Federal Register / Vol. 73, No. 16 / Thursday, January 24, 2008 / Rules and Regulations
impose any information collection
requirements that require the approval
of the Office of Management and Budget
under 44 U.S.C. 3501, et seq.
D. Determination To Issue an Interim
Rule
A determination has been made under
the authority of the Secretary of Defense
that urgent and compelling reasons exist
to publish an interim rule prior to
affording the public an opportunity to
comment. This interim rule implements
Section 818 of the National Defense
Authorization Act for Fiscal Year 2007
(Pub. L. 109–364). Section 818 requires
DoD to modify regulations regarding the
determination of contract type for major
development programs to address
requirements for selection of the
contract type that is consistent with the
level of program risk. Comments
received in response to this interim rule
will be considered in the formation of
the final rule.
List of Subjects in 48 CFR Parts 234 and
235
Government procurement.
Michele P. Peterson,
Editor, Defense Acquisition Regulations
System.
Therefore, 48 CFR parts 234 and 235
are amended as follows:
I 1. The authority citation for 48 CFR
parts 234 and 235 continues to read as
follows:
I
Authority: 41 U.S.C. 421 and 48 CFR
Chapter 1.
PART 234—MAJOR SYSTEM
ACQUISITION
2. Section 234.004 is revised to read
as follows:
I
jlentini on PROD1PC65 with RULES
234.004
Acquisition strategy.
(1) See 209.570 for policy applicable
to acquisition strategies that consider
the use of lead system integrators.
(2) In accordance with Section 818 of
the National Defense Authorization Act
for Fiscal Year 2007 (Pub. L. 109–364),
for major defense acquisition programs
as defined in 10 U.S.C. 2430—
(i) The Milestone Decision Authority
shall select, with the advice of the
contracting officer, the contract type for
a development program at the time of
Milestone B approval or, in the case of
a space program, Key Decision Point B
approval;
(ii) The basis for the contract type
selection shall be documented in the
acquisition strategy. The
documentation—
(A) Shall include an explanation of
the level of program risk; and
VerDate Aug<31>2005
19:26 Jan 23, 2008
Jkt 214001
(B) If program risk is determined to be
high, shall outline the steps taken to
reduce program risk and the reasons for
proceeding with Milestone B approval
despite the high level of program risk;
and
(iii) If a cost-type contract is selected,
the contract file shall include the
Milestone Decision Authority’s written
determination that—
(A) The program is so complex and
technically challenging that it would
not be practicable to reduce program
risk to a level that would permit the use
of a fixed-price type contract; and
(B) The complexity and technical
challenge of the program is not the
result of a failure to meet the
requirements of 10 U.S.C. 2366a.
PART 235—RESEARCH AND
DEVELOPMENT CONTRACTING
obtain USD(AT&L) approval of the
negotiated agreement with the
contractor before the agreement is
executed, for any action that is—
(1) An increase of more than $250
million in the price or ceiling price of
a fixed-price type development contract,
or a fixed-price type contract for the
lead ship of a class;
(2) A reduction in the amount of work
under a fixed-price type development
contract or a fixed-price type contract
for the lead ship of a class, when the
value of the work deleted is $100
million or more; or
(3) A repricing of fixed-price type
production options to a development
contract, or a contract for the lead ship
of a class, that increases the price or
ceiling price by more than $250 million
for equivalent quantities.
[FR Doc. E8–1092 Filed 1–23–08; 8:45 am]
3. Section 235.006 is revised to read
as follows:
BILLING CODE 5001–08–P
235.006
type.
DEPARTMENT OF COMMERCE
I
Contracting methods and contract
(b)(i) For major defense acquisition
programs as defined in 10 U.S.C. 2430—
(A) Follow the procedures at 234.004;
and
(B) Notify the Under Secretary of
Defense (Acquisition, Technology, and
Logistics) (USD(AT&L)) of an intent not
to exercise a fixed-price production
option on a development contract for a
major weapon system reasonably in
advance of the expiration of the option
exercise period.
