Limited Work Authorizations for Nuclear Power Plants, 57416-57447 [E7-19312]
Download as PDF
57416
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
NUCLEAR REGULATORY
COMMISSION
10 CFR Parts 2, 50, 51, 52, and 100
RIN 3150–AI05
Limited Work Authorizations for
Nuclear Power Plants
Nuclear Regulatory
Commission.
ACTION: Final rule.
AGENCY:
rwilkins on PROD1PC63 with RULES_2
SUMMARY: The Nuclear Regulatory
Commission (NRC) is amending its
regulations applicable to limited work
authorizations (LWAs), which allow
certain construction activities on
production and utilization facilities to
commence before a construction permit
or combined license is issued. This final
rule modifies the scope of activities that
are considered construction for which a
construction permit, combined license,
or LWA is necessary, specifies the scope
of construction activities that may be
performed under an LWA, and changes
the review and approval process for
LWA requests. The NRC is adopting
these changes to enhance the efficiency
of its licensing and approval process for
production and utilization facilities,
including new nuclear power reactors.
DATES: The effective date is November 8,
2007.
FOR FURTHER INFORMATION CONTACT:
Nanette V. Gilles, Office of New
Reactors, U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001; telephone 301–415–1180; e-mail:
NVG@nrc.gov or Geary Mizuno, Office
of the General Counsel, U.S. Nuclear
Regulatory Commission, Washington,
DC 20555–0001; telephone 301–415–
1639; e-mail: GSM@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Background
A. Development of the Supplemental
Proposed LWA Rule
1. 10 CFR Part 52 Rulemaking
2. Industry Stakeholder Comments Seeking
Changes to LWA Process
B. Publication of Supplemental Proposed
LWA Rule and External Stakeholder
Interactions During the Public Comment
Period
C. Description of Supplemental Proposed
LWA Rule
II. Public Comments
A. Overview of Public Comments
B. NRC Response to Public Comments
1. Commission Questions
2. LWA Process
3. SSCs Within Scope of ‘‘Construction’’
4. Excavation
5. Compliance With NEPA
6. LWA Application Process
7. Other Topics
III. Discussion
A. History of the NRC’s Concept of
Construction and the LWA
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
B. NRC’s Concept of Construction and the
AEA
C. NRC’s LWA Rule Complies With NEPA
1. NRC’s Concept of Construction Is
Consistent With the Legal Effect of NEPA
2. NRC’s Concept of the ‘‘Major Federal
Action’’ Is Consistent With NEPA Law
3. NRC’s Phased Approval Approach Is Not
Illegal Segmentation Under NEPA
D. Consideration of Activities as
‘‘Construction.’’
1. Driving of Piles
2. Excavation
3. Temporary Structures and Activities in
the Excavation
4. Construction SSCs
E. Phased Application and Approval
Process
F. EIS Prepared, but Facility Construction
Was Not Completed
G. Commission Action on PRM–50–82
IV. Section-by-Section Analysis
V. Availability of Documents
VI. Agreement State Compatibility
VII. Voluntary Consensus Standards
VIII. Environmental Impact—Categorical
Exclusion
IX. Paperwork Reduction Act Statement
X. Regulatory Analysis
XI. Regulatory Flexibility Act Certification
XII. Backfit Analysis
XIII. Congressional Review Act
I. Background
A. Development of the Supplemental
Proposed LWA Rule
1. 10 CFR Part 52 Rulemaking
This LWA rulemaking originated as a
supplement to an NRC rulemaking effort
to revise 10 CFR part 52. The NRC
issued 10 CFR part 52 on April 18, 1989
(54 FR 15372), to reform its licensing
process for future nuclear power plants.
10 CFR part 52 added alternative
licensing processes in 10 CFR part 52
for early site permits (ESPs), standard
design certifications, and combined
licenses. These were additions to the
two-step licensing process that already
existed in 10 CFR part 50. The processes
in 10 CFR part 52 allow for resolving
safety and environmental issues early in
the licensing proceedings and were
intended to enhance the safety and
reliability of nuclear power plants
through standardization.
The NRC had planned to update 10
CFR part 52 after using the standard
design certification process. The
proposed rulemaking action began with
the issuance of SECY–98–282, ‘‘Part 52
Rulemaking Plan,’’ on December 4,
1998. The Commission issued a staff
requirements memorandum (SRM) on
January 14, 1999 (SRM on SECY–98–
282), approving the NRC staff’s plan for
revising 10 CFR part 52. Subsequently,
the NRC obtained considerable
stakeholder comments on its planned
action, conducted three public meetings
on the proposed rulemaking, and twice
PO 00000
Frm 00002
Fmt 4701
Sfmt 4700
posted draft rule language on the NRC’s
rulemaking Web site before issuance of
the initial proposed rule on July 3, 2003
(68 FR 40026). However, a number of
factors, including the experience gained
in using the 10 CFR part 52 early site
permit process, led the NRC to question
whether the July 2003 proposed rule
would meet the NRC’s objective of
improving the effectiveness of its
processes for licensing future nuclear
power plants (March 13, 2006; 71 FR
12782). As a result, the NRC decided
that a substantial rewrite and expansion
of the original proposed rulemaking was
desirable so that the agency may more
effectively and efficiently implement
the licensing and approval processes for
future nuclear power plants under part
52. Accordingly, the Commission
decided to revise the July 2003
proposed rule and published the revised
proposed rule for public comment on
March 13, 2006 (71 FR 12782). The
public comment period on the March
2006 proposed rule ended on May 30,
2006.
2. Industry Stakeholder Comments
Seeking Changes to LWA Process
In a May 25, 2006 comment letter,1
the Nuclear Energy Institute (NEI)
suggested modifications to the NRC’s
LWA process including: (1) That nonsafety-related ‘‘LWA–1’’ activities,
currently reflected in §§ 50.10(c) and
50.10(e)(1), be allowed to proceed
without prior authorization from the
NRC, and (2) that the approval process
for safety-related ‘‘LWA–2’’ activities be
accelerated. NEI’s comment also stated
that the current definition of
construction in § 50.10(b) reflects the
correct interpretation of the
Commission’s licensing authority under
the Atomic Energy Act of 1954, as
amended.
NEI supported its suggested changes
to the LWA process, stating that the
business environment requires that new
plant applicants seek to minimize the
time interval between a decision to
proceed with a combined license
application and the start of commercial
operation. To achieve this goal, NEI
stated that non-safety-related ‘‘LWA–1’’
activities would need to be initiated up
to 2 years before the activities currently
defined as ‘‘construction’’ in § 50.10(b).
NEI believes that the current LWA
1 See Letter from Adrian P. Heymer, Nuclear
Energy Institute, to Annette L. Vietti-Cook,
Secretary, U.S. Nuclear Regulatory Commission,
Pre-Licensing Construction Activity and Limited
Work Authorization Issues relating to NRC
Proposed Rule, ‘‘Licenses, Certifications and
Approvals for Nuclear Power Plants,’’ 71 FR 12782
(March 13, 2006) (RIN 3150–AG24) (May 25, 2006)
(ADAMS ML061510471).
E:\FR\FM\09OCR2.SGM
09OCR2
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
approval process would constrain the
industry’s ability to use modern
construction practices and needlessly
add 18 months to estimated
construction schedules for new plants
that did not reference an early site
permit with LWA authority. NEI’s
comment letter stated that ‘‘[t]o the
extent the NRC determines that these
LWA issues cannot be addressed in the
current rulemaking, we ask that the
Commission initiate an expedited
rulemaking.’’
The NRC determined that the changes
suggested in the NEI letter could not be
incorporated into the final part 52 rule
without re-noticing, but that the NEI
letter met the sufficiency requirements
for a petition for rulemaking as
described in 10 CFR 2.802(c). Therefore,
the NRC elected to treat the letter as a
petition for rulemaking (PRM–50–82).
rwilkins on PROD1PC63 with RULES_2
B. Publication of Supplemental
Proposed LWA Rule and External
Stakeholder Interactions During the
Public Comment Period
The supplemental proposed LWA rule
was published in the Federal Register
on October 17, 2006 (71 FR 61330) for
a 30-day public comment period which
ended November 16, 2006. During the
public comment period, the NRC held a
public meeting on November 1, 2006, to
answer external stakeholder questions
about the supplemental proposed LWA
rule. A transcript of the public meeting
was made (Agencywide Documents
Access and Management System
(ADAMS) Accession No.
ML063190396), as referenced in the
meeting summary (ADAMS Accession
No. ML062970517).
In addition, the NRC informally
contacted several Federal agencies that
traditionally have been interested in
environmental impacts statements
(EISs) prepared by the NRC before the
issuance of LWAs and construction
permits, for the purpose of seeking their
comments on the supplemental
proposed LWA rule. These Federal
agencies were the Council on
Environmental Quality (CEQ), the U.S.
Environmental Protection Agency
(EPA), the Federal Energy Regulatory
Commission (FERC), and the U.S.
Department of the Interior, Fish, and
Wildlife Service (FWS).
Finally, the Commission held a public
meeting on November 9, 2006, on the
overall part 52 rulemaking, at which
time industry stakeholders presented
additional information on the
supplemental proposed LWA rule.
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
C. Description of Supplemental
Proposed LWA Rule
The supplemental proposed LWA rule
would narrow the scope of activities
requiring permission from the NRC in
the form of an LWA by eliminating the
concept of ‘‘commencement of
construction’’ currently described in
§ 50.10(c) and the authorization
described in § 50.10(e)(1). Instead,
under the supplemental proposed rule,
NRC authorization would be required
only before undertaking activities that
have a reasonable nexus to radiological
health and safety and/or common
defense and security (i.e., excavation,
subsurface preparation, installation of
the foundation, and on-site, in-place
fabrication, erection, integration or
testing, for any structure, system, or
component of a facility required by the
Commission’s rules and regulations to
be described in the site safety analysis
report or preliminary or final safety
analysis report). While the proposed
redefinition of ‘‘construction’’ would
result in fewer activities requiring NRC
permission in the form of an LWA, it
also would redefine certain activities
(such as the driving of piles) that are
currently excluded from the regulatory
definition of construction given in
§ 50.10(b), as construction requiring an
LWA.
Further, the supplemental proposed
LWA rule provided an optional, phased
application and approval procedure for
construction permit and combined
license applicants to obtain LWAs. The
supplemental proposed rule provided
for an environmental review and
approval process for LWA requests that
would allow the NRC to grant an
applicant permission to engage in LWA
activities after completion of an EIS
addressing those activities, but before
completion of the comprehensive EIS
addressing the underlying request for a
construction permit or combined
license. The supplemental proposed
rule also delineated the environmental
review required in situations where the
LWA activities are to be conducted at
sites for which the Commission has
previously prepared an EIS for the
construction and operation of a nuclear
power plant, and for which a
construction permit was issued, but
construction of the plant was never
completed.
II. Public Comments
A. Overview of Public Comments
The NRC received 13 public
comments 2 on the supplemental
2 A public comment dated November 7, 2006,
from Westinghouse Electric Company LLC, on the
PO 00000
Frm 00003
Fmt 4701
Sfmt 4700
57417
proposed rule. Ten comments were from
external industry stakeholders,
consisting of NEI and 7 nuclear power
plant licensees—including the 3
applicants for ESPs whose applications
are currently pending before the NRC,
and 2 companies who have applied (or
are expected to apply) for standard
design certifications (GE Nuclear and
Areva NP). One commenter, Dianne
Curran, submitted a comment on behalf
of Public Citizen, a consumer advocacy
organization, and the Nuclear
Information and Resource Service
(NIRS), an information and networking
organization for organizations
concerned about nuclear issues and
energy sustainability. One comment was
received from the EPA, and one
comment was received from an NRC
staff individual.
NEI supported the general approach
and objective of the supplemental
proposed rule, but raised three key
issues on the supplemental proposed
rule: (1) Inclusion of excavation in the
definition of ‘‘construction;’’ (2)
Designation of structures, systems, and
components (SSCs) ‘‘required to be
described’’ in the standard safety
analysis report or final safety analysis
report (FSAR) as a key element of the
definition of ‘‘construction;’’ and (3)
Limiting submittal of LWA applications
up to 12 months in advance of a
combined license application. NEI also
proposed a number of changes to the
supplemental proposed rule to address
three less-significant areas of concern:
(1) An LWA applicant’s reliance on an
earlier EIS for an unconstructed facility;
(2) LWA applicant’s ability to take
advantage of the provisions of
§ 2.101(a)(9) for an accelerated hearing
schedule when submitting an LWA
application in advance of a combined
license application; and (3) The need for
‘‘grandfathering’’ of current ESP
applicants. Finally, NEI suggested that
§ 2.101(a)(5) be modified from the
March 2006 proposed rule to allow one
part of a combined license application
to precede or follow the other part of the
application by no more than 12 months.
The other industry commenters,
including GE Nuclear and Areva NP,
generally supported the NEI comments,
and in some cases provided additional
discussion in support of one or more of
NEI’s specific comments.
Public Citizen and NIRS opposed
granting of an LWA in advance of
issuance of a construction permit or
combined license, in general because
main part 52 rulemaking, was erroneously
designated as comment no. 1 on the supplemental
proposed LWA rule. This number was later
assigned to a comment filed by Diane Curran on
behalf of Public Citizen and the NIRS.
E:\FR\FM\09OCR2.SGM
09OCR2
57418
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
these commenters perceived the process
as introducing additional complexity to
the licensing process, and increasing the
cost to individuals who wish to
participate in the licensing process.
These organizations supported the
NRC’s proposal to include excavation
and the driving of piles in the definition
of construction.
The EPA indicated that it had no
objections to the supplemental proposed
LWA rule, stating that the supplemental
rule would ‘‘enhance the efficiency of
the NRC’s LWA approval process, while
maintaining appropriate consideration
of environmental effects pursuant to
NEPA [National Environmental Policy
Act of 1969, as amended].’’ In addition,
NRC was advised by telephone that CEQ
had no objection to the supplemental
proposed LWA rule, and therefore
would not submit a written comment on
the rule.
The NRC staff individual provided
eight numbered comments on the
supplemental proposed LWA rule. The
commenter focused on compliance with
the NEPA and the potential adverse
effect of the supplemental proposed rule
on the NRC staff’s resources.
rwilkins on PROD1PC63 with RULES_2
B. NRC Response to Public Comments
The NRC has carefully considered the
stakeholder comments, and is adopting
a final LWA rule which differs in some
respects from the supplemental
proposed LWA rule. The final rule is
described and discussed in more detail
in Sections III. Discussion, and IV.
Section-by-Section Analysis of this
document.
The NRC is adopting the LWA rule as
a separate final rule, rather than
incorporating its provisions into the
final part 52 rule. Incorporating the
provisions of the final LWA rule into
the final part 52 rulemaking would have
resulted in a delay in publication of the
final part 52 rule, because of the
additional time needed for NRC
consideration and resolution of the
substantial issues raised in the public
comments on the supplemental
proposed LWA rule. Accordingly, the
NRC has adopted the final part 52
rulemaking in a separate action, in
advance of this final LWA rule.
1. Commission Questions
In the statement of considerations
(SOC) for the supplementary proposed
LWA rule, the Commission posed three
questions, as follows (October 17, 2006;
71 FR 61340, second column):
As explained above, this supplemental
proposed rule would impact the types of
activities that could be undertaken without
prior approval from the NRC, with NRC
approval in the form of an LWA, and with
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
NRC approval in the form of a construction
permit or combined license. Therefore, in
addition to the general invitation to submit
comments on the proposed rule, the NRC
also requests comments on the following
questions:
1. What types of activities should be
permitted without prior NRC approval?
2. What types of activities should be
permitted under an LWA?
3. What types of activities should only be
permitted after issuance of a construction
permit or combined license?
Only one commenter provided
separate responses to these three
Commission questions; but the
responses were simply an abbreviated
version of the comments. The remaining
commenters addressed the issues raised
in these questions in the course of the
commenters’ discussion on the
supplementary proposed LWA rule.
Accordingly, the NRC is not providing
a separate discussion of these questions
and commenters’ responses. Instead, the
NRC is responding to these issues in the
NRC’s responses to specific comments.
2. LWA Process
Comment: The Commission should
adopt the LWA final rule as a necessary
improvement to the existing LWA
process. (NEI, Dominion Nuclear North
Anna, Duke Energy, Florida Power and
Light, Progress Energy, Southern
Company, Unistar, Areva, and GE
Nuclear)
NRC Response: The NRC agrees with
the commenters that the former NRC
provisions on LWAs should be amended
to improve the LWA process.
Comment: The Commission should
not adopt regulations that allow
approval of LWA activities in advance
of the issuance of a construction permit
or combined license. Allowing LWA
activities before a plant is licensed
would confirm to the public that the
licensing process is a sham. The LWA
process represents a further
segmentation of the licensing process,
which will add complexity to the
licensing process, and result in further
disenfranchisement of the public.
(Public Citizen/NIRS 1)
NRC Response: The NRC disagrees
with these commenters. The
commenters’ position fails to recognize
that the LWA process has been used by
the agency for over 30 years, and
therefore the proposed changes to the
LWA process would not add to
complexity, or otherwise represent
further segmentation. The agency’s rules
include several longstanding
requirements directed at avoiding NEPA
segmentation. These requirements are
retained in their essential form in the
final LWA rulemaking.
PO 00000
Frm 00004
Fmt 4701
Sfmt 4700
The NRC does not believe that the
final LWA rule adds any further
complexity to the licensing process, or
otherwise results in further
‘‘disenfranchisement’’ of the public. As
stated above, the NRC’s regulatory
regime already includes the LWA
process, and the rule does not modify or
change the public’s ability to participate
in the licensing process. Indeed, rather
than ‘‘disenfranchising’’ the public, the
LWA rule may have the effect of
enhancing the ability of external
stakeholders to participate in a hearing
to resolve their issues with respect to a
particular nuclear power plant. Because
of resource limitations, many public
stakeholders have expressed their
concern that, because of the broad range
of issues addressed by the NRC at each
stage of licensing, it is difficult for them
to seek resolution in an NRC hearing for
the full range of issues that they are
interested in. For these stakeholders, the
LWA process—by separating out a
defined set of issues to be resolved in
advance of the underlying combined
license or construction permit
proceeding—allows public stakeholders
to focus their resources on the relevant
issues in an LWA hearing. The
‘‘complexity’’ of the process provides an
orderly sequencing of the overall set of
issues that must be resolved, without
introducing unlawful segmentation. The
NRC believes that if these public
stakeholders consider the revised
process in this light, they should
conclude that the LWA process
enhances, rather than detracts from,
participation in the licensing process by
interested members of the public who
are resource-limited.
The NRC does not believe that the
NRC’s proposed redefinition of
‘‘construction’’ constitutes unlawful
‘‘segmentation’’ which results in noncompliance with NEPA. Segmentation,
as discussed elsewhere in this SOC,
embraces the situation where a Federal
agency divides what would otherwise
be regarded as a single, integrated
Federal action into separate, smaller
Federal actions, for the purpose of
avoiding compliance with NEPA, or
otherwise minimizing the apparent
impact of the single, integrated Federal
action. The NRC’s redefinition of
construction is not motivated by a
desire to avoid compliance with NEPA,
nor will it result in a single Federal
action being divided into smaller,
sequential Federal actions. Rather, the
NRC’s redefinition reflects its
reconsideration of the proper regulatory
jurisdiction of the agency, and properly
divides what was considered a single
Federal action into private action for
E:\FR\FM\09OCR2.SGM
09OCR2
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
which the NRC has no statutory basis
for regulation, and the Federal action
(licensing of construction activities with
a reasonable nexus to radiological
health and safety or common defense
and security, for which no other
regulatory approach is acceptable)
which will require compliance with
NEPA.
rwilkins on PROD1PC63 with RULES_2
3. SSCs Within Scope of ‘‘Construction’’
Comment: The scope of SSCs that
must be described in the FSAR is not
always clear, even under the words of
existing NRC regulations (e.g., 10 CFR
50.34(b)(2)(i)), which requires
discussion of certain systems ‘‘insofar as
they are pertinent.’’ (Areva 1, 2)
NRC Response: The NRC agrees, in
part, with these comments and has
revised the scope of SSCs that fall
within the definition of construction to
clearly identify the SSCs that have a
reasonable nexus to radiological health
and safety, or the common defense and
security.
Comment: The NRC’s description of
activities constituting ‘‘construction,’’
which require a combined license or
construction permit (October 17, 2006;
71 FR 61337), should be modified to
refer to the ‘‘installation or integration
of that structure, system, or component
into its final plant location and
elevation * * *.’’ (Progress Energy 4)
NRC Response: The NRC agrees in
part with the commenter, and the
corresponding language of this SOC has
been modified to state ‘‘into its final
plant location would require * * *.’’
4. Excavation
Comment: It is not necessary to define
construction as including excavation of
portions of the nuclear power plant
facility having a ‘‘reasonable nexus to
radiological health and safety.’’
Problems identified during excavation
should be identified as part of the site
characterization and investigation
required for preparing a combined
license or construction permit. NRC
Regulatory Guide (RG) 1.165,
‘‘Identification and Characterization of
Seismic Sources and Determination of
Safe-Shutdown Earthquake Ground
Motion,’’ was updated in 1997 to
provide that combined license (COL)
applicants’ FSARs should include a
commitment to geologically map all
excavations and notify the NRC when
excavations are open for inspection. For
safety-related SSCs, these excavations
and characterization/investigation
activities would be conducted under the
applicant’s quality assurance (QA)
program. This could result in relocation
of such SSCs. This provides a better
process for ensuring safety and would
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
better support an effective licensing
process. In addition, NRC will be
involved in pre-application activities
and may elect to conduct oversight of
any activity involving site
characterization and site preparation.
