BPUS Generation Development, LLC; Notice of Application Accepted for Filing and Soliciting Motions To Intervene, Protests, and Comments, 64605-64606 [E7-22398]

Download as PDF mstockstill on PROD1PC66 with NOTICES Federal Register / Vol. 72, No. 221 / Friday, November 16, 2007 / Notices n. Competing Development Application: Any qualified development applicant desiring to file a competing development application must submit to the Commission, on or before a specified comment date for the particular application, either a competing development application or a notice of intent to file such an application. Submission of a timely notice of intent to file a development application allows an interested person to file the competing application no later than 120 days after the specified comment date for the particular application. A competing license application must conform with 18 CFR 4.30 and 4.36. o. Notice of Intent: A notice of intent must specify the exact name, business address, and telephone number of the prospective applicant, and must include an unequivocal statement of intent to submit, if such an application may be filed, either a preliminary permit application or a development application (specify which type of application). A notice of intent must be served on the applicant(s) named in this public notice. p. Proposed Scope of Studies Under Permit: A preliminary permit, if issued, does not authorize construction. The term of the proposed preliminary permit would be 36 months. The work proposed under the preliminary permit would include economic analysis, preparation of preliminary engineering plans, and a study of environmental impacts. Based on the results of these studies, the Applicant would decide whether to proceed with the preparation of a development application to construct and operate the project. q. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, 385.211, 385.214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. r. Filing and Service of Responsive Documents: Any filings must bear in all capital letters the title ‘‘COMMENTS’’, ‘‘NOTICE OF INTENT TO FILE COMPETING APPLICATION’’, ‘‘COMPETING APPLICATION’’, ‘‘PROTEST’’, and ‘‘MOTION TO INTERVENE’’, as applicable, and the VerDate Aug<31>2005 21:48 Nov 15, 2007 Jkt 214001 Project Number of the particular application to which the filing refers. Any of the above-named documents must be filed by providing the original and the number of copies provided by the Commission’s regulations to: The Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. An additional copy must be sent to Director, Division of Hydropower Administration and Compliance, Federal Energy Regulatory Commission, at the above-mentioned address. A copy of any notice of intent, competing application or motion to intervene must also be served upon each representative of the Applicant specified in the particular application. s. Agency Comments: Federal, State, and local agencies are invited to file comments on the described application. A copy of the application may be obtained by agencies directly from the Applicant. If an agency does not file comments within the time specified for filing comments, it will be presumed to have no comments. One copy of an agency’s comments must also be sent to the Applicant’s representatives. Kimberly D. Bose, Secretary. [FR Doc. E7–22397 Filed 11–15–07; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 12892–000] BPUS Generation Development, LLC; Notice of Application Accepted for Filing and Soliciting Motions To Intervene, Protests, and Comments November 8, 2007. Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Type of Application: Preliminary Permit. b. Project No.: 12892–000. c. Date filed: July 30, 2007. d. Applicant: BPUS Generation Development, LLC. e. Name of Project: Columbia Lock & Dam Hydroelectric Project. f. Location: Ouachita River in Caldwell County, Louisiana. It would use the U.S. Army Corps of Engineers’ Columbia Lock & Dam. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Mr. Jeffrey M. Auser, P.E., BPUS Generation Development, LLC, 225 Greenfield PO 00000 Frm 00032 Fmt 4703 Sfmt 4703 64605 Parkway, Suite 201, Liverpool, NY 13088, (315) 413–2700. i. FERC Contact: Robert Bell, (202) 502–4126. j. Deadline for filing comments, protests, and motions to intervene: 60 days from the issuance date of this notice. All documents (original and eight copies) should be filed with: Kimberly, D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. Comments, protests, and interventions may be filed electronically via the Internet in lieu of paper; see 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s web site under the ‘‘e-Filing’’ link. The Commission strongly encourages electronic filings. Please include the project number (P– 12892–000) on any comments or motions filed. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person in the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. Description of Project: The proposed project using the U.S. Army Corps of Engineers’ Columbia Lock & Dam and operated in a run-of-river mode would consist of: (1) A new 55foot long, 100-foot wide, 35-foot high concrete powerhouse; (2) a new intake channel and tailrace channel on the west side of the river; (3) two turbine/ generator units with a combined installed capacity of 6 megawatts; (4) a new 12,000-foot long above ground transmission line extending from the switchyard near the powerhouse to an interconnection point with an existing transmission line northwest of the powerhouse; and (5) appurtenant facilities. The proposed Columbia Lock & Dam Project would have an average annual generation of 47 gigawatt-hours. l. This filing is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, call toll-free 1–866–208– 3676 or e-mail ferconlinesupport@ferc.gov. For TTY, call (202) 502–8659. A copy is also available for inspection and E:\FR\FM\16NON1.SGM 16NON1 mstockstill on PROD1PC66 with NOTICES 64606 Federal Register / Vol. 72, No. 221 / Friday, November 16, 2007 / Notices reproduction at the address in item h above. m. Competing Preliminary Permit: Anyone desiring to file a competing application for preliminary permit for a proposed project must submit the competing application itself, or a notice of intent to file such an application, to the Commission on or before the specified comment date for the particular application (see 18 CFR 4.36). Submission of a timely notice of intent allows an interested person to file the competing preliminary permit application no later than 30 days after the specified comment date for the particular application. A competing preliminary permit application must conform with 18 CFR 4.30 and 4.36. n. Competing Development Application: Any qualified development applicant desiring to file a competing development application must submit to the Commission, on or before a specified comment date for the particular application, either a competing development application or a notice of intent to file such an application. Submission of a timely notice of intent to file a development application allows an interested person to file the competing application no later than 120 days after the specified comment date for the particular application. A competing license application must conform with 18 CFR 4.30 and 4.36. o. Notice of Intent: A notice of intent must specify the exact name, business address, and telephone number of the prospective applicant, and must include an unequivocal statement of intent to submit, if such an application may be filed, either a preliminary permit application or a development application (specify which type of application). A notice of intent must be served on the applicant(s) named in this public notice. p. Proposed Scope of Studies Under Permit: A preliminary permit, if issued, does not authorize construction. The term of the proposed preliminary permit would be 36 months. The work proposed under the preliminary permit would include economic analysis, preparation of preliminary engineering plans, and a study of environmental impacts. Based on the results of these studies, the Applicant would decide whether to proceed with the preparation of a development application to construct and operate the project. q. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. VerDate Aug<31>2005 21:48 Nov 15, 2007 Jkt 214001 In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. r. Filing and Service of Responsive Documents: Any filings must bear in all capital letters the title ‘‘COMMENTS’’, ‘‘NOTICE OF INTENT TO FILE COMPETING APPLICATION’’, ‘‘COMPETING APPLICATION’’, ‘‘PROTEST’’, and ‘‘MOTION TO INTERVENE’’, as applicable, and the Project Number of the particular application to which the filing refers. Any of the above-named documents must be filed by providing the original and the number of copies provided by the Commission’s regulations to: The Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. An additional copy must be sent to Director, Division of Hydropower Administration and Compliance, Federal Energy Regulatory Commission, at the above-mentioned address. A copy of any notice of intent, competing application or motion to intervene must also be served upon each representative of the Applicant specified in the particular application. s. Agency Comments: Federal, state, and local agencies are invited to file comments on the described application. A copy of the application may be obtained by agencies directly from the Applicant. If an agency does not file comments within the time specified for filing comments, it will be presumed to have no comments. One copy of an agency’s comments must also be sent to the Applicant’s representatives. Kimberly D. Bose, Secretary. [FR Doc. E7–22398 Filed 11–15–07; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 12893–000] BPUS Generation Development, LLC; Notice of Application Accepted for Filing and Soliciting Motions To Intervene, Protests, and Comments November 8, 2007. Take notice that the following hydroelectric application has been filed PO 00000 Frm 00033 Fmt 4703 Sfmt 4703 with the Commission and is available for public inspection: a. Type of Application: Preliminary Permit. b. Project No.: 12893–000. c. Date filed: July 30, 2007. d. Applicant: BPUS Generation Development, LLC. e. Name of Project: Montgomery Locks & Dam Hydroelectric Project. f. Location: Ohio River in Beaver County, Pennsylvania. It would use the U.S. Army Corps of Engineers’ Montgomery Locks & Dam. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Mr. Jeffrey M. Auser, P.E., BPUS Generation Development, LLC, 225 Greenfield Parkway, Suite 201, Liverpool, NY 13088, (315) 413–2700. i. FERC Contact: Robert Bell, (202) 502–4126. j. Deadline for filing comments, protests, and motions to intervene: 60 days from the issuance date of this notice. All documents (original and eight copies) should be filed with: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. Comments, protests, and interventions may be filed electronically via the Internet in lieu of paper; see 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. The Commission strongly encourages electronic filings. Please include the project number (P– 12893–000) on any comments or motions filed. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person in the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. Description of Project: The proposed project using the U.S. Army Corps of Engineers’ Montgomery Locks & Dam and operated in a run-of-river mode would consist of: (1) A new 200foot long, 250-foot wide, 50-foot high concrete powerhouse; (2) a new intake channel and tailrace channel on the north side of the river within an existing spillway bay opposite the lock structure; (3) three turbine/generator units with a combined installed capacity of 50 megawatts; (4) a new 1,600-foot long above ground transmission line extending from the switchyard near the E:\FR\FM\16NON1.SGM 16NON1

