Sierra Pacific Power Company and Nevada Power Company; Notice of Institution of Proceeding and Refund Effective Date, 65715-65716 [E7-22826]
Download as PDF
Federal Register / Vol. 72, No. 225 / Friday, November 23, 2007 / Notices
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Comments, protests and interventions
may be filed electronically via the
Internet in lieu of paper. See, 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under the
‘‘e-Filing’’ link.
Comment Date: December 5, 2007.
Kimberly D. Bose,
Secretary.
[FR Doc. E7–22823 Filed 11–21–07; 8:45 am]
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on November 26, 2007.
Kimberly D. Bose,
Secretary.
[FR Doc. E7–22802 Filed 11–21–07; 8:45 am]
BILLING CODE 6717–01–P
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Federal Energy Regulatory
Commission
Ontelaunee Power Operating
Company, LLC v. Metropolitan Edison
Company; Notice of Filing
mstockstill on PROD1PC66 with NOTICES
November 15, 2007.
Take notice that on November 5,
2007, Metropolitan Edison Company
filed a compliance filing pursuant to the
Commission’s ‘‘Order Approving
Uncontested Settlement,’’ 121 FERC ¶
61,017, issued October 4, 2007.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. On or before the
comment date, it is not necessary to
serve motions to intervene or protests
on persons other than the Applicant.
The Commission encourages
electronic submission of protests and
VerDate Aug<31>2005
16:16 Nov 21, 2007
Jkt 214001
Public Utility District No. 1 of
Snohomish County, WA and the City of
Everett; Henry M. Jackson
Hydroelectric Project; Notice of Filing
of Joint Petition for Declaratory Order
November 15, 2007.
Take noticed that on November 1,
2007, The City of Everett, Washington
(City) and Public Utility District No. 1
of Snohomish County, Washington
(PUD) filed a joint petition for
declaratory order requesting the
Commission to issue a order finding that
the City need not be named a coapplicant for a new license to operate
the Henry M. Jackson Hydroelectric
Project after it’s current license expires
in 2011.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
PO 00000
Frm 00018
Fmt 4703
Sfmt 4703
protests must be filed on or before the
comment date. On or before the
comment date, it is not necessary to
serve motions to intervene or protests
on persons other than the Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on December 3, 2007.
Kimberly D. Bose,
Secretary.
[FR Doc. E7–22800 Filed 11–21–07; 8:45 am]
[Docket No. P–2157–000]
[Docket No. EL07–15–003]
65715
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. EL08–6–000]
Sierra Pacific Power Company and
Nevada Power Company; Notice of
Institution of Proceeding and Refund
Effective Date
November 14, 2007.
On November 13, 2007, the
Commission issued an order that
instituted a proceeding in the abovereferenced docket, pursuant to Section
206 of the Federal Power Act (FPA) 16
U.S.C. 824e, concerning the justness and
reasonableness of Sierra Pacific Power
Company’s and Nevada Power
Company’s rates, as discussed in the
November 13, 2007 Order. Sierra Pacific
Power Company and Nevada Power
Company, 121 FERC ¶ 61,160 (2007).
The refund effective date in the
above-docketed proceeding, established
pursuant to section 206(b) of the FPA,
E:\FR\FM\23NON1.SGM
23NON1
65716
Federal Register / Vol. 72, No. 225 / Friday, November 23, 2007 / Notices
will be the date of publication of this
notice in the Federal Register.
Kimberly D. Bose,
Secretary.
[FR Doc. E7–22826 Filed 11–21–07; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. EL08–9–000]
Cargill Power Markets, LLC,
Complainant, v. Southwest Power
Pool, Inc., Respondent; Notice of
Complaint
mstockstill on PROD1PC66 with NOTICES
November 15, 2007.
Take notice that on November 9,
2007, Cargill Power Markets, LLC (CPM)
filed a formal complaint against
Southwest Power Pool, Inc. (SPP),
alleging that SPP processed a queue of
requests for long-term firm point-topoint transmission service in a manner
that violated FERC policy and SPP’s
open access transmission tariff.
CPM certifies that copies of the
complaint were served on the contacts
for SPP as listed on the Commission’s
Corporate Officials.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. The Respondent’s answer
and all interventions, or protests must
be filed on or before the comment date.
The Respondent’s answer, motions to
intervene, and protests must be served
on the Complainants.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
VerDate Aug<31>2005
16:16 Nov 21, 2007
Jkt 214001
Filed Date: 11/08/2007.
Accession Number: 20071113–0003.
Comment Date: 5 p.m. Eastern Time
on Friday, November 23, 2007.
Docket Numbers: ER08–107–000.
Applicants: FirstEnergy Generation
Mansfield Unit 1.
Description: FirstEnergy Generation
Mansfield Unit 1 Corp submits
application for order granting market
Kimberly D. Bose,
based rate authority, accepting marketSecretary.
based rate tariff etc.