The examples cited by the NRC in the
public meeting as a basis for including
excavation within the definition of
‘‘construction’’ did not involve
questions about the safety of the
excavation activities themselves, but
rather the conditions that were
identified as the result of excavation. In
these cases, the commitments to
geologic mapping and notification of the
NRC are sufficient to meet the NRC’s
regulatory interests. Accordingly,
§§ 50.10(b) and 51.4 should be revised
in the final rule to exclude excavation
from the definition of construction,
provided that the entity conducting
excavation geologically maps the
excavations and the NRC staff is notified
when the excavations are opened for
inspection. (NEI 1; GE Nuclear; Progress
Energy 1)
NRC Response: The NRC agrees, in
part, with this comment and has deleted
excavation from the definition of
construction in 10 CFR 50.10(a). A
construction permit or combined license
applicant is responsible, under the
current regulations, to demonstrate that
the site conditions are acceptable for the
proposed facility design. This
responsibility exists regardless of
whether or not the NRC reviews and
approves the proposed excavation
activities and inspects the excavation
activities as they are accomplished.
Inasmuch as NRC inspection and
regulatory oversight of the excavation
are not necessary for reasonable
assurance of adequate protection to
public health and safety or common
defense and security, and because the
applicant bears the burden for
accurately characterizing the parent
material, the NRC concludes that
excavation may be excluded from the
definition of construction.
Comment: Excavation and the driving
of piles should be considered
‘‘construction.’’ Prior agency experience
has shown that safety issues have been
identified during excavation, citing to
the experience of North Anna nuclear
power plant, as well as a nuclear power
plant in the Midwest where soil
conditions identified during excavation
necessitated a change in foundation
design. Neither the public nor a
reviewing court would think that the
NRC would be able to make the
underlying licensing decision (i.e.,
granting a construction permit or a
combined license) in an unbiased
fashion if excavation proceeded in
PO 00000
Frm 00005
Fmt 4701
Sfmt 4700
57419
advance of the underlying licensing
decision. (Public Citizen/NIRS 2)
NRC Response: The NRC disagrees, in
part, with this comment. As discussed
in the response immediately above, the
NRC concludes that excavation may be
excluded from the definition of
construction. However, the driving of
piles and any other foundation work is
defined as construction.
Comment: The SOC for the final rule
should specify that excavation includes
appropriate erosion control measures
necessary to stabilize site excavations
pending LWA or license (i.e., combined
license or construction permit) approval
of construction activities. (NEI 1.5)
NRC Response: The NRC agrees, in
part, with this comment. The NRC’s
definition of construction in the final
LWA rule includes: (1) Any change
made to the parent material in which
the excavation occurs (e.g., soil
compaction, rock grouting); and (2) The
placement of permanent SSCs that are
put into the excavation during or after
the excavation (e.g., installation of
permanent drainage systems, or
placement of mudmats). If the erosion
control measures are conducted outside
of the excavated hole and do not cover
up the exposed soil conditions, then
those activities would be allowed under
§ 50.10(a). However, under the final
LWA rule, the placement of temporary
SSCs in the excavation, such as
retaining walls, drainage systems, and
erosion control barriers, all of which are
to be removed before fuel load, would
not be considered construction.
Comment: ‘‘Construction’’ should be
limited to above-ground installation of
certain SSCs. (Areva 1)
NRC Response: The NRC disagrees.
Even under the former provisions of
§ 50.10(e)(3), construction included the
setting of foundations and other work
accomplished below grade. The
commenter provided no basis for
limiting the definition of construction to
the above-grade installation of SSCs of
interest. No change was made in the
final rule as the result of this comment.
Comment: Temporary buildings,
structures, and roads, may be located in
the eventual location of SSCs for which
an LWA is required for excavation
under the supplemental proposed LWA
rule. If excavation is required for the
temporary buildings, structures, and
roads, the supplemental proposed rule
would appear to prohibit such
excavation. The final rule should make
clear that excavation for SSCs outside
the scope of an LWA, such as temporary
buildings, structures, and roads, should
be excluded from the definition of
construction. (Areva 3)
E:\FR\FM\09OCR2.SGM
09OCR2
57420
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
rwilkins on PROD1PC63 with RULES_2
NRC Response: As discussed
previously, the NRC has decided to
exclude all excavation from the
definition of construction. In addition,
the NRC notes that under the final LWA
rule, SSCs that are not within the scope
of construction may be installed before
receipt of an LWA, construction permit,
or combined license. Accordingly, the
final rule resolves the commenter’s
issue.
5. Compliance With NEPA
Comment: The impacts of the
construction activities that the NRC
proposes to exclude from its regulations
have been part of the NRC regulations
since 1972. What has changed causing
the NRC to decided that these activities
will not longer be part of the
environmental review? Has NRC been
doing it wrong for more than 30 years
(including the 3 early site permits that
are either completed or near
completion)? (Kugler 1)
NRC Response: As discussed in the
‘‘Discussion’’ section of this final rule
(as well as the supplemental proposed
rule), the 1972 amendment to the
definition of construction in 10 CFR
50.10 was made early in the Federal
government’s implementation of thennew NEPA. Since that time, the Federal
case law on NEPA has evolved, with
several U.S. Supreme Court decisions
on the requirements of NEPA. In
addition, in preparing for the expected
next generation of nuclear power plant
construction applications, the nuclear
power industry has reviewed the overall
construction process based upon lessons
learned from the construction and
licensing process used for currently
operating reactors. The industry
submitted what is essentially a petition
for rulemaking seeking changes to the
LWA process, reflecting those lessons
learned and their understanding of the
current state of NEPA law. The NRC has
reviewed the applicable law, and for the
reasons stated elsewhere in this SOC,
agrees with the petitioner that the
current definition of construction and
the current LWA requirements in
§ 50.10 are not compelled by NEPA or
the Atomic Energy Act (AEA) of 1954,
as amended. While the agency’s
regulations on construction and LWAs
were a reasonable implementation of
NEPA as understood in 1972, the NRC
believes that, with more than 30 years
experience in implementing NEPA and
the evolving jurisprudence, the time is
appropriate for reconsideration and
revamping of these NRC requirements.
Comment: The impacts of the
construction of a nuclear power plant
that NRC now proposes to exclude from
NRC regulations are probably 90 percent
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
of the true environmental impacts of
construction. Before even talking to the
NRC, a power company can clear and
grade the land, build roads and railroad
spurs, erect permanent and temporary
buildings, build numerous plant
structures (e.g., cooling water intake and
discharge, cooling towers), and build
switchyards and transmission lines.
After potentially doing all of that, THEN
the company would come to the NRC
and ask permission to build the power
plant for which all of this work was
done. How does this comply with
NEPA? The commenter asserts that the
NRC is going to ignore almost all of the
construction impacts of the proposed
action. (Kugler 2)
NRC Response: The commenter
assumes that, if a private action is
preparatory to Federal action, then
NEPA provides a statutory basis for the
agency to extend its otherwise limited
jurisdiction under the AEA to those
private, preparatory actions, solely for
the purpose of agency consideration of
the environmental impacts under NEPA.
The commenter has not pointed to, and
the NRC has not identified, Federal case
law that supports such a position.
Indeed, even in a case where the Federal
agency had unequivocal statutory
authority to grant or deny a Federal
permit, the U.S. Supreme Court
specifically held that the Federal agency
was not compelled to require mitigation
based upon environmental
considerations identified in the NEPA
review. Robertson v. Methow Valley
Citizens Council, 490 U.S. 332 (1989).
The commenter also asserts that the
NRC is going to ‘‘ignore all the [pre]construction impacts of the proposed
action.’’ On the contrary, as stated
elsewhere in this SOC, the preconstruction private actions of clearing,
grading, access road construction, etc.,
will be considered in the cumulative
impacts analysis in the LWA EIS as the
baseline for analyzing the
environmental impacts associated with
the Federal action authorizing LWA
activities. This information will be used
when evaluating the environmental
impacts of construction and operation of
the proposed nuclear power plant.
Comment: The commenter states that
the final rule says NRC won’t consider
the sunk costs of all of this work in your
decision whether to approve the request
to build the plant. The commenter
asserts that NRC has allowed the
company to do most of the
environmental damage. Who cleans up
the mess if the NRC says no? The
commenter states that because the NRC
has excluded from its review all of this
work that’s specifically for the purpose
of building the plant, the NRC also can’t
PO 00000
Frm 00006
Fmt 4701
Sfmt 4700
require any redress plan for the site for
those impacts. (Kugler 2.a)
NRC Response: The commenter
appears to believe that the NRC has
authority to exercise its regulatory
jurisdiction in an area where it does not
otherwise possess regulatory authority
under its organic statute, solely for the
purpose of ensuring environmental
redress of private activities with
significant environmental impacts. The
NRC does not agree with the
commenter’s implicit suggestion. As
discussed in the response to the
previous comment as well as elsewhere
in this SOC, the NRC does not possess
statutory authority to regulate activities
that do not have an impact upon
radiological health and safety or
common defense and security, and
NEPA does not provide independent
statutory authority to extend the
agency’s jurisdiction solely for the
purpose of assuring that adverse
environmental impacts are considered
and mitigated. While this may be a
worthy goal, the NRC may not lawfully
act in such a manner, absent additional
statutory authority which is not
currently provided by either NEPA or
the AEA.
Comment: The commenter asserts that
NRC won’t consider the sunk costs in its
review. The commenter also asserts that
it sounds like the ‘‘baseline’’ for the
environmental review will include the
environmental damage done by a
company in terms of ‘‘pre-application’’
activities. In other words, if an applicant
for an LWA, CP, or COL has done all of
the things NRC now allows without
NRC review, the condition of the
cleared and partially built site is now
the starting point for the environmental
review. The commenter states that in
terms of comparing this partially built
site to any alternative site, NRC has
essentially ‘‘pre-selected’’ the site
chosen by the applicant. The
commenter states there will be less
environmental impacts at a site that has
already had most of the damage done to
it as compared to any other site. The
commenter believes the NRC has
handed its responsibility for the site
suitability determination over to the
applicant. (Kugler 2.b)
NRC Response: The commenter makes
two incorrect assumptions. First, the
commenter implicitly assumes that
environmental matters are the key
determinants of site suitability. The
NRC believes that, as a practical matter
and as borne out by the history of site
suitability determinations in the past,
other factors, such as seismic activity
and intensity, geological structures,
meteorological factors, impediments to
development of emergency plans,
E:\FR\FM\09OCR2.SGM
09OCR2
rwilkins on PROD1PC63 with RULES_2
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
security issues, and demographics
(population density and distance) from
a safety perspective are at least as
important, if not more important, than
‘‘environmental’’ matters as a key
determinant of site suitability.
Second, the commenter assumes that
clearing of a site will always tilt the
environmental balance in favor of the
applicant’s ‘‘pre-selected site.’’ This
may not be true in most cases. For
example, even an ‘‘obviously superior’’
site from the standpoint of
environmental impacts on water—
which is likely to be the determining
‘‘environmental’’ impact—will require
grading and clearing in order to be used.
If construction were to be abandoned at
the applicant’s ‘‘pre-selected site’’ and
commenced at the ‘‘obviously superior
site,’’ the environmental impacts of preconstruction activities such as clearing
and grading would still have to be
performed at the ‘‘obviously superior’’
site. In essence, the ‘‘sunk
environmental impacts’’ associated with
preconstruction at the pre-selected site
are balanced out by the ‘‘future’’
environmental impacts associated with
preconstruction at the ‘‘obviously
superior’’ site. Thus, pre-construction at
a ‘‘pre-selected’’ site could not, in and
of itself, lead to automatic dismissal of
otherwise ‘‘obviously superior’’ sites.
In any event, the issue of the
‘‘baseline’’ for purposes of alternative
sites is not addressed directly in the
final LWA rule and will be resolved in
the development of NRC guidance on
implementation of the final LWA rule.
Furthermore, the NRC notes that preconstruction impacts will be evaluated
as part of the cumulative impacts
analysis, which may render moot some
aspects of the commenter’s concerns in
this area.
Comment: How can NRC tell the
world in an EIS that the only real
impacts of construction of a nuclear
power plant will be related to digging a
big hole and a few other straggling items
that will occur while the structures
described in the FSAR are being built?
(Kugler 2.c)
NRC Response: The commenter
appears to assert that the NRC’s EIS for
a combined license must attribute to the
NRC’s Federal action all of the
environmental impacts of constructing a
nuclear power facility, including the
private, pre-construction activities that
may be accomplished by the applicant
without any NRC approval. The
commenter’s implicit assertion is
incorrect. The NRC’s EIS need only
describe the environmental impacts of
the Federal action as those construction
activities, as defined under § 50.10,
which can only be accomplished under
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
an LWA and combined license or
construction permit.
The environmental impacts of preconstruction activities will also be
described in the NRC’s EIS because such
description is necessary to evaluate the
cumulative impacts of the Federal
action, in light of the pre-existing
impacts of the private, pre-construction
action. The cumulative impacts
discussion should provide information
on the total environmental impacts of
constructing the nuclear power plant to
both the NRC decisionmaker and the
general public.
The NRC notes that, under the final
LWA rule, excavation for SSCs that are
important from a radiological health and
safety or common defense and security
standpoint will not be treated as
‘‘construction.’’ Therefore, the
environmental effects of excavation
would not be evaluated as an impact
attributable to the Federal licensing
action, but instead be added to the
environmental baseline for a site.
Comment: How are applicants and
NRC going to divide impacts if some of
the construction activities now out side
(sic.) the NRC’s scope are going on at the
same time as activities inside NRC’s
scope? For example, traffic impacts of
the construction workforce are often an
issue. But how does the NRC deal with
it if part of the workforce is building
cooling towers and intake systems, and
part is building FSAR-listed structures?
Another case is property taxes. The
property taxes paid by the company are
a significant item in the socioeconomic
review. Are the applicant and the NRC
now going to have to differentiate
between taxes paid for FSAR-related
facilities and taxes paid for other
facilities? (Kugler 2.d)
NRC Response: The commenter raises
a number of detailed issues with respect
to NRC implementation of the final rule
in the course of preparing EISs. None of
these matters appear to raise issues that
are insurmountable or would be
unusually difficult to resolve. For
example, the need to apportion the taxes
for FSAR-related SSCs, versus taxes on
other portions of the facility whose
construction does not require NRC
approval could be resolved by simply
treating all the taxes paid as a benefit of
operation, and the impacts from all
portions of the plant as an impact of
operation. The NRC expects that the
staff will develop supplemental
guidance to the environmental standard
review plan on these and other
implementation matters.
Comment: The commenter states that
the rule says that if an LWA is issued,
the EIS to build and operate a nuclear
power plant will be a supplement to the
PO 00000
Frm 00007
Fmt 4701
Sfmt 4700
57421
EIS for the LWA. The commenter
believes this means that the EIS that
evaluates the impacts of building and
operating a large commercial power
plant will be a supplement to the EIS for
digging a big hole. The commenter
states that assuming the EIS for the big
hole ignores all of the other impacts of
construction that may already have
taken place, it’s going to be pretty
limited in scope. The commenter states
that this EIS of very limited scope will
now become the base document, and the
EIS that considers ALL of the impacts of
operations will be a supplement to it.
(Kugler 3)
NRC Response: The NRC believes that
the proposed rule is consistent with
NEPA. The commenter presented no
rationale why the NRC’s proposal
violates either NEPA or CEQ’s
implementing regulations. NEPA itself
only requires that a statement be
prepared addressing the environmental
impacts and alternatives of major
Federal actions significantly affecting
the environment. The statute does not
contain any language specifically
constraining the manner in which each
EIS for two sequential Federal actions
must be prepared. Hence, the NRC is
free to select a manner of NEPA
compliance which best meets the
agency’s needs.
The commenter appears to be
concerned that, if the LWA applicant
chooses to submit an environmental
report limited to LWA activities, then
the LWA EIS would be a relatively
narrow document which cannot be the
basis for a supplemental EIS with a
greatly expanded scope of subject
matters addressed. The NRC does not
believe that the commenter’s concern is
well-founded. First, the CEQ’s
regulations specifically permit ‘‘tiering’’
of EISs to ‘‘eliminate repetitive
discussions of the same issues and to
focus on the actual issue ripe for
consideration at each level of the
environmental review * * *’’ (40 CFR
1502.20). Although most of the tiering
discussion refers to a broad initial EIS
followed by more specific EIS tiering on
the earlier EIS, 40 CFR 1502.20 also
states, ‘‘Tiering may also be appropriate
for different stages of actions (emphasis
added).’’ The NRC believes that the
LWA is a stage in the overall Federal
action of issuing a license for
construction (and, in the case of a
combined license under part 52,
operation) of a nuclear power plant. It
is logical to evaluate the environmental
impacts of the activities that occur first
(i.e., LWA activities), followed by
evaluation of the impacts of activities
that occur thereafter (i.e., main
construction and operation). The
E:\FR\FM\09OCR2.SGM
09OCR2
rwilkins on PROD1PC63 with RULES_2
57422
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
potential for segmentation of the Federal
impacts is minimized, as discussed
previously, by various provisions of the
rule which, inter alia, prohibit NRC
consideration of sunk costs, require
consideration of all environmental
impacts and benefits attributable to
LWA activities in the supplemental EIS
prepared for the underlying combined
license or construction permit
application, and require the applicant/
licensee to develop and, if necessary,
implement a redress plan. Second, the
CEQ regulations also encourage agencies
to incorporate by reference material into
an EIS to cut down on bulk without
impeding agency and public review of
the action. Nothing in the CEQ
regulations suggests that incorporation
by reference is precluded where the
material being incorporated is smaller in
bulk than the EIS into which the
material is being incorporated. The NRC
believes the purpose of incorporation by
reference is served by incorporating the
LWA EIS into the supplemental EIS
prepared at the combined license or
construction permit stage.
Comment: The commenter states the
LWA EIS will only be looking at the
impacts of digging the big hole and
pouring the foundation. At what point
does the NRC staff evaluate the impacts
of construction and operation to
determine whether the site is
SUITABLE for the construction and
operation of a nuclear power plant? Is
that done later? Does that mean that
NRC could authorize digging the hole at
a site that could later be determined by
NRC to be unsuitable? (Kugler 4)
NRC Response: The NRC has decided
that excavation should not be
considered ‘‘construction,’’ and that
NRC permission is not required to
undertake excavation activities.
Accordingly, a response to this
comment, to the extent that it is focused
on NRC consideration of the impacts of
excavation as an impact of the issuance
of the LWA, construction permit, or
combined license, is unnecessary. As
discussed elsewhere in this document,
the impacts of preconstruction activities
performed by the ESP holder,
construction permit, or combined
license applicant must be described by
the applicant in its environmental
report, and must be considered in the
cumulative impacts analysis.
Under the final LWA rule, the NRC’s
evaluation of site suitability must be
made when it issues a construction
permit or combined license, unless the
applicant seeks, either as part of an
LWA or in advance of the issuance of
the construction permit or combined
license under subpart F of part 2, an
early decision on site suitability and/or
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
the environmental impacts of
construction and operation.
Comment: Has the NRC discussed
these changes with key stakeholders like
EPA, CEQ, and FERC? What do they
think of this change? The commenter
states that this is a major shift by the
NRC away from its NEPA
responsibilities, and believes that other
agencies may have real problems with it
beyond the basic NEPA issues. For
example, will FERC commence a review
for transmission lines if the power
company hasn’t submitted an
application to the NRC to build the
plant for which it’s needed? Similarly,
will the Corps of Engineers issue
Section 404 permits to damage wetlands
and dredge if there’s no request to build
a plant yet? Has anybody talked to
them? (Kugler 5)
NRC Response: The NRC sought
comments on the proposed rule from
four Federal agencies who have
historically been interested in NRC
construction licensing from an
environmental standpoint. Advance
copies of the proposed rule as approved
by the Commission were provided to the
CEQ, the EPA, FERC, and the U.S.
Department of the Interior, FWS, and
copies of the proposed rule as published
in the Federal Register were
electronically transmitted to cognizant
individuals in these agencies on the
date of publication of the proposed rule
in the Federal Register (ADAMS
Accession Nos. ML062840445,
ML062910051, and ML062910049).
Additional telephone calls were made to
describe the proposed rule and to
answer any questions from these agency
officials. As discussed earlier in this
document, the NRC has received
comments from the EPA, which has no
objection to the change. NRC was
advised by telephone that CEQ had no
objection to the supplemental proposed
LWA rule. The NRC has been advised
by FERC that it ordinarily would not
review transmission line routings for
lines commencing at nuclear power
facilities. The NRC believes that it has
made reasonable efforts to obtain input
from other cognizant Federal agencies,
and none appear to share the concerns
of the commenter. No change from the
supplemental proposed LWA rule has
been made as the result of this
comment.
Comment: How does this change
affect the current early site permit
applicants? The commenter states that,
for example, Exelon and Dominion
submitted redress plans for all of the
impacts of construction they’d be
allowed to carry out before receiving a
license to build and operate a plant. The
petitioner also believes Southern
PO 00000
Frm 00008
Fmt 4701
Sfmt 4700
submitted redress plans. Future
applicants won’t have to do this. What
happens to the Exelon and Dominion
redress plans? Do they get out of them
now? If so, how does NRC explain that
to all of the folks involved in those
reviews who relied on the NRC’s
representations that a redress plan was
required (e.g., the public, Federal and
State environmental regulatory
agencies)? What happens to Southern,
which is early in its review? (Kugler 6)
NRC Response: The final rule does
not affect the NRC staff’s approval of a
full-scope redress plan to support LWA
activities under the former LWA
provisions in §§ 50.10 and 52.17. The
three applicants for ESP which are
currently before the NRC are required to
meet the NRC’s requirements in effect at
the time of the application, with respect
to the content of the application. If the
final rule is adopted before ESPs are
issued to the current ESP applicants,
then the applicant may (but is not
required to seek to revise its redress
plan and seek NRC approval of a
(narrowed) redress plan that meets the
requirements of the final LWA rule. In
such a case, the NRC would advise other
Federal and State agencies of the change
in NRC’s regulatory requirements and
any change in the scope of the approved
redress plan which may be requested by
the ESP applicant. Alternatively, upon
issuance of the ESP, the ESP holder may
request an amendment to its ESP,
consistent with the recently-adopted
revisions to 10 CFR part 52, to seek NRC
approval of a (narrowed) redress plan
which is consistent with the
requirements of the final LWA rule. In
such an event, the NRC would—as part
of its routine procedures—consult with
relevant Federal agencies. No change
from the supplemental proposed LWA
rule was made as a result of this
comment.
