Placer County Water Agency; Notice of Intent To File License Application, Filing of Pre-Application Document, Commencement of Licensing Proceeding, Scoping, Solicitation of Comments on the Pad and Scoping Document, and Identification Issues and Associated Study Requests, 9113-9114 [E8-2989]

Download as PDF Federal Register / Vol. 73, No. 33 / Tuesday, February 19, 2008 / Notices Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5 p.m. Eastern Time on February 15, 2008. Kimberly D. Bose, Secretary. [FR Doc. E8–2971 Filed 2–15–08; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2079–061] Placer County Water Agency; Notice of Intent To File License Application, Filing of Pre-Application Document, Commencement of Licensing Proceeding, Scoping, Solicitation of Comments on the Pad and Scoping Document, and Identification Issues and Associated Study Requests mstockstill on PROD1PC66 with NOTICES February 11, 2008. a. Type of Filing: Notice of Intent to File License Application for a New License and Commencing Licensing Proceeding. b. Project No.: 2079–061. c. Dated Filed: December 13, 2007. d. Submitted By: Placer County Water Agency. e. Name of Project: Middle Fork American River Project. f. Location: The Middle Fork American River Project is located in Placer and El Dorado counties, almost entirely within the Tahoe and El Dorado National Forests. The project occupies 3811 acres of United States lands under the jurisdiction of the Forest Service. g. Filed Pursuant to: 18 CFR Part 5 of the Commission’s Regulations. h. Applicant Contact: David A. Breninger, General Manager, Placer County Water Agency, P.O. Box 6570, Auburn, CA 95604. VerDate Aug<31>2005 16:52 Feb 15, 2008 Jkt 214001 i. FERC Contact: Jim Fargo at 202– 502–6095 or e-mail james.fargo@ferc.gov. j. We are asking Federal, State, local, and tribal agencies with jurisdiction and/or special expertise with respect to environmental issues to cooperate with us in the preparation of the environmental document. Agencies who would like to request cooperating status should follow the instructions for filing comments described in paragraph o below. Cooperating agencies should note the Commission’s policy that agencies that cooperate in the preparation of the environmental document cannot also intervene. See, 94 FERC 61,076 (2001). k. With this notice, we are initiating informal consultation with: (a) The U.S. Fish and Wildlife Service and/or NOAA Fisheries under section 7 of the Endangered Species Act and the joint agency regulations thereunder at 50 CFR Part 402 and (b) the State Historic Preservation Officer, as required by section 106, National Historical Preservation Act, and the implementing regulations of the Advisory Council on Historic Preservation at 36 CFR 800.2. l. With this notice, we are designating Placer County Water Agency as the Commission’s non-federal representative for carrying out informal consultation, pursuant to section 7 of the Endangered Species Act and section 106 of the National Historic Preservation Act. m. Placer County Water Agency filed a Pre-Application Document (PAD; including a proposed process plan and schedule) with the Commission, pursuant to 18 CFR 5.6 of the Commission’s regulations. n. A copy of the PAD is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site (https:// www.ferc.gov), using the ‘‘eLibrary’’ link. Enter the docket number, excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at 1–866–208–3676, of for TTY, (202) 502–8659. A copy is also available for inspection and reproduction at the address in paragraph h. Register online at https://ferc.gov/ esubscribenow.htm to be notified via email of new filing and issuances related to this or other pending projects. For assistance, contact FERC Online Support. o. With this notice, we are soliciting comments on the PAD and Scoping Document 1 (SD1), as well as study requests. All comments on the PAD and PO 00000 Frm 00028 Fmt 4703 Sfmt 4703 9113 SD1, and study requests should be sent to the address above in paragraph h. In addition, all comments on the PAD and SD1, study requests, requests for cooperating agency status, and all communications to and from Commission staff related to the merits of the potential application (original and eight copies) must be filed with the Commission at the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. All filings with the Commission must include on the first page, the project name (Middle Fork American River Project) and number (P–2079–061), and bear the heading ‘‘Comments on PreApplication Document,’’ ‘‘Study Requests,’’ ‘‘Comments on Scoping Document 1,’’ ‘‘Request for Cooperating Agency Status,’’ or ‘‘Communications to and from Commission Staff.’’ Any individual or entity interested in submitting study requests, commenting on the PAD or SD1, and any agency requesting cooperating status must do so by April 11, 2008. Comments on the PAD and SD1, study requests, requests for cooperating agency status, and other permissible forms of communications with the Commission may be filed electronically via the Internet in lieu of paper. The Commission strongly encourages electronic filings. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site (https:// www.ferc.gov) under the ‘‘e-filing’’ link. p. Our intent is to prepare an Environmental Impact Statement (EIS) for which the planned meetings will satisfy the NEPA scoping requirements. Scoping Meetings Commission staff will hold two scoping meetings in the vicinity of the project at the time and place noted below. The daytime meeting will focus on resource agency, Indian tribes, and non-governmental organization concerns, while the evening meeting is primarily for receiving input from the public. We invite all interested individuals, organizations, and agencies to attend one or both of the meetings, and to assist staff in identifying particular study needs, as well as the scope of environmental issues to be addressed in the environmental document. The times and locations of these meetings are as follows: Daytime Scoping Meeting Date and Time: Tuesday, March 4, 2008, 9 a.m. Location: Auburn Recreation DistrictCanyon View Community Center. E:\FR\FM\19FEN1.SGM 19FEN1 9114 Federal Register / Vol. 73, No. 33 / Tuesday, February 19, 2008 / Notices Evening Scoping Meeting Date and Time: Tuesday, March 4, 2008, 6:30 p.m. Location: Auburn Recreation DistrictCanyon View Community Center. Scoping Document 1 (SD1), which outlines the subject areas to be addressed in the environmental document, was mailed to the individuals and entities on the Commission’s mailing list. Copies of SD1 will be available at the scoping meetings, or may be viewed on the web at https://www.ferc.gov, using the ‘‘eLibrary’’ link. Follow the directions for accessing information in paragraph n. Based on all oral and written comments, a Scoping Document 2 (SD2) may be issued. SD2 may include a revised process plan and schedule, as well as a list of issues, identified through the scoping process. mstockstill on PROD1PC66 with NOTICES Site Visit Typically, a site visit is held together with the scoping meeting. However, because most of the project sites will not be accessible in March, the licensees and Commission staff will visit the project sites on Wednesday, June 25, 2008, starting at 8 AM. All participants should meet at Auburn Recreation District Canyon View Community Center, located at 471 Maidu Drive, Auburn, California. Placer County Water Agency will provide transportation for participants. Anyone interested in attending the site visit should contact Mr. Mal Toy of Placer County Water Agency at (530) 823–4889 by June 11, 2008. Meeting Objectives At the scoping meetings, staff will: (1) Initiate scoping of the issues; (2) review and discuss existing conditions and resource management objectives; (3) review and discuss existing information and identify preliminary information and study needs; (4) review and discuss the process plan and schedule for prefiling activity that incorporates the time frames provided for in Part 5 of the Commission’s regulations and, to the extent possible, maximizes coordination of federal, state, and tribal permitting and certification processes; and (5) discuss the appropriateness of any federal or state agency or Indian tribe acting as a cooperating agency for development of an environmental document. Meeting participants should come prepared to discuss their issues and/or concerns. Please review the PAD in preparation for the scoping meetings. Directions on how to obtain a copy of the PAD and SD1 are included in item n. of this document. VerDate Aug<31>2005 16:52 Feb 15, 2008 Jkt 214001 Meeting Procedures The meetings will be recorded by a stenographer and will become part of the formal record of the Commission proceeding on the project. FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5 p.m. Eastern Time on March 5, 2008. Kimberly D. Bose, Secretary. [FR Doc. E8–2989 Filed 2–15–08; 8:45 am] Kimberly D. Bose, Secretary. [FR Doc. E8–2968 Filed 2–15–08; 8:45 am] BILLING CODE 6717–01–P BILLING CODE 6717–01–P DEPARTMENT OF ENERGY DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Federal Energy Regulatory Commission [Docket No. RC08–4–000] [Docket No. ER08–499–000] New Harquahala Generating Company, LLC; Notice of Filing Pacific Gas and Electric Company; Notice of Filing February 8, 2008. February 8, 2008. Take notice that on February 4, 2008, New Harquahala Generating Company, LLC (Harquahala) submitted a request for appeal of a NERC decision regarding Harquahala’s registration as a Transmission Owner and Transmission Operator in the NERC Compliance Registry. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the comment date. On or before the comment date, it is not necessary to serve motions to intervene or protests on persons other than the Applicant. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail PO 00000 Frm 00029 Fmt 4703 Sfmt 4703 Take notice that on January 31, 2008, Pacific Gas and Electric Company (PG&E) and Sierra Pacific Power Company tendered for filing a replacement Interconnection Agreement between both parties and a Notice of Termination of PG&E First Revised Rate Schedule No. 72, the existing Interconnection Agreement. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the comment date. On or before the comment date, it is not necessary to serve motions to intervene or protests on persons other than the Applicant. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC E:\FR\FM\19FEN1.SGM 19FEN1

