Dynegy Moss Landing, LLC, Dynegy Morro Bay, LLC, El Segundo Power LLC, and Reliant Energy, Inc., Complainants v. California Independent System Operator Corporation, Respondents; Notice of Complaint, 70579-70580 [E7-24027]
Download as PDF
Federal Register / Vol. 72, No. 238 / Wednesday, December 12, 2007 / Notices
First Revised Sheet No. 335
First Revised Sheet No. 337
First Revised Sheet No. 338
DEPARTMENT OF ENERGY
FGT states that the filing is being
made in compliance with the
Commission’s ‘‘Order Issuing
Certificates’’ issued on June 15, 2006 in
the above referenced proceeding.
Any person desiring to protest this
filing must file in accordance with Rule
211 of the Commission’s Rules of
Practice and Procedure (18 CFR
385.211). Protests to this filing will be
considered by the Commission in
determining the appropriate action to be
taken, but will not serve to make
protestants parties to the proceeding.
Such protests must be filed in
accordance with the provisions of
Section 154.210 of the Commission’s
regulations (18 CFR 154.210). Anyone
filing a protest must serve a copy of that
document on all the parties to the
proceeding.
The Commission encourages
electronic submission of protests in lieu
of paper using the ‘‘eFiling’’ link at
https://www.ferc.gov. Persons unable to
file electronically should submit an
original and 14 copies of the protest to
the Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington, DC 20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
December 12, 2007.
Kimberly D. Bose,
Secretary.
[FR Doc. E7–24030 Filed 12–11–07; 8:45 am]
mstockstill on PROD1PC66 with NOTICES
BILLING CODE 6717–01–P
VerDate Aug<31>2005
15:54 Dec 11, 2007
Jkt 214001
Federal Energy Regulatory
Commission
[Docket No. EL08–14–000]
Black Oak Energy, LLC, EPIC Merchant
Energy, LP, SESCO Enterprises, LLC,
Complainants v. PJM Interconnection,
Inc., Respondent; Notice of Complaint
December 4, 2007.
Take notice that on December 3, 2007,
Black Oak Energy, LLC (Black Oak),
EPIC Merchant Energy, LP and SESCO
Enterprises, LLC (collectively, Financial
Marketers), filed a formal complaint
against PJM Interconnection, Inc. (PJM)
pursuant to section 206 and 306 of the
Federal Power Act, 16 U.S.C. 824e and
825e (2000), and Rule 206 of the
Commission’s Rules of Practice and
Procedure, 18 CFR 385.206 (2007),
alleging that the PJM Tariff is
improperly allocating physical
transmission line losses to virtual
transactions and also distributing overcollected transmission line losses in a
manner that discriminates against
virtual Market Participants.
Financial Marketers certify that copies
of the complaint were served on the
contacts for PJM as listed on the
Commission’s list of Corporate Officials.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. The Respondent’s answer
and all interventions, or protests must
be filed on or before the comment date.
The Respondent’s answer, motions to
intervene, and protests must be served
on the Complainants.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
70579
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on December 26, 2007.
Kimberly D. Bose,
Secretary.
[FR Doc. E7–24028 Filed 12–11–07; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. EL08–13–000]
Dynegy Moss Landing, LLC, Dynegy
Morro Bay, LLC, El Segundo Power
LLC, and Reliant Energy, Inc.,
Complainants v. California
Independent System Operator
Corporation, Respondents; Notice of
Complaint
December 4, 2007.
Take notice that on November 30,
2007, Dynegy Moss Landing, LLC,
Dynegy Morro Bay, LLC, El Segundo
Power LLC, and Reliant Energy, Inc.
(Complainants), filed a formal
complaint against the California
Independent System Operator
Corporation (Respondent) pursuant to
sections 206 and 306 of the Federal
Power Act, alleging that Respondent’s
application of the must-offer
compensation provisions under its tariff
commencing January 1, 2008, is unjust
and unreasonable and unduly
discriminatory. The Complainants have
requested fast track processing.
Complainants certify that copies of
the complaint were served on the
contacts for Respondent as listed on the
Commission’s list of Corporate Officials.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. The Respondent’s answer
and all interventions, or protests must
be filed on or before the comment date.
The Respondent’s answer, motions to
intervene, and protests must be served
on the Complainants.
E:\FR\FM\12DEN1.SGM
12DEN1
70580
Federal Register / Vol. 72, No. 238 / Wednesday, December 12, 2007 / Notices
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on December 20, 2007.
Kimberly D. Bose,
Secretary.
[FR Doc. E7–24027 Filed 12–11–07; 8:45 am]
The Commission encourages
electronic submission of protests in lieu
of paper using the ‘‘eFiling’’ link at
https://www.ferc.gov. Persons unable to
file electronically should submit an
original and 14 copies of the protest to
the Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington, DC 20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
December 12, 2007.
Kimberly D. Bose,
Secretary.
[FR Doc. E7–24026 Filed 12–11–07; 8:45 am]
BILLING CODE 6717–01–P
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Federal Energy Regulatory
Commission
[Docket No. OR08–4–000]
[Docket No. CP06–441–001]
Texas Gas Transmission, LLC; Notice
of Compliance Filing
mstockstill on PROD1PC66 with NOTICES
December 4, 2007.