Comment: Section 51.49(a)(2) should
be revised to delete the requirement for
an LWA applicant to state the need for
an LWA. (Progress Energy 5)
NRC Response: The NRC disagrees
with the commenter’s proposal. An EIS
should state the purpose and need for a
proposed action. 10 CFR part 51,
appendix A, paragraph 4; 40 CFR
1502.13. Inasmuch as the NRC is acting
on a private entity’s request in a
licensing action, the purpose and need
should be, in the first instance,
determined by the applicant and be
adopted by the NRC. No change was
made to the final rule as a result of this
comment.
Comment: Sections 51.20(b)(1) and
(5), and 51.76(b) and (e) should be
revised to allow the NRC staff the option
of preparing and issuing an
E:\FR\FM\09OCR2.SGM
09OCR2
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
rwilkins on PROD1PC63 with RULES_2
environmental assessment (EA) if the
environmental report shows no
significant environmental impacts
associated with LWA activities.
(Progress Energy 6, 7, 8)
NRC Response: The NRC disagrees
with the commenter’s proposal. In
preparing the supplementary proposed
rule, the NRC considered the approach
recommended by the commenter.
However, the NRC rejected proposing
such an approach because it would
increase the perception of Federal
segmentation, without any significant
countervailing benefits, in terms of
resources or time necessary to complete
the NEPA process. Furthermore, the
tiering concept, under CEQ regulations,
involves sequential EISs rather than an
EA followed by an EIS. The NRC
believes that it would not be prudent to
pursue a new approach to NEPA
compliance, which may result in legal
instability in an area of critical interest
to industry stakeholders. The
commenter presented no information in
favor of its proposal. Accordingly, in the
absence of new information suggesting
that the Commission’s initial
determination should be revisited, the
Commission declines to adopt the
commenter’s proposal. No change was
made to the final rule as a result of this
comment.
6. LWA Application Process
Comment: The commenter states that
the NRC expects over 15 applications
for COLs in the next 3 years or so.
Perhaps it can staff up to meet the
challenge of preparing those 15 EISs.
But can it possibly handle 30? If most
or all of the COL applicants choose to
submit an LWA application too, which
would seem likely, the NRC staff will
have to prepare two EISs for each site.
Has the NRC considered the resource
implications? (And if an applicant
chooses to go the ESP route for some
reason, there will be three EISs.) (Kugler
7)
NRC Response: The commenter
appears to believe that, under a revised
LWA rule, the overall resources
expended by the NRC in preparing EISs
would increase over the current
regulatory regime in a time frame that
would exacerbate any problems that
may be caused by limited NRC staff
resources. The NRC disagrees with the
commenter. The final LWA rule merely
governs the timing of the NRC’s
environmental review of the overall
action of licensing the construction and
operation of a nuclear power plant,
consistent with NEPA.
Taking the specific example identified
by the commenter of a combined license
applicant, who both seeks an LWA and
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
references an ESP, it is possible—as the
commenter correctly points out—that
three EISs may be prepared in the worst
case of a less than complete ESP EIS.
However, the final LWA rule does not
require the NRC staff to prepare entirely
new, full-scope EISs at either the LWA
or the combined license issuance stages.
Instead, the EIS at the LWA stage would
be limited to considering the
environmental impacts of LWA
activities only (assuming that the LWA
ER is limited to providing information
on the environmental impacts of LWA
activities). This is consistent with NRC
and CEQ regulations that allow
incorporation by reference. Preparation
of an LWA EIS limited to those subjects
would not be redundant of the ESP EIS,
inasmuch as the impacts of construction
under this scenario were not addressed
in the ESP EIS. Accordingly, there is no
unnecessary expenditure of NRC
resources attributable to anything in the
LWA rule. When the combined license
supplemental EIS is prepared, that EIS
will be limited to considering new and
significant information related to
matters concerning construction and
operation of the facility which was not
addressed in the ESP EIS, unless the
matter was discussed in the LWA EIS.
In that limited case, the nature and
description of the LWA construction
impacts are deemed to be resolved, and
these impacts would be considered in
the overall balancing and
decisionmaking on issuance of a
combined license without the need to
re-examine the nature and description
of those LWA impacts. Again, the final
LWA rule avoids redundant NRC review
to the maximum extent practicable,
inasmuch as the combined license EIS
relies upon the determinations
regarding the nature and impacts of
construction and operation which were
made at both the ESP and LWA stages.
The overall scope of the NRC
environmental review is not changed; it
is merely the timing of the review for
individual issues that is affected by the
final LWA rule.
In sum, the NRC does not agree with
the commenter that the LWA rule will,
as the consequence of its provisions,
result in an adverse impact upon the
amount and timing of expenditure of
NRC resources that cannot be managed
in an effective manner. No change from
the supplemental proposed LWA rule
was made in response to this comment.
Comment: One commenter states that
it appears that this new process will
require major changes to NRC guidance
documents such as RGs and the
environmental standard review plan.
Almost everything related to the
impacts of construction will have to be
PO 00000
Frm 00009
Fmt 4701
Sfmt 4700
57423
completely rewritten. Can this be done
before the first applicant uses the new
rule? (Kugler 8)
NRC Response: The NRC agrees with
the commenter that changes to the NRC
RGs and the environmental standard
review plan will be necessary to provide
complete guidance to potential
applicants and the NRC review staff
with respect to implementation of the
new LWA process in the final LWA
rule. However, the NRC does not agree
with the commenter’s implicit assertion
that the guidance must be finalized
before the first applicant (or several
applicants) can use the new LWA
process in an effective manner. The
NRC has, in many other instances,
adopted rules containing substantial
changes to its technical and regulatory
requirements applicable to nuclear
power reactors. Although the NRC does
not wish to understate the challenge of
implementing new rules, it is confident
that the NRC working level technical
staff, under careful and timely oversight
by NRC staff management, will be able
to implement the final LWA rule in a
timely, consistent, and effective manner.
Comment: One commenter states that
the supplemental proposed rule does
not appear to allow an applicant to use
both a phased LWA process and the
hearing process for early partial
decision on site suitability issues,
thereby allowing an applicant who
wishes to apply for an LWA to also
submit the environmental information
under § 2.101(a)(5) and proceed with an
accelerated hearing on the full scope of
environmental matters. The
Commission should adopt changes in
§§ 50.10(c)(2) and 2.101(a)(5) to allow
an applicant to use both processes
simultaneously. (NEI 5; Unistar 1)
NRC Response: The NRC believes that
the commenter misunderstood the
provisions of the supplemental
proposed rule. The NRC’s intent is that:
• Applicants may submit a two-part
(phased) application for an LWA in
advance of the application for the
underlying combined license or
construction permit, see § 2.101(a)(9).
• The environmental information
submitted in the LWA portion of the
application may either be limited to the
LWA activities requested, or the full
scope of construction and operation
impacts, see § 51.49(b) and (f).
• An LWA applicant may seek an
early decision on siting and
environmental matters. If the LWA is
submitted in advance of the underlying
construction permit or combined license
application, the procedures in 10 CFR
part 2, subpart F, §§ 2.641 through 2.649
apply. If the LWA is submitted as part
of (or after) the construction permit or
E:\FR\FM\09OCR2.SGM
09OCR2
rwilkins on PROD1PC63 with RULES_2
57424
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
combined license application, then the
procedures in subpart F, §§ 2.601
through 2.629 would apply because this
is the ordinary procedure for obtaining
an early decision on siting and
environmental matters under the
existing provisions of subpart F.
The NRC does not believe the specific
language changes to the proposed rule
described by the commenter are
necessary to accomplish these three
objectives. Accordingly, the
Commission declines to adopt the
changes proposed by the commenter,
and no change from the supplemental
proposed LWA rule was made in
response to this comment.
Comment: One commenter proposed
that the timing provisions in 10 CFR
2.101(a)(5), requiring that each part of a
two-part combined license application
be submitted within 6 months of each
other, should be revised to be consistent
with 10 CFR 2.101(a)(9) of the
supplemental proposed rule, which
permits the LWA application to be
submitted up to 12 months in advance
of the underlying combined license or
construction permit. The commenter
believes that additional conforming
changes should be made to implement
this concept, including changes in
§ 50.10(c)(2). (Unistar 2) Another
commenter made the same proposal, but
separately suggested that the overall
time between parts of applications be
lengthened to 18 months. (NEI 6)
NRC Response: The NRC agrees with
the commenters that the timing
provisions should be consistent.
Furthermore, the NRC agrees with the
second commenter (NEI) that the overall
time between parts of applications may
be lengthened to 18 months. The 6
month limitation in former § 2.101(a)(5)
for two-part applications was set many
years ago and reflected internal NRC
administrative considerations, including
maximizing efficiency and ensuring
continuity of review oversight. The 12month limitation between submission of
the LWA application and the underlying
combined license or construction permit
application, as proposed in the
supplemental proposed LWA rule, was
based upon the same considerations, as
well as environmental/NEPA
considerations. The NRC did not want
the time between the initial submission
of LWA environmental information and
the subsequent consideration of the
overall environmental impacts to be
lengthened to the point that there would
be a substantial likelihood of new and
significant information that would
require updating. A 12-month limitation
was established as a reasonable
limitation. No consideration was given
to having a consistent limitation in both
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
existing paragraph (a)(5) and proposed
paragraph (a)(9).
However, after further consideration
based upon public comments, the NRC
concludes that the 6-month limitation in
paragraph (a)(5) and the proposed 12month limitation in paragraph (a)(9) are
unduly restrictive. The NRC believes
that administrative efficiency can be
maintained with longer time periods
between parts of applications, in view of
modern information technology, NRC’s
restructuring of the licensing process in
part 52, the NRC’s recent adoption of
changes to part 2, subpart D and part 52,
appendix N, and the NRC’s projected
use of design-centered reviews. In
addition, the NRC understands, in
response to informal inquiries with
EPA, that 18 months is well within the
time period considered by EPA to be
acceptable for referencing a previouslyprepared EIS without updating. For
these reasons, the Commission is
adopting an 18-month limitation in
paragraphs (a)(5) and (a)(9) of § 2.101.
7. Other Topics
Comment: The NRC should include a
‘‘grandfathering’’ provision in the final
rule to make clear that the final rule
does not require any change to ESP
applications filed before the effective
date of the rule, such as supplementing
the application to require a showing of
technical qualifications. The NRC
should also clarify that the final rule
would not reduce or limit the authority
that such applicants would be entitled
to receive upon issuance of their ESPs
under the current regulations (e.g.,
perform construction of non-safetyrelated SSCs). (NEI 4, Dominion 1)
NRC Response: The NRC agrees with
the commenters that the final LWA rule
does not require any change to ESP
applications filed before the effective
date of the rule. Upon further
consideration, the NRC has decided to
include a ‘‘grandfathering’’ provision in
the final rule which will provide that
ESP applications which are under
consideration as of the effective date of
the final LWA rule, which include a
request to conduct § 50.10(e)(1)
activities, need not comply with the
‘‘content of application’’ requirements
in the final rule.
The NRC does not agree with the
commenter’s view that the final rule
and/or the SOC for the final rule should
clarify that the current ESP applicants
should be provided with the authority
to conduct LWA activities under the
former provisions of § 50.10(e)(1), that
is, not be bound by the final LWA rule’s
provisions. The final LWA rule does
allow excavation without an LWA.
However, the NRC continues to believe
PO 00000
Frm 00010
Fmt 4701
Sfmt 4700
that pile driving and other subsurface
preparation should be considered
construction, inasmuch as none of the
comments received addressed this
matter or brought information to the
NRC’s attention that suggests that the
NRC’s regulatory basis for its position
should be reconsidered (the public
comments received only addressed
excavation per se, and did not mention
pile driving or other subsurface
preparation). In addition, as discussed
elsewhere in this SOC, the NRC has
redefined and limited the SSCs whose
construction requires an LWA,
construction permit, or combined
license. Thus, the NRC believes that the
current ESP applicants will have
sufficient authority and flexibility under
the final rule, without any
grandfathering of the LWA provisions.
Furthermore, regulatory stability from
the standpoint of backfitting is not
relevant, inasmuch as it has been the
Commission’s longstanding position
that backfitting does not protect an
applicant from changes to regulatory
requirements.
Comment: The commenter states that
proposed § 50.10(c)(3)(i) requires the
LWA application to: (1) Describe the
design and construction information
otherwise required to be submitted for
a combined license, but limited to the
portions of the facility that are within
the scope of the limited work
authorization; and (2) Demonstrate
compliance with ‘‘technically relevant
Commission requirements in 10 CFR
Chapter I’’ applicable to the design of
those portions of the facility within the
scope of the limited work authorization,
is unduly vague. If specific technical
requirements are deemed applicable,
they should be justified and identified
in the rule. (Dominion 3)
NRC Response: The NRC disagrees
with the commenter that the language of
§ 50.10(c)(3)(i) (§ 50.10(d)(3)(i) in the
final LWA rule) is unnecessarily vague,
or that it would be practical for the rule
language to specify the technical
requirements which are deemed
applicable. The technical requirements
that are applicable will depend upon
the scope and nature of LWA activities
requested. Furthermore, this regulatory
requirement is modeled on the
provisions of former §§ 50.10(e)(2),
(e)(3)(i), and (e)(3)(ii), for which the
NRC and the nuclear power industry
has had decades of experience. The
commenter did not present either
alternative language that would address
its concern with vagueness, or otherwise
present a list of NRC technical
requirements that should be specified as
applicable. The original commenter
whose submission led to this
E:\FR\FM\09OCR2.SGM
09OCR2
rwilkins on PROD1PC63 with RULES_2
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
rulemaking did not identify this aspect
of the former rule as presenting a
problem which should be addressed as
part of the reformulated rule. To modify
the rule language to include a list of
technically relevant requirements would
likely require renoticing of this aspect of
the rule for public comment, which
would delay issuance of the rule with
little benefit, given the 30+ years of
experience in implementing analogous
rule language in the former versions of
§ 50.10. Accordingly, the Commission
declines to adopt the commenter’s
proposal, and no change from the
supplemental proposed LWA rule was
made in response to this comment.
Comment: The commenter states that
the finding of technical qualifications
should be limited to LWA activities
applicable to safety-related activities,
because there are no design,
construction, or technical requirements
in the NRC’s rules applicable to nonsafety-related construction work.
(Dominion 4)
NRC Response: The NRC disagrees
with the commenter’s proposal,
inasmuch as it is based on the
longstanding industry misconception
that the NRC’s regulations in part 50
apply only to ‘‘safety-related’’ SSCs and
activities relevant to those SSCs, as that
term is defined in 10 CFR 50.2. This is
not a correct understanding. For
example, the general design criteria in
10 CFR part 50, appendix A, apply to
SSCs ‘‘important to safety; that is,
structures, systems, and components
that provide reasonable assurance that
the facility can be operated without
undue risk to the health and safety of
the public.’’ Id. (first introductory
paragraph). There are numerous other
regulations applicable to the design,
construction, and operation of a nuclear
power facility whose applicability
extends beyond ‘‘safety-related’’ SSCs. It
is consistent with Section 182.a of the
AEA and the NRC’s past practice that a
technical qualifications finding be made
as part of the finding necessary for NRC
issuance of an LWA. Accordingly, the
NRC declines to adopt the commenter’s
proposal, and no change from the
supplemental proposed LWA rule was
made in response to this comment.
Comment: The commenter states that
the reference in § 50.10(d)(2) to
§ 52.17(c) should be changed to
§ 50.10(c)(3)(iii), inasmuch as the
requirement for a redress plan has been
removed from § 52.17(c) and relocated
in § 50.19(c)(3)(iii). (Progress Energy 3)
NRC Response: The NRC agrees with
the substance of this comment.
Inasmuch as the proposed rule has been
reorganized in the final rule, the final
rule refers to the appropriate paragraph.
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
Comment: The commenter states that
an LWA is not the functional equivalent
of an ESP. There are significant
differences between them, and the time
and level of NRC staff effort necessary
to conduct an LWA review should not
be as great as for an ESP review. The
NRC should clarify the differences
between an LWA and ESP in the SOC
for the final rule. (Areva 4)
NRC Response: NRC agrees with the
commenter that there are some
significant differences between an LWA
review and an ESP. In particular,
issuance of an LWA does not require the
NRC to make a finding with respect to
site suitability from either a safety or
environmental standpoint (although the
LWA applicant may, under
§§ 2.101(a)(9), 52.17, and 51.49 of the
final rule, submit an environmental
report addressing the issues of
alternative, obviously superior sites, and
the impacts of construction and
operation of the nuclear power plant, in
which case the NRC would make a
finding on all environmental matters,
including alternative, obviously
superior sites). The NRC has modified
the section-by-section discussion of the
SOC to make clearer the requirements
for obtaining an LWA.
Comment: The commenter states that
proposed §§ 51.76(e) and 51.49(e) are
slightly inconsistent, in that the former
refers to the LWA applicant’s authority
to incorporate by reference an earlier
EIS prepared for the same site if a
construction permit was issued but
construction never commenced. By
contrast, § 51.49(e) refers to the LWA
applicant’s environmental report to
reference an earlier EIS prepared for the
same site if a construction permit was
issued but construction was never
completed. The commenter also states
that inasmuch as the NRC intended to
adopt the more expansive concept
embodied in § 51.49(e), the final rule
should modify § 51.76(e) to be
consistent to refer to construction not
being ‘‘completed.’’ (NEI 3)
NRC Response: The NRC agrees, and
the language of § 51.76(e) has been
conformed in the final rule. In addition,
conforming changes were made in the
subtitles of §§ 51.49(e) and 51.76(e), and
the relevant SOC discussion.
III. Discussion
A. History of the NRC’s Concept of
Construction and the LWA
Section 101 of the AEA prohibits the
manufacture, production, or use of a
commercial nuclear power reactor,
except where the manufacture,
production, or use is conducted under
a license issued by the NRC. While
PO 00000
Frm 00011
Fmt 4701
Sfmt 4700
57425
construction of a nuclear power reactor
is not mentioned in Section 101, Section
185 of the AEA requires that the NRC
grant construction permits to applicants
for licenses to construct or modify
production or utilization facilities, if the
applications for such permits are
acceptable to the NRC. However, the
term construction is not defined
anywhere in the AEA or in the
legislative history of the AEA.
To prevent the construction of
production or utilization facilities
before a construction permit is issued,
the NRC proposed a regulatory
definition of construction in 1960 (25
FR 1224; February 11, 1960). The
definition of construction was adopted
in a final rule that same year and
codified in 10 CFR 50.10(b) (25 FR 8712;
September 9, 1960). As promulgated,
§ 50.10(b) stated that no person shall
begin the construction of a production
or utilization facility on a site on which
the facility is to be operated until a
construction permit had been issued.
Construction was defined in § 50.10(b)
as including:
* * * pouring the foundation for, or the
installation of, any portion of the permanent
facility on the site; but [not to] include: (1)
Site exploration, site excavation, preparation
of the site for construction of the facility and
construction of roadways, railroad spurs, and
transmission lines; (2) Procurement or
manufacture of components of the facility; (3)
Construction of non-nuclear facilities (such
as turbogenerators and turbine buildings) and
temporary buildings (such as construction
equipment storage sheds) for use in
connection with the construction of the
facility; and (4) With respect to production or
utilization facilities, other than testing
facilities, required to be licensed pursuant to
Section 104a or Section 104c of the Act, the
construction of buildings which will be used
for activities other than operation of a facility
and which may also be used to house a
facility. (For example, the construction of a
college laboratory building with space for
installation of a training reactor is not
affected by this paragraph.) (25 FR 8712;
September 9, 1960)
The definition of construction
remained unchanged until 1968, when
the driving of piles was specifically
excluded from the definition (33 FR
2381; January 31, 1968). This change
was implemented by amending
§ 50.10(b)(1) to read: ‘‘Site exploration,
site excavation, preparation of the site
for construction of the reactor, including
the driving of piles, and construction of
roadways, railroad spurs, and
transmission lines.’’ The rationale for
this change, as articulated in the
proposed rule (32 FR 11278; August 3,
1967), seems to have been that the
driving of piles was closely related to
‘‘preparation of the site for
E:\FR\FM\09OCR2.SGM
09OCR2
57426
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
construction’’ and that the performance
of this type of site preparation activity
would not affect the NRC’s subsequent
decision to grant or deny the
construction permit. With the exception
of the exclusion of the driving of piles
from the definition of construction in
1968, the NRC’s interpretation of the
scope of activities requiring a
construction permit under the AEA has
remained largely unchanged.
However, following the enactment of
the NEPA, as amended, the NRC
adopted a major amendment to the
definition of construction in § 50.10 (37
FR 5745; March 21, 1972). In that
rulemaking, the NRC adopted a much
more expansive concept of construction.
Specifically, a new § 50.10(c) was
adopted stating that no person shall
effect ‘‘commencement of construction’’
of a production or utilization facility on
the site on which the facility will be
constructed until a construction permit
has been issued. ‘‘Commencement of
construction’’ was defined as:
* * * any clearing of land, excavation, or
other substantial action that would adversely
affect the natural environment of a site and
construction of non-nuclear facilities (such as
turbogenerators and turbine buildings) for
use in connection with the facility, but does
not mean: (1) Changes desirable for the
temporary use of the land for public
recreational uses, necessary boring to
determine foundation conditions or other
preconstruction monitoring to establish
background information related to the
suitability of the site or to the protection of
environmental values; (2) Procurement or
manufacture of components of the facility;
and (3) With respect to production or
utilization facilities, other than testing
facilities, required to be licensed pursuant to
Section 104a or Section 104c of the Act, the
construction of buildings which will be used
for activities other than operation of a facility
and which may also be used to house a
facility * * * (37 FR 5748; March 21, 1972)
rwilkins on PROD1PC63 with RULES_2
The NRC explained that expansion of
the NRC’s permitting authority was:
[C]onsistent with the direction of the
Congress, as expressed in Section 102 of the
NEPA, that, to the fullest extent possible, the
policies, regulations, and public laws of the
United States shall be interpreted and
administered in accordance with the policies
set forth in that Act. Since site preparation
constitutes a key point from the standpoint
of environmental impact, in connection with
the licensing of nuclear facilities and
materials, these amendments will facilitate
consideration and balancing of a broader
range of realistic alternatives and provide a
more significant mechanism for protecting
the environment during the earlier stages of
a project for which a facility or materials
license is being sought. (37 FR 5746; March
21, 1972)
Thus, the NRC’s interpretation of its
responsibilities under NEPA, not the
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
AEA, was the driving factor leading to
its adoption of § 50.10(c).3
The NRC issued § 50.10(e) two (2)
years after the expansion of the NRC’s
permitting authority resulting from the
issuance of § 50.10(c) (39 FR 14506;
April 24, 1974). This provision created
the current LWA process, which was
added to allow site preparation,
excavation, and certain other onsite
activities to proceed before issuance of
a construction permit. Before the
issuance of § 50.10(e), NRC permission
to engage in site preparation activities
before a construction permit was issued
could only be obtained via an
exemption issued under § 50.12. Section
50.10(e) allowed the NRC to authorize
the commencement of both safetyrelated (known as ‘‘LWA–2’’ activities)
and non-safety-related (known as
‘‘LWA–1’’ activities) onsite construction
activities before issuance of a
construction permit, if the NRC had
completed a site suitability report and a
final environmental impact statement
(FEIS) on the issuance of the
construction permit, and the presiding
officer in the construction permit
proceeding had made the requisite site
suitability, environmental and, in the
case of an LWA–2, safety-related
findings.