[FR Doc. E7–22803 Filed 11–21–07; 8:45 am]
Filed Date: 10/26/2007.
BILLING CODE 6717–01–P
Accession Number: 20071114–0177.
Comment Date: 5 p.m. Eastern Time
on Monday, November 26, 2007.
DEPARTMENT OF ENERGY
Docket Numbers: ER08–197–000.
Applicants: FPL Energy Oliver Wind
Federal Energy Regulatory
II, LLC.
Commission
Description: FPL Energy Oliver Wind
II, LLC submits their request for
Combined Notice of Filings # 1
authorization to sell energy and capacity
November 14, 2007.
at market-based rates, and waiver of the
Take notice that the Commission
60-day notice requirement.
received the following electric rate
Filed Date: 11/08/2007.
filings:
Accession Number: 20071113–0004.
Docket Numbers: ER07–1109–001.
Comment Date: 5 p.m. Eastern Time
Applicants: American Electric Power
on Thursday, November 29, 2007.
Service Corp.
Docket Numbers: ER08–198–000.
Description: American Electric Power
Applicants: Pacific Gas and Electric
Corp on behalf of Ohio Power Co et. al.,
Company.
submits a Stipulation and Agreement
Description: Pacific Gas and Electric
with attachments etc.
Co submits an annual adjustment to a
Filed Date: 10/15/2007.
transmission service rate under the
Accession Number: 20071017–0106.
Interconnection Agreement with
Comment Date: 5 p.m. Eastern Time
Sacramento Municipal Utility District.
on Wednesday, November 21, 2007.
Filed Date: 11/09/2007.
Docket Numbers: ER02–305–006.
Accession Number: 20071113–0005.
Applicants: Condon Wind Power,
Comment Date: 5 p.m. Eastern Time
LLC.
on Friday, November 30, 2007.
Description: Condon Wind Power,
Any person desiring to intervene or to
LLC submits a notice of non-material
protest in any of the above proceedings
change in status in accordance with
must file in accordance with Rules 211
Order 652.
and 214 of the Commission’s Rules of
Filed Date: 11/09/2007.
Practice and Procedure (18 CFR 385.211
Accession Number: 20071114–0083.
and 385.214) on or before 5 p.m. Eastern
Comment Date: 5 p.m. Eastern Time
time on the specified comment date. It
on Friday, November 30, 2007.
is not necessary to separately intervene
Docket Numbers: ER07–1019–002;
again in a subdocket related to a
ER07–1020–002; ER07–1021–002.
compliance filing if you have previously
Applicants: Niagara Mohawk Power
intervened in the same docket. Protests
Corporation.
Description: Refund Report of Niagara will be considered by the Commission
in determining the appropriate action to
Mohawk Power Corporation in
be taken, but will not serve to make
Compliance with October 30, 2007
protestants parties to the proceeding.
Order.
Anyone filing a motion to intervene or
Filed Date: 11/14/2007.
Accession Number: 20071114–5053.
protest must serve a copy of that
Comment Date: 5 p.m. Eastern Time
document on the Applicant. In reference
on Wednesday, December 5, 2007.
to filings initiating a new proceeding,
interventions or protests submitted on
Docket Numbers: ER07–1386–002.
or before the comment deadline need
Applicants: Tatanka Wind Power,
not be served on persons other than the
LLC.
Description: Tatanka Wind Power LLC Applicant.
The Commission encourages
amends an application to replace the
electronic submission of protests and
pivotal supplier screen and market
interventions in lieu of paper, using the
share screen currently set forth in
FERC Online links at https://
section III.A of the 9/17/07 application
www.ferc.gov. To facilitate electronic
with screens as Attachment A etc.
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on November 29, 2007.
PO 00000
Frm 00019
Fmt 4703
Sfmt 4703
E:\FR\FM\23NON1.SGM
23NON1
Agencies
[Federal Register Volume 72, Number 225 (Friday, November 23, 2007)]
[Notices]
[Pages 65715-65716]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-22826]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. EL08-6-000]
Sierra Pacific Power Company and Nevada Power Company; Notice of
Institution of Proceeding and Refund Effective Date
November 14, 2007.
On November 13, 2007, the Commission issued an order that
instituted a proceeding in the above-referenced docket, pursuant to
Section 206 of the Federal Power Act (FPA) 16 U.S.C. 824e, concerning
the justness and reasonableness of Sierra Pacific Power Company's and
Nevada Power Company's rates, as discussed in the November 13, 2007
Order. Sierra Pacific Power Company and Nevada Power Company, 121 FERC
] 61,160 (2007).
The refund effective date in the above-docketed proceeding,
established pursuant to section 206(b) of the FPA,
[[Page 65716]]
will be the date of publication of this notice in the Federal Register.
Kimberly D. Bose,
Secretary.
[FR Doc. E7-22826 Filed 11-21-07; 8:45 am]
BILLING CODE 6717-01-P