BPUS Generation Development, LLC; Notice of Application Accepted for Filing and Soliciting Motions To Intervene, Protests, and Comments, 71395-71396 [E7-24300]

Download as PDF Federal Register / Vol. 72, No. 241 / Monday, December 17, 2007 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13033–000] BPUS Generation Development, LLC; Notice of Application Accepted for Filing and Soliciting Motions To Intervene, Protests, and Comments ebenthall on PROD1PC69 with NOTICES December 10, 2007. Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Type of Application: Preliminary Permit. b. Project No.: 13033–000. c. Date filed: September 28, 2007. d. Applicant: BPUS Generation Development, LLC. e. Name of Project: Ferrells Bridge Dam Hydroelectric Project. f. Location: Cypress Creek in Marion County, Texas. It would use the U.S. Army Corps of Engineers’ Ferrells Bridge Dam. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Mr. Jeffrey M. Auser, P.E., BPUS Generation Development, LLC, 225 Greenfield Parkway, Suite 201, Liverpool, NY 13088, (315) 413–2700. i. FERC Contact: Robert Bell, (202) 502–4126. j. Deadline for filing comments, protests, and motions to intervene: 60 days from the issuance date of this notice. All documents (original and eight copies) should be filed with: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. Comments, protests, and interventions may be filed electronically via the Internet in lieu of paper; see 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. The Commission strongly encourages electronic filings. Please include the project number ( P–13033–000) on any comments or motions filed. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person in the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. Description of Project: The proposed project using the U.S. Army VerDate Aug<31>2005 15:28 Dec 14, 2007 Jkt 214001 Corps of Engineers’ Ferrells Bridge Dam and operated in a run-of-river mode would consist of: (1) A new 75-foot long, 75-foot wide, 50-foot high concrete powerhouse; (2) two 100-foot-long, 9foot-diameter steel penstocks; (3) a new tailrace channel immediately downstream, river right, of the existing Corps’ outlet works; (4) two turbine/ generator units with a combined installed capacity of 9 megawatts; (5) a new 28,805-foot long above ground transmission line extending from the switchyard near the powerhouse northeast to an interconnection point with an existing transmission; and (6) appurtenant facilities. The proposed Ferrells Bridge Dam Project would have an average annual generation of 24 gigawatt-hours. l. This filing is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, call toll-free 1–866–208– 3676 or e-mail FERCONLINESUPPORT@FERC.GOV. For TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item h above. m. Competing Preliminary Permit: Anyone desiring to file a competing application for preliminary permit for a proposed project must submit the competing application itself, or a notice of intent to file such an application, to the Commission on or before the specified comment date for the particular application (see 18 CFR 4.36). Submission of a timely notice of intent allows an interested person to file the competing preliminary permit application no later than 30 days after the specified comment date for the particular application. A competing preliminary permit application must conform with 18 CFR 4.30 and 4.36. n. Competing Development Application: Any qualified development applicant desiring to file a competing development application must submit to the Commission, on or before a specified comment date for the particular application, either a competing development application or a notice of intent to file such an application. Submission of a timely notice of intent to file a development application allows an interested person to file the competing application no later than 120 days after the specified comment date for the particular application. A competing license PO 00000 Frm 00051 Fmt 4703 Sfmt 4703 71395 application must conform with 18 CFR 4.30 and 4.36. o. Notice of Intent: A notice of intent must specify the exact name, business address, and telephone number of the prospective applicant, and must include an unequivocal statement of intent to submit, if such an application may be filed, either a preliminary permit application or a development application (specify which type of application). A notice of intent must be served on the applicant(s) named in this public notice. p. Proposed Scope of Studies Under Permit: A preliminary permit, if issued, does not authorize construction. The term of the proposed preliminary permit would be 36 months. The work proposed under the preliminary permit would include economic analysis, preparation of preliminary engineering plans, and a study of environmental impacts. Based on the results of these studies, the Applicant would decide whether to proceed with the preparation of a development application to construct and operate the project. q. