El Paso Natural Gas Pipeline Company; Notice of Intent To Prepare an Environmental Assessment for the Proposed Hobbs Expansion Project and Request for Comments on Environmental Issues, 71677-71678 [E7-24413]
Download as PDF
Federal Register / Vol. 72, No. 242 / Tuesday, December 18, 2007 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP08–14–000]
El Paso Natural Gas Pipeline
Company; Notice of Intent To Prepare
an Environmental Assessment for the
Proposed Hobbs Expansion Project
and Request for Comments on
Environmental Issues
December 11, 2007.
yshivers on PROD1PC62 with NOTICES
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Hobbs Expansion Project involving
construction and operation of natural
gas pipeline facilities by El Paso Natural
Gas Pipeline Company (El Paso) in Lea
County, New Mexico and Winkler
County, Texas. The EA will be used by
the Commission in its decision-making
process to determine whether the
project is in the public convenience and
necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the project.
Your input will help determine which
issues need to be evaluated in the EA.
Please note that the scoping period will
close on January 11, 2008. Details on
how to submit comments are provided
in the Public Participation section of
this notice.
This notice is being sent to affected
landowners; federal, state, and local
government agencies; elected officials;
Native American tribes; other interested
parties; and local libraries and
newspapers. State and local government
representatives are asked to notify their
constituents of this proposed project
and to encourage them to comment on
their areas of concern.
A fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ addresses a number of
typically asked questions, including the
use of eminent domain and how to
participate in the Commission’s
proceedings. It is available for viewing
on the FERC Internet Web site (https://
www.ferc.gov).
Summary of the Proposed Project
El Paso proposes three components
(compression, new pipeline, and piping
modifications) to meet the natural gas
delivery requirements at the SPS Hobbs
Power Plant in Lea County, New
Mexico. El Paso proposes to construct,
own, and operate:
VerDate Aug<31>2005
15:19 Dec 17, 2007
Jkt 214001
• A natural gas-fired, reciprocating
jumper compressor unit totalling 3,550
horsepower (HP), with appurtenances,
at it Eunice ‘‘C’’ Compressor Station;
• 7.3 miles of 20-inch-diameter
pipeline and the new Hobbs Delivery
Meter Station;
• Pipeline system improvements to
include the Maximum Allowable
Operation Pressure (MAOP) up-rate of
5.7 miles of the existing 16-inchdiameter Line No. 30131; and
• Plant yard pipe modifications at El
Paso’s existing Keystone and Eunice
‘‘B’’ Compressor Stations.
All work would occur in Lea County,
New Mexico except for the work at the
Keystone Compressor Station in
Winkler County, Texas. El Paso also
proposes to abandon in place 1,700 feet
of existing Line No. 30131 pipeline in
Lea County, New Mexico.
The general location of the proposed
facilities is shown in Appendix 1.1
The EA Process
We 2 are preparing this EA to comply
with the National Environmental Policy
Act (NEPA) which requires the
Commission to take into account the
environmental impact that could result
if it authorizes El Paso’s proposal. By
this notice, we are also asking federal,
state, and local agencies with
jurisdiction and/or special expertise
with respect to environmental issues to
formally cooperate with us in the
preparation of the EA.
With this notice, we are asking
federal, state, and local agencies with
jurisdiction and/or special expertise
with respect to environmental issues to
formally cooperate with us in the
preparation of the EA. These agencies
may choose to participate once they
have evaluated the proposal relative to
their responsibilities. Additional
agencies that would like to request
cooperating agency status should follow
the instructions for filing comments
provided under the Public Participation
section of this notice.
NEPA also requires the FERC to
discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping.’’ The
1 The appendices referenced in this notice are not
being printed in the Federal Register. Copies of all
appendices are available on the Commission’s
website at the ‘‘eLibrary’’ link or from the
Commission’s Public Reference Room, 888 First
Street, NE., Washington, DC 20426, or call (202)
502–8371. For instructions on connecting to
eLibrary refer to the ‘‘Additional Information’’
section of this notice. Copies of the appendices
were sent to all those receiving this notice in the
mail. Requests for detailed maps of the proposed
facilities should be made directly to El Paso.
