City of Ottumwa, IA; Notice of Availability of Environmental Assessment, 1333-1334 [E8-44]
Download as PDF
pwalker on PROD1PC71 with NOTICES
Federal Register / Vol. 73, No. 5 / Tuesday, January 8, 2008 / Notices
impose requirements relating to the
design of rates that are not applicable to
market-based rates).
Chestnut Ridge states that the JCT
Project would provide necessary natural
gas infrastructure in furtherance of the
Commission’s policies supporting the
development of new natural gas storage
capacity. According to Chestnut Ridge,
the JCT Project will increase the
reliability of natural gas supply during
periods of production and
transportation interruptions and will
enhance the reliability of the interstate
pipeline grid. Chestnut Ridge states that
the JCT Project will include up to
twenty-six (26) storage injection/
withdrawal wells with a total working
gas storage capacity of up to 25 billion
cubic feet (Bcf). Chestnut Ridge also
states that the JCT Project will have gas
injection and withdrawal capabilities of
up to 500,000 dekatherms per day (Dth/
d).
Chestnut Ridge represents that
construction and operation of the JCT
Project will have minimal impacts on
the natural environment and on
adjacent landowners. Chestnut Ridge
states that the market power study
included with its Application
demonstrates that Chestnut Ridge will
not have market power in any relevant
market. It asserts that the Commission
can therefore conclude that Chestnut
Ridge will be unable to charge or collect
rates for its services that exceed just and
reasonable levels.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: Complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding, or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211 and
385.214). Protests will be considered by
VerDate Aug<31>2005
17:32 Jan 07, 2008
Jkt 214001
the Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be file on or before the
comment date. Anyone filing a motion
to intervene or protest must serve a copy
of that document on the Applicant. On
or before the comment date, it is not
necessary to serve motions to intervene
or protests on persons other than the
Applicant.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenters will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit the original and 14
copies of the protest or intervention to
the Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington, DC 20426.
PO 00000
Frm 00020
Fmt 4703
Sfmt 4703
1333
Comment Date: January 22, 2008.
Kimberly D. Bose,
Secretary.
[FR Doc. E8–69 Filed 1–7–08; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 925–010 (IA)]
City of Ottumwa, IA; Notice of
Availability of Environmental
Assessment
December 21, 2007.
In accordance with the National
Environmental Policy Act of 1969 and
the Federal Energy Regulatory
Commission’s regulations, 18 CFR Part
380 (Order No. 486, 52 FR 47879), the
Office of Energy Projects has reviewed
the application for a new license for the
Ottumwa Hydroelectric Project, located
on the Des Moines River in the City of
Ottumwa, Wapello County, Iowa, and
has prepared an Environmental
Assessment (EA). In the EA,
Commission staff analyze the potential
environmental effects of relicensing the
project and conclude that issuing a new
license for the project, with appropriate
environmental measures, would not
constitute a major federal action
significantly affecting the quality of the
human environment.
A copy of the EA is on file with the
Commission and is available for public
inspection. The EA may also be viewed
on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659.
Any comments should be filed within
30 days from the issuance date of this
notice, and should be addressed to the
Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE.,
Room 1–A, Washington, DC 20426.
Please affix ‘‘Ottumwa Project No. 925–
010’’ to all comments. Comments may
be filed electronically via Internet in
lieu of paper. The Commission strongly
encourages electronic filings. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site under the ‘‘eFiling’’ link. For further
E:\FR\FM\08JAN1.SGM
08JAN1
1334
Federal Register / Vol. 73, No. 5 / Tuesday, January 8, 2008 / Notices
information, contact Timothy Konnert at
(202) 502–6359.
Kimberly D. Bose,
Secretary.
[FR Doc. E8–44 Filed 1–7–08; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP07–207–000]
Colorado Interstate Gas Company;
Notice of Availability of the Final
Environmental Impact Statement for
the Proposed High Plains Expansion
Project
pwalker on PROD1PC71 with NOTICES
December 28, 2007.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) has prepared this Final
Environmental Impact Statement (EIS)
for the natural gas pipeline facilities
proposed by Colorado Interstate Gas
Company (CIG) under the abovereferenced docket. CIG’s High Plains
Expansion Project (Project) would be
located in Weld, Morgan, and Adams
Counties, Colorado.
The Final EIS was prepared to satisfy
the requirements of the National
Environmental Policy Act. The FERC
staff concludes that the proposed
Project, with the appropriate mitigation
measures as recommended, would have
limited adverse environmental impact.
The purpose of the Project is to
expand CIG’s existing pipeline system
along Colorado’s Front Range in order to
provide additional transportation
services to this rapidly growing market.
CIG is proposing to construct about
163.7 miles of 24-inch and 30-inchdiameter pipeline in four separate
pipeline segments and associated
ancillary facilities.
The Final EIS addresses the potential
environmental impacts resulting from
the construction and operation of the
following facilities:
• Line 250A: 64.5 miles of 30-inchdiameter pipeline and 20.3 miles of 24inch-diameter pipeline that would
extend from CIG’s existing Cheyenne
Compressor Station to an interconnect
point on the proposed Line 251A in
northeast Adams County;
• Line 251A: 57.9 miles of 24-inchdiameter pipeline between CIG’s
existing Watkins and Fort Morgan
Compressor Stations;
• Line 252A: 14.9 miles of 30-inchdiameter pipeline extending westward
from a point on the proposed Line 250A
about one mile north of the existing
VerDate Aug<31>2005
17:32 Jan 07, 2008
Jkt 214001
Hudson Power Plant in the Town of
Hudson, Colorado, to a new
interconnect with Public Service
Company of Colorado’s existing TriTown facilities in Weld County,
Colorado;
• Line 253A: 6.1 miles of 24-inchdiameter pipeline extending westward
from the Watkins Compressor Station to
CIG’s existing East Denver measurement
facility in Adams County, Colorado;
• Ten new meter stations and 19 new
block valves; and
• Twelve pig launcher/receivers.