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. r. Filing and Service of Responsive Documents: Any filings must bear in all capital letters the title ‘‘COMMENTS’’, ‘‘NOTICE OF INTENT TO FILE COMPETING APPLICATION’’, ‘‘COMPETING APPLICATION’’, ‘‘PROTEST’’, and ‘‘MOTION TO INTERVENE’’, as applicable, and the Project Number of the particular application to which the filing refers. Any of the above-named documents must be filed by providing the original and the number of copies provided by the Commission’s regulations to: The Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. An additional copy must be sent to Director, Division of Hydropower Administration and Compliance, Federal Energy Regulatory Commission, at the above-mentioned address. A copy of any notice of intent, competing application or motion to intervene must also be served upon each E:\FR\FM\17DEN1.SGM 17DEN1 71396 Federal Register / Vol. 72, No. 241 / Monday, December 17, 2007 / Notices representative of the Applicant specified in the particular application. s. Agency Comments: Federal, State, and local agencies are invited to file comments on the described application. A copy of the application may be obtained by agencies directly from the Applicant. If an agency does not file comments within the time specified for filing comments, it will be presumed to have no comments. One copy of an agency’s comments must also be sent to the Applicant’s representatives. Kimberly D. Bose, Secretary. [FR Doc. E7–24300 Filed 12–14–07; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13034–000] BPUS Generation Development, LLC; Notice of Application Accepted for Filing and Soliciting Motions To Intervene, Protests, and Comments ebenthall on PROD1PC69 with NOTICES December 10, 2007. Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Type of Application: Preliminary Permit. b. Project No.: 13034–000. c. Date filed: September 28, 2007. d. Applicant: BPUS Generation Development, LLC. e. Name of Project: Mississippi River Lock & Dam No. 17 Hydroelectric Project f. Location: Mississippi River in Mercer County, Iowa. It would use the U.S. Army Corps of Engineers’ Mississippi River Lock & Dam No. 17. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Mr. Jeffrey M. Auser, P.E., BPUS Generation Development, LLC, 225 Greenfield Parkway, Suite 201, Liverpool, NY 13088, (315) 413–2700. i. FERC Contact: Robert Bell, (202) 502–4126. j. Deadline for filing comments, protests, and motions to intervene: 60 days from the issuance date of this notice. All documents (original and eight copies) should be filed with: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. Comments, protests, and interventions may be filed electronically via the VerDate Aug<31>2005 15:28 Dec 14, 2007 Jkt 214001 Internet in lieu of paper; see 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. The Commission strongly encourages electronic filings. Please include the project number (P– 13034–000) on any comments or motions filed. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person in the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. Description of Project: The proposed project using the U.S. Army Corps of Engineers’ Mississippi River Lock & Dam No. 17 and operated in a run-of-river mode would consist of: (1) A new 90-foot long, 130-foot wide, 60foot high concrete powerhouse; (2) a new intake channel and tailrace channel on the levee section of the Corps’ facility, on the Iowa shore, opposite the river from the lock structure; (3) two turbine/generator units with a combined installed capacity of 8 megawatts; (4) a new 27,217-foot long above ground transmission line extending from the switchyard near the powerhouse west to an interconnection point with an existing transmission line; and (5) appurtenant facilities. The proposed Mississippi River Lock & Dam No. 17 Project would have an average annual generation of 45 gigawatt-hours. l. This filing is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, call toll-free 1–866–208– 3676 or e-mail FERCONLINESUPPORT@FERC.GOV. For TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item h above. m. Competing Preliminary Permit— Anyone desiring to file a competing application for preliminary permit for a proposed project must submit the competing application itself, or a notice of intent to file such an application, to the Commission on or before the specified comment date for the particular application (see 18 CFR 4.36). Submission of a timely notice of intent allows an interested person to file the competing preliminary permit PO 00000 Frm 00052 Fmt 4703 Sfmt 4703 application no later than 30 days after the specified comment date for the particular application. A competing preliminary permit application must conform with 18 CFR 4.30 and 4.36. n. Competing Development Application—Any qualified development applicant desiring to file a competing development application must submit to the Commission, on or before a specified comment date for the particular application, either a competing development application or a notice of intent to file such an application. Submission of a timely notice of intent to file a development application allows an interested person to file the competing application no later than 120 days after the specified comment date for the particular application. A competing license application must conform with 18 CFR 4.30 and 4.36. o. Notice of Intent—A notice of intent must specify the exact name, business address, and telephone number of the prospective applicant, and must include an unequivocal statement of intent to submit, if such an application may be filed, either a preliminary permit application or a development application (specify which type of application). A notice of intent must be served on the applicant(s) named in this public notice. p. Proposed Scope of Studies Under Permit—A preliminary permit, if issued, does not authorize construction. The term of the proposed preliminary permit would be 36 months. The work proposed under the preliminary permit would include economic analysis, preparation of preliminary engineering plans, and a study of environmental impacts. Based on the results of these studies, the Applicant would decide whether to proceed with the preparation of a development application to construct and operate the project. q. Comments, Protests, or Motions to Intervene—Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. r. Filing and Service of Responsive Documents—Any filings must bear in all capital letters the title E:\FR\FM\17DEN1.SGM 17DEN1