2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the
environmental staff of the FERC’s Office of Energy
Projects.
PO 00000
Frm 00063
Fmt 4703
Sfmt 4703
71677
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
Notice of Intent, we are requesting
public comments on the scope of the
issues to address in the EA. All
comments received are considered
during the preparation of the EA.
The EA will discuss impacts that
could occur as a result of the
construction and operation of the
proposed project under these general
headings:
• Geology and soils.
• Land use.
• Water resources, fisheries, and
wetlands.
• Cultural resources.
• Vegetation and wildlife.
• Air quality and noise.
• Endangered and threatened species.
We will also evaluate possible
alternatives to the proposed project or
portions of the project, where necessary,
and make recommendations on how to
lessen or avoid impacts on the various
resource areas.
Our independent analysis of the
issues will be in the EA. Depending on
the comments received during the
scoping process, the EA may be
published and mailed to federal, state,
and local agencies, public interest
groups, interested individuals, affected
landowners, newspapers, libraries, and
the Commission’s official service list for
this proceeding. A comment period will
be allotted for review if the EA is
published. We will consider all
comments on the EA before we make
our recommendations to the
Commission.
To ensure your comments are
considered, please carefully follow the
instructions in the Public Participation
section below.
Public Participation
You can make a difference by
providing us with your specific
comments or concerns about the project.
By becoming a commentor, your
concerns will be addressed in the EA
and considered by the Commission. You
should focus on the potential
environmental effects of the proposal,
alternatives to the proposal including
alternative compressor station sites, and
measures to avoid or lessen
environmental impact. The more
specific your comments, the more useful
they will be. Please carefully follow
these instructions to ensure that your
comments are received in time and
properly recorded:
• Send an original and two copies of
your letter to: Kimberley D. Bose,
Secretary, Federal Energy Regulatory
E:\FR\FM\18DEN1.SGM
18DEN1
71678
Federal Register / Vol. 72, No. 242 / Tuesday, December 18, 2007 / Notices
yshivers on PROD1PC62 with NOTICES
Commission, 888 First St., NE., Room
1A, Washington, DC 20426;
• Label one copy of the comments for
the attention of Gas Branch 2, PJ–11.2;
• Reference Docket No. CP08–14–
000; and
• Mail your comments so that they
will be received in Washington, DC on
or before January 11, 2008.
The Commission encourages
electronic filing of comments. See 18
Code of Federal Regulations
385.2001(a)(1)(iii) and the instructions
on the Commission’s Internet Web site
at https://www.ferc.gov under the
‘‘eFiling’’ link and the link to the User’s
Guide. Prepare your submission in the
same manner as you would if filing on
paper and save it to a file on your hard
drive. Before you can file comments you
will need to create an account by
clicking on ‘‘Login to File’’ and then
‘‘New User Account.’’ You will be asked
to select the type of filing you are
making. This filing is considered a
‘‘Comment on Filing.’’
We will mail the EA for public
comment. If you are interested in
receiving it, please return the
Information Request (Appendix 2). If
you do not return the Information
Request, you will be taken off the
mailing list.
Becoming an Intervenor
In addition to involvement in the EA
scoping process, you may want to
become an official party to the
proceeding, or ‘‘intervenor’’. To become
an intervenor you must file a motion to
intervene according to Rule 214 of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214). Intervenors
have the right to seek rehearing of the
Commission’s decision. Motions to
Intervene should be electronically
submitted using the Commission’s
eFiling system at https://www.ferc.gov.
