State of Nevada; Denial of Petition for Rulemaking, 5762-5767 [E8-1751]
Download as PDF
5762
Proposed Rules
Federal Register
Vol. 73, No. 21
Thursday, January 31, 2008
This section of the FEDERAL REGISTER
contains notices to the public of the proposed
issuance of rules and regulations. The
purpose of these notices is to give interested
persons an opportunity to participate in the
rule making prior to the adoption of the final
rules.
NUCLEAR REGULATORY
COMMISSION
10 CFR Part 51
[Docket No. PRM–51–9]
State of Nevada; Denial of Petition for
Rulemaking
Nuclear Regulatory
Commission.
ACTION: Petition for rulemaking: denial.
sroberts on PROD1PC70 with PROPOSALS
AGENCY:
SUMMARY: The U.S. Nuclear Regulatory
Commission (NRC or Commission) is
denying a petition for rulemaking
submitted by the State of Nevada (PRM–
51–9). The petition requests that NRC
modify its regulation setting criteria for
adoption of an environmental impact
statement prepared by the Secretary of
the Department of Energy in
proceedings for issuance of a
construction authorization and
materials license with respect to a
geologic repository. The petitioner
asserts that the current regulation must
be ‘‘corrected’’ because it is at odds with
a recent court of appeals decision.
Further, petitioner asserts that certain
litigation procedures that will be used
in the proceedings to consider the
adoption question violate the National
Environmental Policy Act of 1969, as
amended (NEPA). NRC is denying the
petition because the court found no
reason for NRC to correct its adoption
criteria and because the petition does
not demonstrate that NRC’s litigation
procedures violate NEPA.
Commissioner Gregory B. Jaczko’s vote
on this denial is included in Appendix
I to this notice.
ADDRESSES: Publicly available
documents related to this petition,
including the petition for rulemaking,
the comments received, and NRC’s letter
of denial to the petitioner may be
viewed electronically on public
computers in NRC’s Public Document
Room (PDR), 01F21, One White Flint
North, 11555 Rockville Pike, Rockville,
Maryland. The PDR reproduction
VerDate Aug<31>2005
17:23 Jan 30, 2008
Jkt 214001
contractor will copy documents for a
fee.
Publicly available documents created
or received at NRC after November 1,
1999, are also available electronically at
the NRC’s Electronic Reading Room at
https://www.nrc.gov/reading-rm/
adams.html. From this site, the public
can gain entry into the NRC’s
Agencywide Documents Access and
Management System (ADAMS), which
provides text and image files of NRC’s
public documents. If you do not have
access to ADAMS or if there are
problems in accessing the documents
located in ADAMS, contact the PDR
reference staff at (800) 387–4209, (301)
415–4737 or by e-mail to pdr@nrc.gov.
Jerry
Bonanno, Office of the General Counsel,
U.S. Nuclear Regulatory Commission,
Washington, DC 20555–0001, telephone
(301) 415–1328 or Toll Free: 1–800–
368–5642, e-mail: jxb5@nrc.gov.
FOR FURTHER INFORMATION CONTACT:
SUPPLEMENTARY INFORMATION:
Introduction
On April 8, 2005, the State of Nevada
(petitioner or the State) submitted a
‘‘Petition by the State of Nevada to
Amend 10 CFR 51.109’’ (petition),
which was docketed as a petition for
rulemaking under 10 CFR 2.802 of the
Commission’s regulations (PRM–51–9).
The petition was noticed on August 12,
2005 (70 FR 47148) with a public
comment period that closed on October
26, 2005. Three comment letters were
received. The petition requests
amendments to the Commission’s
regulation at 10 CFR 51.109 governing
NRC’s adoption of the Department of
Energy’s (DOE) final environmental
impact statement (FEIS), and any
supplements thereto, which
accompanied the Secretary of Energy’s
(the Secretary) recommendation to the
President that the Yucca Mountain,
Nevada (YM) site be approved for the
development of a geologic repository.
Petitioner believes that the current
regulation is contrary to the NEPA, the
Nuclear Waste Policy Act of 1982, as
amended (NWPA), and the decision of
the U.S. Court of Appeals for the District
of Columbia Circuit in Nuclear Energy
Institute, Inc. v. Environmental
Protection Agency, 373 F.3d 1251 (D.C.
Cir. 2004) (NEI).
PO 00000
Frm 00001
Fmt 4702
Sfmt 4702
Background
A. Statutory and Regulatory Background
of § 51.109
Section 114(f)(4) of the NWPA
provides that ‘‘[a]ny [EIS] prepared in
connection with a repository proposed
to be constructed by the Secretary under
this subtitle shall, to the extent
practicable, be adopted by the
Commission in connection with the
issuance by the Commission of a
construction authorization and license
for such repository’’ (emphasis added).
The statute further provides that ‘‘[t]o
the extent such statement is adopted by
the Commission, such adoption shall be
deemed to also satisfy the
responsibilities of the Commission
under the [NEPA] and no further
consideration shall be required, except
that nothing in this subsection shall
affect any independent responsibilities
of the Commission to protect public
health under the Atomic Energy Act of
1954 (42 U.S.C. 2011 et seq.).’’ In 1988–
89, NRC conducted a rulemaking to set
out the standards and procedures that
would be used in licensing proceedings
for determining whether NRC’s
adoption of DOE’s FEIS is practicable.
See, 53 FR 16131; May 5, 1988
(proposed rule); 54 FR 27864; July 3,
1989 (final rule). In that rulemaking,
NRC determined that the NWPA had
altered NRC’s ordinary NEPA
responsibilities in such a manner as to
narrow the scope of NRC’s independent
review of environmental issues that had
been decided by DOE in its FEIS. As
summarized by the Commission in the
final rule,
[T]he Commission continues to emphasize
its view that its role under NWPA is oriented
toward health and safety issues and that, in
general, nonradiological environmental
issues are intended to be resolved in advance
of NRC licensing decisions through the
actions of the Department of Energy, subject
to Congressional and judicial review in
accordance with NWPA and other applicable
law. The Commission anticipates that many
environmental questions would have been, or
at least could have been, adjudicated in
connection with an environmental impact
statement prepared by DOE, and such
questions should not be reopened in
proceedings before NRC.
54 FR at 27865.
Accordingly, NRC’s 1989 final rule
established, in a new 10 CFR 51.109,
‘‘Public hearings in proceedings for
issuance of materials license with
E:\FR\FM\31JAP1.SGM
31JAP1
Federal Register / Vol. 73, No. 21 / Thursday, January 31, 2008 / Proposed Rules
respect to a geologic repository,’’
procedures and criteria for
implementing the statutory directive to
adopt DOE’s FEIS to the extent
practicable. Under § 51.109(a)(1), the
NRC staff must present its position on
whether it is practicable to adopt,
without further supplementation, DOE’s
FEIS upon publication of the notice of
hearing in the Federal Register. Under
§ 51.109(a)(2), parties to a proceeding
are given the opportunity to submit
contentions asserting that it is not
practicable to adopt:
(a)(2) Any other party to the proceeding
who contends that it is not practicable to
adopt the DOE [FEIS], as it may have been
supplemented, shall file a contention to that
effect within thirty (30) days after the
publication of the notice of hearing in the
Federal Register. Such contention must be
accompanied by one or more affidavits which
set forth factual and/or technical bases for the
claim that, under the principles set forth in
paragraphs (c) and (d) of this section, it is not
practicable to adopt the DOE [FEIS], as it may
have been supplemented. The presiding
officer shall resolve disputes concerning
adoption of the DOE [FEIS] by using, to the
extent possible, the criteria and procedures
that are followed in ruling on motions to
reopen under § 2.236 of this chapter.
10 CFR 51.109(a)(2)(2007).1 The criteria
governing the practicability of adoption
are set forth in § 51.109(c):
(c) The presiding officer will find that it is
practicable to adopt any environmental
impact statement prepared by the Secretary
of Energy in connection with a geologic
repository proposed to be constructed under
Title I of the Nuclear Waste Policy Act of
1982, as amended, unless:
(1)(i) The action proposed to be taken by
the Commission differs from the action
proposed in the license application
submitted by the Secretary of Energy; and
(ii) The difference may significantly affect
the quality of the human environment; or
(2) Significant and substantial new
information or new considerations render
such environmental impact statement
inadequate.
sroberts on PROD1PC70 with PROPOSALS
10 CFR 51.109(c) (2007).
B. DOE’s FEIS
The NWPA, inter alia, establishes a
process for the characterization, siting,
construction, and operation of a
geologic repository at the YM site. As
relevant here, when site characterization
activities are completed, the Secretary of
Energy may recommend site approval to
the President and any such
recommendation must be accompanied
by a FEIS. See, section 114(a)(1) of the
1 In 2004, § 51.109(a)(2) was revised to reference
a new section number for motions to reopen as part
of the Commission’s revision of its rules of practice
in adjudicatory proceedings. See 69 FR 2182, 2276
(January 14, 2004). The standards for reopening
were not changed.
VerDate Aug<31>2005
17:23 Jan 30, 2008
Jkt 214001
NWPA. Then, the President may
recommend the site to the Congress and
must include a copy of the documents
comprising the basis of the Secretary’s
recommendation, including the FEIS.
See, section 114(a)(2). The State is then
given an opportunity to submit a notice
of disapproval of the site designation
which, however, may be overcome by a
joint resolution of the Congress
approving the recommended repository
site. See, sections 115 and 116 of the
NWPA. If the site designation is
permitted to take effect under the
provisions of section 115, the Secretary
of Energy shall submit an application
for a construction authorization to NRC.