Agencies

[Federal Register Volume 72, Number 221 (Friday, November 16, 2007)]
[Notices]
[Pages 64605-64606]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-22398]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 12892-000]


BPUS Generation Development, LLC; Notice of Application Accepted 
for Filing and Soliciting Motions To Intervene, Protests, and Comments

November 8, 2007.
    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Type of Application: Preliminary Permit.
    b. Project No.: 12892-000.
    c. Date filed: July 30, 2007.
    d. Applicant: BPUS Generation Development, LLC.
    e. Name of Project: Columbia Lock & Dam Hydroelectric Project.
    f. Location: Ouachita River in Caldwell County, Louisiana. It would 
use the U.S. Army Corps of Engineers' Columbia Lock & Dam.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: Mr. Jeffrey M. Auser, P.E., BPUS Generation 
Development, LLC, 225 Greenfield Parkway, Suite 201, Liverpool, NY 
13088, (315) 413-2700.
    i. FERC Contact: Robert Bell, (202) 502-4126.
    j. Deadline for filing comments, protests, and motions to 
intervene: 60 days from the issuance date of this notice.
    All documents (original and eight copies) should be filed with: 
Kimberly, D. Bose, Secretary, Federal Energy Regulatory Commission, 888 
First Street, NE., Washington, DC 20426. Comments, protests, and 
interventions may be filed electronically via the Internet in lieu of 
paper; see 18 CFR 385.2001(a)(1)(iii) and the instructions on the 
Commission's web site under the ``e-Filing'' link. The Commission 
strongly encourages electronic filings. Please include the project 
number (P-12892-000) on any comments or motions filed.
    The Commission's Rules of Practice and Procedure require all 
intervenors filing documents with the Commission to serve a copy of 
that document on each person in the official service list for the 
project. Further, if an intervenor files comments or documents with the 
Commission relating to the merits of an issue that may affect the 
responsibilities of a particular resource agency, they must also serve 
a copy of the document on that resource agency.
    k. Description of Project: The proposed project using the U.S. Army 
Corps of Engineers' Columbia Lock & Dam and operated in a run-of-river 
mode would consist of: (1) A new 55-foot long, 100-foot wide, 35-foot 
high concrete powerhouse; (2) a new intake channel and tailrace channel 
on the west side of the river; (3) two turbine/generator units with a 
combined installed capacity of 6 megawatts; (4) a new 12,000-foot long 
above ground transmission line extending from the switchyard near the 
powerhouse to an interconnection point with an existing transmission 
line northwest of the powerhouse; and (5) appurtenant facilities. The 
proposed Columbia Lock & Dam Project would have an average annual 
generation of 47 gigawatt-hours.
    l. This filing is available for review at the Commission in the 
Public Reference Room or may be viewed on the Commission's Web site at 
https://www.ferc.gov using the ``eLibrary'' link. Enter the docket 
number excluding the last three digits in the docket number field to 
access the document. For assistance, call toll-free 1-866-208-3676 or 
e-mail ferconlinesupport@ferc.gov. For TTY, call (202) 502-8659. A copy 
is also available for inspection and