Persons without Internet access should
send an original and 14 copies of their
motion to the Secretary of the
Commission at the address indicated
previously. Persons filing Motions to
Intervene on or before the comment
deadline indicated above must send a
copy of the motion to the Applicant. All
filings, including late interventions,
submitted after the comment deadline
must be served on the Applicant and all
other intervenors identified on the
Commission’s service list for this
proceeding. Persons on the service list
with email addresses may be served
electronically; others must be served a
hard copy of the filing.
Affected landowners and parties with
environmental concerns may be granted
intervenor status upon showing good
cause by stating that they have a clear
VerDate Aug<31>2005
15:19 Dec 17, 2007
Jkt 214001
and direct interest in this proceeding
which would not be adequately
represented by any other parties. You do
not need intervenor status to have your
environmental comments considered.
DEPARTMENT OF ENERGY
Environmental Mailing List
Leaf River Energy Center LLC; Notice
of Intent To Prepare an Environmental
Assessment for the Proposed Leaf
River Storage Project and Request for
Comments on Environmental Issues
An effort is being made to send this
notice to all individuals, organizations,
and government entities interested in
and/or potentially affected by the
proposed project. This includes all
landowners who own homes within
distances defined in the Commission’s
regulations of certain aboveground
facilities.
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at 1–866–208–FERC or on the FERC
Internet Web site (https://www.ferc.gov)
using the ‘‘eLibrary’’ link. Click on the
eLibrary link, then on ‘‘General Search’’
and enter the docket number excluding
the last three digits in the Docket
Number field. Be sure you have selected
an appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or toll free at 1–866–208–3676, or for
TTY, contact (202) 502–8659. The
eLibrary link also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries and direct links to
the documents. Go to https://
www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at https://www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Kimberly D. Bose,
Secretary.
[FR Doc. E7–24413 Filed 12–17–07; 8:45 am]
Frm 00064
Fmt 4703
[Docket No. CP08–8–000]
December 11, 2007.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Leaf River Storage Project involving
construction and operation of
underground natural gas storage and
pipeline header facilities by Leaf River
Energy Center LLC (Leaf River) in
Smith, Jasper, and Clarke Counties,
Mississippi. The EA will be used by the
Commission in its decision-making
process to determine whether the
project is in the public convenience and
necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the project.
Your input will help determine which
issues need to be evaluated in the EA.
Please note that the scoping period will
close on January 10, 2008. Details on
how to submit comments are provided
in the Public Participation section of
this notice.
This notice is being sent to affected
landowners; federal, state, and local
government agencies; elected officials;
Native American tribes; other interested
parties; and local libraries and
newspapers. State and local government
representatives are asked to notify their
constituents of this proposed project
and to encourage them to comment on
their areas of concern.
A fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ addresses a number of
typically asked questions, including the
use of eminent domain and how to
participate in the Commission’s
proceedings. It is available for viewing
on the FERC Internet Web site (https://
www.ferc.gov).
Summary of the Proposed Project
Leaf River proposes to:
• Construct four storage wells and
caverns with a total working gas
capacity of 32 billion cubic feet (Bcf);
• Install seven 4,800 horsepower gas
driven reciprocating compressor units at
its proposed compressor station/gas
BILLING CODE 6717–01–P
PO 00000
Federal Energy Regulatory
Commission
Sfmt 4703
E:\FR\FM\18DEN1.SGM
18DEN1
Agencies
[Federal Register Volume 72, Number 242 (Tuesday, December 18, 2007)]
[Notices]
[Pages 71677-71678]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-24413]
[[Page 71677]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP08-14-000]
El Paso Natural Gas Pipeline Company; Notice of Intent To Prepare
an Environmental Assessment for the Proposed Hobbs Expansion Project
and Request for Comments on Environmental Issues
December 11, 2007.