See, section 114(b) of the NWPA. In
February 2002, the Secretary issued the
Final Environmental Impact Statement
for a Geologic Repository for the
Disposal of Spent Nuclear Fuel and
High-Level Radioactive Waste at Yucca
Mountain, Nye County, Nevada and
recommended the YM site to the
President. The President then
recommended the YM site to the
Congress. In April 2002, the State of
Nevada submitted a notice of
disapproval to the Congress. However,
Congress approved the site designation
by a Joint Resolution signed by the
President on July 23, 2002. Public Law
107–200, 116 Stat. 735 (2002) (codified
at 42 U.S.C. 10135 note (Supp. IV
2004)).
C. The NEI Decision
Thereafter, the State of Nevada sought
court review of the Secretary’s decision
to recommend the YM site to the
President, the President’s decision to
recommend the YM site to the Congress,
and DOE’s FEIS, which had been used
to support both recommendations. In
response, DOE argued that the Joint
Resolution had rendered moot Nevada’s
challenges to the Secretary’s and the
President’s recommendations, with the
result that Nevada’s claims that the FEIS
was inadequate could not be considered
as part of the challenges to these
recommendations. Further, DOE argued
that, insofar as the FEIS might be used
to support future DOE and NRC
decisions, the FEIS was unripe for
review because there was no final
agency action affecting the State at that
time.
In the litigation resulting in the NEI
decision, the State’s challenges to the
Secretary’s and the President’s
recommendations and to the FEIS were
combined with other issues raised by
the State and with other lawsuits
concerning the YM repository,
including challenges to both the
Environmental Protection Agency’s final
standards (66 FR 32,074; June 13, 2001)
PO 00000
Frm 00002
Fmt 4702
Sfmt 4702
5763
and NRC’s final regulations for the
proposed geologic repository at YM (66
FR 55,732; November 2, 2001).
However, NRC’s procedures and criteria
for adoption of DOE’s FEIS were not
issues raised in any of the lawsuits and
NRC’s rationale for adoption of the
§ 51.109 procedures and criteria was
neither briefed nor argued by NRC. NRC
did describe in its brief its regulatory
adoption process in the context of an
issue raised by Nevada concerning
NRC’s regulation at 10 CFR 63.341,
which required DOE to include the
results of its projections of peak dose in
its FEIS.2 See, Brief for the Federal
Respondents, State of Nevada v. U.S.
Nuclear Regulatory Commission, Nos.
01–1116 and 03–1058, June 6, 2003, at
44–45. In resolving this issue, the court
noted NRC’s statement ‘‘that it has
imposed no categorical limitation on
any challenge to DOE’s peak dose
calculations and that, under its
regulations, parties to the proceeding
may challenge the practicability of
adopting aspects of DOE’s EIS,
including the peak dose calculations,
based on substantial new information to
the contrary.’’ 375 F.3d 1251, at 1300
(internal quotations omitted).
In NEI, the court agreed with DOE
that Congress’ enactment of the Joint
Resolution had rendered moot issues
raised concerning the Secretary’s and
the President’s recommendation of the
YM site. See 373 F.3d at 1309. Thus, the
court held that ‘‘[i]nsofar as Nevada’s
instant challenge to the FEIS is intended
to reverse the decision to select the
Yucca site, the challenge is moot * * *’’
373 F.3d at 1312. However, the court
noted the anticipated use of the FEIS in
future decisionmaking related to YM,
including its potential adoption by NRC
in NRC’s licensing proceeding, and
considered whether the court should
review the FEIS because it might be
used to support future decisions. The
court determined that the FEIS was not
ripe for review under the two-part test
used to determine ripeness: The fitness
of the issue for judicial decision and the
hardship to the parties of withholding
court consideration. Under the first
prong of the test, the court noted that it
was unclear to what extent NRC would
adopt the FEIS and whether the FEIS
would require supplementation prior to
any adoption. The court concluded that
‘‘[o]ur review of the FEIS therefore
would benefit from postponing
consideration until the FEIS has been
used to support a specific, concrete, and
final decision.’’ 373 F.3d at 1313. Under
2 In 2005, NRC proposed to eliminate § 63.341 as
part of its proposed amendments to 10 CFR Part 63.
See, 70 FR 53313 (September 8, 2005).
E:\FR\FM\31JAP1.SGM
31JAP1
5764
Federal Register / Vol. 73, No. 21 / Thursday, January 31, 2008 / Proposed Rules
the second prong of the test, the court
concluded that ‘‘withholding
consideration of Nevada’s substantive
claims at this time imposes no hardship
on Nevada * * * [because] Nevada may
raise its substantive claims against the
FEIS if and when NRC or DOE makes
* * * a final decision.’’ Id. In reaching
this conclusion as to hardship, the court
stated that ‘‘we rely on the assurances
of counsel for both NRC and DOE at oral
argument that Nevada will be permitted
to raise its substantive challenges to the
FEIS in any NRC proceeding to decide
whether to adopt the FEIS and in any
DOE proceeding to select a
transportation alternative.’’ Id.
The Petition
sroberts on PROD1PC70 with PROPOSALS
The petitioner agrees that § 51.109 ‘‘in
most respects tracks the language of
[section 114(f)(4) of the NWPA]’’ on
which it is based. Petition at 2.
However, the petitioner claims that this
regulation also adds three special
provisions not found in the statute: (1)
Special procedures for litigation of
NEPA issues; (2) allowance for adoption
of DOE supplements to the FEIS; and (3)
special standards that specify in some
detail precisely when NRC will adopt
the FEIS. The petitioner believes that
the Commission must conduct a
rulemaking to eliminate the ‘‘special
litigation procedures’’ and to correct the
‘‘special adoption standards.’’ The
petition makes no further reference to
the second ‘‘special provision’’ and
suggests no rule change with respect to
this provision. There is no apparent
reason why Congress would have
intended to exclude supplements to the
FEIS in its requirement for NRC to adopt
DOE’s FEIS to the extent practicable, so
we do not regard this provision of the
regulation as being within the petition
for rulemaking.
To correct the criteria for assessing
the practicability of adoption, petitioner
requests that the Commission add a new
paragraph (h) to § 51.109:
Nothing in this section shall be construed
to limit the ability of any party or interested
governmental participant to challenge in a
licensing hearing any environmental impact
statement (including any supplement thereto)
prepared by the Secretary of Energy on the
ground that such statement violates NEPA or
the regulations of the Council on
Environmental Quality, provided that the
challenge is not barred by traditional
principles of federal collateral estoppel.
Collateral estoppel shall not bar the
admission of a NEPA contention if the
standards in subparagraphs (c)(1) and (c)(2)
of this section are met, provided that the
change in the proposed action or new
information or considerations became known
after the litigation in question.
VerDate Aug<31>2005
17:23 Jan 30, 2008
Jkt 214001
Petitioner further proposes that the
Commission delete § 51.109(a)(2), with
the result that the admission of NEPA
contentions will be guided by the same
principles in 10 CFR 2.309(f) that apply
to other kinds of contentions.
Public Comments on the Petition
Three comment letters were received
on the petition. The Board of Lincoln
County Commissioners supports the
petition for the reasons advanced in the
petition, noting that it expects to
participate in an NRC proceeding which
will examine NRC’s independent review
of the FEIS. The National Association of
Regulatory Utility Commissioners
(NARUC) expressed the view that
Nevada’s substantive issues on the FEIS
could be considered in NRC’s licensing
proceeding without any need to amend
the regulations because, inter alia, ‘‘the
Court of Appeals provided the State the
right to have consideration be given to
outstanding concerns with the EIS
prepared for the Yucca Mountain
repository when * * * the NRC
prepares its own EIS for the licensing
decision.’’ 3 DOE does not think that
Nevada’s requested rulemaking is
warranted because ‘‘[t]he regulation at
issue comports with NRC’s
responsibilities under both NEPA and
the NWPA, and nothing in the NEI case
supports Nevada’s claim that the
regulation must be revised.’’
Reasons for Denial
A. The Adoption Standards in
§ 51.109(c)
With regard to the ‘‘special adoption
standards’’ in § 51.109(c), petitioner
notes that both Nevada and the Council
on Environmental Quality (CEQ) had
objected to NRC’s criteria for
determining that it is practicable to
adopt the FEIS. In comments submitted
at the time of the 1988–89 rulemaking,
Nevada and CEQ argued that NEPA does
not allow NRC to adopt the FEIS
without a full and independent review
of the FEIS. Further, Nevada also
disagreed, and continues to disagree,
with NRC’s position in that rulemaking
that in the NWPA, Congress intended to
alter NRC’s ordinary NEPA obligations
and lessened the need for NRC to
conduct a fully independent review of
the FEIS prior to adoption. In support of
its position, the petitioner cites the
statements of two Senators made during
the congressional debates leading to the
NWPA, statements considered by NRC
in its rulemaking but rejected as ‘‘less
illuminating’’ than the legislative
3 It is not clear whether NARUC recognizes that
NRC may adopt DOE’s EIS to the extent practicable,
rather than prepare its own EIS.
PO 00000
Frm 00003
Fmt 4702
Sfmt 4702
history stemming from the House of
Representatives’ consideration of the
issues. See, 53 FR 16137.
The State’s main basis for requesting
rulemaking stems from the NEI court’s
discussion of NRC’s potential adoption
of the FEIS. The petitioner notes the
court’s observations that Nevada may
raise its substantive claims against the
FEIS when it is used by NRC to support
a future construction authorization or
licensing decision, and that NRC
counsel had assured the court that
Nevada would be permitted to raise its
substantive challenges to the FEIS in
any NRC proceeding to decide whether
to adopt the FEIS. The petitioner further
notes the court’s statement that NWPA’s
mandate that the FEIS be adopted by
NRC ‘‘to the extent practicable’’ * * *
‘‘cannot reasonably be interpreted to
permit NRC to premise a constructionauthorization or licensing decision upon
an EIS that does not meet the
substantive requirements of the NEPA
or [CEQ’s] NEPA regulations.’’ 373 F.3d
at 1314.
