Public Utility District No. 1 of Chelan County; Notice of Application for Amendment of License and Soliciting Comments, Motions To Intervene, and Protests, 58654 [E7-20284]
Download as PDF
58654
Federal Register / Vol. 72, No. 199 / Tuesday, October 16, 2007 / Notices
Date and time
Location
Tuesday, November 6, 2007, 6:30 p.m. to 10
p.m. (PST).
Wednesday, November 7, 2007, 9 a.m. to 12
p.m. (PST).
Wednesday, November 7, 2007, 6:30 p.m. to
10 p.m. (PST).
Thursday, November 8, 2007, 6:30 p.m. to 10
p.m. (PST).
J.A. Wendt Elementary School, 265 S. 3rd St., Cathlamet, Washington 98612, Telephone:
360–795–3261.
Cowlitz County Expo and Conference Center, 1900 7th Ave., Longview, Washington 98632,
Telephone: 360–577–3121.
Cowlitz County Expo and Conference Center, 1900 7th Ave., Longview, Washington 98632,
Telephone: 360–577–3121.
Hilda Lahti Elementary School, 42535 Old Highway 30, Astoria, Oregon 97103, Telephone:
503–458–6162.
These events are posted on the
Commission’s calendar located at https://
www.ferc.gov/EventCalendar/
EventsList.aspx along with other related
information. For additional information,
please contact the Commission’s Office
of External Affairs at 1–866–208–FERC.
Kimberly D. Bose,
Secretary.
[FR Doc. E7–20296 Filed 10–15–07; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 943–102]
Public Utility District No. 1 of Chelan
County; Notice of Application for
Amendment of License and Soliciting
Comments, Motions To Intervene, and
Protests
mmaher on PROD1PC70 with NOTICES
October 4, 2007.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Application Type: Non-Project Use
of Project Lands and Waters.
b. Project No: 943–102.
c. Date Filed: September 14, 2007.
d. Applicant: Public Utility District
No. 1 of Chelan County.
e. Name of Project: Rock Island
Hydroelectric Project.
f. Location: The project is located on
the Columbia River in Chelan County,
Washington. The project does not
occupy any Federal or tribal lands.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Michelle Smith,
License and Natural Resource
Compliance Manager, Public Utility
District No. 1 of Chelan County, P.O.
Box 1231, Wenatchee, WA 98807–1231.
Phone: (888) 663–8121, Ext. 4180.
i. FERC Contact: Any questions on
this notice should be addressed to Jon
Cofrancesco at (202) 502–8951 or by
e-mail: jon.cofrancesco@ferc.gov.
j. Deadline for filing comments and/
or motions: October 26, 2007.
VerDate Aug<31>2005
04:12 Oct 16, 2007
Jkt 214001
All documents (original and eight
copies) should be filed with: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person whose name appears on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency. A copy of any
motion to intervene must also be served
upon each representative of the
Applicant specified in the particular
application.
k. Description of the Application: The
Public Utility District No. 1 of Chelan
County, Washington, licensee of the
Rock Island Hydroelectric Project, has
filed an application seeking
authorization from the Federal Energy
Regulatory Commission to grant a
permit to Dr. Thomas Hurst for a 12-slip
community dock for a 13 lot, 20-acre
residential subdivision located on
upland property adjacent to the project.
The proposed 1,444 square-foot floating
dock includes a ramp, a main float, and
one T-section with six fingers on each
side; extends 130 feet from the ordinary
high water mark; and is located
approximately four miles upriver from
Rock Island dam in Chelan County,
Washington.
l. Location of the Application: This
filing is available for review at the
Commission or may be viewed on the
Commission’s Web site at https://
www.ferc.gov, using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. You may
also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
e-mail of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or toll-
PO 00000
Frm 00024
Fmt 4703
Sfmt 4703
free at (866) 208–3676, or for TTY,
contact (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item (h)
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene—Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
o. Any filings must bear in all capital
letters the title ‘‘COMMENTS’’,
‘‘PROTEST’’, OR ‘‘MOTION TO
INTERVENE’’, as applicable, and the
Project Number of the particular
application to which the filing refers.
p. Agency Comments—Federal, state,
and local agencies are invited to file
comments on the application. A copy of
the application may be obtained by
agencies directly from the Applicant. If
an agency does not file comments
within the time specified for filing
comments, it will be presumed to have
no comments. One copy of an agency’s
comments must also be sent to the
Applicant’s representatives.
q. Comments, protests and
interventions may be filed electronically
via the Internet in lieu of paper. See, 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site at https://www.ferc.gov under the
‘‘e-Filing’’ link.