(ii) For other than major defense
acquisition programs—
(A) Do not award a fixed-price type
contract for a development program
effort unless—
(1) The level of program risk permits
realistic pricing;
(2) The use of a fixed-price type
contract permits an equitable and
sensible allocation of program risk
between the Government and the
contractor; and
(3) A written determination that the
criteria of paragraphs (b)(ii)(A)(1) and
(2) of this section have been met is
executed—
(i) By the USD(AT&L) if the contract
is over $25 million and is for: research
and development for a non-major
system; the development of a major
system (as defined in FAR 2.101); or the
development of a subsystem of a major
system; or
(ii) By the contracting officer for any
development not covered by paragraph
(b)(ii)(A)(3)(i) of this section.
(B) Obtain USD(AT&L) approval of
the Government’s prenegotiation
position before negotiations begin, and
PO 00000
Frm 00068
Fmt 4700
Sfmt 4700
National Oceanic and Atmospheric
Administration
50 CFR Part 229
[Docket No. 080117051–8053–01]
RIN 0648–XF17
Taking of Marine Mammals Incidental
to Commercial Fishing Operations;
Atlantic Large Whale Take Reduction
Plan
National Marine Fisheries
Service (NMFS), National Oceanic and
Atmospheric Administration (NOAA),
Commerce.
ACTION: Temporary rule.
AGENCY:
SUMMARY: The Assistant Administrator
for Fisheries (AA), NOAA, announces
temporary restrictions consistent with
the requirements of the Atlantic Large
Whale Take Reduction Plan’s
(ALWTRP) implementing regulations.
These regulations apply to lobster trap/
pot and anchored gillnet fishermen in
an area totaling approximately 2,251
nm2 (7,720 km2), southeast of
Portsmouth, New Hampshire, for 15
days. The purpose of this action is to
provide protection to an aggregation of
northern right whales (right whales).
DATES: Effective beginning at 0001 hours
January 26, 2008, through 2400 hours
February 9, 2008.
ADDRESSES: Copies of the proposed and
final Dynamic Area Management (DAM)
rules, Environmental Assessments
(EAs), Atlantic Large Whale Take
Reduction Team (ALWTRT) meeting
summaries, and progress reports on
E:\FR\FM\24JAR1.SGM
24JAR1
Federal Register / Vol. 73, No. 16 / Thursday, January 24, 2008 / Rules and Regulations
implementation of the ALWTRP may
also be obtained by writing Diane
Borggaard, NMFS/Northeast Region,
One Blackburn Drive, Gloucester, MA
01930.
FOR FURTHER INFORMATION CONTACT:
Diane Borggaard, NMFS/Northeast
Region, 978–281–9300 x6503; or Kristy
Long, NMFS, Office of Protected
Resources, 301–713–2322.
SUPPLEMENTARY INFORMATION:
Electronic Access
Several of the background documents
for the ALWTRP and the take reduction
planning process can be downloaded
from the ALWTRP web site at https://
www.nero.noaa.gov/whaletrp/.
jlentini on PROD1PC65 with RULES
Background
The ALWTRP was developed
pursuant to section 118 of the Marine
Mammal Protection Act (MMPA) to
reduce the incidental mortality and
serious injury of three endangered
species of whales (right, fin, and
humpback) due to incidental interaction
with commercial fishing activities. In
addition, the measures identified in the
ALWTRP would provide conservation
benefits to a fourth species (minke),
which are neither listed as endangered
nor threatened under the Endangered
Species Act (ESA). The ALWTRP,
implemented through regulations
codified at 50 CFR 229.32, relies on a
combination of fishing gear
modifications and time/area closures to
reduce the risk of whales becoming
entangled in commercial fishing gear
(and potentially suffering serious injury
or mortality as a result).
On January 9, 2002, NMFS published
the final rule to implement the
ALWTRP’s DAM program (67 FR 1133).
On August 26, 2003, NMFS amended
the regulations by publishing a final
rule, which specifically identified gear
modifications that may be allowed in a
DAM zone (68 FR 51195). The DAM
program provides specific authority for
NMFS to restrict temporarily on an
expedited basis the use of lobster trap/
pot and anchored gillnet fishing gear in
areas north of 40° N. lat. to protect right
whales. Under the DAM program,
NMFS may: (1) require the removal of
all lobster trap/pot and anchored gillnet
fishing gear for a 15–day period; (2)
allow lobster trap/pot and anchored
gillnet fishing within a DAM zone with
gear modifications determined by NMFS
to sufficiently reduce the risk of
entanglement; and/or (3) issue an alert
to fishermen requesting the voluntary
removal of all lobster trap/pot and
anchored gillnet gear for a 15–day
period and asking fishermen not to set
VerDate Aug<31>2005
19:26 Jan 23, 2008
Jkt 214001
any additional gear in the DAM zone
during the 15–day period.
