FFP Project 45, LLC; Notice of Application Accepted for Filing and Soliciting Motions To Intervene, Protests, and Comments, 62471-62472 [E7-21657]
Download as PDF
ycherry on PRODPC74 with NOTICES
Federal Register / Vol. 72, No. 213 / Monday, November 5, 2007 / Notices
prospective applicant, and must include
an unequivocal statement of intent to
submit, if such an application may be
filed, either a preliminary permit
application or a development
application (specify which type of
application). A notice of intent must be
served on the applicant(s) named in this
public notice.
q. Proposed Scope of Studies under
Permit—A preliminary permit, if issued,
does not authorize construction. The
term of the proposed preliminary permit
would be 36 months. The work
proposed under the preliminary permit
would include economic analysis,
preparation of preliminary engineering
plans, and a study of environmental
impacts. Based on the results of these
studies, the Applicant would decide
whether to proceed with the preparation
of a development application to
construct and operate the project.
r. Comments, Protests, or Motions to
Intervene—Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
Comments, protests and interventions
may be filed electronically via the
Internet in lieu of paper. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under
‘‘e-filing’’ link. The Commission
strongly encourages electronic filing.
Filing and Service of Responsive
Documents—Any filings must bear in
all capital letters the title
‘‘COMMENTS’’, ‘‘COMPETING
APPLICATION’’,
‘‘RECOMMENDATIONS FOR TERMS
AND CONDITIONS’’, ‘‘PROTEST’’, OR
‘‘MOTION TO INTERVENE’’, as
applicable, and the Project Number of
the particular application to which the
filing refers. Any of the above-named
documents must be filed by providing
the original and the number of copies
provided by the Commission’s
regulations to: The Secretary, Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
A copy of any motion to intervene must
also be served upon each representative
of the Applicant specified in the
particular application.
VerDate Aug<31>2005
17:17 Nov 02, 2007
Jkt 214001
t. Agency Comments—Federal, state,
and local agencies are invited to file
comments on the described application.
A copy of the application may be
obtained by agencies directly from the
Applicant. If an agency does not file
comments within the time specified for
filing comments, it will be presumed to
have no comments. One copy of an
agency’s comments must also be sent to
the Applicant’s representatives.
Kimberly D. Bose,
Secretary.
[FR Doc. E7–21656 Filed 11–2–07; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 12937–000]
FFP Project 45, LLC; Notice of
Application Accepted for Filing and
Soliciting Motions To Intervene,
Protests, and Comments
October 29, 2007.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Preliminary
Permit.
b. Project No.: 12937–000.
c. Date filed: August 6, 2007.
d. Applicant: FFP Project 45, LLC.
e. Name of Project: Huffman Light
Project.
f. Location: The project would be
located on the Mississippi River in
Mississippi County, Arkansas and Dyer
County, Tennessee. The project uses no
dam or impoundment.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Mr. Dan Irvin,
FFP Project 45, LLC, 69 Bridge Street,
Manchester, MA 01944, phone (978)
232–3536.
i. FERC Contact: Robert Bell, (202)
502–6062.
j. Deadline for filing comments,
protests, and motions to intervene: 60
days from the issuance date of this
notice.
All documents (original and eight
copies) should be filed with: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
Comments, protests, and interventions
may be filed electronically via the
Internet in lieu of paper; see 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under the
‘‘e-Filing’’ link. The Commission
PO 00000
Frm 00044
Fmt 4703
Sfmt 4703
62471
strongly encourages electronic filings.
Please include the project number
(P–12937–000) on any comments or
motions filed.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person in the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
k. Description of Project: The
proposed project consists of: (1) 1,900
proposed 20 kilowatt Free Flow
generating units having a total installed
capacity of 38 megawatts, (2) a proposed
transmission line; and (3) appurtenant
facilities. The FFP Project 45, LLC,
project would have an average annual
generation of 166.44 gigawatt-hours and
be sold to a local utility.
l. Locations of Applications: A copy of
the application is available for
inspection and reproduction at the
Commission in the Public Reference
Room, located at 888 First Street, NE.,
Room 2A, Washington DC 20426, or by
calling (202) 502–8371. This filing may
also be viewed on the Commission’s
Web site at https://www.ferc.gov using
the ‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, call toll-free
1–866–208–3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY,
call (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item h
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Competing Preliminary Permit:
Anyone desiring to file a competing
application for preliminary permit for a
proposed project must submit the
competing application itself, or a notice
of intent to file such an application, to
the Commission on or before the
specified comment date for the
particular application (see 18 CFR 4.36).