Agencies

[Federal Register Volume 73, Number 33 (Tuesday, February 19, 2008)]
[Notices]
[Pages 9113-9114]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-2989]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2079-061]


Placer County Water Agency; Notice of Intent To File License 
Application, Filing of Pre-Application Document, Commencement of 
Licensing Proceeding, Scoping, Solicitation of Comments on the Pad and 
Scoping Document, and Identification Issues and Associated Study 
Requests

February 11, 2008.
    a. Type of Filing: Notice of Intent to File License Application for 
a New License and Commencing Licensing Proceeding.
    b. Project No.: 2079-061.
    c. Dated Filed: December 13, 2007.
    d. Submitted By: Placer County Water Agency.
    e. Name of Project: Middle Fork American River Project.
    f. Location: The Middle Fork American River Project is located in 
Placer and El Dorado counties, almost entirely within the Tahoe and El 
Dorado National Forests. The project occupies 3811 acres of United 
States lands under the jurisdiction of the Forest Service.
    g. Filed Pursuant to: 18 CFR Part 5 of the Commission's 
Regulations.
    h. Applicant Contact: David A. Breninger, General Manager, Placer 
County Water Agency, P.O. Box 6570, Auburn, CA 95604.
    i. FERC Contact: Jim Fargo at 202-502-6095 or e-mail 
james.fargo@ferc.gov.
    j. We are asking Federal, State, local, and tribal agencies with 
jurisdiction and/or special expertise with respect to environmental 
issues to cooperate with us in the preparation of the environmental 
document. Agencies who would like to request cooperating status should 
follow the instructions for filing comments described in paragraph o 
below. Cooperating agencies should note the Commission's policy that 
agencies that cooperate in the preparation of the environmental 
document cannot also intervene. See, 94 FERC 61,076 (2001).
    k. With this notice, we are initiating informal consultation with: 
(a) The U.S. Fish and Wildlife Service and/or NOAA Fisheries under 
section 7 of the Endangered Species Act and the joint agency 
regulations thereunder at 50 CFR Part 402 and (b) the State Historic 
Preservation Officer, as required by section 106, National Historical 
Preservation Act, and the implementing regulations of the Advisory 
Council on Historic Preservation at 36 CFR 800.2.
    l. With this notice, we are designating Placer County Water Agency 
as the Commission's non-federal representative for carrying out 
informal consultation, pursuant to section 7 of the Endangered Species 
Act and section 106 of the National Historic Preservation Act.
    m. Placer County Water Agency filed a Pre-Application Document 
(PAD; including a proposed process plan and schedule) with the 
Commission, pursuant to 18 CFR 5.6 of the Commission's regulations.
    n. A copy of the PAD is available for review at the Commission in 
the Public Reference Room or may be viewed on the Commission's Web site 
(https://www.ferc.gov), using the ``eLibrary'' link. Enter the docket 
number, excluding the last three digits in the docket number field to 
access the document. For assistance, contact FERC Online Support at 
FERCOnlineSupport@ferc.gov or toll free at 1-866-208-3676, of for TTY, 
(202) 502-8659. A copy is also available for inspection and 
reproduction at the address in paragraph h.
    Register online at https://ferc.gov/esubscribenow.htm to be notified 
via e-mail of new filing and issuances related to this or other pending 
projects. For assistance, contact FERC Online Support.
    o. With this notice, we are soliciting comments on the PAD and 
Scoping Document 1 (SD1), as well as study requests. All comments on 
the PAD and SD1, and study requests should be sent to the address above 
in paragraph h. In addition, all comments on the PAD and SD1, study 
requests, requests for cooperating agency status, and all 
communications to and from Commission staff related to the merits of 
the potential application (original and eight copies) must be filed 
with the Commission at the following address: Kimberly D. Bose, 
Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., 
Washington, DC 20426. All filings with the Commission must include on 
the first page, the project name (Middle Fork American River Project) 
and number (P-2079-061), and bear the heading ``Comments on Pre-
Application Document,'' ``Study Requests,'' ``Comments on Scoping 
Document 1,'' ``Request for Cooperating Agency Status,'' or 
``Communications to and from Commission Staff.'' Any individual or 
entity interested in submitting study requests, commenting on the PAD 
or SD1, and any agency requesting cooperating status must do so by 
April 11, 2008.
    Comments on the PAD and SD1, study requests, requests for 
cooperating agency status, and other permissible forms of 
communications with the Commission may be filed electronically via the 
Internet in lieu of paper. The Commission strongly encourages 
electronic filings. See 18 CFR 385.2001(a)(1)(iii) and the instructions 
on the Commission's Web site (https://www.ferc.gov) under the ``e-
filing'' link.
    p. Our intent is to prepare an Environmental Impact Statement (EIS) 
for which the planned meetings will satisfy the NEPA scoping 
requirements.