A DAM zone is triggered when NMFS
receives a reliable report from a
qualified individual of three or more
right whales sighted within an area (75
nm2 (139 km2)) such that right whale
density is equal to or greater than 0.04
right whales per nm2 (1.85 km2). A
qualified individual is an individual
ascertained by NMFS to be reasonably
able, through training or experience, to
identify a right whale. Such individuals
include, but are not limited to, NMFS
staff, U.S. Coast Guard and Navy
personnel trained in whale
identification, scientific research survey
personnel, whale watch operators and
naturalists, and mariners trained in
whale species identification through
disentanglement training or some other
training program deemed adequate by
NMFS. A reliable report would be a
credible right whale sighting.
On January 13, 2008, an aerial survey
reported two aggregations of right
whales, totaling seven individuals: four
whales in the proximity of 42° 37′ N.
latitude and 70° 01′ W. longitude, and
three whales in the proximity of 42° 51′
N. latitude and 70° 04′ W. longitude.
These positions lie northeast of Boston,
Massachusetts, and southeast of
Portsmouth, New Hampshire,
respectively. After conducting an
investigation, NMFS ascertained that
the report came from a qualified
individual and determined that the
report was reliable. Thus, NMFS has
received a reliable report from a
qualified individual of the requisite
right whale density to trigger the DAM
provisions of the ALWTRP.
Once a DAM zone is triggered, NMFS
determines whether to impose
restrictions on fishing and/or fishing
gear in the zone. This determination is
based on the following factors,
including but not limited to: the
location of the DAM zone with respect
to other fishery closure areas, weather
conditions as they relate to the safety of
human life at sea, the type and amount
of gear already present in the area, and
a review of recent right whale
entanglement and mortality data.
NMFS has reviewed the factors and
management options noted above
relative to the DAM under
consideration. As a result of this review,
NMFS prohibits lobster trap/pot and
anchored gillnet gear in this area during
the 15–day restricted period unless it is
modified in the manner described in
this temporary rule.
The DAM Zone is bound by the
following coordinates:
43° 09′ N., 70° 29′ W. (NW Corner)
43° 09′ N., 69° 39′ W.
PO 00000
Frm 00069
Fmt 4700
Sfmt 4700
4119
42° 56′ N., 69° 39′ W.
42° 56′ N., 69° 33′ W.
42° 16′ N., 69° 33′ W.
42° 16′ N., 70° 33′ W.
42° 56′ N., 70° 33′ W.
42° 56′ N., 70° 29′ W.
43° 09′ N., 70° 29′ W. (NW Corner)
In addition to those gear
modifications currently implemented
under the ALWTRP at 50 CFR 229.32,
the following gear modifications are
required in the DAM zone. If the
requirements and exceptions for gear
modification in the DAM zone, as
described below, differ from other
ALWTRP requirements for any
overlapping areas and times, then the
more restrictive requirements will apply
in the DAM zone.
Lobster Trap/pot Gear
Fishermen utilizing lobster trap/pot
gear within the portions of Northern
Nearshore Lobster Waters, Northern
Inshore State Lobster Waters, and the
Stellwagen Bank/Jeffrey’s Ledge
Restricted Area that overlap with the
DAM zone are required to utilize all of
the following gear modifications while
the DAM zone is in effect:
1. Groundlines must be made of either
sinking or neutrally buoyant line.
Floating groundlines are prohibited;
2. All buoy lines must be made of
either sinking or neutrally buoyant line,
except the bottom portion of the line,
which may be a section of floating line
not to exceed one-third the overall
length of the buoy line;
3. Fishermen are allowed to use two
buoy lines per trawl; and
4. A weak link with a maximum
breaking strength of 600 lb (272.4 kg)
must be placed at all buoys.