Finally, the petitioner notes the
court’s rejection of the position taken in
a letter from NRC counsel to the court
that § 51.109(c) only affected issues that
could be raised and litigated in NRC
administrative proceedings and not
issues that could be raised on judicial
review. See, Petition at 5; 373 F.3d
1314. Rather, the court stated,
‘‘Nevada’s claims have not been
adjudicated on the merits here and
presumably will not have been passed
upon by any court prior to the relevant
NRC proceedings. The claims thus
would certainly raise ‘new
considerations’ with regard to any
decision to adopt the FEIS.’’ Id. The
petitioner believes that ‘‘any
Commission interpretation of 10 CFR
51.109 at odds with counsel’s
representation at oral argument would
clearly be unlawful’’ and asserts that
‘‘[NRC’s] current regulation is directly at
odds with [its counsel’s and the court’s]
interpretation,’’ so that the Commission
must correct the regulation. Petition at
5–6.
Petitioner’s assertion that § 51.109(c)
must be ‘‘corrected’’ because it is
‘‘directly at odds’’ with the
interpretation of this regulation by the
NEI court directly contradicts what the
court itself said on the subject of any
need for the Commission to amend its
regulations. The court stated:
Government counsel’s unequivocal
representation to the court during oral
argument that Nevada will not be foreclosed
from raising substantive claims against the
FEIS in administrative proceedings comports
with the terms of the regulation and reflects
a reasonable and compelling interpretation.
E:\FR\FM\31JAP1.SGM
31JAP1
Federal Register / Vol. 73, No. 21 / Thursday, January 31, 2008 / Proposed Rules
sroberts on PROD1PC70 with PROPOSALS
Therefore, on the record at hand, there is no
reason to assume that the regulation will bar
consideration of Nevada’s substantive claims
in the relevant NRC administrative
proceedings.
373 F.3d at 1314.
Far from suggesting that NRC’s
regulation needed to be amended to
accommodate the court’s interpretation
of the regulation, the court expressed its
satisfaction that there was no reason to
assume that the present language of the
regulation would bar consideration of
Nevada’s substantive claims. This
conclusion follows the court’s explicit
consideration of the language of the
§ 51.109(c) criteria. The court focused
on the second criterion; i.e., that it
might not be practicable for NRC to
adopt the FEIS if ‘‘significant and
substantial new information or new
considerations render such
environmental impact statement
inadequate.’’ The court noted that
‘‘Government counsel assured the court
that NRC will not construe the ‘new
information or new considerations’
requirement to preclude Nevada from
raising substantive claims against the
FEIS in administrative proceedings.’’ Id.
Further, the court observed that
‘‘Nevada’s claims have not been
adjudicated on the merits here and
presumably will not have been passed
upon by any court prior to the relevant
NRC proceedings. The claims thus
would certainly raise ‘new
considerations’ with regard to any
decision to adopt the FEIS.’’ Id.4 There
is no need for the Commission to
expend the resources needed for a
rulemaking to ‘‘correct’’ a rule which
the court gave no indication of needing
correction. NRC will treat Nevada’s
substantive claims against the FEIS as
‘‘new considerations’’ within the
framework of § 51.109(c).
Although the petitioner frames its
request for correction of § 51.109(c) in
terms of a supposed need to bring the
regulation into line with the views of
the court, the petitioner may actually be
seeking to raise once again the issues
the State and CEQ raised in comments
made during the 1988–89 rulemaking.
The petition raises no issues that were
not raised and fully considered in that
rulemaking. The Commission’s rationale
for the adoption criteria issued as part
of that rulemaking was not before the
court in NEI and the court, as explained
above, found nothing amiss with the
criteria. The court’s decision presents
4 At
the same time, the court recognized that
‘‘[t]he NWPA’s mandate that the FEIS be adopted
by NRC ‘to the extent practicable’ is intended to
avoid duplication of the environmental review
process.’’ 373 F.3d 1251.
VerDate Aug<31>2005
17:23 Jan 30, 2008
Jkt 214001
no reasons for the Commission to
reexamine the basis of that rulemaking.
B. The Litigation Procedures in
§ 51.109(a)(2)
With regard to the ‘‘special litigation
procedures,’’ the petitioner notes that
§ 51.109(a)(2) conditions the
admissibility of a contention which
asserts that NRC should not adopt the
FEIS on satisfaction, to the extent
possible, of the standards for reopening
a closed record under 10 CFR 2.326. The
petitioner asserts that the principal
difference between this standard and
the contention standard in 10 CFR
2.309(f) that applies to other issues is
that the former requires submission of
admissible evidence, while the latter
does not. The petitioner asserts that
NRC’s creation of ‘‘special litigation
procedures’’ violates NEPA: ‘‘Section
102(2)(C) of NEPA requires that an FEIS
must be considered in the ‘existing
agency review processes’ [emphasis
added], not some different review
process applicabl[e] only to NEPA
where interested persons must satisfy
additional pleading requirements that
would otherwise not apply.’’ Petition at
6 (citing Calvert Cliffs, 449 F.2d 1109
(D.C. Cir. 1971); 40 CFR 1505.1;
Aberdeen & Rockfish R. Co. v. SCRAP,
422 U.S. 289, 320 (1975)).
The relevant portion of section
102(2)(C) of the NEPA states that copies
of the requisite ‘‘detailed statement’’
must ‘‘accompany the proposal through
the existing agency review processes.’’ 5
This language does not require that an
agency establish one uniform agency
process for all NEPA reviews. Here,
NRC has adopted a contention standard
in § 51.109(a)(2) which takes account of
the NWPA’s effect on its NEPA
responsibilities as explained in its
1988–89 rulemaking. In the relevant
portion of the Calvert Cliffs decision,
the question before the court was
‘‘whether the [Atomic Energy]
Commission is correct in thinking that
its NEPA responsibilities may be carried
out in toto outside the hearing process—
whether it is enough that environmental
data and evaluations merely accompany
the application through the review
process, but receive no consideration
whatever from the hearing board.’’
Calvert Cliffs, 449 F.2d at 1117 (internal
quotation marks omitted). In the
discussion that follows, the court
focused on the meaning of the term
‘‘accompany,’’ not whether changes in
5 The CEQ regulation at 40 CFR 1505.1 is based
on the statutory language and requires that agency
procedures require ‘‘that relevant environmental
documents * * * accompany the proposal through
existing agency review processes so that agency
officials use the statement in making decisions.’’
PO 00000
Frm 00004
Fmt 4702
Sfmt 4702
5765
agency procedures for considering
NEPA issues would be inconsistent with
the ‘‘existing agency review process’’
language. The court concluded that the
word ‘‘accompany’’ meant that the
detailed statement must be considered
during the agency review process. In
Aberdeen, the Court held that an oral
hearing held before an agency made a
recommendation or report on a proposal
for Federal action was not an ‘‘existing
agency review process’’ under section
102(2)(C) of the NEPA and thus, a FEIS
was not required to be available during
this hearing. See, 422 U.S. at 320–21.
Thus, the Supreme Court’s discussion in
Aberdeen focuses on when the FEIS
must be made available, not whether the
term ‘‘existing agency review process’’
means that one contention standard
must apply to all NEPA reviews in all
cases before an agency. In short, the case
law cited by the petitioner does not
provide a reason for NRC to delete
§ 51.109(a)(2) from its regulations.
Conclusion
The NEI court found no need for NRC
to amend its regulations for the purpose
of allowing the State to have its
substantive claims examined in NRC’s
licensing proceeding for a potential YM
repository. Petitioner’s claims that
NRC’s adoption criteria violate the
NEPA or the NWPA were addressed in
the 1988–89 rulemaking and petitioner
offers no new arguments for the
Commission’s consideration. Nor does
the petitioner provide adequate legal
support for NRC to amend its litigation
procedures. Given this, it would be an
unwise expenditure of resources for the
Commission to conduct a rulemaking on
this matter.
For these reasons, the Commission
denies PRM–51–9.
Dated at Rockville, Maryland, this 25th day
of January 2008.
For the Nuclear Regulatory Commission.
Annette L. Vietti-Cook,
Secretary of the Commission.
Appendix I—Commissioner Jaczko’s
Comments on SECY–07–0159, Denial of
a Petition for Rulemaking (PRM–51–
9)—State of Nevada
I approve in part and disapprove in part
the recommendation to proceed with option
2 which would deny the rulemaking petition
while offering the assurance that the NRC
will interpret the existing regulations to
allow substantive claims to the Department
of Energy’s (DOE) Final Environmental
Impact Statement (FEIS). Instead, I approve
a combination of options 1 and 2. The
original regulations governing the agency’s
review of the FEIS were based upon an
assumption of how the site selection process
for a potential repository would unfold. But
because the judicial review of environmental
E:\FR\FM\31JAP1.SGM
31JAP1
sroberts on PROD1PC70 with PROPOSALS
5766
Federal Register / Vol. 73, No. 21 / Thursday, January 31, 2008 / Proposed Rules
issues did not happen as we envisioned, I
believe we should grant the petition and fix
the corresponding regulations to
appropriately reflect that the entire FEIS will
be open for litigation in any NRC
administrative proceeding regarding a
repository application. At the same time, I
believe the notice of the proposed rule
should explain that the agency will interpret
the regulations in a manner consistent with
this approach should the rulemaking not be
completed in time for a hearing on a
potential Yucca Mountain license
application.
Based upon the history of this issue, I think
granting the petition and amending our
regulations is the right answer in this case.