B. NRC’s Concept of Construction and
the AEA
Industry stakeholders have stated that
the business environment, today and in
the foreseeable future, requires that new
plant applicants minimize the time
interval between a decision to proceed
with the construction of a nuclear
power plant and the start of commercial
operation. To achieve that goal, these
stakeholders have indicated that nonsafety-related ‘‘LWA–1’’ activities
would need to be initiated up to 2 years
before the activities currently defined as
‘‘construction’’ in § 50.10(b). NEI
believes that the current LWA approval
process would constrain the nuclear
industry’s ability to use modern
construction/management practices and
needlessly add 18 months to estimated
construction schedules for new plants
that did not reference an early site
permit with LWA authority.
3 See Carolina Power and Light Company
(Shearon Harris Nuclear Power Plant, Units 1, 2, 3
and 4), 7 AEC 939, 943 (June 11, 1974) (hereinafter
Shearon Harris) (‘‘The regulations were revised in
1972, not because of any requirements of the
Atomic Energy Act, but rather to implement the
precepts of NEPA which had then recently been
enacted.’’); Kansas Gas and Electric Company (Wolf
Creek Nuclear Generating Station, Unit No. 1), 5
NRC 1, 5 (January 12, 1977) (explaining that NEPA
led the AEC to amend its regulations in several
respects, including the changes to § 50.10(c)).
PO 00000
Frm 00012
Fmt 4701
Sfmt 4700
Based upon the representations of the
industry, the NRC agrees that the
agency’s regulatory processes should be
revised and optimized to ensure that
these stakeholder’s needs are met,
consistent with the NRC’s statutory
obligations and in a manner that is fair
to all stakeholders. Accordingly, the
NRC is adopting this LWA final rule
which revises 10 CFR 50.10, and makes
conforming changes in 10 CFR parts 2,
51, and 52. The LWA final rule narrows
the scope of activities requiring
permission from the NRC in the form of
an LWA by eliminating the concept of
‘‘commencement of construction’’
formerly described in § 50.10(c) and the
authorization formerly described in
§ 50.10(e)(1). Instead, under the final
LWA rule, NRC authorization would
only be required before undertaking
activities that have a reasonable nexus
to radiological health and safety and/or
common defense and security for which
regulatory oversight is necessary and/or
most effective in ensuring reasonable
assurance of adequate protection to
public health and safety or common
defense and security. While the NRC’s
redefinition of ‘‘construction’’ will
result in fewer activities requiring NRC
permission in the form of an LWA,
construction permit, or combined
license, it will also define certain
activities (such as the driving of piles)
that are currently excluded from the
regulatory definition of construction
given in § 50.10(b), as construction
requiring such NRC review and
approval.
The LWA final rule also provides an
optional, phased application and
approval procedure for construction
permit and combined license applicants
to obtain LWAs. An applicant may
either submit its LWA application
jointly with a complete construction
permit or combined license application,
or submit it in two parts, with the
information relevant to issuance of an
LWA submitted up to 18 months in
advance of the remainder of the
application addressing the underlying
construction permit or combined
license. Furthermore, under the LWA
final rule, the NRC need not address the
suitability of the site for the operation
of a nuclear power plant before issuing
an LWA. Site suitability will be
addressed as part of the NRC’s
consideration of the underlying
construction permit or combined
license. Moreover, under the LWA final
rule the applicant could seek a separate
determination on site suitability issues
under subpart F of 10 CFR part 2.
The phased approach in the final
LWA rule also provides for an
environmental review and approval
E:\FR\FM\09OCR2.SGM
09OCR2
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
process for LWA requests which allows
the NRC to grant an applicant
permission to engage in LWA activities
after completion of a limited EIS
addressing those activities, but before
completion of the comprehensive EIS
addressing the underlying request for a
construction permit or combined
license. The final LWA rule also
delineates the environmental review
required in situations where the LWA
activities are to be conducted at sites for
which the NRC has previously prepared
an EIS for the construction and
operation of a nuclear power plant, and
for which a construction permit was
issued, but construction of the plant was
never completed.
The NRC concludes that the LWA
final rule is fully consistent with the
NRC’s radiological health and safety and
common defense and security
responsibilities under the AEA.4 As
previously mentioned, the term
‘‘construction’’ is not defined in the
AEA or in the legislative history of the
AEA. Instead of expressly defining the
term in the AEA, Congress entrusted the
agency with the responsibility of
determining what activities constitute
construction.5 The NRC has determined
that the site-preparation activities that
would no longer be considered
construction under this proposed rule
do not have a reasonable nexus to
radiological health and safety, or the
common defense and security.
Accordingly, the NRC concludes that its
definition of the term, ‘‘construction,’’ is
reasonable and complies with the AEA.
The NRC also concludes that issuance
of the LWA in advance of a
consideration of site suitability is
reasonable and complies with the AEA.
Any work under the LWA is done at the
risk of the LWA holder.
C. NRC’s LWA Rule Complies With
NEPA
rwilkins on PROD1PC63 with RULES_2
1. NRC’s Concept of Construction is
Consistent With the Legal Effect of
NEPA
The definition of construction in the
LWA final rule is consistent with the
legal effect of NEPA. Section 50.10(c)
was originally added to part 50 due to
the interpretation that the enactment of
NEPA, not a change in the powers given
to the agency in the AEA, required the
NRC to expand its permitting/licensing
authority. However, subsequent judicial
decisions have made it clear that NEPA
is a procedural statute and does not
expand the jurisdiction delegated to an
4 See State of New Hampshire v. Atomic Energy
Commission, 406 F.2d 170, 174–75 (1st Cir. 1969).
5 Shearon Harris, 7 AEC 939.
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
agency by its organic statute.6 Therefore,
while NEPA may require the NRC to
consider the environmental effects
caused by the exercise of its permitting/
licensing authority, the statute cannot
be the source of the expansion of the
NRC’s authority to require construction
permits, combined licenses, or other
forms of permission for activities that
are not reasonably related to
radiological health and safety or
protection of the common defense and
security. Since NEPA cannot expand the
NRC’s permitting/licensing authority
under the AEA, the elimination of the
blanket inclusion of site preparation
activities in the definition of
construction under § 50.10(c) does not
violate NEPA.
2. NRC’s Concept of the ‘‘Major Federal
Action’’ Is Consistent With NEPA Law
The AEA does not authorize the NRC
to require an applicant to obtain
permission before undertaking site
preparation activities that do not
implicate radiological health and safety
or common defense and security. As a
general matter, the NRC considers these
activities to involve ‘‘non-Federal
action’’ for the purposes of
implementing its NEPA responsibilities.
Generally, non-Federal actions are not
subject to the requirements of NEPA.7
Further, the NRC believes that these
non-Federal site preparation activities
would not generally be ‘‘federalized’’ if
the NRC were to ultimately grant a
combined license or construction
permit. The grant of a construction
permit or combined license by the NRC
is not a legal condition precedent to
these non-Federal, site preparation
activities. While the NRC recognizes
that there may be a ‘‘but for’’ causal
relationship between certain nonFederal site preparation activities and
the major Federal action of issuing a
construction permit or combined
license, such a ‘‘but for’’ causal
relationship is not sufficient to require
non-Federal, site preparation activities
to be treated as Federal action for the
purposes of NEPA.8
In addition, under the narrowed
definition of construction in the LWA
final rule, the NRC concludes that it
does not have the ability or discretion
to influence or control the non-Federal,
6 See,e.g., Robertson v. Methow Valley Citizens
Council, 490 US 332, 350–52 (1989); Natural
Resources Defense Counsel v. U.S. Environmental
Protection Agency, 822 F.2d 104, 129 (D.C. Cir
1987); Kitchen v. Federal Communications
Commission, 464 F.2d 801, 802 (D.C. Cir. 1972).
7 Save the Bay, Inc., v. U.S. Army Corps of
Engineers, 610 F.2d 322, 326 (5th Cir. 1980).
8 See Landmark West! v. U.S. Postal Service, 840
F. Supp. 994, 1006 (S.D.N.Y. 1993) (citing cases).
PO 00000
Frm 00013
Fmt 4701
Sfmt 4700
57427
site preparation activities to the extent
that its influence or control would
constitute practical or factual veto
power over the non-Federal action.
Further, the NRC does not believe that
allowing the non-Federal, site
preparation activities to be undertaken
would restrict its consideration of
alternative sites or the need to assess
whether there is an ‘‘obviously
superior’’ site. Specifically, while the
NRC recognizes that narrowing the
definition of construction may result in
substantial changes to the physical
properties of a site, many of the
fundamental elements that enter into a
determination of the existence of an
‘‘obviously superior’’ site would not be
affected by the changes to those
physical properties. For example,
seismology would not be affected in any
significant way by the non-Federal site
preparation activities. However, while
the effects caused by the non-Federal,
site preparation activities would not be
considered effects of the NRC’s
licensing action, the effects of the nonFederal activities would be considered
during any subsequent ‘‘cumulative
impacts’’ analysis. Specifically, the
effects of the non-Federal activities will
be considered in order to establish a
baseline against which the incremental
effect of the NRC’s major Federal action
(i.e., issuing an LWA, construction
permit, or combined license) would be
measured. These incremental impacts
may be additive or synergistic. To
ensure that the NRC has sufficient
information to perform the cumulative
impacts analysis in a timely fashion, the
final LWA rule includes a requirement,
in § 51.45(c), for the environmental
report submitted by an applicant for an
ESP, construction permit, or combined
license to include a description of
impacts of the applicant’s
preconstruction activities at the
proposed site (i.e., the activities listed in
paragraph (b)(1) through (8) in the
definition of construction contained in
§ 51.4) that are necessary to support the
construction and operation of the
facility which is the subject of the LWA,
construction permit, or combined
license application, and an analysis of
the cumulative impacts of the activities
to be authorized by the LWA,
construction permit, or combined
license in light of the preconstruction
impacts.
3. NRC’s Phased Approval Approach Is
Not Illegal Segmentation Under NEPA
The phased application and approval
of LWAs does not raise the concerns
underlying the prohibition of
segmentation under NEPA law.
Generally, the NEPA segmentation
E:\FR\FM\09OCR2.SGM
09OCR2
rwilkins on PROD1PC63 with RULES_2
57428
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
problem arises when the environmental
impacts of projects are evaluated in a
piecemeal fashion and, as a result, the
comprehensive environmental impacts
of the entire Federal action are never
considered or are only considered after
the agency has committed itself to
continuation of the project. Another
associated segmentation problem arises
when pieces of a Federal action are
evaluated separately and, as a result,
none of the individual pieces are
considered ‘‘major Federal actions’’
requiring an EIS.9
Neither of these segmentation
concerns are presented by the approach
embodied in the LWA final rule. First,
under both LWA application options in
the LWA final rule, the environmental
effects associated with the LWA
activities and the project as a whole (i.e.,
issuance of a construction permit or
combined license) would be evaluated
in an EIS. Therefore, the segmentation
problem of considering a project in
phases, thereby avoiding completion of
an EIS, is not an issue. In addition, all
of the environmental impacts associated
with the construction and operation of
the proposed plant, including the
impacts associated with the LWA
activities, would be considered together,
through incorporation by reference, in
the EIS prepared on the construction
permit or combined license application.
This comprehensive consideration of
environmental impacts would take
place before the NRC is committed to
issuing any construction permit or
combined license. The fact that the NRC
will not have prejudged the ultimate
decision of whether to grant a
construction permit or a combined
license by issuing the LWA, coupled
with the requirement that the site
redress plan be implemented in the
event that the permit or license is
ultimately not issued, also ensures that
issuance of the LWA would not
foreclose reasonable alternatives.
In addition, the proposed application
and approval process is consistent with
the NRC’s previously expressed position
that NEPA does not, as a general matter,
prohibit an agency from undertaking
part of a project without a complete
environmental analysis of the whole
project.10 The key factors used to
support the Commission’s position in
Clinch River were: (1) That the site
preparation activities in that case would
not result in irreversible or irretrievable
commitments to the remaining portions
9 Daniel R. Mandelker, NEPA Law and Litigation,
9–25 (2nd ed. 2004).
10 See Tennessee Valley Authority (Clinch River
Breeder Reactor Plant), 16 NRC 412, 424 (August
17, 1982) (hereinafter Clinch River).
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
of the project, and (2) The
environmental impacts of the site
preparation activities allowed in that
case were substantially redressable.11
These considerations are reflected in
the provisions of the LWA final rule.
Specifically, § 50.10(f) states that any
activity undertaken pursuant to an LWA
are entirely at the risk of the applicant,
that the issuance of the LWA has no
bearing on whether the construction
permit or combined license should be
issued, and that the EIS associated with
the underlying request will not consider
the sunk costs associated with the LWA
activities. In addition, § 50.10(d)(3)
requires an applicant requesting an
LWA to submit a plan for redress of the
activities permitted by the LWA, which
would to be implemented in the event
that the LWA holder is ultimately not
issued a construction permit or
combined license. The redress plan
would achieve this objective by
addressing impacts resulting from LWA
activities (e.g., pile driving, placement
of permanent retaining walls in
excavations, and construction of
foundations for SSCs within the scope
of the LWA final rule). Impacts
associated with pre-LWA activities
would not be addressed in the redress
plan. Further, § 50.10(f) requires that the
site redress plan be implemented within
a reasonable time and that the redress of
the site occur within 18 months of the
Commission’s final decision denying a
construction permit or combined
license.
It should be noted that while redress
of site impacts may have the practical
effect of mitigating some environmental
impacts, the redress plan is not a
substitute for a thorough evaluation of
environmental impacts, or development
of mitigation measures that may be
necessary to provide relief from
environmental impacts associated with
the proposed LWA activities. The
primary purpose of the site redress plan
is to ensure that impacts associated with
any LWA activities performed at the site
will not prevent the site from being used
for a permissible, non-nuclear
alternative use. In this way, the redress
plan helps to preserve the NRC’s ability
to objectively evaluate an application
for a construction permit or combined
license, despite the fact that LWA
activities have been undertaken at the
site.
In sum, the LWA final rule does not
constitute unlawful segmentation in
view of the provisions ensuring that the
issuance of an LWA does not predispose
or bias the NRC’s decision on the
11 Id.
PO 00000
Frm 00014
Fmt 4701
Sfmt 4700
underlying construction permit or
combined license application.
D. Consideration of Activities as
‘‘Construction’’
1. Driving of Piles
A significant change proposed in the
LWA supplemental proposed rule is the
inclusion of the driving of piles for
certain SSCs in the definition of
construction that are not currently
defined as construction in § 50.10(b).
Although the driving of piles was not
expressly included in the definition of
‘‘construction’’ contained in § 50.10(b)
before the amendment of § 50.10(b)(1) in
1968, this activity was generally
considered to be encompassed in the
existing definition of construction at
that time (See 33 FR 2381; January 31,
1968). The 1967 proposed rule
suggested that the driving of piles be
expressly excluded from the definition
of construction because that activity ‘‘is
closely related to, and may be
appropriately included in’’ site
preparation activities, which were not
considered construction (32 FR 11278;
August 3, 1967).12 The rationale for noninclusion of pile driving (and site
preparation activities generally) in the
definition of construction seems to have
been that these activities would have no
effect on the NRC’s ultimate decision to
grant or deny a construction permit, and
that these activities were undertaken
entirely at the applicant’s risk. See 32
FR 11278; August 3, 1967.
The NRC does not believe that the
exclusion of pile driving from the
definition of construction should hinge
on these factors. The Commission
believes that the driving of piles for
certain SSCs (as discussed separately
below) has a reasonable nexus to
radiological health and safety, and/or
common defense and security and,
therefore, is properly considered
‘‘construction’’ as that term is used in
Section 185 of the AEA. In addition, the
inclusion of these activities in the
definition of construction (i.e., requiring
an LWA before they are undertaken),
coupled with the phased approval
process suggested in this supplemental
proposed rule, would allow for early
resolution of the safety issues associated
with these activities. Early resolution of
safety issues is consistent with the
general rationale underlying the
licensing and permitting processes
provided in 10 CFR part 52.
Accordingly, the final rule’s definition
of construction includes the driving of
piles for certain SSCs.
12 The proposed rule language was issued without
modification in the final rule. (33 FR 2381; January
31, 1968.)
E:\FR\FM\09OCR2.SGM
09OCR2
rwilkins on PROD1PC63 with RULES_2
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
2. Excavation
The LWA supplemental proposed rule
would have included excavation within
the definition of construction. The
inclusion of excavation within the ambit
of construction was based upon two
factors: (1) Excavation activities in the
past have uncovered potentially adverse
geologic, soil, and hydrological
conditions not anticipated by the
construction permit applicant, which
have resulted in design changes; and (2)
Excavation activities in the past have
caused unanticipated damage to
surrounding native rock, which had to
be corrected by the construction permit
holder. The NRC believed that, in these
situations, these considerations
provided the ‘‘reasonable nexus to
radiological health and safety and/or
common defense and security’’
necessary to include excavation in the
definition of construction.
Upon consideration of stakeholder
comments and further evaluation, the
NRC has determined that it is not
necessary to include excavation within
the definition of construction, thus
requiring some kind of NRC review and
approval before undertaking excavation,
to ensure public health and safety or
common defense and security in the
situations noted previously. With
respect to geologic, soils, and
hydrological matters, prior NRC review
and approval of excavation is not
necessary to ensure that any adverse
geologic, soil, or hydrological
conditions that result in the need for
design changes or some other form of
mitigation are considered in NRC’s
review of the associated LWA,
construction permit, or combined
license application. In the situation
where a potential applicant performs
excavation activities before submitting
its LWA, construction permit, or
combined license application, 10 CFR
52.6(a) requires that information
provided to the Commission by an
applicant for a license be complete and
accurate in all material respects. In the
situation where an applicant performs
excavation activities after submitting its
LWA, construction permit, or combined
license application, 10 CFR 52.6(b)
requires the applicant to notify the
Commission of information identified
by the applicant as having, for the
regulated activity, a significant
implication for public health and safety
or common defense and security. The
staff believes that 10 CFR 52.6 provides
an equally-acceptable way of ensuring
public health and safety if excavation is
eliminated from the definition of
construction for those limited situations
where excavation activities uncover
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
potentially adverse geologic, soil, and
hydrological conditions not anticipated
by the applicant, or if excavation
activities cause unanticipated damage to
the surrounding native rock. The LWA,
construction permit, and combined
license applicant, as applicable, would
be responsible—as is currently the
case—for adequately describing the
geologic, soil, and hydrologic conditions
of the site. The difference with the
approach in this final rule is that the
approved site description will, in many
cases, be based upon actual knowledge
of the conditions as revealed or
confirmed by the excavation activities,
and not only on reasonable assumptions
based upon extrapolations from test
borings and other indirect information.
Therefore, in many cases, the actual
foundation and structural design to be
approved at the construction permit or
combined license stage would be based
upon actual geologic, soils, and
hydrological information as revealed or
confirmed by the excavation.
For these reasons, the Commission
concludes that existing regulatory
mechanisms provide reasonable
assurance of public health and safety
and common defense and security
without imposition of the regulatory
mechanism of prior NRC review and
approval of excavation activities.
Accordingly, the LWA final rule does
not define excavation as being within
the ambit of construction.
3. Temporary Structures and Activities
in the Excavation
Construction, under the LWA final
rule, includes the placement/
installation of backfill, concrete, or
permanent retaining walls within an
excavation. These activities involve the
placement/installation of permanent
parts of the overall facility, and
therefore are properly considered
‘‘construction.’’ By contrast, the
placement/installation of temporary
SSCs which will not become part of the
final facility, and therefore are removed,
should not be treated as ‘‘construction,’’
inasmuch as they have no ongoing
nexus to radiological health and safety
or common defense and security.
Accordingly, activities in the excavation
for SSCs within the scope of
construction, such as the placement/
installation of temporary drainage,
erosion control, retaining walls,
environmental mitigation, are not
considered to be within the purview of
‘‘construction,’’ so long as these
temporary items are removed from the
excavation before fuel load. The NRC
chose fuel loading as a convenient, well
understood and clear event for
delineating the time by which
PO 00000
Frm 00015
Fmt 4701
Sfmt 4700
57429
temporary SSCs must be removed from
the excavation, in order for those
temporary SSCs to be excluded from the
definition of construction.
4. Construction SSCs
The LWA supplemental proposed rule
revised the former definition of
construction in 10 CFR 50.10(c) to
include the onsite, in-place fabrication,
erection, integration, or testing of any
SSC required by the Commission’s rules
and regulations to be described in the
site safety analysis report, preliminary
safety analysis report, or final safety
analysis report. This definition of
construction included basically all SSCs
of a facility, except for those SSCs that
were specifically excluded by the
proposed definition (e.g., potable water
systems). However, as stated in the
supplemental proposed rule, the
Commission has determined that
construction should include all of the
activities that have a reasonable nexus
to radiological health and safety, or
common defense and security.
Upon consideration of stakeholder
comments and further evaluation, the
NRC has determined that there may be
some SSCs of a facility which are
required to be described in the FSAR,
but which do not have a reasonable
nexus to radiological health and safety
or the common defense and security.