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Hobbs Expansion Project
involving construction and operation of natural gas pipeline facilities
by El Paso Natural Gas Pipeline Company (El Paso) in Lea County, New
Mexico and Winkler County, Texas. The EA will be used by the Commission
in its decision-making process to determine whether the project is in
the public convenience and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the project. Your input will help determine which issues
need to be evaluated in the EA. Please note that the scoping period
will close on January 11, 2008. Details on how to submit comments are
provided in the Public Participation section of this notice.
This notice is being sent to affected landowners; federal, state,
and local government agencies; elected officials; Native American
tribes; other interested parties; and local libraries and newspapers.
State and local government representatives are asked to notify their
constituents of this proposed project and to encourage them to comment
on their areas of concern.
A fact sheet prepared by the FERC entitled ``An Interstate Natural
Gas Facility On My Land? What Do I Need To Know?'' addresses a number
of typically asked questions, including the use of eminent domain and
how to participate in the Commission's proceedings. It is available for
viewing on the FERC Internet Web site (https://www.ferc.gov).
Summary of the Proposed Project
El Paso proposes three components (compression, new pipeline, and
piping modifications) to meet the natural gas delivery requirements at
the SPS Hobbs Power Plant in Lea County, New Mexico. El Paso proposes
to construct, own, and operate:
A natural gas-fired, reciprocating jumper compressor unit
totalling 3,550 horsepower (HP), with appurtenances, at it Eunice ``C''
Compressor Station;
7.3 miles of 20-inch-diameter pipeline and the new Hobbs
Delivery Meter Station;
Pipeline system improvements to include the Maximum
Allowable Operation Pressure (MAOP) up-rate of 5.7 miles of the
existing 16-inch-diameter Line No. 30131; and
Plant yard pipe modifications at El Paso's existing
Keystone and Eunice ``B'' Compressor Stations.
All work would occur in Lea County, New Mexico except for the work
at the Keystone Compressor Station in Winkler County, Texas. El Paso
also proposes to abandon in place 1,700 feet of existing Line No. 30131
pipeline in Lea County, New Mexico.
The general location of the proposed facilities is shown in
Appendix 1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice are not being
printed in the Federal Register. Copies of all appendices are
available on the Commission's website at the ``eLibrary'' link or
from the Commission's Public Reference Room, 888 First Street, NE.,
Washington, DC 20426, or call (202) 502-8371. For instructions on
connecting to eLibrary refer to the ``Additional Information''
section of this notice. Copies of the appendices were sent to all
those receiving this notice in the mail. Requests for detailed maps
of the proposed facilities should be made directly to El Paso.
---------------------------------------------------------------------------
The EA Process
We \2\ are preparing this EA to comply with the National
Environmental Policy Act (NEPA) which requires the Commission to take
into account the environmental impact that could result if it
authorizes El Paso's proposal. By this notice, we are also asking
federal, state, and local agencies with jurisdiction and/or special
expertise with respect to environmental issues to formally cooperate
with us in the preparation of the EA.
---------------------------------------------------------------------------
\2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff
of the FERC's Office of Energy Projects.
---------------------------------------------------------------------------
With this notice, we are asking federal, state, and local agencies
with jurisdiction and/or special expertise with respect to
environmental issues to formally cooperate with us in the preparation
of the EA. These agencies may choose to participate once they have
evaluated the proposal relative to their responsibilities. Additional
agencies that would like to request cooperating agency status should
follow the instructions for filing comments provided under the Public
Participation section of this notice.
NEPA also requires the FERC to discover and address concerns the
public may have about proposals. This process is referred to as
``scoping.'' The main goal of the scoping process is to focus the
analysis in the EA on the important environmental issues. By this
Notice of Intent, we are requesting public comments on the scope of the
issues to address in the EA. All comments received are considered
during the preparation of the EA.
The EA will discuss impacts that could occur as a result of the
construction and operation of the proposed project under these general
headings:
Geology and soils.
Land use.
Water resources, fisheries, and wetlands.
Cultural resources.
Vegetation and wildlife.
Air quality and noise.
Endangered and threatened species.
