days after the specified comment date for the particular application. A competing license application must conform with 18 CFR 4.30 and 4.36. o. Notice of Intent—A notice of intent must specify the exact name, business address, and telephone number of the prospective applicant, and must include an unequivocal statement of intent to submit, if such an application may be filed, either a preliminary permit application or a development application (specify which type of application). A notice of intent must be served on the applicant(s) named in this public notice. p. Proposed Scope of Studies Under Permit—A preliminary permit, if issued, does not authorize construction. The term of the proposed preliminary permit would be 36 months. The work proposed under the preliminary permit would include economic analysis, preparation of preliminary engineering plans, and a study of environmental impacts. Based on the results of these studies, the Applicant would decide whether to proceed with the preparation of a development application to construct and operate the project. q. Comments, Protests, or Motions to Intervene—Anyone may submit comments, a protest, or a motion to intervene in accordance with the E:\FR\FM\24MRN1.SGM 24MRN1

Agencies

[Federal Register Volume 73, Number 57 (Monday, March 24, 2008)]
[Notices]
[Pages 15503-15504]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-5832]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 618-175]


Alabama Power Company; Notice of Application for Amendment of 
License and Soliciting Comments, Motions To Intervene, and Protests

March 14, 2008.
    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Type of Application: Request for Temporary Variance of Minimum 
Flow Requirement.
    b. Project No.: 618-175.
    c. Date Filed: March 13, 2008.
    d. Applicant: Alabama Power Company.
    e. Name of Project: Jordan Dam.
    f. Location: On the Coosa River, in Elmore, Chilton, and Coosa 
Counties, Alabama.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
    h. Applicant Contact: Barry Lovett, Alabama Power Company, 600 N. 
18th Street, P.O. Box 2641, Birmingham, AL 35291, (205) 257-1258.
    i. FERC Contact: Peter Yarrington, peter.yarrington@ferc.gov, (202) 
502-6129.
    j. Deadline for filing comments, motions to intervene and protests: 
March 28, 2008.
    All documents (original and eight copies) should be filed with: 
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 
First Street, NE., Washington, DC 20426.
    The Commission's Rules of Practice and Procedure require all 
intervenors filing documents with the Commission to serve a copy of 
that document on each person whose name appears on the official service 
list for the project. Further, if an intervenor files comments or 
documents with the Commission relating to the merits of an issue that 
may affect the responsibilities of a particular resource agency, they 
must also serve a copy of the document on that resource agency. A copy 
of any motion to intervene must also be served upon each representative 
of the Applicant specified in the particular application.
    k. Description of Request: Alabama Power Company (APC) is 
requesting a temporary variance of the Jordan Dam Project's minimum 
flow requirements due to continuing drought conditions in the 
southeast, and to ensure, to the extent possible, that there will be 
sufficient water available in the Coosa River to support both reservoir 
and downstream environmental, municipal and industrial water supply and 
navigation needs. Beginning April 1, the project license requires a 
continuous minimum base flow of 4,000 cubic feet per second (cfs) for 
18 hours per day and a pulse flow release for 6 hours per day. During 
June, the base and pulse flows are ramped down in daily increments, to 
a continuous 2,000 cfs, which is required up to March 31. APC is 
requesting a variance to release from Jordan Dam no less than a 
continuous flow of 2,000 cfs ( 5 percent) from April 1 
through December 31, 2008, unless further reduction in flows becomes 
necessary to address emergency operating conditions. Any reduction in 
flows would be achieved by ramping down flows by no more than 66.7 cfs 
per day. The licensee is also proposing to conduct weekly conference 
calls with the resource agencies to discuss project releases and 
operations to address drought related issues.
    l. Location of the Application: The filing is available for 
inspection and reproduction at the Commission's Public Reference Room, 
located at 888 First Street, NE., Room 2A, Washington, DC 20426 or by 
calling (202) 502-8371, or by calling (202) 502-8371. This filing may 
also be viewed on the Commission's Web site at https://ferc.gov using 
the ``eLibrary'' link. Enter the docket number (P-618) in the docket 
number field to access the document. You may also register online at 
https://www.ferc.gov/docsfiling/esubscription.asp to be notified via e-
mail or new filings and issuances related to this or other pending 
projects. For assistance, call 1-866-208-3676 or e-mail 
FERCOnlineSupport@ferc.gov, for TTY, call (202) 502-8659. A copy is 
also available for inspection and reproduction at the address in item 
(h) above.
    m. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    n. Comments, Protests, or Motions to Intervene: Anyone may submit

[[Page 15504]]

comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214. In determining the appropriate action to take, the Commission 
will consider all protests or other comments filed, but only those who 
file a motion to intervene in accordance with the Commission's Rules 
may become a party to the proceeding. Any comments, protests, or 
motions to intervene must be received on or before the specified 
comment date for the particular application.
    o. Any filings must bear in all capital letters the title 
``COMMENTS'', ``PROTEST'', or ``MOTION TO INTERVENE'', as applicable, 
and the Project Number of the particular application to which the 
filing refers.
    p. Agency Comments: Federal, state, and local agencies are invited 
to file comments on the described application. A copy of the 
application may be obtained by agencies directly from the Applicant. If 
an agency does not file comments within the time specified for filing 
comments, it will be presumed to have no comments. One copy of an 
agency's comments must also be sent to the Applicant's representatives.
    q. Comments, protests and interventions may be filed electronically 
via the Internet in lieu of paper. See, 18 CFR 385.2001(a)(I)(iii) and 
the instructions on the Commission's Web site at https://www.ferc.gov 
under the ``e-Filing'' link.

Kimberly D. Bose,
Secretary.
 [FR Doc. E8-5832 Filed 3-21-08; 8:45 am]
BILLING CODE 6717-01-P