Fishermen utilizing lobster trap/pot
gear within the portion of the Offshore
Lobster Waters Area that overlap with
the DAM zone are required to utilize all
of the following gear modifications
while the DAM zone is in effect:
1. Groundlines must be made of either
sinking or neutrally buoyant line.
Floating groundlines are prohibited;
2. All buoy lines must be made of
either sinking or neutrally buoyant line,
except the bottom portion of the line,
which may be a section of floating line
not to exceed one-third the overall
length of the buoy line;
3. Fishermen are allowed to use two
buoy lines per trawl; and
4. A weak link with a maximum
breaking strength of 1,500 lb (680.4 kg)
must be placed at all buoys.
Anchored Gillnet Gear
Fishermen utilizing anchored gillnet
gear within the portions of Other
Northeast Gillnet Waters and the
E:\FR\FM\24JAR1.SGM
24JAR1
4120
Federal Register / Vol. 73, No. 16 / Thursday, January 24, 2008 / Rules and Regulations
jlentini on PROD1PC65 with RULES
Stellwagen Bank/Jeffrey’s Ledge
Restricted Area that overlap with the
DAM zone are required to utilize all the
following gear modifications while the
DAM zone is in effect:
1. Groundlines must be made of either
sinking or neutrally buoyant line.
Floating groundlines are prohibited;
2. All buoy lines must be made of
either sinking or neutrally buoyant line,
except the bottom portion of the line,
which may be a section of floating line
not to exceed one-third the overall
length of the buoy line;
3. Fishermen are allowed to use two
buoy lines per string;
4. The breaking strength of each net
panel weak link must not exceed 1,100
lb (498.8 kg). The weak link
requirements apply to all variations in
net panel size. One weak link must be
placed in the center of the floatline and
one weak link must be placed in the
center of each of the up and down lines
at both ends of the net panel.
Additionally, one weak link must be
placed as close as possible to each end
of the net panels on the floatline; or, one
weak link must be placed between
floatline tie-loops between net panels
and one weak link must be placed
where the floatline tie-loops attach to
the bridle, buoy line, or groundline at
each end of a net string;
5. A weak link with a maximum
breaking strength of 1,100 lb (498.8 kg)
must be placed at all buoys; and
6. All anchored gillnets, regardless of
the number of net panels, must be
securely anchored with the holding
power of at least a 22 lb (10.0 kg)
Danforth-style anchor at each end of the
net string.
The restrictions will be in effect
beginning at 0001 hours January 26,
2008, through 2400 hours February 9,
2008, unless terminated sooner or
extended by NMFS through another
notification in the Federal Register.
The restrictions will be announced to
state officials, fishermen, ALWTRT
members, and other interested parties
through e-mail, phone contact, NOAA
website, and other appropriate media
immediately upon issuance of the rule
by the AA.
Classification
In accordance with section 118(f)(9) of
the MMPA, the Assistant Administrator
(AA) for Fisheries has determined that
this action is necessary to implement a
take reduction plan to protect North
Atlantic right whales.
Environmental Assessments for the
DAM program were prepared on
VerDate Aug<31>2005
19:26 Jan 23, 2008
Jkt 214001
December 28, 2001, and August 6, 2003.
This action falls within the scope of the
analyses of these EAs, which are
available from the agency upon request.
NMFS provided prior notice and an
opportunity for public comment on the
regulations establishing the criteria and
procedures for implementing a DAM
zone. Providing prior notice and
opportunity for comment on this action,
pursuant to those regulations, would be
impracticable because it would prevent
NMFS from executing its functions to
protect and reduce serious injury and
mortality of endangered right whales.
The regulations establishing the DAM
program are designed to enable the
agency to help protect unexpected
concentrations of right whales. In order
to meet the goals of the DAM program,
the agency needs to be able to create a
DAM zone and implement restrictions
on fishing gear as soon as possible once
the criteria are triggered and NMFS
determines that a DAM restricted zone
is appropriate. If NMFS were to provide
prior notice and an opportunity for
public comment upon the creation of a
DAM restricted zone, the aggregated
right whales would be vulnerable to
entanglement which could result in
serious injury and mortality.
Additionally, the right whales would
most likely move on to another location
before NMFS could implement the
restrictions designed to protect them,
thereby rendering the action obsolete.
Therefore, pursuant to 5 U.S.C.