Submission of a timely notice of intent
allows an interested person to file the
competing preliminary permit
application no later than 30 days after
the specified comment date for the
particular application. A competing
preliminary permit application must
conform with 18 CFR 4.30 and 4.36.
o. Competing Development
Application: Any qualified development
applicant desiring to file a competing
E:\FR\FM\05NON1.SGM
05NON1
ycherry on PRODPC74 with NOTICES
62472
Federal Register / Vol. 72, No. 213 / Monday, November 5, 2007 / Notices
development application must submit to
the Commission, on or before a
specified comment date for the
particular application, either a
competing development application or a
notice of intent to file such an
application. Submission of a timely
notice of intent to file a development
application allows an interested person
to file the competing application no
later than 120 days after the specified
comment date for the particular
application. A competing license
application must conform with 18 CFR
4.30 and 4.36.
p. Notice of Intent: A notice of intent
must specify the exact name, business
address, and telephone number of the
prospective applicant, and must include
an unequivocal statement of intent to
submit, if such an application may be
filed, either a preliminary permit
application or a development
application (specify which type of
application). A notice of intent must be
served on the applicant(s) named in this
public notice.
q. Proposed Scope of Studies under
Permit: A preliminary permit, if issued,
does not authorize construction. The
term of the proposed preliminary permit
would be 36 months. The work
proposed under the preliminary permit
would include economic analysis,
preparation of preliminary engineering
plans, and a study of environmental
impacts. Based on the results of these
studies, the Applicant would decide
whether to proceed with the preparation
of a development application to
construct and operate the project.
r. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
Comments, protests and interventions
may be filed electronically via the
Internet in lieu of paper. See 18 CFR
385.2001 (a)(1)(iii) and the instructions
on the Commission’s Web site under
‘‘e-filing’’ link. The Commission
strongly encourages electronic filing.
s. Filing and Service of Responsive
Documents: Any filings must bear in all
capital letters the title ‘‘COMMENTS’’,
‘‘COMPETING APPLICATION’’,
VerDate Aug<31>2005
15:04 Nov 02, 2007
Jkt 214001
‘‘RECOMMENDATIONS FOR TERMS
AND CONDITIONS’’, ‘‘PROTEST’’, OR
‘‘MOTION TO INTERVENE’’, as
applicable, and the Project Number of
the particular application to which the
filing refers. Any of the above-named
documents must be filed by providing
the original and the number of copies
provided by the Commission’s
regulations to: The Secretary, Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
A copy of any motion to intervene must
also be served upon each representative
of the Applicant specified in the
particular application.
t. Agency Comments: Federal, State,
and local agencies are invited to file
comments on the described application.
A copy of the application may be
obtained by agencies directly from the
Applicant. If an agency does not file
comments within the time specified for
filing comments, it will be presumed to
have no comments. One copy of an
agency’s comments must also be sent to
the Applicant’s representatives.
Kimberly D. Bose,
Secretary.
[FR Doc. E7–21657 Filed 11–2–07; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[FFP Project 42, LLC, Project No. 12938–
000]
Notice of Application Accepted for
Filing and Soliciting Motions To
Intervene, Protests, and Comments
October 29, 2007.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Preliminary
Permit.
b. Project No.: 12938–000.
c. Date filed: August 6, 2007.
d. Applicant: FFP Project 42, LLC.
e. Name of Project: Hope Field Point
Project.
f. Location: The project would be
located on the Mississippi River in
Crittenden County, Arkansas and
Shelby County, Tennessee. The project
uses no dam or impoundment.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Mr. Dan Irvin,
FFP Project 42, LLC, 69 Bridge Street,
Manchester, MA 01944, phone (978)
232–3536.
i. FERC Contact: Robert Bell, (202)
502–6062.
PO 00000
Frm 00045
Fmt 4703
Sfmt 4703
j. Deadline for filing comments,
protests, and motions to intervene: 60
days from the issuance date of this
notice.
All documents (original and eight
copies) should be filed with: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
Comments, protests, and interventions
may be filed electronically via the
Internet in lieu of paper; see 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under the
‘‘e-Filing’’ link. The Commission
strongly encourages electronic filings.
Please include the project number (P–
12938–000) on any comments or
motions filed.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person in the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
k. Description of Project: The
proposed project consists of: (1) 5,600
proposed 20 kilowatt Free Flow
generating units having a total installed
capacity of 112 megawatts, (2) a
proposed transmission line, and (3)
appurtenant facilities. The FFP Project
42, LLC, project would have an average
annual generation of 490.56 gigawatthours and be sold to a local utility.
l. Locations of Applications: A copy of
the application is available for
inspection and reproduction at the
Commission in the Public Reference
Room, located at 888 First Street, NE.,
Room 2A, Washington, DC 20426, or by
calling (202) 502–8371. This filing may
also be viewed on the Commission’s
Web site at https://www.ferc.gov using
the ‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, call toll-free
1–866–208–3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY,
call (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item h
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Competing Preliminary Permit—
Anyone desiring to file a competing
application for preliminary permit for a
proposed project must submit the
competing application itself, or a notice
E:\FR\FM\05NON1.SGM
05NON1
Agencies
[Federal Register Volume 72, Number 213 (Monday, November 5, 2007)]
[Notices]
[Pages 62471-62472]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-21657]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 12937-000]
FFP Project 45, LLC; Notice of Application Accepted for Filing
and Soliciting Motions To Intervene, Protests, and Comments
October 29, 2007.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Application: Preliminary Permit.
b. Project No.: 12937-000.
c. Date filed: August 6, 2007.
d. Applicant: FFP Project 45, LLC.
e. Name of Project: Huffman Light Project.
f. Location: The project would be located on the Mississippi River
in Mississippi County, Arkansas and Dyer County, Tennessee. The project
uses no dam or impoundment.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Mr. Dan Irvin, FFP Project 45, LLC, 69 Bridge
Street, Manchester, MA 01944, phone (978) 232-3536.
i. FERC Contact: Robert Bell, (202) 502-6062.
j. Deadline for filing comments, protests, and motions to
intervene: 60 days from the issuance date of this notice.