Kimberly D. Bose,
Secretary.
[FR Doc. E7–20284 Filed 10–15–07; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\16OCN1.SGM
16OCN1
Agencies
[Federal Register Volume 72, Number 199 (Tuesday, October 16, 2007)]
[Notices]
[Page 58654]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-20284]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 943-102]
Public Utility District No. 1 of Chelan County; Notice of
Application for Amendment of License and Soliciting Comments, Motions
To Intervene, and Protests
October 4, 2007.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Application Type: Non-Project Use of Project Lands and Waters.
b. Project No: 943-102.
c. Date Filed: September 14, 2007.
d. Applicant: Public Utility District No. 1 of Chelan County.
e. Name of Project: Rock Island Hydroelectric Project.
f. Location: The project is located on the Columbia River in Chelan
County, Washington. The project does not occupy any Federal or tribal
lands.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Michelle Smith, License and Natural Resource
Compliance Manager, Public Utility District No. 1 of Chelan County,
P.O. Box 1231, Wenatchee, WA 98807-1231. Phone: (888) 663-8121, Ext.
4180.
i. FERC Contact: Any questions on this notice should be addressed
to Jon Cofrancesco at (202) 502-8951 or by e-mail:
jon.cofrancesco@ferc.gov.
j. Deadline for filing comments and/or motions: October 26, 2007.
All documents (original and eight copies) should be filed with:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
The Commission's Rules of Practice and Procedure require all
intervenors filing documents with the Commission to serve a copy of
that document on each person whose name appears on the official service
list for the project. Further, if an intervenor files comments or
documents with the Commission relating to the merits of an issue that
may affect the responsibilities of a particular resource agency, they
must also serve a copy of the document on that resource agency. A copy
of any motion to intervene must also be served upon each representative
of the Applicant specified in the particular application.
k. Description of the Application: The Public Utility District No.
1 of Chelan County, Washington, licensee of the Rock Island
Hydroelectric Project, has filed an application seeking authorization
from the Federal Energy Regulatory Commission to grant a permit to Dr.
Thomas Hurst for a 12-slip community dock for a 13 lot, 20-acre
residential subdivision located on upland property adjacent to the
project. The proposed 1,444 square-foot floating dock includes a ramp,
a main float, and one T-section with six fingers on each side; extends
130 feet from the ordinary high water mark; and is located
approximately four miles upriver from Rock Island dam in Chelan County,
Washington.
l. Location of the Application: This filing is available for review
at the Commission or may be viewed on the Commission's Web site at
https://www.ferc.gov, using the ``eLibrary'' link. Enter the docket
number excluding the last three digits in the docket number field to
access the document. You may also register online at https://
www.ferc.gov/docs-filing/esubscription.asp to be notified via e-mail of
new filings and issuances related to this or other pending projects.
For assistance, contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll-free at (866) 208-3676, or for TTY,
contact (202) 502-8659. A copy is also available for inspection and
reproduction at the address in item (h) above.
m. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
n. Comments, Protests, or Motions to Intervene--Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214. In determining the appropriate action to take, the Commission
will consider all protests or other comments filed, but only those who
file a motion to intervene in accordance with the Commission's Rules
may become a party to the proceeding. Any comments, protests, or
motions to intervene must be received on or before the specified
comment date for the particular application.
o. Any filings must bear in all capital letters the title
``COMMENTS'', ``PROTEST'', OR ``MOTION TO INTERVENE'', as applicable,
and the Project Number of the particular application to which the
filing refers.
p. Agency Comments--Federal, state, and local agencies are invited
to file comments on the application. A copy of the application may be
obtained by agencies directly from the Applicant. If an agency does not
file comments within the time specified for filing comments, it will be
presumed to have no comments. One copy of an agency's comments must
also be sent to the Applicant's representatives.
q. Comments, protests and interventions may be filed electronically
via the Internet in lieu of paper. See, 18 CFR 385.2001(a)(1)(iii) and
the instructions on the Commission's Web site at https://www.ferc.gov
under the ``e-Filing'' link.
Kimberly D. Bose,
Secretary.
[FR Doc. E7-20284 Filed 10-15-07; 8:45 am]