553(b)(B), the AA finds that good cause
exists to waive prior notice and an
opportunity to comment on this action
to implement a DAM restricted zone to
reduce the risk of entanglement of
endangered right whales in commercial
lobster trap/pot and anchored gillnet
gear as such procedures would be
impracticable.
For the same reasons, the AA finds
that, under 5 U.S.C. 553(d)(3), good
cause exists to waive the 30–day delay
in effective date. If NMFS were to delay
for 30 days the effective date of this
action, the aggregated right whales
would be vulnerable to entanglement,
which could cause serious injury and
mortality. Additionally, right whales
would likely move to another location
between the time NMFS approved the
action creating the DAM restricted zone
and the time it went into effect, thereby
rendering the action obsolete and
ineffective. Nevertheless, NMFS
recognizes the need for fishermen to
have time to either modify or remove (if
not in compliance with the required
PO 00000
Frm 00070
Fmt 4700
Sfmt 4700
restrictions) their gear from a DAM zone
once one is approved. Thus, NMFS
makes this action effective 2 days after
the date of publication of this document
in the Federal Register. NMFS will also
endeavor to provide notice of this action
to fishermen through other means upon
issuance of the rule by the AA, thereby
providing approximately 3 additional
days of notice while the Office of the
Federal Register processes the
document for publication.
NMFS determined that the regulations
establishing the DAM program and
actions such as this one taken pursuant
to those regulations are consistent to the
maximum extent practicable with the
enforceable policies of the approved
coastal management program of the U.S.
Atlantic coastal states. This
determination was submitted for review
by the responsible state agencies under
section 307 of the Coastal Zone
Management Act. Following state
review of the regulations creating the
DAM program, no state disagreed with
NMFS’ conclusion that the DAM
program is consistent to the maximum
extent practicable with the enforceable
policies of the approved coastal
management program for that state.
The DAM program under which
NMFS is taking this action contains
policies with federalism implications
warranting preparation of a federalism
assessment under Executive Order
13132. Accordingly, in October 2001
and March 2003, the Assistant Secretary
for Intergovernmental and Legislative
Affairs, Department of Commerce,
provided notice of the DAM program
and its amendments to the appropriate
elected officials in states to be affected
by actions taken pursuant to the DAM
program. Federalism issues raised by
state officials were addressed in the
final rules implementing the DAM
program. A copy of the federalism
Summary Impact Statement for the final
rules is available upon request
(ADDRESSES).
The rule implementing the DAM
program has been determined to be not
significant under Executive Order
12866.
Authority: 16 U.S.C. 1361 et seq. and 50
CFR 229.32(g)(3)
Dated: January 17, 2008.
John Oliver,
Deputy Assistant Administrator for
Operations, National Marine Fisheries
Service.
[FR Doc. 08–262 Filed 1–18–08; 2:32 pm]
BILLING CODE 3510–22–S
E:\FR\FM\24JAR1.SGM
24JAR1
Agencies
[Federal Register Volume 73, Number 16 (Thursday, January 24, 2008)]
[Rules and Regulations]
[Pages 4118-4120]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 08-262]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF COMMERCE
National Oceanic and Atmospheric Administration
50 CFR Part 229
[Docket No. 080117051-8053-01]
RIN 0648-XF17
Taking of Marine Mammals Incidental to Commercial Fishing
Operations; Atlantic Large Whale Take Reduction Plan
AGENCY: National Marine Fisheries Service (NMFS), National Oceanic and
Atmospheric Administration (NOAA), Commerce.
ACTION: Temporary rule.
-----------------------------------------------------------------------
SUMMARY: The Assistant Administrator for Fisheries (AA), NOAA,
announces temporary restrictions consistent with the requirements of
the Atlantic Large Whale Take Reduction Plan's (ALWTRP) implementing
regulations. These regulations apply to lobster trap/pot and anchored
gillnet fishermen in an area totaling approximately 2,251 nm\2\ (7,720
km\2\), southeast of Portsmouth, New Hampshire, for 15 days. The
purpose of this action is to provide protection to an aggregation of
northern right whales (right whales).
DATES: Effective beginning at 0001 hours January 26, 2008, through 2400
hours February 9, 2008.