First, it is important to remember that the
NRC could have originally interpreted the
Nuclear Waste Policy Act (NWPA) to allow
the NRC to handle the adoption of DOE’s
FEIS in the same manner it currently handles
the adoption of any other federal agency EIS
in the NEPA review process. The NWPA’s
direction to avoid duplicative environmental
analysis does not necessarily equate to a
direction to eliminate most, if not all, of the
FEIS from the NRC’s hearing process. I
believe we should treat DOE’s FEIS in the
same manner as we treat any other FEIS
submitted by a similarly situated regulated
entity. In this case, that would mean
defending the agency’s independent review
of the entire FEIS—not just limited portions
of it—in the NRC’s administrative
proceedings. Commenters, including the
Council on Environmental Quality, said as
much in comments to this rulemaking and I
find their logic persuasive. Had the agency
opted for that interpretation in the proposed
rulemaking, perhaps we would not find
ourselves facing this petition today.
NRC’s rationale for not doing so, however,
while not ideal, made sense in the context of
what the agency thought would happen with
the FEIS. According to the rulemaking
history, section 51.109 of NRC’s regulations
was based, at least in large part, upon the
theory that the administrative litigation of
NEPA issues at the NRC should be limited
because many of these issues should have
already had the opportunity to be litigated in
another forum. Thus, legal doctrines which
prevent issues and claims from being relitigated, such as res judicata and collateral
estoppel, would prevent the re-litigation of
these issues in NRC hearings. This was
premised upon NRC’s expectation that an
interested person would have had an
opportunity to legally challenge DOE’s FEIS
after it was used to support the
recommendations of Yucca Mountain as a
site for a repository by the Secretary of
Energy and the President.
With that expectation in mind, the
regulations were then designed to ensure that
the environmental issues in any NRC
proceeding on the proposed repository would
appropriately focus on issues that were
new—that were not able to be raised at the
earlier opportunity to challenge the FEIS. So
the regulations adopted in section 51.109
focused not on the entire FEIS, as would be
the normal NRC practice, but on the NRC’s
decision to adopt the FEIS. The regulations
limited challenges to NRC’s adoption
VerDate Aug<31>2005
17:23 Jan 30, 2008
Jkt 214001
decision to those issues that had changed
from the original application, or that were
issues raising ‘‘significant and substantial
new information’’ since that earlier
opportunity to challenge the FEIS. This
makes sense if any of the other issues
regarding the FEIS had already had the
opportunity to be challenged. Given that
presumption, it also explains why the
regulations direct the Board to use the higher
standards governing a motion to reopen
when ruling upon the issues raised regarding
adoption of the FEIS—because litigating the
FEIS in NRC’s administrative proceeding was
seen as re-opening the record on an already
litigated FEIS.
All that being said, as is often the case,
actual events regarding judicial review of
environmental issues transpired differently.
Instead of the FEIS being used to support the
recommendation of Yucca Mountain as a site
for a repository, there was a Joint Resolution
of Congress approving the Yucca Mountain
site designation. This change of events,
according to the Federal Court of Appeals
decision in Nuclear Energy Institute, Inc. v.
Environmental Protection Agency, 373 F.3d
1251 (D.C. Circuit 2004), rendered any such
challenge to the FEIS’ support for the Yucca
Mountain site moot; and to the extent the
NRC may rely upon the FEIS, rendered
challenges unripe because the NRC had not
reached a decision regarding adopting or
relying upon the FEIS in a way that could
have yet harmed the parties.
It was part of this discussion that led the
NRC and DOE to assure the court that the
parties would have an opportunity during
NRC’s administrative hearing to raise
substantive challenges to the FEIS. And it is
this assurance from NRC counsel that
generated the petition for rulemaking. In
essence, the petitioners do not understand
how NRC’s current regulations can be in
accord with the assurance the court relied
upon—that parties would have the
opportunity at the NRC to substantively
challenge the FEIS. Because current NRC
regulations limit challenges to NRC’s
decision about adoption of the FEIS rather
than the FEIS itself; and further limit those
challenges to require they be based upon
significant and substantial new information,
it is easy to see how our stakeholders might
be confused. Add to that the direction in the
current regulations that the Boards are
directed to review any challenge to the
decision regarding adoption using the
standards that govern re-opening a record—
which is an intentionally higher bar for
review—and there can be little question that
the current regulations are confusing in light
of the discussion in front of the court and the
relied upon assurance that substantive issues
regarding the FEIS could, in fact, be raised
in NRC proceedings.
For all of these reasons, it appears to me
that the best way to transparently resolve the
real question presented—the question of
what issues surrounding the FEIS can be
challenged in a prospective hearing on an
application for a construction
authorization—is to grant this petition and
ensure that the regulations transparently
capture precisely how the environmental
review will be conducted in NRC’s
PO 00000
Frm 00005
Fmt 4702
Sfmt 4702
administrative proceeding. The earlier
rulemaking was based upon assumptions, but
we can now answer the questions with the
benefit of knowing now what we did not
know then.
I recognize that the timing of the agency’s
decision on this petition is not ideal because
an application for a repository may be
submitted before this rulemaking would end.
That is especially unfortunate in this
particular situation where the petition was
filed in 2005. Had we granted this petition
at the close of the public comment period in
October 2005, we likely would now be voting
on the final rule instead of voting on this
petition. I am hopeful that the staff’s work to
improve the rulemaking process will include
ways to improve the timeliness of the
petition process so we are not in this
unfortunate position in the future.
But we are where we are, and with that in
mind, I believe the notice that grants the
petition for rulemaking should indicate that,
if the rulemaking is not resolved prior to the
receipt of an application for a repository, the
agency intends to interpret the regulations in
a manner consistent with the court’s
decision—as the staff has drafted in the
notice accompanying option 2—with some
additional clarification. The notice should
also explain that section 51.109(c), which
indicates that challenges to the NRC’s
adoption decision are to be based upon
‘‘significant and substantial new
information’’, will be interpreted in a manner
that recognizes, as the court did, that claims
regarding DOE’s FEIS have not been
adjudicated on the merits and thus, would
certainly raise ‘‘new considerations’’ with
regard to any decision to adopt the FEIS. The
notice should also make it clear that the
current direction in section 51.109(a) that the
presiding officer should, to the extent
possible, use the criteria for ruling on a
motion to reopen in resolving disputes
regarding the adoption of the FEIS, is
rendered moot. The notice should clearly
state that it is not possible to rely upon
criteria used for a motion to reopen given the
relevant history of this matter where there
was no opportunity to originally open these
issues. Instead, the contention admissibility
should be determined by reliance upon
section 2.309(f), the agency’s current
contention standard.
I appreciate that because these regulations
have not yet been interpreted and applied in
any proceeding, the agency has more
flexibility to interpret them now without
recreating them in a new rulemaking—and
thus the recommendation for option 2. But
this is not a situation where the regulations
intent could have been clearer; this is a
situation where the interpretation of the
regulations will essentially require the
agency to exercise great latitude in applying
them in a manner consistent with the
discussion in court. Transparency should
dictate that we, at least, try to correct this
situation through the appropriate rulemaking
channels regardless of the impacts of the
timing of this decision. We should not let the
prospect of a potential application
complicate what is clearly the right answer.
We can and should deal with the possible
complications of an intervening application
E:\FR\FM\31JAP1.SGM
31JAP1
Federal Register / Vol. 73, No. 21 / Thursday, January 31, 2008 / Proposed Rules
by providing appropriate guidance should
the rulemaking not resolve itself in time. But
the two are not mutually exclusive and thus,
I support a combination of options 1 and 2—
granting the petition and clarifying in the
notice the agency’s regulatory interpretation
of the existing regulations should they be
required to be used prior to completion of the
rulemaking.
Also, this paper should be reviewed for a
release determination and, at a minimum, the
voting record and SRM from this paper
should be made publicly available five
business days after the letter is sent to the
petitioner, as is current practice for release of
information regarding decisions on
rulemaking petitions.
Gregory B. Jaczko.
[FR Doc. E8–1751 Filed 1–30–08; 8:45 am]
BILLING CODE 7590–01–P
DEPARTMENT OF TRANSPORTATION
Federal Aviation Administration
14 CFR Part 39
[Docket Nos. FAA–2007–0413 and FAA–
2007–0414; Directorate Identifiers 2007–
NM–341–AD and 2007–NM–340–AD]
RIN 2120–AA64
Airworthiness Directives; Bombardier
Model CL–600–2B19 (Regional Jet
Series 100 & 440), CL–600–2C10
(Regional Jet Series 700, 701 & 702),
CL–600–2D15 (Regional Jet Series
705), and CL–600–2D24 (Regional Jet
Series 900) Airplanes
Federal Aviation
Administration (FAA), Department of
Transportation (DOT).
ACTION: Notice of proposed rulemaking
(NPRM); correction.
sroberts on PROD1PC70 with PROPOSALS
AGENCY:
SUMMARY: The FAA is correcting
typographical errors in two NPRMs that
were published in the Federal Register
on January 4, 2008 (73 FR 833, and 73
FR 830). The errors resulted in incorrect
docket numbers. One NPRM applies to
all Bombardier Model CL–600–2B19
(Regional Jet Series 100 & 440)
airplanes. The other NPRM applies to
all Bombardier Model CL–600–2C10
(Regional Jet Series 700, 701 & 702), CL–
600–2D15 (Regional Jet Series 705), and
CL–600–2D24 (Regional Jet Series 900)
airplanes. Both actions proposed to
require revising the Airworthiness
Limitations Section of the Instructions
for Continued Airworthiness to
incorporate new limitations for fuel tank
systems.
ADDRESSES: You may examine the AD
docket on the Internet at https://
www.regulations.gov; or in person at the
Docket Management Facility between 9
VerDate Aug<31>2005
17:23 Jan 30, 2008
Jkt 214001
a.m. and 5 p.m., Monday through
Friday, except Federal holidays. The AD
docket contains this AD, the regulatory
evaluation, any comments received, and
other information. The address for the
Docket Office (telephone 800–647–5527)
is the Document Management Facility,
U.S. Department of Transportation,
Docket Operations, M–30, West
Building Ground Floor, Room W12–140,
1200 New Jersey Avenue SE.,
Washington, DC 20590.
