Entergy Nuclear Vermont Yankee, LLC and Entergy Nuclear Operations, Inc.; Receipt of Request for Action Under 10 CFR 2.206, 63933-63934 [E7-22093]
Download as PDF
rfrederick on PROD1PC67 with NOTICES
Federal Register / Vol. 72, No. 218 / Tuesday, November 13, 2007 / Notices
NSF may not conduct or sponsor a
collection of information unless the
collection of information displays a
currently valid OMB control number
and the agency informs potential
persons who are to respond to the
collection of information that such
persons are not required to respond to
the collection of information unless it
displays a currently valid OMB control
number.
SUPPLEMENTARY INFORMATION:
Title of Collection: Evaluation of the
National Science Foundation-National
Institutes for Health Bioengineering and
Bioinformatics Summer Institutes
(BBSI) Program.
OMB Number: 3145–NEW.
Abstract: The National Science
Foundation (NSF) and the National
Institute of Bioinformatics and
Bioengineering (NIBIB), a new
component of the National Institutes of
Health, established a jointly funded
program run by NSF called the
Bioengineering and Bioinformatics
Summer Institutes (BBSI) Program to
begin creating a supply of professionals
trained in bioengineering and
bioinformatics. This workforce initiative
complements research and education
efforts in these fields funded by both
agencies and constitutes a high profile
effort to meet the anticipated human
resource needs for bioengineering and
bioinformatics.
The program is designed to provide
students majoring in the biological
sciences, computer sciences,
engineering, mathematics, and physical
sciences with well-planned
interdisciplinary experiences in
bioengineering or bioinformatics
research and education, in very active
‘Summer Institutes’; thereby increasing
the number of young people considering
careers in bioengineering and
bioinformatics at the graduate level and
beyond.
NIBIB and NSF’s Division of
Engineering Education and Centers
(EEC) wish to learn whether the BBSI
Program as originally conceived is
achieving its objectives and programlevel outcomes, and to collect lessons
learned for improvement of program
design and implementation. This shortterm evaluation is expected to provide
information on what educational and
career decisions have been affected by
participation in a Summer Institute,
what elements of the students’ BBSI
affect student outcomes, and how the
program can be improved, e.g., through
changes in specific program-wide
design components, expected outcomes,
proposal review criteria, etc. The survey
data collection will be done on the
World Wide Web.
VerDate Aug<31>2005
15:30 Nov 09, 2007
Jkt 214001
Estimate of Burden: Public reporting
burden for this collection of information
is estimated to average 30 minutes per
response.
Respondents: Individuals.
Estimated Number of Responses: 765.
Estimated Total Annual Burden on
Respondents: 387 hours.
Frequency of Response: Once.
Dated: November 7, 2007.
Suzanne H. Plimpton,
Reports Clearance Officer, National Science
Foundation.
[FR Doc. 07–5629 Filed 11–9–07; 8:45 am]
BILLING CODE 7555–01–M
NUCLEAR REGULATORY
COMMISSION
[Docket No. 50–271; License No. DPR–28]
Entergy Nuclear Vermont Yankee, LLC
and Entergy Nuclear Operations, Inc.;
Receipt of Request for Action Under 10
CFR 2.206
Notice is hereby given that by petition
dated August 27, 2007, the New
England Coalition (NEC or the
petitioner) has requested that the
Nuclear Regulatory Commission (NRC
or the Commission) take action with
regard to the Vermont Yankee Nuclear
Power Station (Vermont Yankee). The
NEC petition requested that NRC
promptly restore reasonable assurance
of adequate protection of public health
and safety that is now degraded by the
failure of the licensee and its employees
to report adverse conditions leading to
a reduction in plant safety margins at
the Vermont Yankee Nuclear Power
Station (Vermont Yankee), or otherwise
to order a derate or shutdown of
Vermont Yankee until it can be
determined to what extent Vermont
Yankee is being operated in an
unanalyzed condition. Specifically, the
petition requested the following actions:
(1) NRC completion of a Diagnostic
Evaluation Team examination or
Independent Safety Assessment of
Vermont Yankee to determine the extent
of condition of non-conformances,
reportable items, hazards to safety, and
the root causes thereof; (2) NRC
completion of a safety culture
assessment to determine why worker
safety concerns were not previously
reported and why assessments of safety
culture under the Reactor Oversight
Process failed to capture the fact or
reasons that safety concerns have gone
unreported; (3) derate Vermont Yankee
to 50% of licensed thermal power with
a mandatory hold at 50% until a
thorough and detailed structural and
performance analysis of the cooling
PO 00000
Frm 00061
Fmt 4703
Sfmt 4703
63933
towers, including the alternate cooling
system, has been completed by the
licensee; reviewed and approved by
NRC; and until the above steps (1) and
(2) have been completed; and (4) NRC
investigation and determination of
whether or not similar non-conforming
conditions and causes exist at other
Entergy-run nuclear power plants.