These SSCs are those which are
required to be described in the FSAR to
provide contextual information for
understanding the overall design and
operation of the facility, but which do
not actually directly affect the
radiological health and safety of the
public or the common defense and
security, and their indirect effect on
such health and safety or common
defense and security is so low as to be
considered negligible. The
determination of SSCs which do not
have a reasonable nexus to radiological
health and safety or common defense
and security depends on the design of
the facility. An example SSC is the
administration building. However, an
administration building that includes
the technical support center would fall
within the scope of SSCs covered by the
definition of construction. In sum, the
NRC has clarified and narrowed the
scope of SSCs falling within the scope
of construction to exclude those SSCs
which have no reasonable nexus to
radiological health and safety or
common defense and security.
For the LWA final rule, the scope of
SSCs falling within the definition of
construction was derived from the scope
of SSCs that are included in the program
for monitoring the effectiveness of
maintenance at nuclear power plants, as
E:\FR\FM\09OCR2.SGM
09OCR2
57430
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
rwilkins on PROD1PC63 with RULES_2
defined in 10 CFR 50.65(b). This
definition is well understood and there
is good agreement on its
implementation. The NRC has
supplemented the definition in
§ 50.65(b) to include the SSCs that are
necessary to comply with 10 CFR 50.48
and criterion 3 of 10 CFR part 50,
appendix A, and the onsite emergency
facilities, that is, technical support and
operations support centers, that are
necessary to comply with 10 CFR 50.47
and 10 CFR part 50, appendix E. These
SSCs were added because they have a
reasonable nexus to radiological health
and safety. The SSCs that are necessary
to comply with 10 CFR part 73 were
added because they are required for the
common defense and security.
E. Phased Application and Approval
Process
Another significant change in this
final rule is the modification of the
procedure for obtaining LWA approval
by implementing an optional phased
application and approval process.
Specifically, § 2.101(a)(9) allows
applicants for construction permits and
combined licenses the option of
submitting either: (1) A complete
application, or (2) a two-part application
with part one including information
required for the NRC to make a decision
on the applicant’s request to undertake
LWA activities, and part two containing
all other information required to obtain
the underlying license or permit. The
final rule allows the NRC to consider
the environmental impacts attributable
to the requested LWA activities
separately, either as part of a
comprehensive EIS in the case where a
complete application is submitted, or in
a separate EIS addressing only the LWA
activities in the case of a two-part
application. After consideration of the
environmental impacts and the relevant
safety-related issues associated with the
LWA activities, the NRC may allow the
applicant to undertake the LWA
activities, even if the EIS on the
underlying request (i.e., construction
permit or combined license) is not
complete.
The NRC believes that this phased
application and approval process is
more efficient because it prevents
unnecessary delay in nuclear power
plant construction schedules. This delay
would result if issuance of an LWA for
safety-related activities were delayed
until the final EIS and adjudicatory
hearing on the entire underlying license
application were complete. In addition,
the final rule’s application and approval
process should result in the timely
resolution of relevant safety and
environmental issues at an earlier stage
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
in the licensing process. As previously
discussed, the NRC believes that these
efficiencies can be gained without
compromising the agency’s NEPA
responsibilities, as the phased approach
presented in this supplemental
proposed rule does not constitute illegal
segmentation.
F. EIS Prepared, but Facility
Construction Was Not Completed
The LWA final rule also addresses the
situation where a request is made to
perform LWA activities at a site for
which an EIS has previously been
prepared for the construction and
operation of a nuclear power plant, and
a construction permit has been issued,
but construction of the plant was never
completed. In this special situation, the
final rule allows an applicant to
reference the previous EIS in its
environmental report, but requires that
the applicant identify any new and
significant information material to the
matters required to be addressed in the
proposed § 51.49(a). Further, in these
special cases the final rule provides that
the NRC will incorporate by reference
the previous EIS when preparing its
draft EIS on the LWA activities. The
draft EIS on the LWA request is limited
to the consideration of any new and
significant information dealing with the
environmental impacts of construction,
relevant to the activities to be carried
out under the LWA. Further, in a
hearing on issuance of an LWA at such
sites, the presiding officer is limited to
determining whether there is new and
significant information pertaining to the
environmental impacts of the
construction activities encompassed by
the previous EIS that are analogous to
the activities to be conducted under the
LWA. The presiding officer would
evaluate new and significant
information in determining whether an
LWA should be issued as proposed by
either the Director of the Office of New
Reactors or the Director of the Office of
Nuclear Reactor Regulation, as
applicable.
This provision is designed to gain
efficiency by using existing EISs to
evaluate the environmental impacts of
activities to be performed under an
LWA. The Commission believes that
this practice is appropriate because the
referenced environmental review will
come in the form of an FEIS prepared
by NRC staff for sites on which
permission to construct a nuclear power
plant was ultimately granted by the
Commission. The Commission
understands that the activities proposed
in a current LWA request may be
different from the activities proposed
and analyzed in the previous FEIS
PO 00000
Frm 00016
Fmt 4701
Sfmt 4700
referenced by an applicant and relied
upon by NRC staff. However, it is the
Commission’s intent that if these
differences result in significant changes
to the environmental impacts caused by
the LWA activities currently proposed
by the applicant, then the differences
should be considered ‘‘new and
significant information’’ material to the
environmental impacts that may
reasonably be expected to result from
the LWA activities. Therefore, these
differences should be addressed in the
applicant’s environmental report,
analyzed by the NRC staff in a
supplement to the existing FEIS, and
considered by the presiding officer.
Further, for the reasons previously
discussed in Section C.3 of this
document, the Commission does not
believe that authorizing LWA activities
before completion of the FEIS on the
combined license or construction permit
will have the effect of prejudging the
license/permit, or foreclosing reasonable
alternatives.
G. Commission Action on PRM–50–82
As discussed previously, the
Commission is treating the May 25,
2006, comments of NEI on the March
2006 proposed part 52 rule as a petition
for rulemaking, which has been
designated PRM–50–82. The petition
was effectively granted when the
supplemental proposed LWA rule was
published (71 FR 61330; October 17,
2006). With the adoption of this final
LWA rule, the Commission has
completed action on PRM–50–82.
IV. Section-by-Section Analysis
Part 2—Rules of Practice for Domestic
Licensing Proceedings and Issuance of
Orders
Section 2.101, Filing of Application
Section 2.101 is revised by adding a
new paragraph (a)(9), which provides
that an applicant for a construction
permit or combined license may submit
a request for an LWA either as part of
a complete application under
paragraphs (a)(1) through (4), or in two
parts under this paragraph (i.e., a
‘‘phased LWA application’’). If the LWA
application is submitted as part of a
complete construction permit or
combined license application, the
application must include the
information required by § 50.10(d)(3).
If the application is a phased LWA
application, the first part must contain
the information required by
§ 50.10(d)(3) on the LWA, as well as the
general information required of all
production and utilization facility
applicants under § 50.33(a) through (f).
The second part of the application must
E:\FR\FM\09OCR2.SGM
09OCR2
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
contain the remaining information
otherwise required to be filed in a
complete application under § 2.101(a)(1)
thorough (4). However, the applicant
would have the further option of
submitting part two in additional
subparts in accordance with § 2.101(a–
1). The second part (or the first subpart
of multiple subparts under § 2.101(a–1))
must be filed no later than 18 months
after the filing of part one. Part two of
the application (or the first subpart of
any additional subparts submitted in
accordance with § 2.101(a–1)) must be
submitted no later than 18 months after
submission of part one of the
application.
An applicant for an ESP may not
submit its LWA application in advance
of the underlying ESP application, and
therefore is not permitted to use the
procedures of subpart F of part 2, or
submit its application in two parts
under § 2.101(a)(9). Similarly, the
holder of an ESP is not permitted to use
the procedures of subpart F of part 2,
nor to submit its ESP amendment
application for LWA authority in two
parts under § 2.101(a)(9).
Section 2.102, Administrative Review of
Application
Paragraph (a) of § 2.102 is revised by
adding an LWA to the list of docketed
applications for which the NRC staff
must establish a schedule for review of
the application.
Section 2.104, Notice of Hearing
The introductory text of paragraph (a)
is revised to add LWAs to the list of
application types for which the
Commission must issue a hearing
notice. In addition, paragraph (c)(1) is
revised to require the relevant NRC Staff
Director to transmit a copy of the notice
of hearing for an application for an LWA
to state and local officials. In many
cases, this is a formality, inasmuch as
pre-application interactions between the
NRC and the potential LWA applicant
will result in informal contacts with
those state and local officials.
rwilkins on PROD1PC63 with RULES_2
Subpart F
The title of subpart F is revised to
reflect the broader scope of matters
covered under this section, as described
under § 2.600.
Section 2.600, Scope of Subpart
The statement of scope in § 2.600 is
revised to reflect the new set of
procedures for phased LWA
applications in proposed §§ 2.641
through 2.649. A new paragraph (d) is
added to refer to §§ 2.641 through 2.649
as containing the applicable procedures
for phased construction permit and
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
combined license applications which
also request LWA authority.
Section 2.606, Partial Decision on Site
Suitability Issues
Paragraph (a) of § 2.606, which
provides that an LWA may not be issued
without completion of the ‘‘full review’’
required by NEPA, is revised to remove
the reference to an LWA, because LWAs
are now covered in §§ 2.641 through
2.649.
Section 2.641, Filing Fees
Section 2.641, which is comparable to
current § 2.602, provides that a phased
LWA application must be accompanied
by the applicable filing fees in § 50.30(e)
and part 170 of this chapter.
Section 2.643, Acceptance and
Docketing of Application for Limited
Work Authorization
Section 2.643, which is comparable to
current § 2.603, describes the
acceptance and docketing requirements
for phased LWA applications, and the
requirement for publication in the
Federal Register of a notice of
docketing. Paragraph (a) provides that
each part of the application, when first
received, will be treated as a tendered
application and assessed for sufficiency.
If the submitted part of the application
is determined to be incomplete, the
relevant Director will inform the
applicant. The determination of
completeness will generally be made in
30 days, barring unusual circumstances.
Under paragraph (b), the Director will
docket part one of the application only
if that part is ‘‘complete.’’ The NRC
would use the existing guidelines and
practices for determining the
completeness of applications under this
section, as are used in determining
completeness under § 2.101. Upon
docketing, the Director will assign a
docket number that will be used
throughout the entire proceeding
(including that part of the proceeding on
part two of the application).
Under paragraph (c), the Director will
make the designated distributions to the
Governor of the State in which the
nuclear power plant will be located, and
publish a notice of docketing in the
Federal Register. Often in practice, the
notice of hearing required by the AEA
is included in the notice of docketing,
but as with existing applications, this
will remain a matter of discretion by the
NRC, who will determine the most
efficient course of action in this regard.
Paragraph (d) provides that part two
of the application will be docketed, as
with part one, when it is determined to
be complete. The Commission reiterates
that ‘‘part two’’ could be submitted in
PO 00000
Frm 00017
Fmt 4701
Sfmt 4700
57431
several subparts if the applicant chose
to take advantage of the provisions of
§ 2.101(a–1), which provides for
submission of applications in three
parts.
Finally, under paragraph (e), the
Director is required to publish a second
notice of docketing in the Federal
Register for part two of the application.
As with the notice of docketing for part
one, the notice of docketing for part two
may also include a notice of hearing on
the second part of the application.
The NRC notes that nothing in
§ 2.101(a)(9), or any part of subpart F of
part 2, requires that the hearing on part
one of the application be completed and
an initial decision issued by the
presiding officer, before part two of the
application is filed.
Section 2.645, Notice of Hearing
Section 2.645, which is comparable to
current § 2.604, sets forth the content of
the notice of hearing for each of the two
parts of the proceeding. Paragraph (a)
provides that the notice of hearing for
part one specify that the hearing will
relate only to consideration of the
matters related to § 50.33(a) through (f),
and the LWA issues under review.
Although not explicitly stated in this
paragraph, interested persons who seek
to intervene in the hearing on part one
of the application must file a petition to
intervene in accordance with the notice
of hearing, and § 2.309.
Under paragraph (b), a supplementary
notice of hearing will be published in
the Federal Register when part two of
the application is docketed. This
provides a second opportunity for
interested persons to file petitions to
intervene with respect to the matters
relevant to part two of the application.
These petitions must be filed within the
time specified in the notice of hearing,
and must meet the applicable
requirements of subpart C of part 2,
including the contention requirements
in § 2.309.
Paragraph (c) addresses continued
participation in a phased application
involving a request for advance
consideration for an LWA. The
provisions of paragraph (c) differ
somewhat from the existing procedures
in § 2.604 applicable to phased
applications which do not involve
LWAs, in that the Commission has
decided not to allow a party admitted in
part one of the proceeding, who did not
withdraw or was not otherwise
dismissed, to automatically continue as
a party in phase two of the proceeding.
Instead, each party who wishes to
participate in the second phase must
submit a second petition to intervene in
accordance with § 2.309. The petition
E:\FR\FM\09OCR2.SGM
09OCR2
57432
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
need not, however, address the interest
and standing requirements in § 2.309(d).
The petition must be filed within the
time provided by the supplementary
notice of hearing published in the
Federal Register for part two of the
application.
Paragraph (d) makes clear that a nontimely petition for intervention filed
under paragraph (b) (incorrectly referred
to as paragraph (c) in the supplemental
proposed rule) must meet the factors in
both 2.309(c)(1)(i) through (iv), as well
as 2.309(d). This is no different than
non-timely petitions for intervention
filed in ordinary, non-phased
proceedings.
As noted in the Section-by-Section
Analysis in this document for § 2.643,
nothing in § 2.101(a)(9) or subpart F of
part 2 requires that the hearing on part
one of the application be completed and
an initial decision issued by the
presiding officer, before part two of the
application is filed. Thus, there may be
simultaneous hearings on parts one and
two of the application. However, as
reflected in paragraph (e), the
Commission’s intent is that the
membership of the Atomic Safety and
Licensing Board designated for hearings
under part one be the same as for the
hearings under part two, to the extent
practical and consistent with timely
completion of each hearing.
Section 2.647 [Reserved]
This section is reserved for future use
by the Commission.
rwilkins on PROD1PC63 with RULES_2
Section 2.649, Partial Decisions on
Limited Work Authorization
Section 2.649, which is comparable to
§ 2.606, denotes the provisions in
subparts C and G to part 2 relative to
issues such as oral arguments,
immediate effectiveness of the presiding
officer’s initial decision, and petitions
for Commission review, that apply to
partial initial decisions on an LWA
rendered in accordance with this
subpart. This section also states that the
LWA may not be issued without
completion of the environmental review
required for LWAs under subpart A of
part 51. Finally, this section provides
that the time for the Commission to
exercise its review and sua sponte
authority is the same time provided for
in part 2 with respect to a final decision
on issuance of a construction permit or
combined license.
Part 50—Domestic Licensing of
Production and Utilization Facilities
50.10, License Required; Limited Work
Authorization
Paragraph (a), which is derived from
former § 50.10(b), sets forth a new
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
definition of ‘‘construction’’ for
purposes of this section (the same
definition is also used in part 51, see 10
CFR 51.4). The definition of
construction has been substantially
modified from the definition in former
§ 50.10(b) in both structure and content,
and supersedes the definition of
construction in former § 50.10(c). The
new definition is divided into two parts,
with the first specifying the activities
deemed to constitute ‘‘construction,’’
and the second part specifying activities
which are excluded from the definition.
Under the new definition, excavation
is excluded from construction.
Excavation includes the removal of any
soil, rock, gravel, or other material
below the final ground elevation to the
final parent material. Thus, all these
excavation activities may be conducted
without an LWA, construction permit,
or combined license. However, the
placement of permanent, non-structural
dewatering materials, mudmats and/or
engineered backfill which are placed in
advance of the placement of the
foundation and associated permanent
retaining walls for SSCs within the
scope of the definition of construction
are not excavation activities, but instead
fall within the scope of construction.
Any person or entity that conducts
excavation, however, should be aware
that the NRC expects any subsequent
LWA, construction permit, or combined
license application to accurately
document and address the conditions
exposed by excavation, to ensure that
the NRC will have an adequate basis for
evaluating the relevant portions of the
LWA, construction permit, or combined
license application.
Whereas former § 50.10(b) allowed the
driving of piles for the facility without
NRC approval, the LWA final rule does
not permit driving of piles for SSCs
described in the definition of
construction, unless NRC permission is
obtained in the form of an LWA,
construction permit, or combined
license. The ‘‘driving of piles’’ not
related to ensuring the structural
stability or integrity of any SSC within
the scope of the definition of
construction does not fall within the
definition of construction in this
paragraph, and therefore may be
accomplished without an LWA,
construction permit, or combined
license. For example, piles driven to
support the erection of a bridge for a
temporary or permanent access road
would not be considered ‘‘construction’’
under this section and may be
performed without an LWA,
construction permit, or combined
license.
PO 00000
Frm 00018
Fmt 4701
Sfmt 4700
The SSCs which are within the scope
of the definition of construction, and
which have a reasonable nexus to
radiological health and safety or
common defense and security are set
forth in paragraph (a)(1). This definition
was derived from the scope of SSCs that
are included in the program for
monitoring the effectiveness of
maintenance at nuclear power plants
under 10 CFR 50.65, and supplemented
with SSCs that are needed for fire
protection, security, and onsite
emergency facilities. There may be some
SSCs of a facility which do not have a
reasonable nexus to radiological health
and safety or common defense and
security. The determination of the SSCs
that do not have a reasonable nexus to
radiological health and safety or
common defense and security will be
dependent upon the design of the
facility. An example SSC that would not
be within the scope of construction is a
cooling tower that is used to cool the
turbine condenser. However, a cooling
system that is used for both safety and
non-safety functions would fall within
the definition of construction.
Construction, as defined in this
paragraph includes installation of the
foundation, including soil compaction;
the installation of permanent drainage
systems and geofabric; the placement of
backfill, concrete (e.g., ‘‘mudmats’’) or
other materials which will not be
removed before placement of the
foundation of a structure; the placement
and compaction of a subbase; the
installation of reinforcing bars to be
incorporated into the foundation of the
structure; the erection of concrete forms
for the foundations that will remain inplace permanently (even if nonstructural); and placement of concrete or
other material constituting the
foundation of any SSC within scope of
the definition of construction.
Foundation installation activities will
require an LWA, construction permit, or
combined license. The term
‘‘permanent’’ in this context, includes
anything that will exist in its final, inplace plant location after fuel load. By
contrast, the term, ‘‘temporary,’’ means
anything that will be removed from the
excavation before fuel load.
Construction also includes the
‘‘onsite, in-place,’’ fabrication, erection,
integration, or testing activities for any
in-scope SSC. The term, ‘‘onsite, in
place, fabrication, erection, integration
or testing’’ is intended to describe the
historical process of constructing a
nuclear power plant in its final, onsite
plant location, where components or
modules are integrated into the final, inplant location. The definition is
intended to exclude persons from
E:\FR\FM\09OCR2.SGM
09OCR2
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
rwilkins on PROD1PC63 with RULES_2
having to obtain an LWA, construction
permit, or combined license, to
fabricate, assemble, and test
components and modules in a shop
building, warehouse, or laydown area
located onsite. However, the installation
or integration of that SSC into its final
plant location would require either a
construction permit or combined
license. The NRC notes that under
§ 50.10(a)(2)(ix), construction does not
include manufacturing of a nuclear
power reactor under subpart F of part
52, even if the manufacturing is
accomplished onsite, so long as the
manufacturing is not done in-place, at
the final (permanent) plant location on
the site.
Paragraph (b), which is derived from
former § 50.10(a), prohibits any person
within the United States from
transferring or receiving in interstate
commerce, manufacturing, producing,
transferring, acquiring, possessing, or
using any production or utilization
facility except as authorized by a license
issued by the Commission, or as
provided in § 50.11.
Paragraph (c), which is substantially
modified from the former § 50.10(b),
prohibits any person from beginning the
‘‘construction’’ of a production or
utilization facility on a site on which
the facility is to be operated until that
person has been issued a construction
permit, a combined license under part
52, or an LWA under paragraph (d) of
this section.
Paragraph (d), which is substantially
modified from the former § 50.10(e),
addresses the need for, nature and
contents of an application for an LWA.
Paragraph (d)(1) allows the Commission
to issue an LWA in advance of a
construction permit or combined
license, authorizing the holder to
perform certain delineated construction
requirements.
Paragraph (d)(2) provides that an
LWA application may be submitted as:
—Part of a complete application for a
construction permit or combined
license under § 2.101(a)(1) through
(4).
—Part one of a phased application
under § 2.101(a)(9).
—Part of a complete application for an
ESP under § 2.101(a)(1) through (4).
—An amendment to an already issued
ESP.
Paragraph (d)(3) establishes the
requirements for the content of an LWA
application. The application must
include a safety analysis report, an
environmental report, and a redress
plan. The safety analysis report, which
may be a stand-alone document or
incorporated into the construction
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
permit or combined license
application’s preliminary or FSAR, as
applicable, must describe the LWA
activities that the applicant seeks to
perform, provide the final design for the
structures to be constructed under the
LWA and a safety analysis for those
portions of the structure, and provide a
safety analysis of the design
demonstrating that the activities will be
conducted in accordance with
applicable Commission safety
requirements.
The environmental report must meet
the requirements of 10 CFR 51.49,
which is discussed in more detail in the
Section-by-Section Analysis in this
document for that provision.
The redress plan must describe the
activities that would be implemented by
the LWA holder, should construction be
terminated by the holder, the LWA is
revoked by the NRC, or upon
effectiveness of the Commission’s final
decision denying the associated
operating license application or the
underlying combined license
application, as applicable. The primary
purpose of the redress plan is to address
the placement of piles and ensure
removal of the foundation, which are
the only activities which may be
accomplished under an LWA. Redress
of site impacts resulting from pre-LWA
activities will not be required under the
redress plan. In addition, while redress
of LWA impacts may have the practical
effect of mitigating some environmental
impacts, the redress plan is not a
substitute for a thorough evaluation of
environmental impacts, or development
of mitigation measures that may be
necessary to provide relief from
environmental impacts associated with
the proposed LWA activities.
