Alabama Power Company; Notice of Application for Amendment of License and Soliciting Comments, Motions to Intervene, and Protests, 8652-8653 [E8-2726]
Download as PDF
8652
Federal Register / Vol. 73, No. 31 / Thursday, February 14, 2008 / Notices
Number of responses per
respondent
Average burden house per
response
Total annual burden hours
(1)
(2)
(3)
(1)×(2)×(3)
200
rwilkins on PROD1PC63 with NOTICES
Number of respondents annually
1
.30
60
The estimated total cost to
respondents is $3,646. The cost per
respondent = $18. (60 hours @ $61
hourly rate (rounded off)).
The reporting burden includes the
total time, effort, or financial resources
expended to generate, maintain, retain,
disclose, or provide the information
including: (1) Reviewing instructions;
(2) developing, acquiring, installing, and
utilizing technology and systems for the
purposes of collecting, validating,
verifying, processing, maintaining,
disclosing and providing information;
(3) adjusting the existing ways to
comply with any previously applicable
instructions and requirements; (4)
training personnel to respond to a
collection of information; (5) searching
data sources; (6) completing and
reviewing the collection of information;
and (7) transmitting, or otherwise
disclosing the information.
The estimate of cost for respondents
is based upon salaries for professional
and clerical support, as well as direct
and indirect overhead costs. Direct costs
include all costs directly attributable to
providing this information, such as
administrative costs and the cost for
information technology. Indirect or
overhead costs are costs incurred by an
organization in support of its mission.
These costs apply to activities which
benefit the whole organization rather
than any one particular function or
activity.
Comments are invited on: (1) Whether
the proposed collection of information
is necessary for the proper performance
of the functions of the Commission,
including whether the information will
have practical utility; (2) the accuracy of
the agency’s estimate of the burden of
the proposed collection of information,
including the validity of the
methodology and assumptions used; (3)
ways to enhance the quality, utility and
clarity of the information to be
collected; and (4) ways to minimize the
burden of the collection of information
on those who are to respond, including
the use of appropriate automated,
electronic, mechanical, or other
technological collection techniques or
other forms of information technology
VerDate Aug<31>2005
16:49 Feb 13, 2008
Jkt 214001
e.g. permitting electronic submission of
responses.
Kimberly D. Bose,
Secretary.
[FR Doc. E8–2720 Filed 2–13–08; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2146–117]
Alabama Power Company; Notice of
Application for Amendment of License
and Soliciting Comments, Motions to
Intervene, and Protests
February 7, 2008.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Application Type: Non-Project Use
of Project Lands and Waters.
b. Project No: 2146–117.
c. Date Filed: January 18, 2008.
d. Applicant: Alabama Power
Company.
e. Name of Project: Coosa River
Project.
f. Location: On the Coosa River, in
Elmore County, Alabama and Floyd
County, Georgia.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r.
h. Applicant Contact: Keith Bryant,
600 18th Street North, Birmingham, AL
35203; (205) 257–1403.
i. FERC Contact: Gina Krump,
Telephone (202) 502–6704, and e-mail:
Gina.Krump@ferc.gov.
j. Deadline for filing comments,
motions to intervene, and protest:
March 3, 2008.
All documents (original and eight
copies) should be filed with: Secretary,
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
The Commission’s Rules of Practice
and Procedure require all interveners
filing documents with the Commission
to serve a copy of that document on
each person whose name appears on the
official service list for the project.
Further, if an intervener files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
PO 00000
Frm 00011
Fmt 4703
Sfmt 4703
particular resource agency, they must
also serve a copy of the document on
that resource agency. A copy of any
motion to intervene must also be served
upon each representative of the
Applicant specified in the particular
application.
k. Description of Request: Alabama
Power Company is seeking Commission
approval to issue a permit to RHEMA,
LLC for the construction of a boat ramp,
four boat docks, totaling 60 slips,
walking trails, and two storm water
drains. The proposed facilities would
serve the residents of Sunset Shores
Condominiums. APC is also seeking
authorization to allow RHEMA, LLC to
withdrawal of up to 2,400 gallons per
day of water from the project reservoir
for landscape watering, as needed. The
proposal would not require dredging or
excavation.