As a basis for the request, the petition
cited problems related to the inadequate
performance of Vermont Yankee
Inservice Inspection, Maintenance,
Engineering, and Quality Assurance
leading to a cooling tower cell collapse
coupled with the employees’ assertion
of degrading plant conditions inimical
to public health.
The request is being treated pursuant
to Title 10 of the Code of Federal
Regulations (10 CFR) section 2.206 of
the Commission’s regulations. The
request has been referred to the Director
of the Office of Nuclear Reactor
Regulation. As provided by 10 CFR
2.206, appropriate action will be taken
on this petition within a reasonable
time. Mr. Raymond Shadis, in his
capacity as the petitioner’s Staff
Technical Advisor, participated in two
telephone conference calls with the
NRC’s Petition Review Board (PRB) on
September 12, 2007, and October 3,
2007, to discuss the petition and
provide any additional explanation in
light of the PRB’s initial
recommendation. The results of those
discussions were considered in the
PRB’s determination regarding the
petitioner’s request for action and in
establishing the schedule for the review
of the petition. The PRB confirmed its
initial recommendation to reject action
items (1), (2), and (4), which are the
diagnostic evaluation team examination,
safety culture assessment, and the NRC
investigation at other Entergy facilities.
These action items were rejected for
review under the 2.206 process because
these actions are not enforcementrelated. However, the PRB has
determined that the petition meets the
criteria for review in Management
Directive 8.11 with respect to a portion
of action item (3). Specifically, the PRB
found that the facts presented in the
petition related to the cooling tower cell
collapse in action (3) were credible and
sufficient to warrant further inquiry.
A copy of the petition and
supplement and the transcripts of the
telephone conference calls are available
for inspection at the Commission’s
Public Document Room (PDR), located
at One White Flint North, Public File
Area O1 F21, 11555 Rockville Pike (first
floor), Rockville, Maryland and from the
NRC’s Agencywide Documents Access
and Management System (ADAMS)
E:\FR\FM\13NON1.SGM
13NON1
63934
Federal Register / Vol. 72, No. 218 / Tuesday, November 13, 2007 / Notices
Public Electronic Reading Room on the
Internet at the NRC Web site, https://
www.nrc.gov/reading-rm/adams.html
(ADAMS Accession Nos. ML072420194,
ML072780363, ML072610466, and
ML07830584). Persons who do not have
access to ADAMS or who encounter
problems in accessing the documents
located in ADAMS, should contact the
NRC PDR Reference staff by telephone
at 1–800–397–4209 or 301–415–4737, or
by e-mail to pdr@nrc.gov.
Dated at Rockville, Maryland, this 6th day
of November 2007.
For the Nuclear Regulatory Commission.
J. T. Wiggins,
Deputy Director, Office of Nuclear Reactor
Regulation.
[FR Doc. E7–22093 Filed 11–9–07; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket No. 40–8905]
Notice of Availability of Environmental
Assessment and Finding of No
Significant Impact for Cell 2 Expansion
Reclamation Plan License
Amendment; Rio Algom Mining LLC,
Ambrosia Lake, NM
Nuclear Regulatory
Commission.
ACTION: Notice of availability.
AGENCY:
FOR FURTHER INFORMATION CONTACT:
Thomas McLaughlin, Project Manager,
Materials Decommissioning Branch,
Division of Waste Management and
Environmental Protection, Office of
Federal and State Materials and
Environmental Management Programs,
U.S. Nuclear Regulatory Commission,
Washington, DC, 20555. Telephone:
(301) 415–5869; fax number: (301) 415–
5369; e-mail: tgm@nrc.gov.
SUPPLEMENTARY INFORMATION:
rfrederick on PROD1PC67 with NOTICES
I. Introduction
The Nuclear Regulatory Commission
(NRC) proposes to issue a license
amendment of Source Materials License
No. SUA–1473 held by Rio Algom
Mining LLC (Rio Algom/the licensee), to
approve a Cell 2 Expansion Reclamation
Plan for its uranium mill tailings site in
Ambrosia Lake, New Mexico. The NRC
has prepared an Environmental
Assessment (EA) for this amendment in
accordance with the requirements of 10
CFR Part 51, and has concluded that a
Finding of No Significant Impact
(FONSI) is appropriate. The amendment
will be issued following the publication
of this Notice.