We will also evaluate possible alternatives to the proposed project
or portions of the project, where necessary, and make recommendations
on how to lessen or avoid impacts on the various resource areas.
Our independent analysis of the issues will be in the EA. Depending
on the comments received during the scoping process, the EA may be
published and mailed to federal, state, and local agencies, public
interest groups, interested individuals, affected landowners,
newspapers, libraries, and the Commission's official service list for
this proceeding. A comment period will be allotted for review if the EA
is published. We will consider all comments on the EA before we make
our recommendations to the Commission.
To ensure your comments are considered, please carefully follow the
instructions in the Public Participation section below.
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the project. By becoming a commentor, your
concerns will be addressed in the EA and considered by the Commission.
You should focus on the potential environmental effects of the
proposal, alternatives to the proposal including alternative compressor
station sites, and measures to avoid or lessen environmental impact.
The more specific your comments, the more useful they will be. Please
carefully follow these instructions to ensure that your comments are
received in time and properly recorded:
Send an original and two copies of your letter to:
Kimberley D. Bose, Secretary, Federal Energy Regulatory
[[Page 71678]]
Commission, 888 First St., NE., Room 1A, Washington, DC 20426;
Label one copy of the comments for the attention of Gas
Branch 2, PJ-11.2;
Reference Docket No. CP08-14-000; and
Mail your comments so that they will be received in
Washington, DC on or before January 11, 2008.
The Commission encourages electronic filing of comments. See 18
Code of Federal Regulations 385.2001(a)(1)(iii) and the instructions on
the Commission's Internet Web site at https://www.ferc.gov under the
``eFiling'' link and the link to the User's Guide. Prepare your
submission in the same manner as you would if filing on paper and save
it to a file on your hard drive. Before you can file comments you will
need to create an account by clicking on ``Login to File'' and then
``New User Account.'' You will be asked to select the type of filing
you are making. This filing is considered a ``Comment on Filing.''
We will mail the EA for public comment. If you are interested in
receiving it, please return the Information Request (Appendix 2). If
you do not return the Information Request, you will be taken off the
mailing list.
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an official party to the proceeding, or ``intervenor''. To
become an intervenor you must file a motion to intervene according to
Rule 214 of the Commission's Rules of Practice and Procedure (18 CFR
385.214). Intervenors have the right to seek rehearing of the
Commission's decision. Motions to Intervene should be electronically
submitted using the Commission's eFiling system at https://www.ferc.gov.
Persons without Internet access should send an original and 14 copies
of their motion to the Secretary of the Commission at the address
indicated previously. Persons filing Motions to Intervene on or before
the comment deadline indicated above must send a copy of the motion to
the Applicant. All filings, including late interventions, submitted
after the comment deadline must be served on the Applicant and all
other intervenors identified on the Commission's service list for this
proceeding. Persons on the service list with email addresses may be
served electronically; others must be served a hard copy of the filing.
Affected landowners and parties with environmental concerns may be
granted intervenor status upon showing good cause by stating that they
have a clear and direct interest in this proceeding which would not be
adequately represented by any other parties. You do not need intervenor
status to have your environmental comments considered.
Environmental Mailing List
An effort is being made to send this notice to all individuals,
organizations, and government entities interested in and/or potentially
affected by the proposed project. This includes all landowners who own
homes within distances defined in the Commission's regulations of
certain aboveground facilities.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at 1-866-208-FERC or on the
FERC Internet Web site (https://www.ferc.gov) using the ``eLibrary''
link. Click on the eLibrary link, then on ``General Search'' and enter
the docket number excluding the last three digits in the Docket Number
field. Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at 1-866-208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission now offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries and direct links to
the documents. Go to https://www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at https://www.ferc.gov/EventCalendar/
EventsList.aspx along with other related information.
Kimberly D. Bose,
Secretary.
[FR Doc. E7-24413 Filed 12-17-07; 8:45 am]
BILLING CODE 6717-01-P