Take notice that on November 30,
2007, Texas Gas Transmission, LLC
(Texas Gas) tendered for filing as part of
its FERC Gas Tariff, Second Revised
Volume No. 1, the tariff sheets listed on
Appendix A to the filing.
Texas Gas states that the filing is
being made in compliance with the
Commission’s ‘‘Order Issuing
Certificates and Granting
Abandonment’’ issued June 18, 2007 in
Docket No. CP06–441–000.
Any person desiring to protest this
filing must file in accordance with Rule
211 of the Commission’s Rules of
Practice and Procedure (18 CFR
385.211). Protests to this filing will be
considered by the Commission in
determining the appropriate action to be
taken, but will not serve to make
protestants parties to the proceeding.
Such protests must be filed on or before
the date as indicated below. Anyone
filing a protest must serve a copy of that
document on all the parties to the
proceeding.
VerDate Aug<31>2005
15:54 Dec 11, 2007
Jkt 214001
Valero Marketing and Supply Company
Complainant, v. Longhorn Pipeline
Partners and Flying J, Inc.
Respondents; Notice of Complaint
December 4, 2007.
Take notice that on November 30,
2007, Valero Marketing and Supply
Company (VMSC), tendered for filing
with the Federal Energy Regulatory
Commission a complaint against
Longhorn Pipeline Partners (Longhorn)
and Flying J, Inc., (Flying J), for undue
discrimination and unreasonable
preferential treatment of an affiliate in
the transportation of refined petroleum
products on Longhorn’s common carrier
pipeline. VMSC alleges that Longhorn,
acting in concert with its affiliate owner,
Flying J, engaged in unduly preferential
and abusive affiliate activity and
unreasonably discriminated against
VMSC, resulting in an undue economic
advantage, by refusing to provide
common carrier transportation services
to VMSC in violation of the Interstate
Commerce Act. VMSC therefore
requests that the Commission set this
complaint for investigation, discovery,
and hearing and that reparations and
damages be awarded to compensate
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
VMSC for injuries incurred as a result
of Longhorn’s and Flying J’s unlawful
and illegal actions. In addition, VMSC
requests the Commission order
disgorgement of all improper profits and
benefits obtained by Flying J as a result
of the complained of activity.
VMSC states that copies of the
complaint were served on Longhorn and
Flying J.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. The Respondent’s answer
and all interventions, or protests must
be filed on or before the comment date.
The Respondent’s answer, motions to
intervene, and protests must be served
on the Complainants.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on December 20, 2007.
Kimberly D. Bose,
Secretary.
[FR Doc. E7–24029 Filed 12–11–07; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\12DEN1.SGM
12DEN1
Agencies
[Federal Register Volume 72, Number 238 (Wednesday, December 12, 2007)]
[Notices]
[Pages 70579-70580]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-24027]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. EL08-13-000]
Dynegy Moss Landing, LLC, Dynegy Morro Bay, LLC, El Segundo Power
LLC, and Reliant Energy, Inc., Complainants v. California Independent
System Operator Corporation, Respondents; Notice of Complaint
December 4, 2007.
Take notice that on November 30, 2007, Dynegy Moss Landing, LLC,
Dynegy Morro Bay, LLC, El Segundo Power LLC, and Reliant Energy, Inc.
(Complainants), filed a formal complaint against the California
Independent System Operator Corporation (Respondent) pursuant to
sections 206 and 306 of the Federal Power Act, alleging that
Respondent's application of the must-offer compensation provisions
under its tariff commencing January 1, 2008, is unjust and unreasonable
and unduly discriminatory. The Complainants have requested fast track
processing.
Complainants certify that copies of the complaint were served on
the contacts for Respondent as listed on the Commission's list of
Corporate Officials.
Any person desiring to intervene or to protest this filing must
file in accordance with Rules 211 and 214 of the Commission's Rules of
Practice and Procedure (18 CFR 385.211, 385.214). Protests will be
considered by the Commission in determining the appropriate action to
be taken, but will not serve to make protestants parties to the
proceeding. Any person wishing to become a party must file a notice of
intervention or motion to intervene, as appropriate. The Respondent's
answer and all interventions, or protests must be filed on or before
the comment date. The Respondent's answer, motions to intervene, and
protests must be served on the Complainants.
[[Page 70580]]
The Commission encourages electronic submission of protests and
interventions in lieu of paper using the ``eFiling'' link at https://
www.ferc.gov. Persons unable to file electronically should submit an
original and 14 copies of the protest or intervention to the Federal
Energy Regulatory Commission, 888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at https://www.ferc.gov, using the
``eLibrary'' link and is available for review in the Commission's
Public Reference Room in Washington, DC. There is an ``eSubscription''
link on the Web site that enables subscribers to receive e-mail
notification when a document is added to a subscribed docket(s). For
assistance with any FERC Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll free). For
TTY, call (202) 502-8659.
Comment Date: 5 p.m. Eastern Time on December 20, 2007.
Kimberly D. Bose,
Secretary.
[FR Doc. E7-24027 Filed 12-11-07; 8:45 am]
BILLING CODE 6717-01-P