Paragraph (e) generally addresses the
requirements associated with issuance
of an LWA. Paragraph (e)(1) sets forth
the requirements for the appropriate
Director to issue an LWA under this
section. The Director may issue an LWA
only after making the appropriate
findings on: (1) Necessary technical
qualifications, and the matter of foreign
ownership or control relevant to the
information required by § 50.33(a)
through (f), as mandated by Sections
103.d. and 182.a. of the AEA; (2) Making
the necessary findings on public health
and safety and common defense and
security with respect to the activities to
be carried out under the LWA; (3) NRC
staff issuance of a final EIS on the LWA
in accordance with the applicable
requirements of part 51; and (4) The
presiding officer finding on the
environmental issues relevant to the
LWA in accordance with the applicable
requirements of part 51, and a finding
PO 00000
Frm 00019
Fmt 4701
Sfmt 4700
57433
on the safety issues relevant to the
LWA.
Paragraph (e)(2) requires that the
LWA specify the activities that the
holder is authorized to perform,
consistent with the LWA application
and as modified based upon the NRC’s
review. In addition, each LWA will be
issued with a condition requiring
implementation of the redress plan if
the LWA holder terminates
construction, the LWA is revoked, or
upon effectiveness of the Commission’s
final decision denying the associated
operating license application or the
underlying combined license
application, as applicable. As discussed
in the analysis of paragraph (e), this
condition survives the merging of the
LWA into the underlying construction
permit, ESP, or combined license.
Paragraph (f), which is also derived
from former § 50.10(e), addresses the
legal effect of an issued LWA. Paragraph
(f)(1) provides that any activities
undertaken under an LWA shall be
entirely at the risk of the applicant and,
with exception of the matters
determined under paragraph (d)(3)(ii)
and (iii), the issuance of the LWA shall
have no bearing on the issuance of a
construction permit or combined license
with respect to the requirements of the
AEA, and rules, regulations, or orders
issued under the AEA. Thus, this
paragraph states that the EIS for a
construction permit or combined license
application for which an LWA was
previously issued will not address, and
the presiding officer will not consider,
the sunk costs of the holder of the LWA
in determining the proposed action (i.e.,
issuance of the construction permit or
combined license).
New paragraph (g) requires the LWA
holder to begin implementation of the
redress plan in a reasonable time, and
complete the redress no later than 18
months after termination of construction
by the holder, revocation of the LWA, or
upon effectiveness of the Commission’s
final decision denying the associated
operating license application, or the
underlying construction permit or the
combined license application, as
applicable.
Part 51—Environmental Protection
Regulations for Domestic Licensing and
Related Regulatory Functions
Section 51.4, Definitions
Section 51.4 is revised by adding a
new definition of ‘‘construction.’’ This
makes applicable throughout part 51 the
definition of construction in proposed
§ 50.10(a), and has the effect of
excluding from an EIS for any ESP,
construction permit, combined license,
E:\FR\FM\09OCR2.SGM
09OCR2
57434
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
or an LWA, any discussion, evaluation
or consideration of the environmental
impacts or benefits associated with nonconstruction activities as set forth in
§ 50.10(a). This also removes the need
for the NRC decision maker, including
a presiding officer, to make a NEPA
finding with respect to the
environmental impacts or benefits
associated with those non-construction
activities.
Section 51.17, Information Collection
Requirements; OMB Approval
Paragraph (b) is revised by adding a
reference to a new § 51.49, which
requires submission of an
environmental report by LWA
applicants. While § 51.49 contains a
new information collection requirement,
this will not result in a net increase in
the burden placed on LWA applicants
because the information required under
this new section was formerly required
to be submitted by these applicants as
part of a complete environmental report
for the underlying ESP, construction
permit or combined license under
§ 51.50. The primary effect of this final
rule would be to allow delayed
submission of most of the
environmental information to the time
that the underlying construction permit
or combined license application and
environmental report is submitted.
Thus, the environmental report
submitted under § 51.49 at the LWA
stage would, in most cases, be limited
in scope to address environmental
impacts of LWA activities only.
rwilkins on PROD1PC63 with RULES_2
Section 51.45, Environmental Report
Paragraph (c) is revised by adding a
new requirement requiring
environmental reports for ESP,
construction permits, and combined
licenses to include a description of
impacts of the applicant’s preconstruction activities at the proposed
site (i.e., the activities listed in
paragraph (b)(1) through (8) in the
definition of construction contained in
§ 51.4) that are necessary to support the
construction and operation of the
facility which is the subject of the LWA,
construction permit, or combined
license application, and an analysis of
the cumulative impacts of the activities
to be authorized by the LWA,
construction permit, or combined
license in light of the preconstruction
impacts.
Section 51.49, Environmental ReportLimited Work Authorization
A new § 51.49 is added to part 51.
This new section requires the applicant
for an LWA to submit an environmental
report containing certain specified
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
information. Both paragraph (a), which
applies to an applicant requesting an
LWA as part of a complete application,
and paragraph (b), which applies to an
applicant submitting its application in
two parts under § 2.101(a)(9), requires
the applicant to submit an
environmental report which describes:
(1) The activities proposed to be
conducted under the LWA; (2) The need
to conduct those LWA activities in
advance of the main action; (3) A
description of the environmental
impacts that may reasonably be
expected to result from the conduct of
the requested LWA activities; (4) The
mitigation measures to be implemented
to achieve the level of environmental
impacts described; and (5) A discussion
of the reasons for rejecting other
mitigation measures that could be used
to further reduce environmental
impacts. Regardless of whether an LWA
applicant submits an application in two
parts, or seeks early consideration and
decision on site suitability and
environmental siting matters, the
environmental report for the LWA
should address any impacts attributable
to activities for which NRC approval is
not required (i.e., the activities excluded
from the definition of construction in
§ 50.12(a)).
Paragraph (c) describes the contents of
the environmental report when the
request for the LWA is submitted as part
of an ESP application. There is no
opportunity for an ESP holder to submit
its application in two parts, with the
LWA information submitted in advance
of the main ESP application.
Paragraph (d) describes the contents
of the environmental report when the
LWA request is submitted by an ESP
holder. In this situation, the
environmental report need only contain
information on the LWA activities and
their environmental impact, and would
not include the general information
required by § 51.50(b).
Paragraph (e) establishes a limited
exception from the information required
by paragraphs (a) and (b) to be
submitted in an environmental report.
For those situations where the LWA is
to be conducted at a site for which the
Commission previously prepared an EIS
for the construction and operation of a
nuclear power plant, the construction
permit was issued, but the construction
of the plant was never completed, then
the applicant’s environmental report
may incorporate by reference the earlier
EIS. However, in the event of
incorporation by reference, the
environmental report must identify
whether there is new and significant
information relative to the matters
required to be addressed in the
PO 00000
Frm 00020
Fmt 4701
Sfmt 4700
environmental report with respect to the
environmental impacts of the requested
LWA activities, as specified in
paragraphs (a) or (b). In addition,
analogous to the requirement in
§ 51.50(c)(1)(iv) of the 2007 final part 52
rule, the environmental report must
include a description of the process for
identifying new and significant
information. The applicant should have
a reasonable process for identifying new
and significant information that may
have a bearing on the earlier NRC
conclusion, and should document the
results of this process in an auditable
form. Documentation related to the
applicant’s search for new information
and its determination about the
significance of that new information
should be maintained in an auditable
form by the applicant. The NRC staff
will verify that the applicant’s process
for identifying new and significant
information is effective.
Paragraph (f) requires, for any
application containing an LWA request,
that the environmental report must
separately evaluate the environmental
impacts and proposed alternatives to the
activities proposed to be conducted
under the LWA. However, at the option
of the applicant, the environmental
report may also include the information
required by § 51.50 to be submitted in
the environmental report for the
construction permit or combined license
application. In those situations, the
‘‘integrated’’ environmental report
would separately address the total
impacts of constructing (including the
LWA activities) and operating the
proposed facility. This will allow the
NRC to prepare in parallel the EIS for
the LWA activities and a supplemental
EIS for the underlying construction
permit or operating license, or a
complete EIS at the LWA stage.
Section 51.71, Draft Environmental
Impact Statement—Contents
Section 51.71 is revised by
redesignating the current paragraph (e)
as paragraph (f), and a new paragraph
(e) is added to re-emphasize that the
draft EIS for the underlying construction
permit or combined license will not
address or consider the sunk costs
associated with the LWA. Paragraph (e)
is consistent with § 50.10(f) and new
§ 51.103(a)(6).
Section 51.76, Draft Environmental
Impact Statement—Limited Work
Authorization
Section 51.76 is a new section
governing the NRC’s preparation of a
draft EIS to support a decision on an
LWA. The internal organization of
§ 51.76 parallels that of § 51.49.
E:\FR\FM\09OCR2.SGM
09OCR2
rwilkins on PROD1PC63 with RULES_2
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
Paragraph (a) addresses the EIS to be
prepared in connection with a complete
application for a construction permit or
combined license. This section allows
the NRC to prepare at the time of the
LWA application either an EIS limited
to LWA activities (to be followed by a
supplemental EIS on the underlying
construction permit or combined
license), or a single, complete EIS for
the construction permit or combined
license. The NRC notes that this
paragraph addresses the situation where
the application for the construction
permit or combined license is complete
and includes the request and necessary
information for an LWA. Paragraph (b),
by contrast, addresses the situation
where the LWA request is submitted in
advance of the complete application for
the construction permit or combined
license.
Paragraph (b) applies to an EIS
prepared in support of a phased LWA
under § 2.101(a)(9). In this situation, if
the environmental report submitted in
part one is limited to the LWA
activities, then the NRC will prepare an
EIS limited to the LWA activities. Once
part two of the application is received,
which includes the environmental
report required by § 51.50, the NRC will
prepare a supplemental EIS for the
construction permit or combined license
in accordance with § 51.71, and
§ 51.75(a) or (c), as applicable. By
contrast, if the environmental report
submitted in part one is a complete
environmental report required by
§ 51.50, then the NRC will prepare at the
LWA phase a single, complete EIS for
the construction permit or combined
license in accordance with § 51.71, and
§ 51.75(a) or (c), as applicable.
Paragraph (c) applies to an EIS
prepared for issuance of an ESP which
will also include an LWA. The EIS will
address the scope of matters required to
be addressed under § 51.75(d), which
depends upon the matters which the
applicant chooses to address in its
environmental report, as well as the
environmental impacts of conducting
the LWA activities requested.
Paragraph (d) addresses the situation
where an ESP holder (as opposed to an
applicant) requests an LWA. In this
situation, siting and many of the
environmental issues have been
addressed and resolved in the EIS
supporting issuance of the ESP. This
paragraph provides for the NRC to
prepare a supplemental EIS, addressing
the impacts of conducting LWA
activities (including any new and
significant information that would
change the NRC’s prior conclusion with
respect to those construction activities
which would actually be conducted
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
earlier under the LWA instead of
referencing a construction permit or
combined license), and the adequacy of
the proposed redress plan. Other than
this updating, the supplemental EIS will
not present any updated information on
the matters resolved in the ESP EIS.
Paragraph (e) addresses the nature of
the EIS prepared for an LWA requested
for a site that was approved by the NRC
and a construction permit issued, but
construction of the nuclear power plant
was not completed. In these cases, the
EIS will incorporate by reference the
earlier EIS, address whether there is any
significant new information with
respect to the environmental impacts of
construction relevant to the scope of
activities to be performed under the
LWA, and evaluate this type of
information in accordance with § 51.71
in determining if the LWA should be
issued, or issued with appropriate
conditions.
Paragraph (f) indicates that in all
cases, the EIS must separately address
the impacts of and proposed alternatives
to the activities to be conducted under
the LWA, to ensure that there are
specific environmental findings
addressing LWA activities for purposes
of transparency of the final NRC NEPA
findings and decision on the LWA
request. However, this paragraph also
makes clear that if the applicant’s
environmental report contains the
comprehensive information necessary to
address construction and operation
impacts for the proposed facility, as is
allowed under 10 CFR 2.101, then the
EIS must similarly address those
impacts, including the costs and
benefits of the underlying proposed
action.
Section 51.103, Record of Decision—
General
Section 51.103 is revised by adding a
new paragraph (a)(6), which specifies
that in a construction permit or
combined license proceeding where an
LWA was previously issued, the
Commission’s decision on the
construction permit or combined license
application will not address or consider
the sunk costs associated with the LWA.
This provision, which is consistent with
§§ 50.10(f) and 51.71(e), is intended to
ensure that the Commission’s decision
whether to issue the construction permit
or combined license is not biased in
favor of issuance in evaluating the
environmental impacts and benefits of
the construction permit or combined
license, and thereby avoid NEPA
segmentation claims.
PO 00000
Frm 00021
Fmt 4701
Sfmt 4700
57435
Section 51.104, NRC Proceeding Using
Public Hearings; Consideration of
Environmental Impact Statement
Section 51.104 is revised by adding a
new paragraph (c) specifying that in an
LWA proceeding, a party may only take
a position and offer evidence on the
aspects of the proposed action within
the scope of NEPA and this subpart
which are within the scope of that
party’s admitted contention. This
paragraph also specifies that, in the
LWA phase of the proceeding, the
presiding officer will decide the matters
in controversy among the parties, viz.,
the contentions related to the adequacy
of the EIS prepared for the LWA. The
scope of the EIS will, in turn, depend
upon whether the LWA applicant
chooses to submit an environmental
report limited to LWA impacts, or
whether the LWA applicant chooses to
submit a more comprehensive
environmental report as permitted
under 10 CFR 2.101 and seeks an early
decision on siting matters under subpart
F of 10 CFR part 2.
Section 51.105, Public Hearings In
Proceedings for Issuance of
Construction Permits or Early Site
Permits; Limited Work Authorizations
The title of this section is revised to
add a reference to LWAs, reflecting the
expanded scope of matters addressed in
this section. Second, a new paragraph
(c) is added to specify the
determinations which must be made by
the presiding officer in an LWA hearing
associated with either a construction
permit or early site permit. Under this
new paragraph, the presiding officer
would:
—Determine whether the requirements
of Section 102(2)(A), (C), and (E) of
NEPA have been met with respect to
the activities to be conducted under
the LWA.
—Independently consider the balance
among conflicting factors with respect
to the LWA.
—Determine whether the applicant’s
proposed redress plan is reasonably
expected, from a technical standpoint,
to redress activities conducted under
the LWA, should LWA activities be
terminated by the holder or the LWA
be revoked by the NRC, or upon
effectiveness of the Commission’s
final decision denying the associated
construction permit or combined
license application, as applicable.
—In an uncontested proceeding,
determine whether the NRC’s NEPA
review has been adequate.
—In a contested proceeding, determine
whether the LWA should be issued in
E:\FR\FM\09OCR2.SGM
09OCR2
57436
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
accordance with the regulations in
part 51.
Section 51.107, Public hearings in
proceedings for issuance of combined
licenses; limited work authorizations
Section 51.107 is revised in two
respects. The title of this section is
revised to add a reference to LWAs,
reflecting the expanded scope of matters
addressed in this section. Finally, a new
paragraph (d) is also added to specify
the determinations which must be made
by the presiding officer in an LWA
hearing associated with a combined
license. This paragraph is essentially the
same as § 51.105(c).
Part 52—Licenses, Certifications, and
Approvals for Nuclear Power Plants
Section 52.1, Definitions
A new definition of LWA is added
which would be defined as the
authorization provided under § 50.10(d).
The NRC notes that an applicant of an
ESP who requests authority to perform
the activities permitted by § 50.10(d),
would not, if the request were granted,
receive an LWA separate from its ESP.
Instead, the ESP itself would authorize
the activities permitted by § 50.10(d).
This regulatory approach is consistent
with the current language of §§ 52.17(c)
and 52.25(b). However once an ESP is
issued, the holder could apply for
permission to conduct LWA activities
under § 52.27 in the form of an
amendment to the ESP.
Section 52.17, Contents of Applications;
Technical Information
Paragraph (c) of § 52.17 is revised by
removing the proposed language with
respect to LWAs, and specifying that if
the applicant wishes to obtain an LWA,
then the information required by
§ 50.10(d)(3) must be included in the
site safety analysis report. This
paragraph also makes clear that for early
site applications which were submitted
before the effective date of the final
LWA rule, the new requirements in
§ 52.17(c) do not apply and their
applications need only meet the
requirements in former § 52.17(c).
Section 52.24, Issuance of Early Site
Permit
Paragraph (c) is revised to state that
an ESP must specify the activities under
§ 50.10 that the permit holder is
authorized to perform.
Section 52.27, Limited Work
Authorization After Issuance of Early
Site Permit
Section 52.27 is redesignated as
§ 52.26, and a new § 52.27 is added. The
new § 52.27 allows an ESP holder to
request an LWA in accordance with
§ 50.10—a matter which was not clear
under the former provisions of part 52.
Section 52.80, Content of Applications;
Additional Technical Information
Paragraph (b) is revised to state that
a combined license application that
does not request an LWA must include
an environmental report prepared in
accordance with § 51.50(c), and that a
combined license application that does
request an LWA must include an
environmental report prepared in
accordance with §§ 51.49 and 51.50(c).
Paragraph (c) is revised to require that
a combined license application
containing a request for an LWA must
contain the information otherwise
required by 10 CFR 50.10.
Section 52.91, Authorization To
Conduct Limited Work Authorization
Activities
The heading for § 52.91 is revised.
Section 52.91 is revised to reflect the
elimination of ‘‘LWA–1’’ and ‘‘LWA–2’’
in former § 50.10(e). Under paragraph
(a) of § 52.91, an applicant for a
combined license may undertake LWA
2006/05/25—Comment (4) submitted by Nuclear Energy Institute, Adrian P. Heymer on Proposed
Rules.
SECY–98–282, Part 52 Rulemaking Plan ..........................................................................................
Staff Requirements—SECY–98–282—Part 52 Rulemaking Plan ......................................................
Draft Regulatory Analysis ....................................................................................................................
Final Regulatory Analysis ....................................................................................................................
Regulatory History Index for October 17, 2006 Supplemental Proposed Rule ..................................
rwilkins on PROD1PC63 with RULES_2
Under the ‘‘Policy Statement on
Adequacy and Compatibility of
Agreement States Programs,’’ approved
by the Commission on June 20, 1997,
and published in the Federal Register
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
(62 FR 46517; September 3, 1997), this
rule is classified as compatibility ‘‘NRC’’
regulations. The NRC program elements
in this category are those that relate
directly to areas of regulation reserved
to the NRC by the AEA or provisions of
Title 10 of the Code of Federal
PO 00000
Frm 00022
Section 52.99, Inspection During
Construction
Paragraph (a) is revised to replace the
reference to 10 CFR 50.10(b) with a
reference to 10 CFR 50.10(a).
Part 100—Reactor Site Criteria
Section 100.23, Geologic and Seismic
Siting Criteria
Paragraph (b) is revised to reflect the
revisions in 10 CFR 50.10 that redefine
what is considered ‘‘construction.’’ This
paragraph formerly stated that the
investigations required in 10 CFR
100.23(c) are within the scope of
investigations permitted by former 10
CFR 50.10(c)(1). This sentence has been
revised to state that the investigations
required in 10 CFR 100.23(c) are not
considered ‘‘construction’’ as defined in
10 CFR 50.10(a).
V. Availability of Documents
The NRC is making the documents
identified below available to interested
persons through one or more of the
following methods as indicated.
Public Document Room (PDR). The
NRC PDR is located at 11555 Rockville
Pike, Rockville, Maryland. https://
www.nrc.gov/reading-rm/contactpdr.html.
The NRC staff contact. Geary Mizuno,
Mail Stop O–15D21, Washington, DC
20555–0001; telephone number 301–
415–1639.
PDR
Document
VI. Agreement State Compatibility
activities only if it: (1) References an
ESP which includes LWA authority; or
(2) the combined license applicant
applies for and is granted LWA
authority under § 50.10. Paragraph (b)
requires the combined license applicant
who begins construction under an LWA,
to implement the LWA redress plan if
the underlying combined license
application is withdrawn by the
applicant or denied by the NRC.
Fmt 4701
Sfmt 4700
Web
ADAMS No.
NRC
staff
X
X
ML061510471
............
ML032801416
ML032801439
ML062750434
ML071870012
ML070240575
............
............
X
X
X
............
............
X
X
............
............
............
X
X
X
Regulations, and although an Agreement
State may not adopt program elements
reserved to NRC, it may wish to inform
its licensees of certain requirements via
a mechanism that is consistent with the
particular State’s administrative
E:\FR\FM\09OCR2.SGM
09OCR2
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
X. Regulatory Analysis
procedure laws, but does not confer
regulatory authority on the State.
IX. Paperwork Reduction Act
Statement
VII. Voluntary Consensus Standards
This final rule amends information
collection requirements contained in (10
CFR parts 50, 51, and 52 that are subject
to the Paperwork Reduction Act of 1995
(44 U.S.C. 3501 et seq.). These
requirements were approved by the
Office of Management and Budget,
approval numbers 3150–0011, 3150–
0021, and 3150–0151 and the changes
contain new or amended information
collection requirements. Existing
requirements were approved by the
Office of Management and Budget,
approval number(s) 3150–0011, 3150–
0021, and 3150–0151.
The net burden to the public for the
information collections in 10 CFR parts
50, 51, and 52 is estimated to average
zero hours per response, as burden is
being shifted from part 52 to part 50,
and within sections of part 51. The
burden to the public for the information
collections in 10 CFR part 50 is
estimated to average 1,900 hours per
response and the burden for the
information collections in 10 CFR part
52 is estimated to average a reduction of
1,900 hours per response, resulting in
no change in burden. The burden to the
public for the information collections in
10 CFR part 51 is estimated to result in
no change in burden, as information
collection requirements are shifted from
one section to another. This includes
the time for reviewing instructions,
searching existing data sources,
gathering and maintaining the data
needed, and completing and reviewing
the information collection. Send
comments on any aspect of these
information collections, including
suggestions for reducing the burden, to
the Records and FOIA/Privacy Services
Branch (T–5 F52), U.S. Nuclear
Regulatory Commission, Washington,
DC 20555–0001, or by Internet
electronic mail to
INFOCOLLECTS@NRC.GOV; and to the
Desk Officer, Office of Information and
Regulatory Affairs, NEOB–10202,
(3150–0011, 3150–0021, 3150–0151; 10
CFR parts 50, 51, and 52), Office of
Management and Budget, Washington,
DC 20503.