Agencies

[Federal Register Volume 72, Number 241 (Monday, December 17, 2007)]
[Notices]
[Pages 71395-71396]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-24300]



[[Page 71395]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 13033-000]


BPUS Generation Development, LLC; Notice of Application Accepted 
for Filing and Soliciting Motions To Intervene, Protests, and Comments

December 10, 2007.
    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Type of Application: Preliminary Permit.
    b. Project No.: 13033-000.
    c. Date filed: September 28, 2007.
    d. Applicant: BPUS Generation Development, LLC.
    e. Name of Project: Ferrells Bridge Dam Hydroelectric Project.
    f. Location: Cypress Creek in Marion County, Texas. It would use 
the U.S. Army Corps of Engineers' Ferrells Bridge Dam.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: Mr. Jeffrey M. Auser, P.E., BPUS Generation 
Development, LLC, 225 Greenfield Parkway, Suite 201, Liverpool, NY 
13088, (315) 413-2700.
    i. FERC Contact: Robert Bell, (202) 502-4126.
    j. Deadline for filing comments, protests, and motions to 
intervene: 60 days from the issuance date of this notice.
    All documents (original and eight copies) should be filed with: 
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 
First Street, NE., Washington, DC 20426. Comments, protests, and 
interventions may be filed electronically via the Internet in lieu of 
paper; see 18 CFR 385.2001(a)(1)(iii) and the instructions on the 
Commission's Web site under the ``e-Filing'' link. The Commission 
strongly encourages electronic filings. Please include the project 
number ( P-13033-000) on any comments or motions filed.
    The Commission's Rules of Practice and Procedure require all 
intervenors filing documents with the Commission to serve a copy of 
that document on each person in the official service list for the 
project. Further, if an intervenor files comments or documents with the 
Commission relating to the merits of an issue that may affect the 
responsibilities of a particular resource agency, they must also serve 
a copy of the document on that resource agency.
    k. Description of Project: The proposed project using the U.S. Army 
Corps of Engineers' Ferrells Bridge Dam and operated in a run-of-river 
mode would consist of: (1) A new 75-foot long, 75-foot wide, 50-foot 
high concrete powerhouse; (2) two 100-foot-long, 9-foot-diameter steel 
penstocks; (3) a new tailrace channel immediately downstream, river 
right, of the existing Corps' outlet works; (4) two turbine/generator 
units with a combined installed capacity of 9 megawatts; (5) a new 
28,805-foot long above ground transmission line extending from the 
switchyard near the powerhouse northeast to an interconnection point 
with an existing transmission; and (6) appurtenant facilities. The 
proposed Ferrells Bridge Dam Project would have an average annual 
generation of 24 gigawatt-hours.
    l. This filing is available for review at the Commission in the 
Public Reference Room or may be viewed on the Commission's Web site at 
https://www.ferc.gov using the ``eLibrary'' link. Enter the docket 
number excluding the last three digits in the docket number field to 
access the document. For assistance, call toll-free 1-866-208-3676 or 
e-mail FERCONLINESUPPORT@FERC.GOV. For TTY, call (202) 502-8659. A copy 
is also available for inspection and reproduction at the address in 
item h above.
    m. Competing Preliminary Permit: Anyone desiring to file a 
competing application for preliminary permit for a proposed project 
must submit the competing application itself, or a notice of intent to 
file such an application, to the Commission on or before the specified 
comment date for the particular application (see 18 CFR 4.36). 