l. Locations of the Application: A
copy of the application is available for
inspection and reproduction at the
Commission’s Public Reference Room,
located at 888 First Street, NE., Room
2A, Washington, DC 20426, or by calling
(202) 502–8371. This filing may also be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. You may also register online
at https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, call 1–866–208–3676 or
e-mail FERCOnlineSupport@ferc.gov,
for TTY, call (202) 502–8659. A copy is
also available for inspection and
reproduction at the address in item (h)
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
E:\FR\FM\14FEN1.SGM
14FEN1
Federal Register / Vol. 73, No. 31 / Thursday, February 14, 2008 / Notices
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
o. Any filings must bear in all capital
letters the title ‘‘COMMENTS’’,
‘‘PROTEST’’, or ‘‘MOTION TO
INTERVENE’’, as applicable, and the
Project Number of the particular
application to which the filing refers.
p. Agency Comments: Federal, State,
and local agencies are invited to file
comments on the described application.
A copy of the application may be
obtained by agencies directly from the
Applicant. If an agency does not file
comments within the time specified for
filing comments, it will be presumed to
have no comments. One copy of an
agency’s comments must also be sent to
the Applicant’s representatives.
q. Comments, protests and
interventions may be filed electronically
via the Internet in lieu of paper. See, 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site at https://www.ferc.gov under the ‘‘eFiling’’ link.
Kimberly D. Bose,
Secretary.
[FR Doc. E8–2726 Filed 2–13–08; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 1951–153]
Georgia Power Company; Notice of
Amendment of License and Soliciting
Comments, Motions To Intervene, and
Protests
rwilkins on PROD1PC63 with NOTICES
February 7, 2008.
Take notice that the following
application has been filed with the
Commission and is available for public
inspection:
a. Application Type: Non-Project Use
of Project Lands and Waters.
b. Project No: 1951–153.
c. Date filed: January 18, 2008.
d. Applicant: Georgia Power
Company.
e. Name of Project: Sinclair Project.
f. Location: The project is located on
the Oconee River in Baldwin and
Putnam Counties, Georgia. The project
does not occupy federal lands.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r) and 799
and 801.
h. Applicant Contact: Mr. Lee B.
Glenn, Georgia Power Company, 125
Wallace Dam Road NE, Eatonton, GA
31024, (706) 485–8704.
VerDate Aug<31>2005
16:49 Feb 13, 2008
Jkt 214001
i. FERC Contact: Rebecca Martin at
202–502–6012, or e-mail
rebecca.martin@ferc.gov
j. Deadline for filing comments and or
motions: March 7, 2008.
All documents (original and eight
copies) should be filed with: The
Secretary, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington DC 20426.
Please include the project number (P–
1951–153) on any comments or motions
filed.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person whose name appears on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency. A copy of any
motion to intervene must also be served
upon each representative of the
Applicant specified in the particular
application.
k. Description of Application: The
licensee requests Commission approval
to grant a permit to SOS Development,
LLC for constructing nine, ten-slip, boat
docks (11,970 square feet total), six of
which would be located within coves;
15,050 linear feet (2.85 miles) of
seawall, and a 200-square foot boat
ramp. Since many of the boat docks
would be constructed in currently
unnavigable, shallow areas,
approximately 7,800 cubic yards of
dredging also would be performed. The
proposed facilities and improvements
would be as part of a development
called ‘‘The Sanctuary on Lake
Sinclair,’’ and would be used by its
residents.
l. Location of Application: A copy of
the application is available for
inspection and reproduction at the
Commission’s Public Reference Room,
located at 888 First Street, NE, Room
2A, Washington, DC 20426, or by calling
(202) 502–8371. This filing may also be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. You may also register online
at https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, call 1–866–208–3676 or
e-mail FERCOnlineSupport@ferc.gov,
for TTY, call (202) 502–8659. A copy is
also available for inspection and
PO 00000
Frm 00012
Fmt 4703
Sfmt 4703
8653
reproduction at the address in item (h)
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
o. Any filings must bear in all capital
letters the title ‘‘COMMENTS’’,
‘‘PROTEST’’, OR ‘‘MOTION TO
INTERVENE’’, as applicable, and the
Project Number of the particular
application to which the filing refers. A
copy of any motion to intervene must
also be served upon each representative
of the Applicant specified in the
particular application.
p. Agency Comments: Federal, State,
and local agencies are invited to file
comments on the described application.
A copy of the application may be
obtained by agencies directly from the
Applicant. If an agency does not file
comments within the time specified for
filing comments, it will be presumed to
have no comments. One copy of an
agency’s comments must also be sent to
the Applicant’s representatives.
q. Comments, protests and
interventions may be filed electronically
via the Internet in lieu of paper. See, 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site at https://www.ferc.gov under the ‘‘eFiling’’ link.
