Notice of Filings, 60340-60341 [E7-20903]

Download as PDF yshivers on PROD1PC62 with NOTICES 60340 Federal Register / Vol. 72, No. 205 / Wednesday, October 24, 2007 / Notices Applicants: National Grid USA. Description: Amendment to and Notice of Partial Withdrawal of Application for Authorization to Issue Securities Under Section 204 of the Federal Power Act, and Motion for Waiver of 15–Day Waiting Period Under Commission Rule 216 of National Grid USA. Filed Date: 10/15/2007. Accession Number: 20071015–5140. Comment Date: 5 p.m. Eastern Time on Monday, November 5, 2007. Take notice that the Commission received the following open access transmission tariff filings: Docket Numbers: OA07–90–001. Applicants: MidAmerican Energy Company. Description: Mid American Energy’s substitute tariff sheet to reflect the correct methodology for calculation of transmission reserve margin in its Open Access Transmission Tariff— Attachment C filed September 11, 2007. Filed Date: 10/16/2007. Accession Number: 20071016–5040. Comment Date: 5 p.m. Eastern Time on Tuesday, November 6, 2007. Any person desiring to intervene or to protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214) on or before 5 p.m. Eastern time on the specified comment date. It is not necessary to separately intervene again in a subdocket related to a compliance filing if you have previously intervened in the same docket. Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. In reference to filings initiating a new proceeding, interventions or protests submitted on or before the comment deadline need not be served on persons other than the Applicant. The Commission encourages electronic submission of protests and interventions in lieu of paper, using the FERC Online links at https:// www.ferc.gov. To facilitate electronic service, persons with Internet access who will eFile a document and/or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. Persons unable to file electronically should submit an original and 14 copies of the intervention or protest to the VerDate Aug<31>2005 15:33 Oct 23, 2007 Jkt 214001 Federal Energy Regulatory Commission, 888 First St. NE., Washington, DC 20426. The filings in the above proceedings are accessible in the Commission’s eLibrary system by clicking on the appropriate link in the above list. They are also available for review in the Commission’s Public Reference Room in Washington, DC. There is an eSubscription link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed dockets(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov. or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Nathaniel J. Davis, Sr., Acting Deputy Secretary. [FR Doc. E7–20902 Filed 10–23–07; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Notice of Filings October 18, 2007. Take notice that the Commission received the following exempt wholesale generator filings: Docket Numbers: EG08–8–000. Applicants: Plum Point Energy Associates, L.L.C. Description: Notice of Self Certification of Exempt Wholesale Generator Status of Plum Point Energy Associates, L.L.C. Filed Date: 10/17/2007. Accession Number: 20071017–5029. Comment Date: 5 p.m. Eastern Time on Wednesday, November 07, 2007. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER03–534–003. Applicants: Ingenco Wholesale Power, L.L.C. Description: Notice of Change in Status of Ingenco Wholesale Power, L.L.C. Filed Date: 10/17/2007. Accession Number: 20071017–5014. Comment Date: 5 p.m. Eastern Time on Wednesday, November 07, 2007. Docket Numbers: ER07–1318–001. Applicants: Wellsboro Electric Company. Description: Wellsboro Electric Co submits a Supplement to the Petition for Acceptance of Initial Tariff, Waivers and Blanket Authority. Filed Date: 10/17/2007. Accession Number: 20071018–0077. PO 00000 Frm 00031 Fmt 4703 Sfmt 4703 Comment Date: 5 p.m. Eastern Time on Wednesday, November 07, 2007. Docket Numbers: ER08–38–001. Applicants: Northern Renewable Energy (USA) Ltd. Description: Northern Renewable Energy (USA) Ltd submits Appendix A to its 10/10/07 submittal of an application. Filed Date: 10/16/2007. Accession Number: 20071018–0084. Comment Date: 5 p.m. Eastern Time on Tuesday, October 23, 2007. Docket Numbers: ER08–40–001. Applicants: PJM Interconnection, L.L.C. Description: PJM Interconnection LLC requests that the language in footnote 2 of the 10/11/07 transmittal letter be replaced. Filed Date: 10/16/2007. Accession Number: 20071018–0098. Comment Date: 5 p.m. Eastern Time on Tuesday, November 06, 2007. Docket Numbers: ER08–62–000. Applicants: Peetz Table Wind Energy, LLC. Description: Peetz Table Wind Energy, LLC submits a Jurisdictional Agreement with Logan Wind Energy, LLC. Filed Date: 10/16/2007. Accession Number: 20071018–0086. Comment Date: 5 p.m. Eastern Time on Tuesday, November 06, 2007. Docket Numbers: ER08–63–000. Applicants: Lincoln Generating Facility, LLC. Description: Lincoln Generating Facility, LLC submits a tariff pursuant to which it will provide up to 320 MW of black start capacity in the Commonwealth Edison Co. Filed Date: 10/16/2007. Accession Number: 20071018–0087. Comment Date: 5 p.m. Eastern Time on Tuesday, November 06, 2007. Docket Numbers: ER08–64–000. Applicants: California Independent System Operator C. Description: California Independent System Operator submits proposed amendment to the currently-effective ISO Tariff. Filed Date: 10/16/2007. Accession Number: 20071018–0085. Comment Date: 5 p.m. Eastern Time on Tuesday, November 06, 2007. Take notice that the Commission received the following electric securities filings: Docket Numbers: ES07–26–004. Applicants: Entergy Gulf States, Inc. Description: Entergy Gulf States Inc et al. submits additional information with respect to their request for relief under FPA. Filed Date: 10/16/2007. Accession Number: 20071018–0088. E:\FR\FM\24OCN1.SGM 24OCN1 yshivers on PROD1PC62 with NOTICES Federal Register / Vol. 72, No. 205 / Wednesday, October 24, 2007 / Notices Comment Date: 5 p.m. Eastern Time on Tuesday, October 23, 2007. Any person desiring to intervene or to protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214) on or before 5 p.m. Eastern time on the specified comment date. It is not necessary to separately intervene again in a subdocket related to a compliance filing if you have previously intervened in the same docket. Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. In reference to filings initiating a new proceeding, interventions or protests submitted on or before the comment deadline need not be served on persons other than the Applicant. The Commission encourages electronic submission of protests and interventions in lieu of paper, using the FERC Online links at https:// www.ferc.gov. To facilitate electronic service, persons with Internet access who will eFile a document and/or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. Persons unable to file electronically should submit an original and 14 copies of the intervention or protest to the Federal Energy Regulatory Commission, 888 First St., NE., Washington, DC 20426. The filings in the above proceedings are accessible in the Commission’s eLibrary system by clicking on the appropriate link in the above list. They are also available for review in the Commission’s Public Reference Room in Washington, DC. There is an eSubscription link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed dockets(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov. or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Nathaniel J. Davis, Acting Deputy Secretary. [FR Doc. E7–20903 Filed 10–23–07; 8:45 am] BILLING CODE 6717–01–P VerDate Aug<31>2005 15:33 Oct 23, 2007 Jkt 214001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. PF07–15–000] Algonquin Gas Transmission, LLC; Notice of Intent To Prepare an Environmental Impact Statement for the Proposed East to West Hubline Expansion Project, Request for Comments on Environmental Issues, and Notice of Public Scoping Meetings October 16, 2007. The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental impact statement (EIS) that will identify and address the environmental impacts that could result from the construction and operation of the East to West HubLine Expansion Project (E2W Project or Project). The E2W Project is proposed by Algonquin Gas Transmission, LLC (Algonquin), which is an indirect wholly owned subsidiary of Spectra Energy Corp. The Commission will use the EIS in its decision-making process to determine whether or not to authorize the Project. This notice describes the proposed Project facilities and explains the scoping process that will be used to gather input from the public and interested agencies on the Project. Your input will help determine the issues that need to be evaluated in the EIS. Please note that the scoping period for the Project will close on November 21, 2007. Comments on the Project may be submitted in written form or verbally. In lieu of or in addition to sending written comments, you are invited to attend the public scoping meetings that have been scheduled in the Project area. These meetings are scheduled for November 5, 2007 in Randolph, Massachusetts; November 7, 2007 in North Andover, Massachusetts; and November 8, 2007 in Norwich, Connecticut. Further instructions on how to submit comments and additional details of the public scoping meetings are provided in the Public Participation section of this notice. The FERC will be the lead federal agency for the preparation of the EIS and will prepare the document to satisfy the requirements of the National Environmental Policy Act (NEPA). The document will be used by the FERC to consider the environmental impacts that could result if it authorizes Algonquin’s Project by issuing a Certificate of Public Convenience and Necessity under section 7 of the Natural Gas Act. It is the FERC’s goal that other federal agencies PO 00000 Frm 00032 Fmt 4703 Sfmt 4703 60341 will participate in the environmental review process as cooperating agencies to satisfy their respective NEPA responsibilities. The Project must also undergo an environmental review pursuant to the Massachusetts Environmental Policy Act (MEPA). The Massachusetts Executive Office of Energy and Environmental Affairs (MEEA) is the lead state agency with responsibility for ensuring compliance with the MEPA regulations for interstate natural gas pipeline projects. The MEPA regulations allow use of a Special Review Procedure that would establish a coordinated review of the Project by the FERC and the MEEA. Establishment of a coordinated review would enable the NEPA EIS (plus an addendum document) to serve as the Environmental Impact Report (EIR) required by MEPA. It is anticipated that the FERC and the MEEA will conduct a coordinated NEPA/MEPA review of the E2W Project to the maximum extent feasible. The Massachusetts Energy Facility Siting Board (MEFSB) is an independent board that licenses major energy facilities in Massachusetts and is charged with ensuring a reliable energy supply for the Commonwealth with a minimum impact on the environment at the lowest possible cost. The MEFSB has no authority over the siting of interstate natural gas facilities; however, it represents the citizens of Massachusetts before the FERC on cases involving the construction of applicable energy infrastructure in Massachusetts. The two Massachusetts public scoping meetings announced in this notice will be joint scoping meetings with participation by the MEFSB. The Connecticut Siting Council (CSC) is an independent board that licenses major energy facilities in Connecticut. The CSC regulates facility siting to balance the need for adequate and reliable public services at the lowest reasonable cost to consumers with the need to protect the environment and ecology of the state. Similar to the MEFSB, the CSC has no authority over the siting of interstate natural gas facilities; however, it may become a party before the FERC on cases involving the construction of applicable energy infrastructure in Connecticut. The CSC will participate in the FERC’s Connecticut scoping meeting and will announce independent hearings at a later date. E:\FR\FM\24OCN1.SGM 24OCN1