FOR FURTHER INFORMATION CONTACT:
Rocco Viselli, Aerospace Engineer,
Airframe and Propulsion Branch, ANE–
171, FAA, New York Aircraft
Certification Office, 1600 Stewart
Avenue, Suite 410, Westbury, New York
11590; telephone (516) 228–7331; fax
(516) 794–5531.
SUPPLEMENTARY INFORMATION: On
December 26, 2007, the FAA issued a
notice of proposed rulemaking (NPRM)
for all Bombardier Model CL–600–2B19
(Regional Jet Series 100 & 440)
airplanes. That NPRM, Directorate
Identifier 2007–NM–341–AD, was
published in the Federal Register on
January 4, 2008 (73 FR 833).
On December 21, 2007, the FAA
issued an NPRM for all Bombardier
Model CL–600–2C10 (Regional Jet
Series 700, 701 & 702), CL–600–2D15
(Regional Jet Series 705), and CL–600–
2D24 (Regional Jet Series 900) airplanes.
That NPRM, Directorate Identifier 2007–
NM–340–AD, was published in the
Federal Register on January 4, 2008 (73
FR 830).
Both actions proposed to require
revising the Airworthiness Limitations
Section of the Instructions for
Continued Airworthiness to incorporate
new limitations for fuel tank systems.
As published, those NPRMs specify
incorrect docket numbers throughout
the preamble and the regulatory text.
The docket number associated with
NPRM Directorate Identifier 2007–NM–
341–AD was FAA–2008–0413, and the
docket number associated with NPRM
Directorate Identifier 2007–NM–340–AD
was FAA–2008–0414. The docket
numbers were assigned by the Federal
Document Management System. We
have been informed that incorrect
docket numbers were assigned. The
correct docket number for NPRM
Directorate Identifier 2007–NM–341–AD
is FAA–2007–0413. The correct docket
number for NPRM Directorate Identifier
2007–NM–340–AD is FAA–2007–0414.
Any commenter who submitted
comments to an original, incorrect
docket number should check Docket No.
FAA–2007–0413 or FAA–2007–0414 on
www.regulations.gov to determine
whether the comments have been
PO 00000
Frm 00006
Fmt 4702
Sfmt 4702
5767
received and filed in the appropriate
docket. If not, or if it is not possible to
determine whether comments have been
posted to the correct docket, the
comments should be resubmitted using
the correct docket number.
No other part of the preamble or
regulatory information has been
changed; therefore, the NPRMs are not
republished in the Federal Register.
The last date for submitting comments
to the NPRMs remains February 4, 2008.
Correction
In the Federal Register of January 4,
2008, on page 833, in the second
column, the headings section of NPRM
Docket No. FAA–2008–0413, Directorate
Identifier 2007–NM–341–AD, is
corrected to read as follows:
‘‘[Docket No. FAA–2007–0413;
Directorate Identifier 2007–NM–
341–AD]’’
In the Federal Register of January 4,
2008, on page 833, in the third column,
the SUPPLEMENTARY INFORMATION section
of NPRM Docket No. FAA–2008–0413,
Directorate Identifier 2007–NM–341–
AD, is corrected to read as follows:
‘‘* * * Include ‘‘Docket No. FAA–
2007–0413; Directorate Identifier 2007–
NM–341–AD’’ at the beginning of your
comments. * * *’’
In the Federal Register of January 4,
2008, on page 830, in the second
column, the headings section of NPRM
Docket No. FAA–2008–0414, Directorate
Identifier 2007–NM–340–AD, is
corrected to read as follows:
‘‘[Docket No. FAA–2007–0414;
Directorate Identifier 2007–NM–340–
AD]’’
In the Federal Register of January 4,
2008, on page 831, in the first column,
the SUPPLEMENTARY INFORMATION section
of NPRM Docket No. FAA–2008–0414,
Directorate Identifier 2007–NM–340–
AD, is corrected to read as follows:
‘‘* * * Include ‘‘Docket No. FAA–
2007–0414; Directorate Identifier 2007–
NM–340–AD’’ at the beginning of your
comments. * * *’’
§ 39.13
[Corrected]
In the Federal Register of January 4,
2008, on page 835, in the first column,
paragraph 2. of PART 39—
AIRWORTHINESS DIRECTIVES of
NPRM Docket No. FAA–2008–0413,
Directorate Identifier 2007–NM–341–AD
is corrected to read as follows:
*
*
*
*
*
Bombardier, Inc. (Formerly Canadair):
Docket No. FAA–2007–0413; Directorate
Identifier 2007–NM–341–AD.
*
*
*
*
*
In the Federal Register of January 4,
2008, on page 832, in the second
E:\FR\FM\31JAP1.SGM
31JAP1
Agencies
[Federal Register Volume 73, Number 21 (Thursday, January 31, 2008)]
[Proposed Rules]
[Pages 5762-5767]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-1751]
========================================================================
Proposed Rules
Federal Register
________________________________________________________________________
This section of the FEDERAL REGISTER contains notices to the public of
the proposed issuance of rules and regulations. The purpose of these
notices is to give interested persons an opportunity to participate in
the rule making prior to the adoption of the final rules.
========================================================================
Federal Register / Vol. 73, No. 21 / Thursday, January 31, 2008 /
Proposed Rules
[[Page 5762]]
NUCLEAR REGULATORY COMMISSION
10 CFR Part 51
[Docket No. PRM-51-9]
State of Nevada; Denial of Petition for Rulemaking
AGENCY: Nuclear Regulatory Commission.
ACTION: Petition for rulemaking: denial.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC or Commission) is
denying a petition for rulemaking submitted by the State of Nevada
(PRM-51-9). The petition requests that NRC modify its regulation
setting criteria for adoption of an environmental impact statement
prepared by the Secretary of the Department of Energy in proceedings
for issuance of a construction authorization and materials license with
respect to a geologic repository. The petitioner asserts that the
current regulation must be ``corrected'' because it is at odds with a
recent court of appeals decision. Further, petitioner asserts that
certain litigation procedures that will be used in the proceedings to
consider the adoption question violate the National Environmental
Policy Act of 1969, as amended (NEPA). NRC is denying the petition
because the court found no reason for NRC to correct its adoption
criteria and because the petition does not demonstrate that NRC's
litigation procedures violate NEPA. Commissioner Gregory B. Jaczko's
vote on this denial is included in Appendix I to this notice.
ADDRESSES: Publicly available documents related to this petition,
including the petition for rulemaking, the comments received, and NRC's
letter of denial to the petitioner may be viewed electronically on
public computers in NRC's Public Document Room (PDR), 01F21, One White
Flint North, 11555 Rockville Pike, Rockville, Maryland. The PDR
reproduction contractor will copy documents for a fee.
Publicly available documents created or received at NRC after
November 1, 1999, are also available electronically at the NRC's
Electronic Reading Room at https://www.nrc.gov/reading-rm/adams.html.
From this site, the public can gain entry into the NRC's Agencywide
Documents Access and Management System (ADAMS), which provides text and
image files of NRC's public documents. If you do not have access to
ADAMS or if there are problems in accessing the documents located in
ADAMS, contact the PDR reference staff at (800) 387-4209, (301) 415-
4737 or by e-mail to pdr@nrc.gov.
FOR FURTHER INFORMATION CONTACT: Jerry Bonanno, Office of the General
Counsel, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001,
telephone (301) 415-1328 or Toll Free: 1-800-368-5642, e-mail:
jxb5@nrc.gov.
SUPPLEMENTARY INFORMATION:
Introduction
On April 8, 2005, the State of Nevada (petitioner or the State)
submitted a ``Petition by the State of Nevada to Amend 10 CFR 51.109''
(petition), which was docketed as a petition for rulemaking under 10
CFR 2.802 of the Commission's regulations (PRM-51-9). The petition was
noticed on August 12, 2005 (70 FR 47148) with a public comment period
that closed on October 26, 2005. Three comment letters were received.
The petition requests amendments to the Commission's regulation at 10
CFR 51.109 governing NRC's adoption of the Department of Energy's (DOE)
final environmental impact statement (FEIS), and any supplements
thereto, which accompanied the Secretary of Energy's (the Secretary)
recommendation to the President that the Yucca Mountain, Nevada (YM)
site be approved for the development of a geologic repository.
Petitioner believes that the current regulation is contrary to the
NEPA, the Nuclear Waste Policy Act of 1982, as amended (NWPA), and the
decision of the U.S. Court of Appeals for the District of Columbia
Circuit in Nuclear Energy Institute, Inc. v. Environmental Protection
Agency, 373 F.3d 1251 (D.C. Cir. 2004) (NEI).