ADDRESSES: Copies of the proposed and final Dynamic Area Management
(DAM) rules, Environmental Assessments (EAs), Atlantic Large Whale Take
Reduction Team (ALWTRT) meeting summaries, and progress reports on
[[Page 4119]]
implementation of the ALWTRP may also be obtained by writing Diane
Borggaard, NMFS/Northeast Region, One Blackburn Drive, Gloucester, MA
01930.
FOR FURTHER INFORMATION CONTACT: Diane Borggaard, NMFS/Northeast
Region, 978-281-9300 x6503; or Kristy Long, NMFS, Office of Protected
Resources, 301-713-2322.
SUPPLEMENTARY INFORMATION:
Electronic Access
Several of the background documents for the ALWTRP and the take
reduction planning process can be downloaded from the ALWTRP web site
at https://www.nero.noaa.gov/whaletrp/.
Background
The ALWTRP was developed pursuant to section 118 of the Marine
Mammal Protection Act (MMPA) to reduce the incidental mortality and
serious injury of three endangered species of whales (right, fin, and
humpback) due to incidental interaction with commercial fishing
activities. In addition, the measures identified in the ALWTRP would
provide conservation benefits to a fourth species (minke), which are
neither listed as endangered nor threatened under the Endangered
Species Act (ESA). The ALWTRP, implemented through regulations codified
at 50 CFR 229.32, relies on a combination of fishing gear modifications
and time/area closures to reduce the risk of whales becoming entangled
in commercial fishing gear (and potentially suffering serious injury or
mortality as a result).
On January 9, 2002, NMFS published the final rule to implement the
ALWTRP's DAM program (67 FR 1133). On August 26, 2003, NMFS amended the
regulations by publishing a final rule, which specifically identified
gear modifications that may be allowed in a DAM zone (68 FR 51195). The
DAM program provides specific authority for NMFS to restrict
temporarily on an expedited basis the use of lobster trap/pot and
anchored gillnet fishing gear in areas north of 40[deg] N. lat. to
protect right whales. Under the DAM program, NMFS may: (1) require the
removal of all lobster trap/pot and anchored gillnet fishing gear for a
15-day period; (2) allow lobster trap/pot and anchored gillnet fishing
within a DAM zone with gear modifications determined by NMFS to
sufficiently reduce the risk of entanglement; and/or (3) issue an alert
to fishermen requesting the voluntary removal of all lobster trap/pot
and anchored gillnet gear for a 15-day period and asking fishermen not
to set any additional gear in the DAM zone during the 15-day period.
A DAM zone is triggered when NMFS receives a reliable report from a
qualified individual of three or more right whales sighted within an
area (75 nm\2\ (139 km\2\)) such that right whale density is equal to
or greater than 0.04 right whales per nm\2\ (1.85 km\2\). A qualified
individual is an individual ascertained by NMFS to be reasonably able,
through training or experience, to identify a right whale. Such
individuals include, but are not limited to, NMFS staff, U.S. Coast
Guard and Navy personnel trained in whale identification, scientific
research survey personnel, whale watch operators and naturalists, and
mariners trained in whale species identification through
disentanglement training or some other training program deemed adequate
by NMFS. A reliable report would be a credible right whale sighting.
On January 13, 2008, an aerial survey reported two aggregations of
right whales, totaling seven individuals: four whales in the proximity
of 42[deg] 37' N. latitude and 70[deg] 01' W. longitude, and three
whales in the proximity of 42[deg] 51' N. latitude and 70[deg] 04' W.
longitude. These positions lie northeast of Boston, Massachusetts, and
southeast of Portsmouth, New Hampshire, respectively. After conducting
an investigation, NMFS ascertained that the report came from a
qualified individual and determined that the report was reliable. Thus,
NMFS has received a reliable report from a qualified individual of the
requisite right whale density to trigger the DAM provisions of the
ALWTRP.
Once a DAM zone is triggered, NMFS determines whether to impose
restrictions on fishing and/or fishing gear in the zone. This
determination is based on the following factors, including but not
limited to: the location of the DAM zone with respect to other fishery
closure areas, weather conditions as they relate to the safety of human
life at sea, the type and amount of gear already present in the area,
and a review of recent right whale entanglement and mortality data.