All documents (original and eight copies) should be filed with:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426. Comments, protests, and
interventions may be filed electronically via the Internet in lieu of
paper; see 18 CFR 385.2001(a)(1)(iii) and the instructions on the
Commission's Web site under the ``e-Filing'' link. The Commission
strongly encourages electronic filings. Please include the project
number (P-12937-000) on any comments or motions filed.
The Commission's Rules of Practice and Procedure require all
intervenors filing documents with the Commission to serve a copy of
that document on each person in the official service list for the
project. Further, if an intervenor files comments or documents with the
Commission relating to the merits of an issue that may affect the
responsibilities of a particular resource agency, they must also serve
a copy of the document on that resource agency.
k. Description of Project: The proposed project consists of: (1)
1,900 proposed 20 kilowatt Free Flow generating units having a total
installed capacity of 38 megawatts, (2) a proposed transmission line;
and (3) appurtenant facilities. The FFP Project 45, LLC, project would
have an average annual generation of 166.44 gigawatt-hours and be sold
to a local utility.
l. Locations of Applications: A copy of the application is
available for inspection and reproduction at the Commission in the
Public Reference Room, located at 888 First Street, NE., Room 2A,
Washington DC 20426, or by calling (202) 502-8371. This filing may also
be viewed on the Commission's Web site at https://www.ferc.gov using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. For
assistance, call toll-free 1-866-208-3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY, call (202) 502-8659. A copy is
also available for inspection and reproduction at the address in item h
above.
m. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
n. Competing Preliminary Permit: Anyone desiring to file a
competing application for preliminary permit for a proposed project
must submit the competing application itself, or a notice of intent to
file such an application, to the Commission on or before the specified
comment date for the particular application (see 18 CFR 4.36).
Submission of a timely notice of intent allows an interested person to
file the competing preliminary permit application no later than 30 days
after the specified comment date for the particular application. A
competing preliminary permit application must conform with 18 CFR 4.30
and 4.36.
o. Competing Development Application: Any qualified development
applicant desiring to file a competing
[[Page 62472]]
development application must submit to the Commission, on or before a
specified comment date for the particular application, either a
competing development application or a notice of intent to file such an
application. Submission of a timely notice of intent to file a
development application allows an interested person to file the
competing application no later than 120 days after the specified
comment date for the particular application. A competing license
application must conform with 18 CFR 4.30 and 4.36.
p. Notice of Intent: A notice of intent must specify the exact
name, business address, and telephone number of the prospective
applicant, and must include an unequivocal statement of intent to
submit, if such an application may be filed, either a preliminary
permit application or a development application (specify which type of
application). A notice of intent must be served on the applicant(s)
named in this public notice.
q. Proposed Scope of Studies under Permit: A preliminary permit, if
issued, does not authorize construction. The term of the proposed
preliminary permit would be 36 months. The work proposed under the
preliminary permit would include economic analysis, preparation of
preliminary engineering plans, and a study of environmental impacts.
Based on the results of these studies, the Applicant would decide
whether to proceed with the preparation of a development application to
construct and operate the project.
r. Comments, Protests, or Motions to Intervene: Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214. In determining the appropriate action to take, the Commission
will consider all protests or other comments filed, but only those who
file a motion to intervene in accordance with the Commission's Rules
may become a party to the proceeding. Any comments, protests, or
motions to intervene must be received on or before the specified
comment date for the particular application.
Comments, protests and interventions may be filed electronically
via the Internet in lieu of paper. See 18 CFR 385.2001 (a)(1)(iii) and
the instructions on the Commission's Web site under ``e-filing'' link.
The Commission strongly encourages electronic filing.
s. Filing and Service of Responsive Documents: Any filings must
bear in all capital letters the title ``COMMENTS'', ``COMPETING
APPLICATION'', ``RECOMMENDATIONS FOR TERMS AND CONDITIONS'',
``PROTEST'', OR ``MOTION TO INTERVENE'', as applicable, and the Project
Number of the particular application to which the filing refers. Any of
the above-named documents must be filed by providing the original and
the number of copies provided by the Commission's regulations to: The
Secretary, Federal Energy Regulatory Commission, 888 First Street, NE.,
Washington, DC 20426. A copy of any motion to intervene must also be
served upon each representative of the Applicant specified in the
particular application.
t. Agency Comments: Federal, State, and local agencies are invited
to file comments on the described application. A copy of the
application may be obtained by agencies directly from the Applicant. If
an agency does not file comments within the time specified for filing
comments, it will be presumed to have no comments. One copy of an
agency's comments must also be sent to the Applicant's representatives.
Kimberly D. Bose,
Secretary.
[FR Doc. E7-21657 Filed 11-2-07; 8:45 am]
BILLING CODE 6717-01-P