Scoping Meetings

    Commission staff will hold two scoping meetings in the vicinity of 
the project at the time and place noted below. The daytime meeting will 
focus on resource agency, Indian tribes, and non-governmental 
organization concerns, while the evening meeting is primarily for 
receiving input from the public. We invite all interested individuals, 
organizations, and agencies to attend one or both of the meetings, and 
to assist staff in identifying particular study needs, as well as the 
scope of environmental issues to be addressed in the environmental 
document. The times and locations of these meetings are as follows:

Daytime Scoping Meeting

    Date and Time: Tuesday, March 4, 2008, 9 a.m.
    Location: Auburn Recreation District-Canyon View Community Center.

[[Page 9114]]

Evening Scoping Meeting

    Date and Time: Tuesday, March 4, 2008, 6:30 p.m.
    Location: Auburn Recreation District-Canyon View Community Center.
    Scoping Document 1 (SD1), which outlines the subject areas to be 
addressed in the environmental document, was mailed to the individuals 
and entities on the Commission's mailing list. Copies of SD1 will be 
available at the scoping meetings, or may be viewed on the web at 
https://www.ferc.gov, using the ``eLibrary'' link. Follow the directions 
for accessing information in paragraph n. Based on all oral and written 
comments, a Scoping Document 2 (SD2) may be issued. SD2 may include a 
revised process plan and schedule, as well as a list of issues, 
identified through the scoping process.

Site Visit

    Typically, a site visit is held together with the scoping meeting. 
However, because most of the project sites will not be accessible in 
March, the licensees and Commission staff will visit the project sites 
on Wednesday, June 25, 2008, starting at 8 AM. All participants should 
meet at Auburn Recreation District Canyon View Community Center, 
located at 471 Maidu Drive, Auburn, California. Placer County Water 
Agency will provide transportation for participants. Anyone interested 
in attending the site visit should contact Mr. Mal Toy of Placer County 
Water Agency at (530) 823-4889 by June 11, 2008.

Meeting Objectives

    At the scoping meetings, staff will: (1) Initiate scoping of the 
issues; (2) review and discuss existing conditions and resource 
management objectives; (3) review and discuss existing information and 
identify preliminary information and study needs; (4) review and 
discuss the process plan and schedule for pre-filing activity that 
incorporates the time frames provided for in Part 5 of the Commission's 
regulations and, to the extent possible, maximizes coordination of 
federal, state, and tribal permitting and certification processes; and 
(5) discuss the appropriateness of any federal or state agency or 
Indian tribe acting as a cooperating agency for development of an 
environmental document.
    Meeting participants should come prepared to discuss their issues 
and/or concerns. Please review the PAD in preparation for the scoping 
meetings. Directions on how to obtain a copy of the PAD and SD1 are 
included in item n. of this document.

Meeting Procedures

    The meetings will be recorded by a stenographer and will become 
part of the formal record of the Commission proceeding on the project.

Kimberly D. Bose,
Secretary.
[FR Doc. E8-2989 Filed 2-15-08; 8:45 am]