The entire project would be capable of
transporting about 899,000 decatherms
of gas per day. CIG proposes to begin
construction in January 2008. It would
put each pipeline segment into service
as it is completed, and the entire Project
would be in service by October 2008.
The Final EIS has been placed in the
public files of the FERC and is available
for public inspection at: Federal Energy
Regulatory Commission, Public
Reference Room, 888 First Street NE.,
Room 2A, Washington, DC 20426, (202)
502–8371.
A limited number of copies of the
Final EIS are available from the Public
Reference Room identified above. In
addition, CD copies of the Final EIS
have been mailed to affected
landowners; various federal, state, and
local government agencies; elected
officials; environmental and public
interest groups; Native American tribes;
local libraries and newspapers;
intervenors; and other individuals that
expressed an interest in the proposed
Project. Hard-copies of the Final EIS
have also been mailed to those who
requested that format during the scoping
and comment periods for the proposed
Project.
Additional information about the
proposed Project is available from the
Commission’s Office of External Affairs,
at 1–866–208–FERC or on the FERC
Internet Web site (https://www.ferc.gov).
To access information via the FERC
Web site click on the ‘‘eLibrary’’ link
then click on ‘‘General Search’’ and
enter the docket number excluding the
last three digits in the Docket Number
field. Be sure you have selected an
appropriate date range. The ‘‘eLibrary’’
link provides access to the texts of
formal documents issued by the
Commission, such as orders, notices,
and rulemakings. For assistance with
‘‘eLibrary’’, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or toll free at 1–866–208–3676, or for
TTY, contact (202) 502–8659.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries and direct links to
these documents. To learn more about
eSubscription and to sign-up for this
service please go to https://www.ferc.gov/
esubscribenow.htm.
Kimberly D. Bose,
Secretary.
[FR Doc. E8–68 Filed 1–7–08; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP08–38–000]
East Tennessee Natural Gas, LLC;
Notice of Request Under Blanket
Authorization
December 21, 2007.
Take notice that on December 18,
2007, East Tennessee Natural Gas, LLC
(East Tennessee), P.O. Box 1642,
Houston, Texas 77251–1642, filed in
Docket No. CP08–38–000 a prior notice
request pursuant to sections 157.205
and 157.210 of the Commission’s
regulations under the Natural Gas Act
(NGA) and East Tennessee’s blanket
certificate issued in Docket No. CP82–
412, for authorization to acquire
approximately 72 miles of transmission
pipeline. East Tennessee proposes to
acquire approximately 72 miles of
Spectra Energy Virginia Pipeline
Company’s 8-inch line, in Smyth and
Washington Counties, Virginia, all as
more fully set forth in the application,
which is on file with the Commission
and open to public inspection. The
filing may also be viewed on the Web
at https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
at FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TTY, (202)
502–8659.
Any questions regarding the
application should be directed to Garth
Johnson, General Manager, Certificates
& Reporting, East Tennessee Natural
Gas, LLC, P.O. Box 1642, Houston,
Texas 77251–1642 at (713) 627–5415.
Any person or the Commission’s Staff
may, within 60 days after the issuance
of the instant notice by the Commission,
file pursuant to Rule 214 of the
Commission’s Procedural Rules (18 CFR
385.214) a motion to intervene or notice
of intervention and, pursuant to section
E:\FR\FM\08JAN1.SGM
08JAN1
Agencies
[Federal Register Volume 73, Number 5 (Tuesday, January 8, 2008)]
[Notices]
[Pages 1333-1334]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E8-44]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 925-010 (IA)]
City of Ottumwa, IA; Notice of Availability of Environmental
Assessment
December 21, 2007.
In accordance with the National Environmental Policy Act of 1969
and the Federal Energy Regulatory Commission's regulations, 18 CFR Part
380 (Order No. 486, 52 FR 47879), the Office of Energy Projects has
reviewed the application for a new license for the Ottumwa
Hydroelectric Project, located on the Des Moines River in the City of
Ottumwa, Wapello County, Iowa, and has prepared an Environmental
Assessment (EA). In the EA, Commission staff analyze the potential
environmental effects of relicensing the project and conclude that
issuing a new license for the project, with appropriate environmental
measures, would not constitute a major federal action significantly
affecting the quality of the human environment.
A copy of the EA is on file with the Commission and is available
for public inspection. The EA may also be viewed on the Commission's
Web site at https://www.ferc.gov using the ``eLibrary'' link. Enter the
docket number excluding the last three digits in the docket number
field to access the document. For assistance, contact FERC Online
Support at FERCOnlineSupport@ferc.gov or toll-free at 1-866-208-3676,
or for TTY, (202) 502-8659.
Any comments should be filed within 30 days from the issuance date
of this notice, and should be addressed to the Secretary, Federal
Energy Regulatory Commission, 888 First Street, NE., Room 1-A,
Washington, DC 20426. Please affix ``Ottumwa Project No. 925-010'' to
all comments. Comments may be filed electronically via Internet in lieu
of paper. The Commission strongly encourages electronic filings. See 18
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web
site under the ``eFiling'' link. For further
[[Page 1334]]
information, contact Timothy Konnert at (202) 502-6359.
Kimberly D. Bose,
Secretary.
[FR Doc. E8-44 Filed 1-7-08; 8:45 am]
BILLING CODE 6717-01-P