Download as PDF mstockstill on PROD1PC66 with NOTICES 5538 Federal Register / Vol. 73, No. 20 / Wednesday, January 30, 2008 / Notices to serve a copy of that document on each person in the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. Description of Project: The proposed project would utilize the existing U.S. Army Corps of Engineers’ Wright Patman Dam and would consist of: (1) A proposed 339-foot-long, 144inch-diameter steel penstock; (2) a proposed powerhouse containing one generating unit with an installed capacity of 5-megawatts; (3) a switchyard; (4) a proposed 2-mile-long, 25-kV transmission line; and (5) appurtenant facilities. The proposed project would have an estimated annual generation of approximately 16gigawatts and would be sold to a local utility. l. Location of Application: A copy of the application is available for inspection and reproduction at the Commission in the Public Reference Room, located at 888 First Street, NE., Room 2A, Washington, DC 20426, or by calling (202) 502–8371. This filing may also be viewed on the Commission’s Web site at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, call toll-free 1–866–208–3676 or e-mail FERCOnlineSupport@ferc.gov. For TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item h above. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Competing Preliminary Permit— Anyone desiring to file a competing application for preliminary permit for a proposed project must submit the competing application itself, or a notice of intent to file such an application, to the Commission on or before the specified comment date for the particular application (see 18 CFR 4.36). Submission of a timely notice of intent allows an interested person to file the competing preliminary permit application no later than 30 days after the specified comment date for the particular application. A competing preliminary permit application must conform with 18 CFR 4.30 and 4.36. o. Competing Development Application—Any qualified development applicant desiring to file a competing development application VerDate Aug<31>2005 18:49 Jan 29, 2008 Jkt 214001 must submit to the Commission, on or before a specified comment date for the particular application, either a competing development application or a notice of intent to file such an application. Submission of a timely notice of intent to file a development application allows an interested person to file the competing application no later than 120 days after the specified comment date for the particular application. A competing license application must conform with 18 CFR 4.30 and 4.36. p. Notice of Intent—A notice of intent must specify the exact name, business address, and telephone number of the prospective applicant, and must include an unequivocal statement of intent to submit, if such an application may be filed, either a preliminary permit application or a development application (specify which type of application). A notice of intent must be served on the applicant(s) named in this public notice. q. Proposed Scope of Studies Under Permit—A preliminary permit, if issued, does not authorize construction. The term of the proposed preliminary permit would be 36 months. The work proposed under the preliminary permit would include economic analysis, preparation of preliminary engineering plans, and a study of environmental impacts. Based on the results of these studies, the Applicant would decide whether to proceed with the preparation of a development application to construct and operate the project. r. Comments, Protests, or Motions To Intervene—Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. Comments, protests and interventions may be filed electronically via the Internet in lieu of paper. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site at https:// www.ferc.gov under the ‘‘e-Filing’’ link. s. Filing and Service of Responsive Documents—Any filings must bear in all capital letters the title ‘‘COMMENTS’’, ‘‘NOTICE OF INTENT TO FILE COMPETING APPLICATION’’, ‘‘COMPETING APPLICATION’’, PO 00000 Frm 00045 Fmt 4703 Sfmt 4703 ‘‘PROTEST’’, and ‘‘MOTION TO INTERVENE’’, as applicable, and the Project Number of the particular application to which the filing refers. Any of the above-named documents must be filed by providing the original and the number of copies provided by the Commission’s regulations to: The Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. An additional copy must be sent to Director, Division of Hydropower Administration and Compliance, Federal Energy Regulatory Commission, at the above-mentioned address. A copy of any notice of intent, competing application or motion to intervene must also be served upon each representative of the Applicant specified in the particular application. t. Agency Comments—Federal, state, and local agencies are invited to file comments on the described application. A copy of the application may be obtained by agencies directly from the Applicant. If an agency does not file comments within the time specified for filing comments, it will be presumed to have no comments. One copy of an agency’s comments must also be sent to the Applicant’s representatives. Kimberly D. Bose, Secretary. [FR Doc. E8–1631 Filed 1–29–08; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP08–52–000] Caledonia Energy Partners, L.L.C.; Notice of Application January 24, 2008. Take notice that on January 14, 2008, Caledonia Energy Partners, L.L.C. (Caledonia), 2001 Timber Creek Road, Flower Mound, TX 75028, filed in Docket No. CP08–52–000, an application under section 7(c) of the Natural Gas Act (NGA), to expand the Caledonia Storage Facility by developing a depleted production reservoir as an additional gas storage field; constructing a pipeline lateral to connect the new field with the existing storage facility; and installation of a total of 10,000 Hp of additional compression which will allow Caledonia to increase its maximum allowable operating pressure to 2,518 psia. The expanded facilities will increase Caledonia’s maximum total storage capacity from 11.7 Bcf to 16.9 Bcf and its maximum daily withdrawal E:\FR\FM\30JAN1.SGM 30JAN1 mstockstill on PROD1PC66 with NOTICES Federal Register / Vol. 73, No. 20 / Wednesday, January 30, 2008 / Notices rate from 330 MMcf/d to 477 MMcf/d, all as more fully set forth in the application which is on file with the Commission and open to public inspection. This filing may also be viewed on the Commission’s Web site at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number, excluding the last three digits, in the docket number field to access the document. For assistance, call (202) 502–8659 or TTY, (202) 208–3676. Any questions regarding this application should be directed to Jim Goetz, Caledonia Energy Partners, L.L.C., 2001 Timber Creek Road, Flower Mound, Texas 75028, at (972) 691–3332, or by fax at (972) 874–8743, or Christopher A. Schindler, Hogan & Hartson L.L.P., 555 Thirteenth Street, NW., Washington, DC 20004, at (202) 637–5723, or by fax at (202) 637–5910. Pursuant to Section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. There are two ways to become involved in the Commission’s review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below, file with the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission’s Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit 14 copies of filings made with the Commission and must mail a copy to VerDate Aug<31>2005 18:49 Jan 29, 2008 Jkt 214001 the applicant and to every other party in the proceeding. Only parties to the proceeding can ask for court review of Commission orders in the proceeding. However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission’s rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commentors will be placed on the Commission’s environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission’s environmental review process. Environmental commentors will not be required to serve copies of filed documents on all other parties. However, the non-party commentors will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https:// www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. PO 00000 Frm 00046 Fmt 4703 Sfmt 4703 5539 Comment Date: February 14, 2008. Kimberly D. Bose, Secretary. [FR Doc. E8–1623 Filed 1–29–08; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. DI08–1–000] City of Aspen; Notice of Declaration of Intention and Soliciting Comments, Protests, and/or Motions To Intervene January 24, 2008. Take notice that the following application has been filed with the Commission and is available for public inspection: a. Application Type: Declaration of Intention. b. Docket No: DI08–1–000. c. Date Filed: January 7, 2008. d. Applicant: City of Aspen, CO. e. Name of Project: Castle Creek Hydroelectric Project. f. Location: The proposed Castle Creek Hydroelectric Project will be located on Castle Creek within the city of Aspen’s existing water transmission system, in Pitkin County, in Aspen, Colorado. g. Filed Pursuant to: Section 23(b)(1) of the Federal Power Act, 16 U.S.C. 817(b). h. Applicant Contact: Richard Smart, Community Hydropower Consulting, LLC, P. O. Box 1091, Fort Collins, CO 80522; telephone: (970) 221–4474; fax: (970) 221–0095; e-mail: https://www.r_ smart@communityhydro.com. i. FERC Contact: Any questions on this notice should be addressed to Henry Ecton, (202) 502–8768, or E-mail address: henry.ecton@ferc.gov. j. Deadline for filing comments, protests, and/or motions: February 25, 2008. All documents (original and eight copies) should be filed with: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. Comments, protests, and/or interventions may be filed electronically via the Internet in lieu of paper. See, 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site at https://www.ferc.gov under the ‘‘eFiling link. Please include the docket number (DI08–1–000) on any comments, protests, and/or motions filed. k. Description of Project: The proposed Castle Creek Hydroelectric Project will include: (1) A run-of-river E:\FR\FM\30JAN1.SGM 30JAN1