Submission of a timely notice of intent allows an interested person to 
file the competing preliminary permit application no later than 30 days 
after the specified comment date for the particular application. A 
competing preliminary permit application must conform with 18 CFR 4.30 
and 4.36.
    n. Competing Development Application: Any qualified development 
applicant desiring to file a competing development application must 
submit to the Commission, on or before a specified comment date for the 
particular application, either a competing development application or a 
notice of intent to file such an application. Submission of a timely 
notice of intent to file a development application allows an interested 
person to file the competing application no later than 120 days after 
the specified comment date for the particular application. A competing 
license application must conform with 18 CFR 4.30 and 4.36.
    o. Notice of Intent: A notice of intent must specify the exact 
name, business address, and telephone number of the prospective 
applicant, and must include an unequivocal statement of intent to 
submit, if such an application may be filed, either a preliminary 
permit application or a development application (specify which type of 
application). A notice of intent must be served on the applicant(s) 
named in this public notice.
    p. Proposed Scope of Studies Under Permit: A preliminary permit, if 
issued, does not authorize construction. The term of the proposed 
preliminary permit would be 36 months. The work proposed under the 
preliminary permit would include economic analysis, preparation of 
preliminary engineering plans, and a study of environmental impacts. 
Based on the results of these studies, the Applicant would decide 
whether to proceed with the preparation of a development application to 
construct and operate the project.
    q. Comments, Protests, or Motions to Intervene: Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214. In determining the appropriate action to take, the Commission 
will consider all protests or other comments filed, but only those who 
file a motion to intervene in accordance with the Commission's Rules 
may become a party to the proceeding. Any comments, protests, or 
motions to intervene must be received on or before the specified 
comment date for the particular application.
    r. Filing and Service of Responsive Documents: Any filings must 
bear in all capital letters the title ``COMMENTS'', ``NOTICE OF INTENT 
TO FILE COMPETING APPLICATION'', ``COMPETING APPLICATION'', 
``PROTEST'', and ``MOTION TO INTERVENE'', as applicable, and the 
Project Number of the particular application to which the filing 
refers. Any of the above-named documents must be filed by providing the 
original and the number of copies provided by the Commission's 
regulations to: The Secretary, Federal Energy Regulatory Commission, 
888 First Street, NE., Washington, DC 20426. An additional copy must be 
sent to Director, Division of Hydropower Administration and Compliance, 
Federal Energy Regulatory Commission, at the above-mentioned address. A 
copy of any notice of intent, competing application or motion to 
intervene must also be served upon each

[[Page 71396]]

representative of the Applicant specified in the particular 
application.
    s. Agency Comments: Federal, State, and local agencies are invited 
to file comments on the described application. A copy of the 
application may be obtained by agencies directly from the Applicant. If 
an agency does not file comments within the time specified for filing 
comments, it will be presumed to have no comments. One copy of an 
agency's comments must also be sent to the Applicant's representatives.

Kimberly D. Bose,
Secretary.
[FR Doc. E7-24300 Filed 12-14-07; 8:45 am]
BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.