Agencies

[Federal Register Volume 72, Number 205 (Wednesday, October 24, 2007)]
[Notices]
[Pages 60340-60341]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-20903]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission


Notice of Filings

October 18, 2007.
    Take notice that the Commission received the following exempt 
wholesale generator filings:
    Docket Numbers: EG08-8-000.
    Applicants: Plum Point Energy Associates, L.L.C.
    Description: Notice of Self Certification of Exempt Wholesale 
Generator Status of Plum Point Energy Associates, L.L.C.
    Filed Date: 10/17/2007.
    Accession Number: 20071017-5029.
    Comment Date: 5 p.m. Eastern Time on Wednesday, November 07, 2007.
    Take notice that the Commission received the following electric 
rate filings:
    Docket Numbers: ER03-534-003.
    Applicants: Ingenco Wholesale Power, L.L.C.
    Description: Notice of Change in Status of Ingenco Wholesale Power, 
L.L.C.
    Filed Date: 10/17/2007.
    Accession Number: 20071017-5014.
    Comment Date: 5 p.m. Eastern Time on Wednesday, November 07, 2007.

    Docket Numbers: ER07-1318-001.
    Applicants: Wellsboro Electric Company.
    Description: Wellsboro Electric Co submits a Supplement to the 
Petition for Acceptance of Initial Tariff, Waivers and Blanket 
Authority.
    Filed Date: 10/17/2007.
    Accession Number: 20071018-0077.
    Comment Date: 5 p.m. Eastern Time on Wednesday, November 07, 2007.

    Docket Numbers: ER08-38-001.
    Applicants: Northern Renewable Energy (USA) Ltd.
    Description: Northern Renewable Energy (USA) Ltd submits Appendix A 
to its 10/10/07 submittal of an application.
    Filed Date: 10/16/2007.
    Accession Number: 20071018-0084.
    Comment Date: 5 p.m. Eastern Time on Tuesday, October 23, 2007.