Agencies

[Federal Register Volume 73, Number 20 (Wednesday, January 30, 2008)]
[Notices]
[Pages 5538-5539]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-1623]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP08-52-000]


Caledonia Energy Partners, L.L.C.; Notice of Application

January 24, 2008.
    Take notice that on January 14, 2008, Caledonia Energy Partners, 
L.L.C. (Caledonia), 2001 Timber Creek Road, Flower Mound, TX 75028, 
filed in Docket No. CP08-52-000, an application under section 7(c) of 
the Natural Gas Act (NGA), to expand the Caledonia Storage Facility by 
developing a depleted production reservoir as an additional gas storage 
field; constructing a pipeline lateral to connect the new field with 
the existing storage facility; and installation of a total of 10,000 Hp 
of additional compression which will allow Caledonia to increase its 
maximum allowable operating pressure to 2,518 psia. The expanded 
facilities will increase Caledonia's maximum total storage capacity 
from 11.7 Bcf to 16.9 Bcf and its maximum daily withdrawal

[[Page 5539]]

rate from 330 MMcf/d to 477 MMcf/d, all as more fully set forth in the 
application which is on file with the Commission and open to public 
inspection. This filing may also be viewed on the Commission's Web site 
at https://www.ferc.gov using the ``eLibrary'' link. Enter the docket 
number, excluding the last three digits, in the docket number field to 
access the document. For assistance, call (202) 502-8659 or TTY, (202) 
208-3676.
    Any questions regarding this application should be directed to Jim 
Goetz, Caledonia Energy Partners, L.L.C., 2001 Timber Creek Road, 
Flower Mound, Texas 75028, at (972) 691-3332, or by fax at (972) 874-
8743, or Christopher A. Schindler, Hogan & Hartson L.L.P., 555 
Thirteenth Street, NW., Washington, DC 20004, at (202) 637-5723, or by 
fax at (202) 637-5910.
    Pursuant to Section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below, file with the Federal Energy 
Regulatory Commission, 888 First Street, NE., Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit 14 copies of filings made with the Commission and must mail a 
copy to the applicant and to every other party in the proceeding. Only 
parties to the proceeding can ask for court review of Commission orders 
in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commentors will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commentors will not be required to serve copies of filed 
documents on all other parties. However, the non-party commentors will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the ``eFiling'' link 
at https://www.ferc.gov. Persons unable to file electronically should 
submit an original and 14 copies of the protest or intervention to the 
Federal Energy Regulatory Commission, 888 First Street, NE., 
Washington, DC 20426.
    This filing is accessible on-line at https://www.ferc.gov, using the 
``eLibrary'' link and is available for review in the Commission's 
Public Reference Room in Washington, DC. There is an ``eSubscription'' 
link on the Web site that enables subscribers to receive e-mail 
notification when a document is added to a subscribed docket(s). For 
assistance with any FERC Online service, please e-mail 
FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll free). For 
TTY, call (202) 502-8659.
    Comment Date: February 14, 2008.