VerDate Aug<31>2005
15:30 Nov 09, 2007
Jkt 214001
The Ambrosia Lake site is in the
Ambrosia Lake mining district of New
Mexico, 25 miles north of Grants, New
Mexico. Rio Algom began processing ore
in 1958, and processed approximately
33 million tons of ore through 1985. The
site continued to be an active uranium
production facility through December
2002. Site reclamation activities
commenced in 1989 with some work on
the top surface of the largest tailings
cell. There are three tailings/waste cells
situated adjacent to each other at the Rio
Algom site: The large Tailings Cell 1,
Tailings Cell 2 to the west of Cell 1, and
a small Cell 3 east of Cell 1 that was
used to dispose of contaminated
windblown material. Reclamation of
Cell 1 is complete, and cover
construction of Cells 2 and 3 is still
ongoing. Reclamation activities have at
times included unlined evaporation
pond residue excavation and disposal,
contaminated windblown soil cleanup,
tailings impoundment reclamation,
surface water erosion protection feature
construction, and mill building
demolition.
The licensee has indicated that this
proposed cell expansion design is one
component of the overall site
reclamation plan. The licensee
previously has addressed, and NRC has
approved, the remaining site-wide
reclamation plan elements through
separate licensing actions, including the
original reclamation plan for Tailings
Cells 1, 2, and 3 (approved in September
1990), mill demolition, relocation of
lined evaporation pond sediments, soil
decommissioning plan, and
groundwater remediation.
II. EA Summary
In April 2005, Rio Algom sent the
NRC a Reclamation Plan for disposal of
evaporation pond sediments for its
Ambrosia Lake uranium mill tailings
facility. In a followup to the proposed
plan, Rio Algom submitted, under letter
dated May 31, 2007, Revision 1 of the
plan and a response to NRC’s request for
additional information. The Uranium
Mill Tailings Radiation Control Act of
1978, as amended, and regulations in
Title 10 of the Code of Federal
Regulations, Part 40 (10 CFR Part 40)
require that material at uranium mill
tailings sites be disposed of in a manner
that protects human health and the
environment.
Rio Algom proposes to excavate its
lined evaporation ponds (Ponds 9 and
11 through 21), and place all the
contaminated sediments, dikes, and
underlying materials onto the existing
Tailings Cell 2. The expanded Cell 2
will then be closed as part of the facility
decommissioning plan. Rio Algom
PO 00000
Frm 00062
Fmt 4703
Sfmt 4703
estimates that up to 3 million cubic
yards of materials will be excavated,
hauled, and compacted as part of this
action. The reclamation of the expanded
Tailings Cell 2 is intended to: (1)
Control radiological hazards for 1,000
years to the extent reasonably
achievable; (2) limit the release of
radon-222 from uranium by-product,
and radon-220 from thorium by-product
materials to the atmosphere so as not to
exceed an average of 20 pCi/m2/sec; (3)
reduce direct gamma exposure from the
reclaimed tailings cell to background
levels; (4) avoid proliferation of small
waste disposal sites; and (5) provide a
final site that is geotechnically stable
and provides protection of water
resources for the long term.
The NRC staff has prepared the EA in
support of the proposed license
amendment. The New Mexico
Environment Department was consulted
during the EA preparation. The staff
considered impacts that the licensee’s
amended Reclamation Plan will have on
ground water, surface water,
socioeconomic conditions, threatened
and endangered species, transportation,
land use, public and occupational
health, and historic and cultural
resources.
The EA supports a FONSI based on
the following conclusions. The potential
impacts of the proposed action are
limited to the land surface and are
temporary during the construction
activity. The direct impacts to the
surface primarily will be dust
generation due to excavating material,
hauling it to the disposal area, and
working it at the disposal area. Fugitive
dust from heavy equipment operation
will be mitigated through the use of dust
suppression methods on haul roads.
Impacts at the expansion cell area itself
are minimal, since the area is already
disturbed from site reclamation
activities. The licensee’s
implementation of its National Pollutant
Discharge Elimination System (NPDES)
permits, its Storm Water Pollution
Prevention Plan for the site, its site
Health, Safety and Environment
Management System, and NRC license
requirements provide adequate
assurances to control impacts to the
environment. Additional ambient air
monitoring stations have been installed
to collect data to demonstrate that
control measures are implemented and
effective.