[[Page 64606]]

reproduction at the address in item h above.
    m. Competing Preliminary Permit: Anyone desiring to file a 
competing application for preliminary permit for a proposed project 
must submit the competing application itself, or a notice of intent to 
file such an application, to the Commission on or before the specified 
comment date for the particular application (see 18 CFR 4.36). 
Submission of a timely notice of intent allows an interested person to 
file the competing preliminary permit application no later than 30 days 
after the specified comment date for the particular application. A 
competing preliminary permit application must conform with 18 CFR 4.30 
and 4.36.
    n. Competing Development Application: Any qualified development 
applicant desiring to file a competing development application must 
submit to the Commission, on or before a specified comment date for the 
particular application, either a competing development application or a 
notice of intent to file such an application. Submission of a timely 
notice of intent to file a development application allows an interested 
person to file the competing application no later than 120 days after 
the specified comment date for the particular application. A competing 
license application must conform with 18 CFR 4.30 and 4.36.
    o. Notice of Intent: A notice of intent must specify the exact 
name, business address, and telephone number of the prospective 
applicant, and must include an unequivocal statement of intent to 
submit, if such an application may be filed, either a preliminary 
permit application or a development application (specify which type of 
application). A notice of intent must be served on the applicant(s) 
named in this public notice.
    p. Proposed Scope of Studies Under Permit: A preliminary permit, if 
issued, does not authorize construction. The term of the proposed 
preliminary permit would be 36 months. The work proposed under the 
preliminary permit would include economic analysis, preparation of 
preliminary engineering plans, and a study of environmental impacts. 
Based on the results of these studies, the Applicant would decide 
whether to proceed with the preparation of a development application to 
construct and operate the project.
    q. Comments, Protests, or Motions to Intervene: Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214. In determining the appropriate action to take, the Commission 
will consider all protests or other comments filed, but only those who 
file a motion to intervene in accordance with the Commission's Rules 
may become a party to the proceeding. Any comments, protests, or 
motions to intervene must be received on or before the specified 
comment date for the particular application.
    r. Filing and Service of Responsive Documents: Any filings must 
bear in all capital letters the title ``COMMENTS'', ``NOTICE OF INTENT 
TO FILE COMPETING APPLICATION'', ``COMPETING APPLICATION'', 
``PROTEST'', and ``MOTION TO INTERVENE'', as applicable, and the 
Project Number of the particular application to which the filing 
refers. Any of the above-named documents must be filed by providing the 
original and the number of copies provided by the Commission's 
regulations to: The Secretary, Federal Energy Regulatory Commission, 
888 First Street, NE., Washington, DC 20426. An additional copy must be 
sent to Director, Division of Hydropower Administration and Compliance, 
Federal Energy Regulatory Commission, at the above-mentioned address. A 
copy of any notice of intent, competing application or motion to 
intervene must also be served upon each representative of the Applicant 
specified in the particular application.
    s. Agency Comments: Federal, state, and local agencies are invited 
to file comments on the described application. A copy of the 
application may be obtained by agencies directly from the Applicant. If 
an agency does not file comments within the time specified for filing 
comments, it will be presumed to have no comments. One copy of an 
agency's comments must also be sent to the Applicant's representatives.

Kimberly D. Bose,
 Secretary.
 [FR Doc. E7-22398 Filed 11-15-07; 8:45 am]
BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.