Kimberly D. Bose,
Secretary.
[FR Doc. E8–2724 Filed 2–13–08; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ID–5604–000]
Lee, John C., Jr.; Notice of Filing
February 7, 2008.
Take notice that on January 25, 2008,
pursuant to section 305(b) of the Federal
E:\FR\FM\14FEN1.SGM
14FEN1
Agencies
[Federal Register Volume 73, Number 31 (Thursday, February 14, 2008)]
[Notices]
[Pages 8652-8653]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-2726]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2146-117]
Alabama Power Company; Notice of Application for Amendment of
License and Soliciting Comments, Motions to Intervene, and Protests
February 7, 2008.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Application Type: Non-Project Use of Project Lands and Waters.
b. Project No: 2146-117.
c. Date Filed: January 18, 2008.
d. Applicant: Alabama Power Company.
e. Name of Project: Coosa River Project.
f. Location: On the Coosa River, in Elmore County, Alabama and
Floyd County, Georgia.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
h. Applicant Contact: Keith Bryant, 600 18th Street North,
Birmingham, AL 35203; (205) 257-1403.
i. FERC Contact: Gina Krump, Telephone (202) 502-6704, and e-mail:
Gina.Krump@ferc.gov.
j. Deadline for filing comments, motions to intervene, and protest:
March 3, 2008.
All documents (original and eight copies) should be filed with:
Secretary, Federal Energy Regulatory Commission, 888 First Street, NE.,
Washington, DC 20426.
The Commission's Rules of Practice and Procedure require all
interveners filing documents with the Commission to serve a copy of
that document on each person whose name appears on the official service
list for the project. Further, if an intervener files comments or
documents with the Commission relating to the merits of an issue that
may affect the responsibilities of a particular resource agency, they
must also serve a copy of the document on that resource agency. A copy
of any motion to intervene must also be served upon each representative
of the Applicant specified in the particular application.
k. Description of Request: Alabama Power Company is seeking
Commission approval to issue a permit to RHEMA, LLC for the
construction of a boat ramp, four boat docks, totaling 60 slips,
walking trails, and two storm water drains. The proposed facilities
would serve the residents of Sunset Shores Condominiums. APC is also
seeking authorization to allow RHEMA, LLC to withdrawal of up to 2,400
gallons per day of water from the project reservoir for landscape
watering, as needed. The proposal would not require dredging or
excavation.
l. Locations of the Application: A copy of the application is
available for inspection and reproduction at the Commission's Public
Reference Room, located at 888 First Street, NE., Room 2A, Washington,
DC 20426, or by calling (202) 502-8371. This filing may also be viewed
on the Commission's Web site at https://www.ferc.gov using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. You may also
register online at https://www.ferc.gov/docs-filing/esubscription.asp to
be notified via e-mail of new filings and issuances related to this or
other pending projects. For assistance, call 1-866-208-3676 or e-mail
FERCOnlineSupport@ferc.gov, for TTY, call (202) 502-8659. A copy is
also available for inspection and reproduction at the address in item
(h) above.
m. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
n. Comments, Protests, or Motions to Intervene: Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214. In determining the appropriate action to take, the Commission
will consider all protests or other comments filed, but only those who
file a motion to intervene in accordance with the Commission's Rules
may become a
[[Page 8653]]
party to the proceeding. Any comments, protests, or motions to
intervene must be received on or before the specified comment date for
the particular application.
o. Any filings must bear in all capital letters the title
``COMMENTS'', ``PROTEST'', or ``MOTION TO INTERVENE'', as applicable,
and the Project Number of the particular application to which the
filing refers.
p. Agency Comments: Federal, State, and local agencies are invited
to file comments on the described application. A copy of the
application may be obtained by agencies directly from the Applicant. If
an agency does not file comments within the time specified for filing
comments, it will be presumed to have no comments. One copy of an
agency's comments must also be sent to the Applicant's representatives.
q. Comments, protests and interventions may be filed electronically
via the Internet in lieu of paper. See, 18 CFR 385.2001(a)(1)(iii) and
the instructions on the Commission's Web site at https://www.ferc.gov
under the ``e-Filing'' link.
Kimberly D. Bose,
Secretary.
[FR Doc. E8-2726 Filed 2-13-08; 8:45 am]