III. Finding of No Significant Impact
On the basis of the EA, NRC has
concluded that there are no significant
environmental impacts from the
proposed amendment, and there is no
E:\FR\FM\13NON1.SGM
13NON1
Agencies
[Federal Register Volume 72, Number 218 (Tuesday, November 13, 2007)]
[Notices]
[Pages 63933-63934]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-22093]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 50-271; License No. DPR-28]
Entergy Nuclear Vermont Yankee, LLC and Entergy Nuclear
Operations, Inc.; Receipt of Request for Action Under 10 CFR 2.206
Notice is hereby given that by petition dated August 27, 2007, the
New England Coalition (NEC or the petitioner) has requested that the
Nuclear Regulatory Commission (NRC or the Commission) take action with
regard to the Vermont Yankee Nuclear Power Station (Vermont Yankee).
The NEC petition requested that NRC promptly restore reasonable
assurance of adequate protection of public health and safety that is
now degraded by the failure of the licensee and its employees to report
adverse conditions leading to a reduction in plant safety margins at
the Vermont Yankee Nuclear Power Station (Vermont Yankee), or otherwise
to order a derate or shutdown of Vermont Yankee until it can be
determined to what extent Vermont Yankee is being operated in an
unanalyzed condition. Specifically, the petition requested the
following actions: (1) NRC completion of a Diagnostic Evaluation Team
examination or Independent Safety Assessment of Vermont Yankee to
determine the extent of condition of non-conformances, reportable
items, hazards to safety, and the root causes thereof; (2) NRC
completion of a safety culture assessment to determine why worker
safety concerns were not previously reported and why assessments of
safety culture under the Reactor Oversight Process failed to capture
the fact or reasons that safety concerns have gone unreported; (3)
derate Vermont Yankee to 50% of licensed thermal power with a mandatory
hold at 50% until a thorough and detailed structural and performance
analysis of the cooling towers, including the alternate cooling system,
has been completed by the licensee; reviewed and approved by NRC; and
until the above steps (1) and (2) have been completed; and (4) NRC
investigation and determination of whether or not similar non-
conforming conditions and causes exist at other Entergy-run nuclear
power plants.
As a basis for the request, the petition cited problems related to
the inadequate performance of Vermont Yankee Inservice Inspection,
Maintenance, Engineering, and Quality Assurance leading to a cooling
tower cell collapse coupled with the employees' assertion of degrading
plant conditions inimical to public health.
The request is being treated pursuant to Title 10 of the Code of
Federal Regulations (10 CFR) section 2.206 of the Commission's
regulations. The request has been referred to the Director of the
Office of Nuclear Reactor Regulation. As provided by 10 CFR 2.206,
appropriate action will be taken on this petition within a reasonable
time. Mr. Raymond Shadis, in his capacity as the petitioner's Staff
Technical Advisor, participated in two telephone conference calls with
the NRC's Petition Review Board (PRB) on September 12, 2007, and
October 3, 2007, to discuss the petition and provide any additional
explanation in light of the PRB's initial recommendation. The results
of those discussions were considered in the PRB's determination
regarding the petitioner's request for action and in establishing the
schedule for the review of the petition. The PRB confirmed its initial
recommendation to reject action items (1), (2), and (4), which are the
diagnostic evaluation team examination, safety culture assessment, and
the NRC investigation at other Entergy facilities. These action items
were rejected for review under the 2.206 process because these actions
are not enforcement-related. However, the PRB has determined that the
petition meets the criteria for review in Management Directive 8.11
with respect to a portion of action item (3). Specifically, the PRB
found that the facts presented in the petition related to the cooling
tower cell collapse in action (3) were credible and sufficient to
warrant further inquiry.
A copy of the petition and supplement and the transcripts of the
telephone conference calls are available for inspection at the
Commission's Public Document Room (PDR), located at One White Flint
North, Public File Area O1 F21, 11555 Rockville Pike (first floor),
Rockville, Maryland and from the NRC's Agencywide Documents Access and
Management System (ADAMS)
[[Page 63934]]
Public Electronic Reading Room on the Internet at the NRC Web site,
https://www.nrc.gov/reading-rm/adams.html (ADAMS Accession Nos.
ML072420194, ML072780363, ML072610466, and ML07830584). Persons who do
not have access to ADAMS or who encounter problems in accessing the
documents located in ADAMS, should contact the NRC PDR Reference staff
by telephone at 1-800-397-4209 or 301-415-4737, or by e-mail to
pdr@nrc.gov.
Dated at Rockville, Maryland, this 6th day of November 2007.
For the Nuclear Regulatory Commission.
J. T. Wiggins,
Deputy Director, Office of Nuclear Reactor Regulation.
[FR Doc. E7-22093 Filed 11-9-07; 8:45 am]
BILLING CODE 7590-01-P