Background
A. Statutory and Regulatory Background of Sec. 51.109
Section 114(f)(4) of the NWPA provides that ``[a]ny [EIS] prepared
in connection with a repository proposed to be constructed by the
Secretary under this subtitle shall, to the extent practicable, be
adopted by the Commission in connection with the issuance by the
Commission of a construction authorization and license for such
repository'' (emphasis added). The statute further provides that ``[t]o
the extent such statement is adopted by the Commission, such adoption
shall be deemed to also satisfy the responsibilities of the Commission
under the [NEPA] and no further consideration shall be required, except
that nothing in this subsection shall affect any independent
responsibilities of the Commission to protect public health under the
Atomic Energy Act of 1954 (42 U.S.C. 2011 et seq.).'' In 1988-89, NRC
conducted a rulemaking to set out the standards and procedures that
would be used in licensing proceedings for determining whether NRC's
adoption of DOE's FEIS is practicable. See, 53 FR 16131; May 5, 1988
(proposed rule); 54 FR 27864; July 3, 1989 (final rule). In that
rulemaking, NRC determined that the NWPA had altered NRC's ordinary
NEPA responsibilities in such a manner as to narrow the scope of NRC's
independent review of environmental issues that had been decided by DOE
in its FEIS. As summarized by the Commission in the final rule,
[T]he Commission continues to emphasize its view that its role
under NWPA is oriented toward health and safety issues and that, in
general, nonradiological environmental issues are intended to be
resolved in advance of NRC licensing decisions through the actions
of the Department of Energy, subject to Congressional and judicial
review in accordance with NWPA and other applicable law. The
Commission anticipates that many environmental questions would have
been, or at least could have been, adjudicated in connection with an
environmental impact statement prepared by DOE, and such questions
should not be reopened in proceedings before NRC.
54 FR at 27865.
Accordingly, NRC's 1989 final rule established, in a new 10 CFR
51.109, ``Public hearings in proceedings for issuance of materials
license with
[[Page 5763]]
respect to a geologic repository,'' procedures and criteria for
implementing the statutory directive to adopt DOE's FEIS to the extent
practicable. Under Sec. 51.109(a)(1), the NRC staff must present its
position on whether it is practicable to adopt, without further
supplementation, DOE's FEIS upon publication of the notice of hearing
in the Federal Register. Under Sec. 51.109(a)(2), parties to a
proceeding are given the opportunity to submit contentions asserting
that it is not practicable to adopt:
(a)(2) Any other party to the proceeding who contends that it is
not practicable to adopt the DOE [FEIS], as it may have been
supplemented, shall file a contention to that effect within thirty
(30) days after the publication of the notice of hearing in the
Federal Register. Such contention must be accompanied by one or more
affidavits which set forth factual and/or technical bases for the
claim that, under the principles set forth in paragraphs (c) and (d)
of this section, it is not practicable to adopt the DOE [FEIS], as
it may have been supplemented. The presiding officer shall resolve
disputes concerning adoption of the DOE [FEIS] by using, to the
extent possible, the criteria and procedures that are followed in
ruling on motions to reopen under Sec. 2.236 of this chapter.
10 CFR 51.109(a)(2)(2007).\1\ The criteria governing the practicability
of adoption are set forth in Sec. 51.109(c):
---------------------------------------------------------------------------
\1\ In 2004, Sec. 51.109(a)(2) was revised to reference a new
section number for motions to reopen as part of the Commission's
revision of its rules of practice in adjudicatory proceedings. See
69 FR 2182, 2276 (January 14, 2004). The standards for reopening
were not changed.
(c) The presiding officer will find that it is practicable to
adopt any environmental impact statement prepared by the Secretary
of Energy in connection with a geologic repository proposed to be
constructed under Title I of the Nuclear Waste Policy Act of 1982,
as amended, unless:
(1)(i) The action proposed to be taken by the Commission differs
from the action proposed in the license application submitted by the
Secretary of Energy; and
(ii) The difference may significantly affect the quality of the
human environment; or
(2) Significant and substantial new information or new
considerations render such environmental impact statement
inadequate.
10 CFR 51.109(c) (2007).
B. DOE's FEIS
The NWPA, inter alia, establishes a process for the
characterization, siting, construction, and operation of a geologic
repository at the YM site. As relevant here, when site characterization
activities are completed, the Secretary of Energy may recommend site
approval to the President and any such recommendation must be
accompanied by a FEIS. See, section 114(a)(1) of the NWPA. Then, the
President may recommend the site to the Congress and must include a
copy of the documents comprising the basis of the Secretary's
recommendation, including the FEIS. See, section 114(a)(2). The State
is then given an opportunity to submit a notice of disapproval of the
site designation which, however, may be overcome by a joint resolution
of the Congress approving the recommended repository site. See,
sections 115 and 116 of the NWPA. If the site designation is permitted
to take effect under the provisions of section 115, the Secretary of
Energy shall submit an application for a construction authorization to
NRC. See, section 114(b) of the NWPA. In February 2002, the Secretary
issued the Final Environmental Impact Statement for a Geologic
Repository for the Disposal of Spent Nuclear Fuel and High-Level
Radioactive Waste at Yucca Mountain, Nye County, Nevada and recommended
the YM site to the President. The President then recommended the YM
site to the Congress. In April 2002, the State of Nevada submitted a
notice of disapproval to the Congress. However, Congress approved the
site designation by a Joint Resolution signed by the President on July
23, 2002. Public Law 107-200, 116 Stat. 735 (2002) (codified at 42
U.S.C. 10135 note (Supp. IV 2004)).
C. The NEI Decision
Thereafter, the State of Nevada sought court review of the
Secretary's decision to recommend the YM site to the President, the
President's decision to recommend the YM site to the Congress, and
DOE's FEIS, which had been used to support both recommendations. In
response, DOE argued that the Joint Resolution had rendered moot
Nevada's challenges to the Secretary's and the President's
recommendations, with the result that Nevada's claims that the FEIS was
inadequate could not be considered as part of the challenges to these
recommendations. Further, DOE argued that, insofar as the FEIS might be
used to support future DOE and NRC decisions, the FEIS was unripe for
review because there was no final agency action affecting the State at
that time.
In the litigation resulting in the NEI decision, the State's
challenges to the Secretary's and the President's recommendations and
to the FEIS were combined with other issues raised by the State and
with other lawsuits concerning the YM repository, including challenges
to both the Environmental Protection Agency's final standards (66 FR
32,074; June 13, 2001) and NRC's final regulations for the proposed
geologic repository at YM (66 FR 55,732; November 2, 2001). However,
NRC's procedures and criteria for adoption of DOE's FEIS were not
issues raised in any of the lawsuits and NRC's rationale for adoption
of the Sec. 51.109 procedures and criteria was neither briefed nor
argued by NRC. NRC did describe in its brief its regulatory adoption
process in the context of an issue raised by Nevada concerning NRC's
regulation at 10 CFR 63.341, which required DOE to include the results
of its projections of peak dose in its FEIS.\2\ See, Brief for the
Federal Respondents, State of Nevada v. U.S. Nuclear Regulatory
Commission, Nos. 01-1116 and 03-1058, June 6, 2003, at 44-45. In
resolving this issue, the court noted NRC's statement ``that it has
imposed no categorical limitation on any challenge to DOE's peak dose
calculations and that, under its regulations, parties to the proceeding
may challenge the practicability of adopting aspects of DOE's EIS,
including the peak dose calculations, based on substantial new
information to the contrary.'' 375 F.3d 1251, at 1300 (internal
quotations omitted).
---------------------------------------------------------------------------
\2\ In 2005, NRC proposed to eliminate Sec. 63.341 as part of
its proposed amendments to 10 CFR Part 63. See, 70 FR 53313
(September 8, 2005).
---------------------------------------------------------------------------
In NEI, the court agreed with DOE that Congress' enactment of the
Joint Resolution had rendered moot issues raised concerning the
Secretary's and the President's recommendation of the YM site. See 373
F.3d at 1309. Thus, the court held that ``[i]nsofar as Nevada's instant
challenge to the FEIS is intended to reverse the decision to select the
Yucca site, the challenge is moot * * *'' 373 F.3d at 1312. However,
the court noted the anticipated use of the FEIS in future
decisionmaking related to YM, including its potential adoption by NRC
in NRC's licensing proceeding, and considered whether the court should
review the FEIS because it might be used to support future decisions.
The court determined that the FEIS was not ripe for review under the
two-part test used to determine ripeness: The fitness of the issue for
judicial decision and the hardship to the parties of withholding court
consideration. Under the first prong of the test, the court noted that
it was unclear to what extent NRC would adopt the FEIS and whether the
FEIS would require supplementation prior to any adoption. The court
concluded that ``[o]ur review of the FEIS therefore would benefit from
postponing consideration until the FEIS has been used to support a
specific, concrete, and final decision.'' 373 F.3d at 1313. Under
[[Page 5764]]
the second prong of the test, the court concluded that ``withholding
consideration of Nevada's substantive claims at this time imposes no
hardship on Nevada * * * [because] Nevada may raise its substantive
claims against the FEIS if and when NRC or DOE makes * * * a final
decision.'' Id. In reaching this conclusion as to hardship, the court
stated that ``we rely on the assurances of counsel for both NRC and DOE
at oral argument that Nevada will be permitted to raise its substantive
challenges to the FEIS in any NRC proceeding to decide whether to adopt
the FEIS and in any DOE proceeding to select a transportation
alternative.'' Id.
The Petition
The petitioner agrees that Sec. 51.109 ``in most respects tracks
the language of [section 114(f)(4) of the NWPA]'' on which it is based.
Petition at 2. However, the petitioner claims that this regulation also
adds three special provisions not found in the statute: (1) Special
procedures for litigation of NEPA issues; (2) allowance for adoption of
DOE supplements to the FEIS; and (3) special standards that specify in
some detail precisely when NRC will adopt the FEIS. The petitioner
believes that the Commission must conduct a rulemaking to eliminate the
``special litigation procedures'' and to correct the ``special adoption
standards.'' The petition makes no further reference to the second
``special provision'' and suggests no rule change with respect to this
provision. There is no apparent reason why Congress would have intended
to exclude supplements to the FEIS in its requirement for NRC to adopt
DOE's FEIS to the extent practicable, so we do not regard this
provision of the regulation as being within the petition for
rulemaking.
To correct the criteria for assessing the practicability of
adoption, petitioner requests that the Commission add a new paragraph
(h) to Sec. 51.109:
Nothing in this section shall be construed to limit the ability
of any party or interested governmental participant to challenge in
a licensing hearing any environmental impact statement (including
any supplement thereto) prepared by the Secretary of Energy on the
ground that such statement violates NEPA or the regulations of the
Council on Environmental Quality, provided that the challenge is not
barred by traditional principles of federal collateral estoppel.