NMFS has reviewed the factors and management options noted above
relative to the DAM under consideration. As a result of this review,
NMFS prohibits lobster trap/pot and anchored gillnet gear in this area
during the 15-day restricted period unless it is modified in the manner
described in this temporary rule.
The DAM Zone is bound by the following coordinates:
43[deg] 09' N., 70[deg] 29' W. (NW Corner)
43[deg] 09' N., 69[deg] 39' W.
42[deg] 56' N., 69[deg] 39' W.
42[deg] 56' N., 69[deg] 33' W.
42[deg] 16' N., 69[deg] 33' W.
42[deg] 16' N., 70[deg] 33' W.
42[deg] 56' N., 70[deg] 33' W.
42[deg] 56' N., 70[deg] 29' W.
43[deg] 09' N., 70[deg] 29' W. (NW Corner)
In addition to those gear modifications currently implemented under
the ALWTRP at 50 CFR 229.32, the following gear modifications are
required in the DAM zone. If the requirements and exceptions for gear
modification in the DAM zone, as described below, differ from other
ALWTRP requirements for any overlapping areas and times, then the more
restrictive requirements will apply in the DAM zone.
Lobster Trap/pot Gear
Fishermen utilizing lobster trap/pot gear within the portions of
Northern Nearshore Lobster Waters, Northern Inshore State Lobster
Waters, and the Stellwagen Bank/Jeffrey's Ledge Restricted Area that
overlap with the DAM zone are required to utilize all of the following
gear modifications while the DAM zone is in effect:
1. Groundlines must be made of either sinking or neutrally buoyant
line. Floating groundlines are prohibited;
2. All buoy lines must be made of either sinking or neutrally
buoyant line, except the bottom portion of the line, which may be a
section of floating line not to exceed one-third the overall length of
the buoy line;
3. Fishermen are allowed to use two buoy lines per trawl; and
4. A weak link with a maximum breaking strength of 600 lb (272.4
kg) must be placed at all buoys.
Fishermen utilizing lobster trap/pot gear within the portion of the
Offshore Lobster Waters Area that overlap with the DAM zone are
required to utilize all of the following gear modifications while the
DAM zone is in effect:
1. Groundlines must be made of either sinking or neutrally buoyant
line. Floating groundlines are prohibited;
2. All buoy lines must be made of either sinking or neutrally
buoyant line, except the bottom portion of the line, which may be a
section of floating line not to exceed one-third the overall length of
the buoy line;
3. Fishermen are allowed to use two buoy lines per trawl; and
4. A weak link with a maximum breaking strength of 1,500 lb (680.4
kg) must be placed at all buoys.
Anchored Gillnet Gear
Fishermen utilizing anchored gillnet gear within the portions of
Other Northeast Gillnet Waters and the
[[Page 4120]]
Stellwagen Bank/Jeffrey's Ledge Restricted Area that overlap with the
DAM zone are required to utilize all the following gear modifications
while the DAM zone is in effect:
1. Groundlines must be made of either sinking or neutrally buoyant
line. Floating groundlines are prohibited;
2. All buoy lines must be made of either sinking or neutrally
buoyant line, except the bottom portion of the line, which may be a
section of floating line not to exceed one-third the overall length of
the buoy line;
3. Fishermen are allowed to use two buoy lines per string;
4. The breaking strength of each net panel weak link must not
exceed 1,100 lb (498.8 kg). The weak link requirements apply to all
variations in net panel size. One weak link must be placed in the
center of the floatline and one weak link must be placed in the center
of each of the up and down lines at both ends of the net panel.
Additionally, one weak link must be placed as close as possible to each
end of the net panels on the floatline; or, one weak link must be
placed between floatline tie-loops between net panels and one weak link
must be placed where the floatline tie-loops attach to the bridle, buoy
line, or groundline at each end of a net string;
5. A weak link with a maximum breaking strength of 1,100 lb (498.8
kg) must be placed at all buoys; and
6. All anchored gillnets, regardless of the number of net panels,
must be securely anchored with the holding power of at least a 22 lb
(10.0 kg) Danforth-style anchor at each end of the net string.
The restrictions will be in effect beginning at 0001 hours January
26, 2008, through 2400 hours February 9, 2008, unless terminated sooner
or extended by NMFS through another notification in the Federal
Register.