The National Technology Transfer
and Advancement Act of 1995, Pub. L.
104–113, requires that Federal agencies
use technical standards that are
developed or adopted by voluntary
consensus standards bodies unless
using such a standard is inconsistent
with applicable law or is otherwise
impractical. In this rule, the NRC is: (1)
Redefining the scope of activities
constituting ‘‘construction’’ for which
NRC approval is required; (2) redefining
the scope of activities constituting
construction which the NRC may
approve in an LWA granted in advance
of the issuance of a construction permit
or combined license, or which may be
conducted by a holder of an ESP; and
(3) revising the NRC’s procedures for
granting LWAs. This rulemaking does
not establish standards or substantive
requirements with which all applicants
and licensees must comply. For these
reasons, the Commission concludes that
this action does not constitute the
establishment that contains generally
applicable standards.
VIII. Environmental Impact—
Categorical Exclusion
rwilkins on PROD1PC63 with RULES_2
The NRC has determined that the
changes made in this rule fall within the
types of actions described in categorical
exclusions described in 10 CFR
51.22(c)(1) and (c)(3). Specifically, the
conforming changes made to 10 CFR
part 2 qualify for the categorical
exclusion described in § 51.22(c)(1). The
changes to parts 50, 51, and 52 that
describe procedures for filing and
reviewing applications for LWAs qualify
for the categorical exclusion described
in § 51.22(c)(3)(i). All other changes
qualify for the categorical exclusion
described in § 51.22(c)(3)(iv).13
Therefore, neither an EIS nor an EA has
been prepared for this rule.
13 Although the industry’s request came in the
form of a comment on the proposed part 52 rule (71
FR 12782; March 13, 2006), the comment letter
stated; ‘‘To the extent the NRC determines that
these LWA issues cannot be addressed in the
current rulemaking, we ask that the Commission
initiate an expedited rulemaking.’’ The NRC has
determined that the changes suggested by the
industry in Comment 4 (docketed on May 30, 2006)
could not be incorporated into the final part 52 rule
without re-noticing. Therefore, the Commission has
decided to treat the comments submitted by the
industry as a petition for expedited rulemaking and
published a supplemental proposed rule for public
comment. The NRC determined that Comment 4
meets the sufficiency requirements described in 10
CFR 2.802(c), and that it was appropriate to seek
public comment on the petition by publishing the
supplemental proposed rule developed in response
to the petition, as allowed under 10 CFR 2.802(e).
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
Public Protection Notification
The NRC may not conduct or sponsor,
and a person is not required to respond
to, a request for information or an
information collection requirement
unless the requesting document
displays a currently valid OMB control
number.
PO 00000
Frm 00023
Fmt 4701
Sfmt 4700
57437
The NRC has prepared a regulatory
analysis for this rule. The analysis
examines the costs and benefits of the
alternatives considered by the
Commission. Availability of the
regulatory analysis is provided in
Section V of this document.
XI. Regulatory Flexibility Act
Certification
In accordance with the Regulatory
Flexibility Act (5 U.S.C. 605(b)), the
Commission certifies that this rule will
not have a significant economic impact
on a substantial number of small
entities. This rule affects only the
licensing of nuclear power plants. The
companies that will apply for an
approval, certification, permit, site
report, or license in accordance with the
regulations in this rule do not fall
within the scope of the definition of
‘‘small entities’’ set forth in the
Regulatory Flexibility Act or the size
standards established by the NRC (10
CFR 2.810).
XII. Backfit Analysis
The NRC has determined that the
backfit rule does not require the NRC to
prepare a backfit analysis for this
rulemaking, because the rulemaking
does not contain any provisions that
would impose backfitting as defined in
the backfit rule, 10 CFR 50.109.
There are no current holders of
construction permits or combined
licenses for nuclear power plants that
would be protected by the backfitting
restrictions in § 50.109. To the extent
that the rulemaking revises the LWA
requirements for future ESPs,
construction permits, or combined
licenses for nuclear power plants, these
revisions do not constitute backfits
because they are prospective in nature
and the backfit rule was not intended to
apply to every NRC action which
substantially changes the expectations
of future applicants. With respect to the
ESPs issued by the NRC prior to
adoption of the final LWA rule, the rule
does not represent backfitting for several
reasons. The ESPs issued prior to the
effective date of the final rule were
granted authority to conduct activities
identified in former § 50.10(e)(1),
commonly referred to as an LWA–1
activities. Under the final rule, NRC
review and approval is not required
before applicants can commence these
activities. In practical effect, the final
rule moots the LWA authority granted
in the applicable ESPs. Therefore, the
final LWA rule has no applicability to
these ESP holders with respect to their
already-complete ESP application
E:\FR\FM\09OCR2.SGM
09OCR2
57438
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
process. Finally, the ESP holders are
free to seek additional authority under
their ESP in accordance with the final
LWA rules provisions; in this respect,
the current LWA holders are treated no
differently than future ESP holders who
do not seek LWA authority in their
initial ESP application. For these
reasons, the NRC concludes that the
final LWA rule does not constitute
backfitting.
XIII. Congressional Review Act
Under the Congressional Review Act
of 1996, the NRC has determined that
this action is not a major rule and has
verified this determination with the
Office of Information and Regulatory
Affairs of OMB.
List of Subjects
10 CFR Part 2
Administrative practice and
procedure, Byproduct material,
Classified information, Environmental
protection, Nuclear materials, Nuclear
power plants and reactors, Penalties,
Sex discrimination, Source material,
Special nuclear material, Waste
treatment and disposal.
10 CFR Part 50
Antitrust, Classified information,
Criminal penalties, Fire protection,
Intergovernmental relations, Nuclear
power plants and reactors, Radiation
protection, Reactor siting criteria,
Reporting and recordkeeping
requirements.
10 CFR Part 51
Administrative practice and
procedure, Environmental Impact
Statement, Nuclear materials, Nuclear
power plants and reactors, Reporting
and recordkeeping requirements.
rwilkins on PROD1PC63 with RULES_2
10 CFR Part 52
Administrative practice and
procedure, Antitrust, Backfitting,
Combined license, Early site permit,
Emergency planning, Fees, Inspection,
Limited work authorization, Nuclear
power plants and reactors, Probabilistic
risk assessment, Prototype, Reactor
siting criteria, Redress of site, Reporting
and recordkeeping requirements,
Standard design, Standard design
certification.
10 CFR Part 100
Nuclear power plants and reactors,
Reactor siting criteria.
I For the reasons set forth in the
preamble and under the authority of the
Atomic Energy Act of 1954, as amended,
the Energy Reorganization Act of 1974,
as amended, and 5 U.S.C. 552 and 553,
the NRC is adopting the following
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
amendments to 10 CFR parts 2, 50, 51,
52 and 100.
PART 2—RULES OF PRACTICE FOR
DOMESTIC LICENSING PROCEEDINGS
AND ISSUANCE OF ORDERS
1. The authority citation for part 2
continues to read as follows:
I
Authority: Secs. 161, 181, 68 Stat. 948,
953, as amended (42 U.S.C. 2201, 2231); sec.
191, as amended, Pub. L. 87–615, 76 Stat. 409
(42 U.S.C. 2241); sec. 201, 88 Stat. 1242, as
amended (42 U.S.C. 5841); 5 U.S.C. 552; sec.
1704, 112 Stat. 2750 (44 U.S.C. 3504 note).
Section 2.101 also issued under secs. 53,
62, 63, 81, 103, 104, 105, 68 Stat. 930, 932,
933, 935, 936, 937, 938, as amended (42
U.S.C. 2073, 2092, 2093, 2111, 2133, 2134,
2135); sec. 114(f), Pub. L. 97–425, 96 Stat.
2213, as amended (42 U.S.C. 10143(f)), sec.
102, Pub. L. 91–190, 83 Stat. 853, as amended
(42 U.S.C. 4332); sec. 301, 88 Stat. 1248 (42
U.S.C. 5871).
Sections 2.102, 2.103, 2.104, 2.105, 2.721
also issued under secs. 102, 103, 104, 105,
183i, 189, 68 Stat. 936, 937, 938, 954, 955,
as amended (42 U.S.C. 2132, 2133, 2134,
2135, 2233, 2239). Sections 2.105 also issued
under Pub. L. 97–415, 96 Stat. 2073 (42
U.S.C. 2239).
Sections 2.200–2.206 also issued under
secs. 161b, i, o, 182, 186, 234, 68 Stat. 948–
951, 955, 83 Stat. 444, as amended (42 U.S.C.
2201(b), (i), (o), 2236, 2282); sec. 206, 88 Stat
1246 (42 U.S.C. 5846). Section 2.205(j) also
issued under Pub. L. 101–410, 104 Stat. 90,
as amended by section 3100(s), Pub. L. 104–
134, 110 Stat. 1321–373 (28 U.S.C. 2461
note). Sections 2.600–2.606 also issued under
sec. 102, Pub. L. 91–190, 83 Stat. 853, as
amended (42 U.S.C. 4332). Sections 2.700a,
2.719 also issued under 5 U.S.C. 554.
Sections 2.754, 2.760, 2.770, 2.780 also
issued under 5 U.S.C. 557. Section 2.764 also
issued under secs. 135, 141, Pub. L. 97–425,
96 Stat. 2232, 2241 (42 U.S.C. 10155, 10161).
Section 2.390 also issued under sec. 103, 68
Stat. 936, as amended (42 U.S.C. 2133), and
5 U.S.C. 552. Sections 2.800 and 2.808 also
issued under 5 U.S.C. 553. Section 2.809 also
issued under 5 U.S.C. 553, and sec. 29, Pub.
L. 85–256, 71 Stat. 579, as amended (42
U.S.C. 2039). Subpart K also issued under
sec. 189, 68 Stat. 955 (42 U.S.C. 2239); sec.
134, Pub. L. 97–425, 96 Stat. 2230 (42 U.S.C.
10154).
Subpart L also issued under sec. 189, 68
Stat. 955 (42 U.S.C. 2239). Subpart M also
issued under sec. 184 (42 U.S.C. 2234) and
sec. 189, 68 stat. 955 (42 U.S.C. 2239).
Appendix A also issued under sec. 6, Pub. L.
91–550, 84 Stat. 1473 (42 U.S.C. 2135).
2. In § 2.101, paragraphs (a)(1), (a)(2),
(a)(3) introductory text, (a)(4), and (a)(5)
are revised, paragraphs (a)(6) through
(a)(8) are reserved, and paragraph (a)(9)
is added to read as follows:
I
§ 2.101
Filing of application.
(a)(1) An application for a limited
work authorization (LWA), a permit, a
license, a license transfer, a license
amendment, a license renewal, or a
PO 00000
Frm 00024
Fmt 4701
Sfmt 4700
standard design approval, shall be filed
with the Director of New Reactors,
Director of Nuclear Reactor Regulation,
or Director of Nuclear Material Safety
and Safeguards, as prescribed by the
applicable provisions of this chapter. A
prospective applicant may confer
informally with the NRC staff before
filing an application.
(2) Each application for a license for
a facility or for receipt of waste
radioactive material from other persons
for the purpose of commercial disposal
by the waste disposal licensee will be
assigned a docket number. However, to
allow a determination as to whether an
application for a limited work
authorization, construction permit,
operating license, early site permit,
standard design approval, combined
license, or manufacturing license for a
production or utilization facility is
complete and acceptable for docketing,
it will be initially treated as a tendered
application. A copy of the tendered
application will be available for public
inspection at the NRC Web site,
https://www.nrc.gov, and/or at the NRC
PDR. Generally, the determination on
acceptability for docketing will be made
within a period of 30 days. However, in
selected applications, the Commission
may decide to determine acceptability
based on the technical adequacy of the
application as well as its completeness.
In these cases, the Commission, under
§ 2.104(a), will direct that the notice of
hearing be issued as soon as practicable
after the application has been tendered,
and the determination of acceptability
will be made generally within a period
of 60 days. For docketing and other
requirements for applications under part
61 of this chapter, see paragraph (g) of
this section.
(3) If the Director of New Reactors,
Director of Nuclear Reactor Regulation,
or Director of Nuclear Material Safety
and Safeguards, as appropriate,
determines that a tendered application
for a limited work authorization,
construction permit, operating license,
early site permit, standard design
approval, combined license, or
manufacturing license for a production
or utilization facility, and/or any
environmental report required under
subpart A of part 51 of this chapter, or
part thereof as provided in paragraphs
(a)(5), (a)(9), or (a-1) of this section are
complete and acceptable for docketing,
a docket number will be assigned to the
application or part thereof, and the
applicant will be notified of the
determination. With respect to the
tendered application and/or
environmental report or part thereof that
E:\FR\FM\09OCR2.SGM
09OCR2
rwilkins on PROD1PC63 with RULES_2
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
is acceptable for docketing, the
applicant will be requested to:
*
*
*
*
*
(4) The tendered application for a
limited work authorization,
construction permit, operating license,
early site permit, standard design
approval, combined license, or
manufacturing license for a production
or utilization facility will be formally
docketed upon receipt by the Director of
New Reactors, Director of Nuclear
Reactor Regulation, or Director of
Nuclear Material Safety and Safeguards,
as appropriate, of the required
additional copies. Distribution of the
additional copies shall be deemed to be
complete as of the time the copies are
deposited in the mail or with a carrier
prepaid for delivery to the designated
addresses. The date of docketing shall
be the date when the required copies are
received by the Director of New
Reactors, Director of Nuclear Reactor
Regulation or Director of Nuclear
Material Safety and Safeguards, as
appropriate. Within 10 days after
docketing, the applicant shall submit to
the Director of New Reactors, Director of
Nuclear Reactor Regulation, or Director
of Nuclear Material Safety and
Safeguards, as appropriate, an affidavit
that distribution of the additional copies
to Federal, State, and local officials has
been completed in accordance with the
requirements of this chapter and written
instructions furnished to the applicant
by the Director of New Reactors,
Director of Nuclear Reactor Regulation,
or Director of Nuclear Material Safety
and Safeguards, as appropriate.
Amendments to the application and
environmental report shall be filed and
distributed, and an affidavit shall be
furnished to the Director of New
Reactors, Director of Nuclear Reactor
Regulation, or Director of Nuclear
Material Safety and Safeguards, as
appropriate, in the same manner as for
the initial application and
environmental report. If it is determined
that all or any part of the tendered
application and/or environmental report
is incomplete and therefore not
acceptable for processing, the applicant
will be informed of this determination,
and the respects in which the document
is deficient.
(5) An applicant for a construction
permit under part 50 of this chapter or
a combined license under part 52 of this
chapter for a production or utilization
facility which is subject to § 51.20(b) of
this chapter, and is of the type specified
in § 50.21(b)(2) or (3) or § 50.22 of this
chapter or is a testing facility may
submit the information required of
applicants by part 50 or part 52 of this
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
chapter in two parts. One part shall be
accompanied by the information
required by § 50.30(f) of this chapter, or
§ 52.80(b) of this chapter, as applicable.
The other part shall include any
information required by § 50.34(a) and,
if applicable, § 50.34a of this chapter, or
§§ 52.79 and 52.80(a), as applicable.
One part may precede or follow other
parts by no longer than 18 months. If it
is determined that either of the parts as
described previously is incomplete and
not acceptable for processing, the
Director of New Reactors, Director of
Nuclear Reactor Regulation, or Director
of Nuclear Material Safety and
Safeguards, as appropriate, will inform
the applicant of this determination and
the respects in which the document is
deficient. A determination of
completeness will generally be made
within a period of 30 days. Whichever
part is filed first shall also include the
fee required by §§ 50.30(e) and 170.21 of
this chapter and the information
required by §§ 50.33, 50.34(a)(1) or
52.79(a)(1), as applicable, and § 50.37 of
this chapter. The Director of New
Reactors, Director Nuclear Reactor
Regulation, or Director of Nuclear
Material Safety and Safeguards, as
appropriate, will accept for docketing an
application for a construction permit
under part 50 of this chapter or a
combined license under part 52 of this
chapter for a production or utilization
facility which is subject to § 51.20(b) of
this chapter, and is of the type specified
in § 50.21(b)(2) or (3) or § 50.22 of this
chapter or is a testing facility where one
part of the application as described
previously is complete and conforms to
the requirements of part 50 or part 52
of this chapter, as applicable. The
additional part will be docketed upon a
determination that it is complete, by the
Director of New Reactors, Director of
Nuclear Reactor Regulation, or Director
of Nuclear Material Safety and
Safeguards, as appropriate.
(6)–(8) [Reserved]
(9) An applicant for a construction
permit for a utilization facility which is
subject to § 51.20(b) of this chapter and
is of the type specified in § 50.21(b)(2)
or (b)(3) or § 50.22 of this chapter, an
applicant for or holder of an early site
permit under part 52 of this chapter, or
an applicant for a combined license
under part 52 of this chapter, who seeks
to conduct the activities authorized
under § 50.10(d) of this chapter may
submit a complete application under
paragraphs (a)(1) through (a)(4) of this
section which includes the information
required by § 50.10(d) of this chapter.
Alternatively, the applicant (other than
an applicant for or holder of an early
PO 00000
Frm 00025
Fmt 4701
Sfmt 4700
57439
site permit) may submit its application
in two parts:
(i) Part one must include the
information required by § 50.33(a)
through (f) of this chapter, and the
information required by § 50.10(d)(2)
and (d)(3) of this chapter.
(ii) Part two must include the
remaining information required by the
Commission’s regulations in this
chapter which was not submitted in part
one, provided, however, that this
information may be submitted in
accordance with the applicable
provisions of paragraph (a)(5) of this
section, or, for a construction permit
applicant, paragraph (a)(1) of this
section. Part two of the application must
be submitted no later than 18 months
after submission of part one.
*
*
*
*
*
3. In § 2.102, paragraph (a) is revised
to read as follows:
I
§ 2.102 Administrative review of
application.
(a) During review of an application by
the NRC staff, an applicant may be
required to supply additional
information. The staff may request any
one party to the proceeding to confer
with the NRC staff informally. In the
case of docketed application for a
limited work authorization,
construction permit, operating license,
early site permit, standard design
approval, combined license, or
manufacturing license under this
chapter, the NRC staff shall establish a
schedule for its review of the
application, specifying the key
intermediate steps from the time of
docketing until the completion of its
review.
*
*
*
*
*
4. In § 2.104, paragraph (a) and
paragraph (c)(1) are revised to read as
follows:
I
§ 2.104
Notice of hearing.
(a) In the case of an application on
which a hearing is required by the Act
or this chapter, or in which the
Commission finds that a hearing is
required in the public interest, the
Secretary will issue a notice of hearing
to be published in the Federal Register.
The notice must be published at least 15
days, and in the case of an application
concerning a limited work
authorization, construction permit, early
site permit, or combined license for a
facility of the type described in
§§ 50.21(b) or 50.22 of this chapter or a
testing facility, at least 30 days, before
E:\FR\FM\09OCR2.SGM
09OCR2
57440
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
the date set for hearing in the notice.1
In addition, in the case of an application
for a limited work authorization,
construction permit, early site permit, or
combined license for a facility of the
type described in § 50.22 of this chapter,
or a testing facility, the notice must be
issued as soon as practicable after the
NRC has docketed the application. If the
Commission decides, under
§ 2.101(a)(2), to determine the
acceptability of the application based on
its technical adequacy as well as
completeness, the notice must be issued
as soon as practicable after the
application has been tendered.
*
*
*
*
*
(c)(1) The Secretary will transmit a
notice of hearing on an application for
a license for a production or utilization
facility, including a limited work
authorization, early site permit,
combined license, but not for a
manufacturing license, for a license for
receipt of waste radioactive material
from other persons for the purpose of
commercial disposal by the waste
disposal licensee, for a license under
part 61 of this chapter, for a
construction authorization for a highlevel waste repository at a geologic
repository operations area under parts
60 or 63 of this chapter, for a license to
receive and possess high-level
radioactive waste at a geologic
repository operations area under parts
60 or 63 of this chapter, and for a
license under part 72 of this chapter to
acquire, receive or possess spent fuel for
the purpose of storage in an
independent spent fuel storage
installation (ISFSI) to the governor or
other appropriate official of the State
and to the chief executive of the
municipality in which the facility is to
be located or the activity is to be
conducted or, if the facility is not to be
located or the activity conducted within
a municipality, to the chief executive of
the county (or to the Tribal organization,
if it is to be located or conducted within
an Indian reservation).
*
*
*
*
*
5. The heading of subpart F is revised
to read as follows:
rwilkins on PROD1PC63 with RULES_2
I
1 If the notice of hearing concerning an
application for a limited work authorization,
construction permit, early site permit, or combined
license for a facility of the type described in
§§ 50.21(b) or 50.22 of this chapter or a testing
facility does not specify the time and place of initial
hearing, a subsequent notice will be published in
the Federal Register which will provide at least 30
days notice of the time and place of that hearing.
After this notice is given, the presiding officer may
reschedule the commencement of the initial hearing
for a later date or reconvene a recessed hearing
without again providing at least 30 days notice.
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
Subpart F—Additional Procedures
Applicable to Early Partial Decisions
on Site Suitability Issues in
Connection With an Application for a
Construction Permit or Combined
License To Construct Certain
Utilization Facilities; and Advance
Issuance of Limited Work
Authorizations
6. In § 2.600, the introductory text is
revised, and a new paragraph (d) is
added to read as follows:
I
§ 2.600
Scope of subpart.
This subpart prescribes procedures
applicable to licensing proceedings
which involve an early submittal of site
suitability information in accordance
with § 2.101(a–1), and a hearing and
early partial decision on issues of site
suitability, in connection with an
application for a permit to construct a
utilization facility which is subject to
§ 51.20(b) of this chapter and is of the
type specified in § 50.21(b)(2) or (3) or
§ 50.22 of this chapter or is a testing
facility. This subpart also prescribes
procedures applicable to proceedings
for a construction permit for a
utilization facility which is subject to
§ 51.20(b) of this chapter and is of the
type specified in § 50.21(b)(2) or (3) or
§ 50.22 of this chapter, or proceedings
for a combined license under part 52 of
this chapter, either of which includes a
request to conduct the activities
authorized under § 50.10(d) of part 50 of
this chapter in advance of issuance of
the construction permit or combined
license, and submits an application in
accordance with § 2.101(a)(9).