Collateral estoppel shall not bar the admission of a NEPA contention
if the standards in subparagraphs (c)(1) and (c)(2) of this section
are met, provided that the change in the proposed action or new
information or considerations became known after the litigation in
question.
Petitioner further proposes that the Commission delete Sec.
51.109(a)(2), with the result that the admission of NEPA contentions
will be guided by the same principles in 10 CFR 2.309(f) that apply to
other kinds of contentions.
Public Comments on the Petition
Three comment letters were received on the petition. The Board of
Lincoln County Commissioners supports the petition for the reasons
advanced in the petition, noting that it expects to participate in an
NRC proceeding which will examine NRC's independent review of the FEIS.
The National Association of Regulatory Utility Commissioners (NARUC)
expressed the view that Nevada's substantive issues on the FEIS could
be considered in NRC's licensing proceeding without any need to amend
the regulations because, inter alia, ``the Court of Appeals provided
the State the right to have consideration be given to outstanding
concerns with the EIS prepared for the Yucca Mountain repository when *
* * the NRC prepares its own EIS for the licensing decision.'' \3\ DOE
does not think that Nevada's requested rulemaking is warranted because
``[t]he regulation at issue comports with NRC's responsibilities under
both NEPA and the NWPA, and nothing in the NEI case supports Nevada's
claim that the regulation must be revised.''
---------------------------------------------------------------------------
\3\ It is not clear whether NARUC recognizes that NRC may adopt
DOE's EIS to the extent practicable, rather than prepare its own
EIS.
---------------------------------------------------------------------------
Reasons for Denial
A. The Adoption Standards in Sec. 51.109(c)
With regard to the ``special adoption standards'' in Sec.
51.109(c), petitioner notes that both Nevada and the Council on
Environmental Quality (CEQ) had objected to NRC's criteria for
determining that it is practicable to adopt the FEIS. In comments
submitted at the time of the 1988-89 rulemaking, Nevada and CEQ argued
that NEPA does not allow NRC to adopt the FEIS without a full and
independent review of the FEIS. Further, Nevada also disagreed, and
continues to disagree, with NRC's position in that rulemaking that in
the NWPA, Congress intended to alter NRC's ordinary NEPA obligations
and lessened the need for NRC to conduct a fully independent review of
the FEIS prior to adoption. In support of its position, the petitioner
cites the statements of two Senators made during the congressional
debates leading to the NWPA, statements considered by NRC in its
rulemaking but rejected as ``less illuminating'' than the legislative
history stemming from the House of Representatives' consideration of
the issues. See, 53 FR 16137.
The State's main basis for requesting rulemaking stems from the NEI
court's discussion of NRC's potential adoption of the FEIS. The
petitioner notes the court's observations that Nevada may raise its
substantive claims against the FEIS when it is used by NRC to support a
future construction authorization or licensing decision, and that NRC
counsel had assured the court that Nevada would be permitted to raise
its substantive challenges to the FEIS in any NRC proceeding to decide
whether to adopt the FEIS. The petitioner further notes the court's
statement that NWPA's mandate that the FEIS be adopted by NRC ``to the
extent practicable'' * * * ``cannot reasonably be interpreted to permit
NRC to premise a construction-authorization or licensing decision upon
an EIS that does not meet the substantive requirements of the NEPA or
[CEQ's] NEPA regulations.'' 373 F.3d at 1314.
Finally, the petitioner notes the court's rejection of the position
taken in a letter from NRC counsel to the court that Sec. 51.109(c)
only affected issues that could be raised and litigated in NRC
administrative proceedings and not issues that could be raised on
judicial review. See, Petition at 5; 373 F.3d 1314. Rather, the court
stated, ``Nevada's claims have not been adjudicated on the merits here
and presumably will not have been passed upon by any court prior to the
relevant NRC proceedings. The claims thus would certainly raise `new
considerations' with regard to any decision to adopt the FEIS.'' Id.
The petitioner believes that ``any Commission interpretation of 10 CFR
51.109 at odds with counsel's representation at oral argument would
clearly be unlawful'' and asserts that ``[NRC's] current regulation is
directly at odds with [its counsel's and the court's] interpretation,''
so that the Commission must correct the regulation. Petition at 5-6.
Petitioner's assertion that Sec. 51.109(c) must be ``corrected''
because it is ``directly at odds'' with the interpretation of this
regulation by the NEI court directly contradicts what the court itself
said on the subject of any need for the Commission to amend its
regulations. The court stated:
Government counsel's unequivocal representation to the court
during oral argument that Nevada will not be foreclosed from raising
substantive claims against the FEIS in administrative proceedings
comports with the terms of the regulation and reflects a reasonable
and compelling interpretation.
[[Page 5765]]
Therefore, on the record at hand, there is no reason to assume that
the regulation will bar consideration of Nevada's substantive claims
in the relevant NRC administrative proceedings.
373 F.3d at 1314.
Far from suggesting that NRC's regulation needed to be amended to
accommodate the court's interpretation of the regulation, the court
expressed its satisfaction that there was no reason to assume that the
present language of the regulation would bar consideration of Nevada's
substantive claims. This conclusion follows the court's explicit
consideration of the language of the Sec. 51.109(c) criteria. The
court focused on the second criterion; i.e., that it might not be
practicable for NRC to adopt the FEIS if ``significant and substantial
new information or new considerations render such environmental impact
statement inadequate.'' The court noted that ``Government counsel
assured the court that NRC will not construe the `new information or
new considerations' requirement to preclude Nevada from raising
substantive claims against the FEIS in administrative proceedings.''
Id. Further, the court observed that ``Nevada's claims have not been
adjudicated on the merits here and presumably will not have been passed
upon by any court prior to the relevant NRC proceedings. The claims
thus would certainly raise `new considerations' with regard to any
decision to adopt the FEIS.'' Id.\4\ There is no need for the
Commission to expend the resources needed for a rulemaking to
``correct'' a rule which the court gave no indication of needing
correction. NRC will treat Nevada's substantive claims against the FEIS
as ``new considerations'' within the framework of Sec. 51.109(c).
---------------------------------------------------------------------------
\4\ At the same time, the court recognized that ``[t]he NWPA's
mandate that the FEIS be adopted by NRC `to the extent practicable'
is intended to avoid duplication of the environmental review
process.'' 373 F.3d 1251.
---------------------------------------------------------------------------
Although the petitioner frames its request for correction of Sec.
51.109(c) in terms of a supposed need to bring the regulation into line
with the views of the court, the petitioner may actually be seeking to
raise once again the issues the State and CEQ raised in comments made
during the 1988-89 rulemaking. The petition raises no issues that were
not raised and fully considered in that rulemaking. The Commission's
rationale for the adoption criteria issued as part of that rulemaking
was not before the court in NEI and the court, as explained above,
found nothing amiss with the criteria. The court's decision presents no
reasons for the Commission to reexamine the basis of that rulemaking.
B. The Litigation Procedures in Sec. 51.109(a)(2)
With regard to the ``special litigation procedures,'' the
petitioner notes that Sec. 51.109(a)(2) conditions the admissibility
of a contention which asserts that NRC should not adopt the FEIS on
satisfaction, to the extent possible, of the standards for reopening a
closed record under 10 CFR 2.326. The petitioner asserts that the
principal difference between this standard and the contention standard
in 10 CFR 2.309(f) that applies to other issues is that the former
requires submission of admissible evidence, while the latter does not.
The petitioner asserts that NRC's creation of ``special litigation
procedures'' violates NEPA: ``Section 102(2)(C) of NEPA requires that
an FEIS must be considered in the `existing agency review processes'
[emphasis added], not some different review process applicabl[e] only
to NEPA where interested persons must satisfy additional pleading
requirements that would otherwise not apply.'' Petition at 6 (citing
Calvert Cliffs, 449 F.2d 1109 (D.C. Cir. 1971); 40 CFR 1505.1; Aberdeen
& Rockfish R. Co. v. SCRAP, 422 U.S. 289, 320 (1975)).
The relevant portion of section 102(2)(C) of the NEPA states that
copies of the requisite ``detailed statement'' must ``accompany the
proposal through the existing agency review processes.'' \5\ This
language does not require that an agency establish one uniform agency
process for all NEPA reviews. Here, NRC has adopted a contention
standard in Sec. 51.109(a)(2) which takes account of the NWPA's effect
on its NEPA responsibilities as explained in its 1988-89 rulemaking. In
the relevant portion of the Calvert Cliffs decision, the question
before the court was ``whether the [Atomic Energy] Commission is
correct in thinking that its NEPA responsibilities may be carried out
in toto outside the hearing process--whether it is enough that
environmental data and evaluations merely accompany the application
through the review process, but receive no consideration whatever from
the hearing board.'' Calvert Cliffs, 449 F.2d at 1117 (internal
quotation marks omitted). In the discussion that follows, the court
focused on the meaning of the term ``accompany,'' not whether changes
in agency procedures for considering NEPA issues would be inconsistent
with the ``existing agency review process'' language. The court
concluded that the word ``accompany'' meant that the detailed statement
must be considered during the agency review process. In Aberdeen, the
Court held that an oral hearing held before an agency made a
recommendation or report on a proposal for Federal action was not an
``existing agency review process'' under section 102(2)(C) of the NEPA
and thus, a FEIS was not required to be available during this hearing.
See, 422 U.S. at 320-21. Thus, the Supreme Court's discussion in
Aberdeen focuses on when the FEIS must be made available, not whether
the term ``existing agency review process'' means that one contention
standard must apply to all NEPA reviews in all cases before an agency.