The restrictions will be announced to state officials, fishermen,
ALWTRT members, and other interested parties through e-mail, phone
contact, NOAA website, and other appropriate media immediately upon
issuance of the rule by the AA.
Classification
In accordance with section 118(f)(9) of the MMPA, the Assistant
Administrator (AA) for Fisheries has determined that this action is
necessary to implement a take reduction plan to protect North Atlantic
right whales.
Environmental Assessments for the DAM program were prepared on
December 28, 2001, and August 6, 2003. This action falls within the
scope of the analyses of these EAs, which are available from the agency
upon request.
NMFS provided prior notice and an opportunity for public comment on
the regulations establishing the criteria and procedures for
implementing a DAM zone. Providing prior notice and opportunity for
comment on this action, pursuant to those regulations, would be
impracticable because it would prevent NMFS from executing its
functions to protect and reduce serious injury and mortality of
endangered right whales. The regulations establishing the DAM program
are designed to enable the agency to help protect unexpected
concentrations of right whales. In order to meet the goals of the DAM
program, the agency needs to be able to create a DAM zone and implement
restrictions on fishing gear as soon as possible once the criteria are
triggered and NMFS determines that a DAM restricted zone is
appropriate. If NMFS were to provide prior notice and an opportunity
for public comment upon the creation of a DAM restricted zone, the
aggregated right whales would be vulnerable to entanglement which could
result in serious injury and mortality. Additionally, the right whales
would most likely move on to another location before NMFS could
implement the restrictions designed to protect them, thereby rendering
the action obsolete. Therefore, pursuant to 5 U.S.C. 553(b)(B), the AA
finds that good cause exists to waive prior notice and an opportunity
to comment on this action to implement a DAM restricted zone to reduce
the risk of entanglement of endangered right whales in commercial
lobster trap/pot and anchored gillnet gear as such procedures would be
impracticable.
For the same reasons, the AA finds that, under 5 U.S.C. 553(d)(3),
good cause exists to waive the 30-day delay in effective date. If NMFS
were to delay for 30 days the effective date of this action, the
aggregated right whales would be vulnerable to entanglement, which
could cause serious injury and mortality. Additionally, right whales
would likely move to another location between the time NMFS approved
the action creating the DAM restricted zone and the time it went into
effect, thereby rendering the action obsolete and ineffective.
Nevertheless, NMFS recognizes the need for fishermen to have time to
either modify or remove (if not in compliance with the required
restrictions) their gear from a DAM zone once one is approved. Thus,
NMFS makes this action effective 2 days after the date of publication
of this document in the Federal Register. NMFS will also endeavor to
provide notice of this action to fishermen through other means upon
issuance of the rule by the AA, thereby providing approximately 3
additional days of notice while the Office of the Federal Register
processes the document for publication.
NMFS determined that the regulations establishing the DAM program
and actions such as this one taken pursuant to those regulations are
consistent to the maximum extent practicable with the enforceable
policies of the approved coastal management program of the U.S.
Atlantic coastal states. This determination was submitted for review by
the responsible state agencies under section 307 of the Coastal Zone
Management Act. Following state review of the regulations creating the
DAM program, no state disagreed with NMFS' conclusion that the DAM
program is consistent to the maximum extent practicable with the
enforceable policies of the approved coastal management program for
that state.
The DAM program under which NMFS is taking this action contains
policies with federalism implications warranting preparation of a
federalism assessment under Executive Order 13132. Accordingly, in
October 2001 and March 2003, the Assistant Secretary for
Intergovernmental and Legislative Affairs, Department of Commerce,
provided notice of the DAM program and its amendments to the
appropriate elected officials in states to be affected by actions taken
pursuant to the DAM program. Federalism issues raised by state
officials were addressed in the final rules implementing the DAM
program. A copy of the federalism Summary Impact Statement for the
final rules is available upon request (ADDRESSES).
The rule implementing the DAM program has been determined to be not
significant under Executive Order 12866.
Authority: 16 U.S.C. 1361 et seq. and 50 CFR 229.32(g)(3)
Dated: January 17, 2008.
John Oliver,
Deputy Assistant Administrator for Operations, National Marine
Fisheries Service.
[FR Doc. 08-262 Filed 1-18-08; 2:32 pm]