    Docket Numbers: ER08-40-001.
    Applicants: PJM Interconnection, L.L.C.
    Description: PJM Interconnection LLC requests that the language in 
footnote 2 of the 10/11/07 transmittal letter be replaced.
    Filed Date: 10/16/2007.
    Accession Number: 20071018-0098.
    Comment Date: 5 p.m. Eastern Time on Tuesday, November 06, 2007.

    Docket Numbers: ER08-62-000.
    Applicants: Peetz Table Wind Energy, LLC.
    Description: Peetz Table Wind Energy, LLC submits a Jurisdictional 
Agreement with Logan Wind Energy, LLC.
    Filed Date: 10/16/2007.
    Accession Number: 20071018-0086.
    Comment Date: 5 p.m. Eastern Time on Tuesday, November 06, 2007.

    Docket Numbers: ER08-63-000.
    Applicants: Lincoln Generating Facility, LLC.
    Description: Lincoln Generating Facility, LLC submits a tariff 
pursuant to which it will provide up to 320 MW of black start capacity 
in the Commonwealth Edison Co.
    Filed Date: 10/16/2007.
    Accession Number: 20071018-0087.
    Comment Date: 5 p.m. Eastern Time on Tuesday, November 06, 2007.

    Docket Numbers: ER08-64-000.
    Applicants: California Independent System Operator C.
    Description: California Independent System Operator submits 
proposed amendment to the currently-effective ISO Tariff.
    Filed Date: 10/16/2007.
    Accession Number: 20071018-0085.
    Comment Date: 5 p.m. Eastern Time on Tuesday, November 06, 2007.
    Take notice that the Commission received the following electric 
securities filings:
    Docket Numbers: ES07-26-004.
    Applicants: Entergy Gulf States, Inc.
    Description: Entergy Gulf States Inc et al. submits additional 
information with respect to their request for relief under FPA.
    Filed Date: 10/16/2007.
    Accession Number: 20071018-0088.

[[Page 60341]]

    Comment Date: 5 p.m. Eastern Time on Tuesday, October 23, 2007.
    Any person desiring to intervene or to protest in any of the above 
proceedings must file in accordance with Rules 211 and 214 of the 
Commission's Rules of Practice and Procedure (18 CFR 385.211 and 
385.214) on or before 5 p.m. Eastern time on the specified comment 
date. It is not necessary to separately intervene again in a subdocket 
related to a compliance filing if you have previously intervened in the 
same docket. Protests will be considered by the Commission in 
determining the appropriate action to be taken, but will not serve to 
make protestants parties to the proceeding. Anyone filing a motion to 
intervene or protest must serve a copy of that document on the 
Applicant. In reference to filings initiating a new proceeding, 
interventions or protests submitted on or before the comment deadline 
need not be served on persons other than the Applicant.
    The Commission encourages electronic submission of protests and 
interventions in lieu of paper, using the FERC Online links at https://
www.ferc.gov. To facilitate electronic service, persons with Internet 
access who will eFile a document and/or be listed as a contact for an 
intervenor must create and validate an eRegistration account using the 
eRegistration link. Select the eFiling link to log on and submit the 
intervention or protests.
    Persons unable to file electronically should submit an original and 
14 copies of the intervention or protest to the Federal Energy 
Regulatory Commission, 888 First St., NE., Washington, DC 20426.
    The filings in the above proceedings are accessible in the 
Commission's eLibrary system by clicking on the appropriate link in the 
above list. They are also available for review in the Commission's 
Public Reference Room in Washington, DC.
    There is an eSubscription link on the Web site that enables 
subscribers to receive e-mail notification when a document is added to 
a subscribed dockets(s). For assistance with any FERC Online service, 
please e-mail FERCOnlineSupport@ferc.gov. or call (866) 208-3676 (toll 
free). For TTY, call (202) 502-8659.

Nathaniel J. Davis,
Acting Deputy Secretary.
 [FR Doc. E7-20903 Filed 10-23-07; 8:45 am]