In short, the case law cited by the petitioner does not provide a
reason for NRC to delete Sec. 51.109(a)(2) from its regulations.
---------------------------------------------------------------------------
\5\ The CEQ regulation at 40 CFR 1505.1 is based on the
statutory language and requires that agency procedures require
``that relevant environmental documents * * * accompany the proposal
through existing agency review processes so that agency officials
use the statement in making decisions.''
---------------------------------------------------------------------------
Conclusion
The NEI court found no need for NRC to amend its regulations for
the purpose of allowing the State to have its substantive claims
examined in NRC's licensing proceeding for a potential YM repository.
Petitioner's claims that NRC's adoption criteria violate the NEPA or
the NWPA were addressed in the 1988-89 rulemaking and petitioner offers
no new arguments for the Commission's consideration. Nor does the
petitioner provide adequate legal support for NRC to amend its
litigation procedures. Given this, it would be an unwise expenditure of
resources for the Commission to conduct a rulemaking on this matter.
For these reasons, the Commission denies PRM-51-9.
Dated at Rockville, Maryland, this 25th day of January 2008.
For the Nuclear Regulatory Commission.
Annette L. Vietti-Cook,
Secretary of the Commission.
Appendix I--Commissioner Jaczko's Comments on SECY-07-0159, Denial of a
Petition for Rulemaking (PRM-51-9)--State of Nevada
I approve in part and disapprove in part the recommendation to
proceed with option 2 which would deny the rulemaking petition while
offering the assurance that the NRC will interpret the existing
regulations to allow substantive claims to the Department of
Energy's (DOE) Final Environmental Impact Statement (FEIS). Instead,
I approve a combination of options 1 and 2. The original regulations
governing the agency's review of the FEIS were based upon an
assumption of how the site selection process for a potential
repository would unfold. But because the judicial review of
environmental
[[Page 5766]]
issues did not happen as we envisioned, I believe we should grant
the petition and fix the corresponding regulations to appropriately
reflect that the entire FEIS will be open for litigation in any NRC
administrative proceeding regarding a repository application. At the
same time, I believe the notice of the proposed rule should explain
that the agency will interpret the regulations in a manner
consistent with this approach should the rulemaking not be completed
in time for a hearing on a potential Yucca Mountain license
application.
Based upon the history of this issue, I think granting the
petition and amending our regulations is the right answer in this
case. First, it is important to remember that the NRC could have
originally interpreted the Nuclear Waste Policy Act (NWPA) to allow
the NRC to handle the adoption of DOE's FEIS in the same manner it
currently handles the adoption of any other federal agency EIS in
the NEPA review process. The NWPA's direction to avoid duplicative
environmental analysis does not necessarily equate to a direction to
eliminate most, if not all, of the FEIS from the NRC's hearing
process. I believe we should treat DOE's FEIS in the same manner as
we treat any other FEIS submitted by a similarly situated regulated
entity. In this case, that would mean defending the agency's
independent review of the entire FEIS--not just limited portions of
it--in the NRC's administrative proceedings. Commenters, including
the Council on Environmental Quality, said as much in comments to
this rulemaking and I find their logic persuasive. Had the agency
opted for that interpretation in the proposed rulemaking, perhaps we
would not find ourselves facing this petition today.
NRC's rationale for not doing so, however, while not ideal, made
sense in the context of what the agency thought would happen with
the FEIS. According to the rulemaking history, section 51.109 of
NRC's regulations was based, at least in large part, upon the theory
that the administrative litigation of NEPA issues at the NRC should
be limited because many of these issues should have already had the
opportunity to be litigated in another forum. Thus, legal doctrines
which prevent issues and claims from being re-litigated, such as res
judicata and collateral estoppel, would prevent the re-litigation of
these issues in NRC hearings. This was premised upon NRC's
expectation that an interested person would have had an opportunity
to legally challenge DOE's FEIS after it was used to support the
recommendations of Yucca Mountain as a site for a repository by the
Secretary of Energy and the President.
With that expectation in mind, the regulations were then
designed to ensure that the environmental issues in any NRC
proceeding on the proposed repository would appropriately focus on
issues that were new--that were not able to be raised at the earlier
opportunity to challenge the FEIS. So the regulations adopted in
section 51.109 focused not on the entire FEIS, as would be the
normal NRC practice, but on the NRC's decision to adopt the FEIS.
The regulations limited challenges to NRC's adoption decision to
those issues that had changed from the original application, or that
were issues raising ``significant and substantial new information''
since that earlier opportunity to challenge the FEIS. This makes
sense if any of the other issues regarding the FEIS had already had
the opportunity to be challenged. Given that presumption, it also
explains why the regulations direct the Board to use the higher
standards governing a motion to reopen when ruling upon the issues
raised regarding adoption of the FEIS--because litigating the FEIS
in NRC's administrative proceeding was seen as re-opening the record
on an already litigated FEIS.
All that being said, as is often the case, actual events
regarding judicial review of environmental issues transpired
differently. Instead of the FEIS being used to support the
recommendation of Yucca Mountain as a site for a repository, there
was a Joint Resolution of Congress approving the Yucca Mountain site
designation. This change of events, according to the Federal Court
of Appeals decision in Nuclear Energy Institute, Inc. v.
Environmental Protection Agency, 373 F.3d 1251 (D.C. Circuit 2004),
rendered any such challenge to the FEIS' support for the Yucca
Mountain site moot; and to the extent the NRC may rely upon the
FEIS, rendered challenges unripe because the NRC had not reached a
decision regarding adopting or relying upon the FEIS in a way that
could have yet harmed the parties.
It was part of this discussion that led the NRC and DOE to
assure the court that the parties would have an opportunity during
NRC's administrative hearing to raise substantive challenges to the
FEIS. And it is this assurance from NRC counsel that generated the
petition for rulemaking. In essence, the petitioners do not
understand how NRC's current regulations can be in accord with the
assurance the court relied upon--that parties would have the
opportunity at the NRC to substantively challenge the FEIS. Because
current NRC regulations limit challenges to NRC's decision about
adoption of the FEIS rather than the FEIS itself; and further limit
those challenges to require they be based upon significant and
substantial new information, it is easy to see how our stakeholders
might be confused. Add to that the direction in the current
regulations that the Boards are directed to review any challenge to
the decision regarding adoption using the standards that govern re-
opening a record--which is an intentionally higher bar for review--
and there can be little question that the current regulations are
confusing in light of the discussion in front of the court and the
relied upon assurance that substantive issues regarding the FEIS
could, in fact, be raised in NRC proceedings.
For all of these reasons, it appears to me that the best way to
transparently resolve the real question presented--the question of
what issues surrounding the FEIS can be challenged in a prospective
hearing on an application for a construction authorization--is to
grant this petition and ensure that the regulations transparently
capture precisely how the environmental review will be conducted in
NRC's administrative proceeding. The earlier rulemaking was based
upon assumptions, but we can now answer the questions with the
benefit of knowing now what we did not know then.
I recognize that the timing of the agency's decision on this
petition is not ideal because an application for a repository may be
submitted before this rulemaking would end. That is especially
unfortunate in this particular situation where the petition was
filed in 2005. Had we granted this petition at the close of the
public comment period in October 2005, we likely would now be voting
on the final rule instead of voting on this petition. I am hopeful
that the staff's work to improve the rulemaking process will include
ways to improve the timeliness of the petition process so we are not
in this unfortunate position in the future.
But we are where we are, and with that in mind, I believe the
notice that grants the petition for rulemaking should indicate that,
if the rulemaking is not resolved prior to the receipt of an
application for a repository, the agency intends to interpret the
regulations in a manner consistent with the court's decision--as the
staff has drafted in the notice accompanying option 2--with some
additional clarification. The notice should also explain that
section 51.109(c), which indicates that challenges to the NRC's
adoption decision are to be based upon ``significant and substantial
new information'', will be interpreted in a manner that recognizes,
as the court did, that claims regarding DOE's FEIS have not been
adjudicated on the merits and thus, would certainly raise ``new
considerations'' with regard to any decision to adopt the FEIS. The
notice should also make it clear that the current direction in
section 51.109(a) that the presiding officer should, to the extent
possible, use the criteria for ruling on a motion to reopen in
resolving disputes regarding the adoption of the FEIS, is rendered
moot. The notice should clearly state that it is not possible to
rely upon criteria used for a motion to reopen given the relevant
history of this matter where there was no opportunity to originally
open these issues. Instead, the contention admissibility should be
determined by reliance upon section 2.309(f), the agency's current
contention standard.
I appreciate that because these regulations have not yet been
interpreted and applied in any proceeding, the agency has more
flexibility to interpret them now without recreating them in a new
rulemaking--and thus the recommendation for option 2. But this is
not a situation where the regulations intent could have been
clearer; this is a situation where the interpretation of the
regulations will essentially require the agency to exercise great
latitude in applying them in a manner consistent with the discussion
in court. Transparency should dictate that we, at least, try to
correct this situation through the appropriate rulemaking channels
regardless of the impacts of the timing of this decision. We should
not let the prospect of a potential application complicate what is
clearly the right answer. We can and should deal with the possible
complications of an intervening application
[[Page 5767]]
by providing appropriate guidance should the rulemaking not resolve
itself in time. But the two are not mutually exclusive and thus, I
support a combination of options 1 and 2--granting the petition and
clarifying in the notice the agency's regulatory interpretation of
the existing regulations should they be required to be used prior to
completion of the rulemaking.
Also, this paper should be reviewed for a release determination
and, at a minimum, the voting record and SRM from this paper should
be made publicly available five business days after the letter is
sent to the petitioner, as is current practice for release of
information regarding decisions on rulemaking petitions.
Gregory B. Jaczko.
[FR Doc. E8-1751 Filed 1-30-08; 8:45 am]