*
*
*
*
*
(d) The procedures in §§ 2.641
through 2.649 apply to phased
applications for construction permits or
combined licenses which request
limited work authorizations to be issued
in advance of issuance of the
construction permit or combined license
(i.e., a phased application).
I 7. In § 2.606, paragraph (a) is revised
to read as follows:
§ 2.606 Partial decision on site suitability
issues.
(a) The provisions of §§ 2.331, 2.339,
2.340(b), 2.343, 2.712, and 2.713 apply
to any partial initial decision rendered
in accordance with this subpart. Section
2.340(c) does not apply to any partial
initial decision rendered in accordance
with this subpart. No construction
permit or combined license may be
issued without completion of the full
review required by Section 102(2) of the
NEPA, as amended, and subpart A of
part 51 of this chapter. The authority of
the Commission to review such a partial
PO 00000
Frm 00026
Fmt 4701
Sfmt 4700
initial decision sua sponte, or to raise
sua sponte an issue that has not been
raised by the parties, will be exercised
within the same time as in the case of
a full decision relating to the issuance
of a construction permit or combined
license.
*
*
*
*
*
I 8. Following § 2.629, an undesignated
center heading and §§ 2.641, 2.643,
2.645, and 2.649 are added and § 2.647
is reserved to read as follows:
Phased Applications Involving Limited
Work Authorizations
Sec.
2.641 Filing fees.
2.643 Acceptance and docketing of
application for limited work
authorization.
2.645 Notice of hearing.
2.647 [Reserved]
2.649 Partial decisions on limited work
authorization.
§ 2.641
Filing fees.
Each application which contains a
request for limited work authorization
under the procedures of § 2.101(a)(9)
and this subpart shall be accompanied
by any fee required by § 50.30(e) and
part 170 of this chapter.
§ 2.643 Acceptance and docketing of
application for limited work authorization.
(a) Each part of an application
submitted in accordance with
§ 2.101(a)(9) will be initially treated as
a tendered application. If it is
determined that any one of the parts as
described in § 2.101(a)(9) is incomplete
and not acceptable for processing, the
Director of New Reactors or the Director
of Nuclear Reactor Regulation will
inform the applicant of this
determination and the respects in which
the document is deficient. A
determination of completeness will
generally be made within a period of 30
days.
(b) The Director will accept for
docketing part one of an application for
a construction permit for a utilization
facility which is subject to § 51.20(b) of
this chapter and is of the type specified
in § 50.21(b)(2) or (3) or § 50.22 of this
chapter or an application for a
combined license where part one of the
application as described in § 2.101(a)(9)
is complete. Part one will not be
considered complete unless it contains
the information required by
§ 50.10(d)(3) of this chapter. Upon
assignment of a docket number, the
procedures in § 2.101(a)(3) and (4)
relating to formal docketing and the
submission and distribution of
additional copies of the application
must be followed.
E:\FR\FM\09OCR2.SGM
09OCR2
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
(c) If part one of the application is
docketed, the Director will cause to be
published in the Federal Register and
send to the Governor or other
appropriate official of the State in which
the site is located, a notice of docketing
of the application which states the
purpose of the application, states the
location of the proposed site, states that
a notice of hearing will be published,
and requests comments on the limited
work authorization from Federal, State,
and local agencies and interested
persons. The notice will state that
comments must be submitted to the
NRC within 60 days or such other time
as may be specified in the notice.
(d) Part two of the application will be
docketed upon a determination by the
Director that it is complete.
(e) If part two of the application is
docketed, the Director will cause to be
published in the Federal Register and
sent to the Governor or other
appropriate official of the State in which
the site is located, a notice of docketing
of part two of the application which
states the purpose of the application,
states that a notice of hearing will be
published, and requests comments on
the construction permit or combined
license application, as applicable, from
Federal, State, and local agencies and
interested persons. The notice will state
that comments must be submitted to the
NRC within 60 days or such other time
as may be specified in the notice.
rwilkins on PROD1PC63 with RULES_2
§ 2.645
Notice of hearing.
(a) The notice of hearing on part one
of the application must set forth the
matters of fact and law to be considered,
as required by § 2.104, which will be
modified to state that the hearing will
relate only to the matters related to
§ 50.33(a) through (f) of this chapter,
and the limited work authorization.
(b) After docketing of part two of the
application, as provided in
§§ 2.101(a)(9) and 2.643(d), a
supplementary notice of hearing will be
published under § 2.104 with respect to
the remaining unresolved issues in the
proceeding within the scope of § 2.104.
The supplementary notice of hearing
will provide that any person whose
interest may be affected by the
proceeding and who desires to
participate as a party in the resolution
of the remaining issues shall, file a
petition for leave to intervene within the
time prescribed in the notice. The
petition to intervene must meet the
applicable requirements in subpart C of
this part, including § 2.309. This
supplementary notice will also provide
appropriate opportunities for
participation by a representative of an
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
interested State under § 2.315(c) and for
limited appearances under § 2.315(a).
(c) Any person who was permitted to
intervene under the initial notice of
hearing on the limited work
authorization and who was not
dismissed or did not withdraw as a
party, may continue to participate as a
party with respect to the remaining
unresolved issues only if, within the
time prescribed for filing of petitions for
leave to intervene in the supplementary
notice of hearing, that person files a
petition for intervention which meets
the applicable requirements in subpart
C of this part, including § 2.309,
provided, however, that the petition
need not address § 2.309(d). However, a
person who was granted discretionary
intervention under § 2.309(e) must
address in its petition the factors in
§ 2.309(e) as they apply to the
supplementary hearing.
(d) A party who files a non-timely
petition for intervention under
paragraph (b) of this section to continue
as a party may be dismissed from the
proceeding, absent a determination that
the party has made a substantial
showing of good cause for failure to file
on time, and with particular reference to
the factors specified in §§ 2.309(c)(1)(i)
through (iv) and 2.309(d). The notice
will be ruled upon by the Commission
or presiding officer designated to rule
on petitions for leave to intervene.
(e) To the maximum extent
practicable, the membership of the
Atomic Safety and Licensing Board, or
the individual presiding officer, as
applicable, designated to preside in the
proceeding on the remaining unresolved
issues under the supplemental notice of
hearing will be the same as the
membership or individual designated to
preside in the initial notice of hearing.
§ 2.647
[Reserved]
§ 2.649 Partial decisions on limited work
authorization.
The provisions of §§ 2.331, 2.339,
2.340(b), 2.343, 2.712, and 2.713 apply
to any partial initial decision rendered
in accordance with this subpart. Section
2.340(c) does not apply to any partial
initial decision rendered in accordance
with this subpart. A limited work
authorization may not be issued under
10 CFR 50.10(d) without completion of
the review for limited work
authorizations required by subpart A of
part 51 of this chapter. The authority of
the Commission to review such a partial
initial decision sua sponte, or to raise
sua sponte an issue that has not been
raised by the parties, will be exercised
within the same time as in the case of
a full decision relating to the issuance
PO 00000
Frm 00027
Fmt 4701
Sfmt 4700
57441
of a construction permit or combined
license.
PART 50—DOMESTIC LICENSING OF
PRODUCTION AND UTILIZATION
FACILITIES
9. The authority citation for part 50
continues to read as follows:
I
Authority: Secs. 102, 103, 104, 105, 161,
182, 183, 186, 189, 68 Stat. 936, 937, 938,
948, 953, 954, 955, 956, as amended, sec.
234, 83 Stat. 444, as amended (42 U.S.C.
2132, 2133, 2134, 2135, 2201, 2232, 2233,
2236, 2239, 2282); secs. 201, as amended,
202, 206, 88 Stat. 1242, as amended, 1244,
1246 (42 U.S.C. 5841, 5842, 5846); sec. 1704,
112 Stat. 2750 (44 U.S.C. 3504 note). Section
50.7 also issued under Pub. L. 95–601, sec.
10, 92 Stat. 2951 (42 U.S.C. 5841). Section
50.10 also issued under secs. 101, 185, 68
Stat. 955, as amended (42 U.S.C. 2131, 2235);
sec. 102, Pub. L. 91–190, 83 Stat. 853 (42
U.S.C. 4332). Sections 50.13, 50.54(dd), and
50.103 also issued under sec. 108, 68 Stat.
939, as amended (42 U.S.C. 2138).
Sections 50.23, 50.35, 50.55, and 50.56 also
issued under sec. 185, 68 Stat. 955 (42 U.S.C.
2235). Sections 50.33a, 50.55a and Appendix
Q also issued under sec. 102, Pub. L. 91–190,
83 Stat. 853 (42 U.S.C. 4332). Sections 50.34
and 50.54 also issued under sec. 204, 88 Stat.
1245 (42 U.S.C. 5844). Sections 50.58, 50.91,
and 50.92 also issued under Pub. L. 97–415,
96 Stat. 2073 (42 U.S.C. 2239). Section 50.78
also issued under sec. 122, 68 Stat. 939 (42
U.S.C. 2152). Sections 50.80–50.81 also
issued under sec. 184, 68 Stat. 954, as
amended (42 U.S.C. 2234). Appendix F also
issued under sec. 187, 68 Stat. 955 (42 U.S.C.
2237).
10. Section 50.10 is revised to read as
follows:
I
§ 50.10 License required; limited work
authorization.
(a) Definitions. As used in this
section, construction means the
activities in paragraph (a)(1) of this
section, and does not mean the activities
in paragraph (a)(2) of this section.
(1) Activities constituting
construction are the driving of piles,
subsurface preparation, placement of
backfill, concrete, or permanent
retaining walls within an excavation,
installation of foundations, or in-place
assembly, erection, fabrication, or
testing, which are for:
(i) Safety-related structures, systems,
or components (SSCs) of a facility, as
defined in 10 CFR 50.2;
(ii) SSCs relied upon to mitigate
accidents or transients or used in plant
emergency operating procedures;
(iii) SSCs whose failure could prevent
safety-related SSCs from fulfilling their
safety-related function;
(iv) SSCs whose failure could cause a
reactor scram or actuation of a safetyrelated system;
E:\FR\FM\09OCR2.SGM
09OCR2
rwilkins on PROD1PC63 with RULES_2
57442
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
(v) SSCs necessary to comply with 10
CFR part 73;
(vi) SSCs necessary to comply with 10
CFR 50.48 and criterion 3 of 10 CFR part
50, appendix A; and
(vii) Onsite emergency facilities, that
is, technical support and operations
support centers, necessary to comply
with 10 CFR 50.47 and 10 CFR part 50,
appendix E.
(2) Construction does not include:
(i) Changes for temporary use of the
land for public recreational purposes;
(ii) Site exploration, including
necessary borings to determine
foundation conditions or other
preconstruction monitoring to establish
background information related to the
suitability of the site, the environmental
impacts of construction or operation, or
the protection of environmental values;
(iii) Preparation of a site for
construction of a facility, including
clearing of the site, grading, installation
of drainage, erosion and other
environmental mitigation measures, and
construction of temporary roads and
borrow areas;
(iv) Erection of fences and other
access control measures;
(v) Excavation;
(vi) Erection of support buildings
(such as, construction equipment
storage sheds, warehouse and shop
facilities, utilities, concrete mixing
plants, docking and unloading facilities,
and office buildings) for use in
connection with the construction of the
facility;
(vii) Building of service facilities,
such as paved roads, parking lots,
railroad spurs, exterior utility and
lighting systems, potable water systems,
sanitary sewerage treatment facilities,
and transmission lines;
(viii) Procurement or fabrication of
components or portions of the proposed
facility occurring at other than the final,
in-place location at the facility;
(ix) Manufacture of a nuclear power
reactor under a manufacturing license
under subpart F of part 52 of this
chapter to be installed at the proposed
site and to be part of the proposed
facility; or
(x) With respect to production or
utilization facilities, other than testing
facilities and nuclear power plants,
required to be licensed under Section
104.a or Section 104.c of the Act, the
erection of buildings which will be used
for activities other than operation of a
facility and which may also be used to
house a facility (e.g., the construction of
a college laboratory building with space
for installation of a training reactor).
(b) Requirement for license. Except as
provided in § 50.11 of this chapter, no
person within the United States shall
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
transfer or receive in interstate
commerce, manufacture, produce,
transfer, acquire, possess, or use any
production or utilization facility except
as authorized by a license issued by the
Commission.
(c) Requirement for construction
permit, early site permit authorizing
limited work authorization activities,
combined license, or limited work
authorization. No person may begin the
construction of a production or
utilization facility on a site on which
the facility is to be operated until that
person has been issued either a
construction permit under this part, a
combined license under part 52 of this
chapter, an early site permit authorizing
the activities under paragraph (d) of this
section, or a limited work authorization
under paragraph (d) of this section.
(d) Request for limited work
authorization. (1) Any person to whom
the Commission may otherwise issue
either a license or permit under Sections
103, 104.b, or 185 of the Act for a
facility of the type specified in
§§ 50.21(b)(2), (b)(3), or 50.22 of this
chapter, or a testing facility, may request
a limited work authorization allowing
that person to perform the driving of
piles, subsurface preparation, placement
of backfill, concrete, or permanent
retaining walls within an excavation,
installation of the foundation, including
placement of concrete, any of which are
for an SSC of the facility for which
either a construction permit or
combined license is otherwise required
under paragraph (c) of this section.
(2) An application for a limited work
authorization may be submitted as part
of a complete application for a
construction permit or combined license
in accordance with 10 CFR 2.101(a)(1)
through (a)(5), or as a partial application
in accordance with 10 CFR 2.101(a)(9).
An application for a limited work
authorization must be submitted by an
applicant for or holder of an early site
permit as a complete application in
accordance with 10 CFR 2.101(a)(1)
through (a)(4).
(3) The application must include:
(i) A safety analysis report required by
10 CFR 50.34, 10 CFR 52.17 or 10 CFR
52.79 of this chapter, as applicable, a
description of the activities requested to
be performed, and the design and
construction information otherwise
required by the Commission’s rules and
regulations to be submitted for a
construction permit or combined
license, but limited to those portions of
the facility that are within the scope of
the limited work authorization. The
safety analysis report must demonstrate
that activities conducted under the
limited work authorization will be
PO 00000
Frm 00028
Fmt 4701
Sfmt 4700
conducted in compliance with the
technically-relevant Commission
requirements in 10 CFR Chapter I
applicable to the design of those
portions of the facility within the scope
of the limited work authorization;
(ii) An environmental report in
accordance with § 51.49 of this chapter;
and
(iii) A plan for redress of activities
performed under the limited work
authorization, should limited work
activities be terminated by the holder or
the limited work authorization be
revoked by the NRC, or upon
effectiveness of the Commission’s final
decision denying the associated
construction permit or combined license
application, as applicable.
(e) Issuance of limited work
authorization. (1) The Director of New
Reactors or the Director of Nuclear
Reactor Regulation may issue a limited
work authorization only after:
(i) The NRC staff issues the final
environmental impact statement for the
limited work authorization in
accordance with subpart A of part 51 of
this chapter;
(ii) The presiding officer makes the
finding in § 51.105(c) or § 51.107(d) of
this chapter, as applicable;
(iii) The Director determines that the
applicable standards and requirements
of the Act, and the Commission’s
regulations applicable to the activities to
be conducted under the limited work
authorization, have been met. The
applicant is technically qualified to
engage in the activities authorized.
Issuance of the limited work
authorization will provide reasonable
assurance of adequate protection to
public health and safety and will not be
inimical to the common defense and
security; and
(iv) The presiding officer finds that
there are no unresolved safety issues
relating to the activities to be conducted
under the limited work authorization
that would constitute good cause for
withholding the authorization.
(2) Each limited work authorization
will specify the activities that the holder
is authorized to perform.
(f) Effect of limited work
authorization. Any activities
undertaken under a limited work
authorization are entirely at the risk of
the applicant and, except as to the
matters determined under paragraph
(e)(1) of this section, the issuance of the
limited work authorization has no
bearing on the issuance of a
construction permit or combined license
with respect to the requirements of the
Act, and rules, regulations, or orders
issued under the Act. The
environmental impact statement for a
E:\FR\FM\09OCR2.SGM
09OCR2
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
construction permit or combined license
application for which a limited work
authorization was previously issued
will not address, and the presiding
officer will not consider, the sunk costs
of the holder of limited work
authorization in determining the
proposed action (i.e., issuance of the
construction permit or combined
license).
(g) Implementation of redress plan. If
construction is terminated by the
holder, the underlying application is
withdrawn by the applicant or denied
by the NRC, or the limited work
authorization is revoked by the NRC,
then the holder must begin
implementation of the redress plan in a
reasonable time. The holder must also
complete the redress of the site no later
than 18 months after termination of
construction, revocation of the limited
work authorization, or upon
effectiveness of the Commission’s final
decision denying the associated
construction permit application or the
underlying combined license
application, as applicable.
PART 51—ENVIRONMENTAL
PROTECTION REGULATIONS FOR
DOMESTIC LICENSING AND RELATED
REGULATORY FUNCTIONS
11. The authority citation for part 51
continues to read as follows:
I
Authority: Sec. 161, 68 Stat. 948, as
amended, sec. 1701, 106 Stat. 2951, 2952,
2953 (42 U.S.C. 2201, 2297f); secs. 201, as
amended, 202, 88 Stat. 1242, as amended,
1244 (42 U.S.C. 5841, 5842); sec. 1704, 112
Stat. 2750 (44 U.S.C. 3504 note). Subpart A
also issued under National Environmental
Policy Act of 1969, secs. 102, 104, 105, 83
Stat. 853–854, as amended (42 U.S.C. 4332,
4334, 4335); and Pub. L. 95–604, Title II, 92
Stat. 3033–3041; and sec. 193, Pub. L. 101–
575, 104 Stat. 2835 (42 U.S.C. 2243). Sections
51.20, 51.30, 51.60, 51.80, and 51.97 also
issued under secs. 135, 141, Pub. L. 97–425,
96 Stat. 2232, 2241, and sec. 148, Pub. L.
100–203, 101 Stat. 1330–223 (42 U.S.C.
10155, 10161, 10168). Section 51.22 also
issued under sec. 274, 73 Stat. 688, as
amended by 92 Stat. 3036–3038 (42 U.S.C.
2021) and under Nuclear Waste Policy Act of
1982, sec. 121, 96 Stat. 2228 (42 U.S.C.
10141). Sections 51.43, 51.67, and 51.109
also issued under Nuclear Waste Policy Act
of 1982, sec. 114(f), 96 Stat. 2216, as
amended (42 U.S.C. 10134(f)).
12. In § 51.4, a new definition of
‘‘construction’’ is added to read as
follows:
rwilkins on PROD1PC63 with RULES_2
I
§ 51.4
Definitions.
*
*
*
*
*
Construction means the activities in
paragraph (1) of this definition, and
does not mean the activities in
paragraph (2) of this definition.
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
(1) Activities constituting
construction are the driving of piles,
subsurface preparation, placement of
backfill, concrete, or permanent
retaining walls within an excavation,
installation of foundations, or in-place
assembly, erection, fabrication, or
testing, which are for:
(i) Safety-related structures, systems,
or components (SSCs) of a facility, as
defined in 10 CFR 50.2;
(ii) SSCs relied upon to mitigate
accidents or transients or used in plant
emergency operating procedures;
(iii) SSCs whose failure could prevent
safety-related SSCs from fulfilling their
safety-related function;
(iv) SSCs whose failure could cause a
reactor scram or actuation of a safetyrelated system;
(v) SSCs necessary to comply with 10
CFR part 73;
(vi) SSCs necessary to comply with 10
CFR 50.48 and criterion 3 of 10 CFR part
50, appendix A; and
(vii) Onsite emergency facilities (i.e.,
technical support and operations
support centers), necessary to comply
with 10 CFR 50.47 and 10 CFR part 50,
appendix E.
(2) Construction does not include:
(i) Changes for temporary use of the
land for public recreational purposes;
(ii) Site exploration, including
necessary borings to determine
foundation conditions or other
preconstruction monitoring to establish
background information related to the
suitability of the site, the environmental
impacts of construction or operation, or
the protection of environmental values;
(iii) Preparation of a site for
construction of a facility, including
clearing of the site, grading, installation
of drainage, erosion and other
environmental mitigation measures, and
construction of temporary roads and
borrow areas;
(iv) Erection of fences and other
access control measures;
(v) Excavation;
(vi) Erection of support buildings
(such as, construction equipment
storage sheds, warehouse and shop
facilities, utilities, concrete mixing
plants, docking and unloading facilities,
and office buildings) for use in
connection with the construction of the
facility;
(vii) Building of service facilities,
such as paved roads, parking lots,
railroad spurs, exterior utility and
lighting systems, potable water systems,
sanitary sewerage treatment facilities,
transmission lines;
(viii) Procurement or fabrication of
components or portions of the proposed
facility occurring at other than the final,
in-place location at the facility;
PO 00000
Frm 00029
Fmt 4701
Sfmt 4700
57443
(ix) Manufacture of a nuclear power
reactor under a manufacturing license
under subpart F of part 52 of this
chapter to be installed at the proposed
site and to be part of the proposed
facility; or
(x) With respect to production or
utilization facilities, other than testing
facilities and nuclear power plants,
required to be licensed under Section
104.a or Section 104.c of the Act, the
erection of buildings which will be used
for activities other than operation of a
facility and which may also be used to
house a facility (e.g., the construction of
a college laboratory building with space
for installation of a training reactor).
*
*
*
*
*
I 13. In § 51.17, paragraph (b) is revised
to read as follows:
§ 51.17 Information collection
requirements; OMB approval.
*
*
*
*
*
(b) The approved information
collection requirements in this part
appear in §§ 51.6, 51.16, 51.41, 51.45,
51.49, 51.50, 51.51, 51.52, 51.53, 51.54,
51.55, 51.58, 51.60, 51.61, 51.62, 51.66,
51.68, and 51.69.
I 14. In § 51.45, paragraph (c) is revised
to read as follows:
§ 51.45
Environmental report.
*
*
*
*
*
(c) Analysis. The environmental
report must include an analysis that
considers and balances the
environmental effects of the proposed
action, the environmental impacts of
alternatives to the proposed action, and
alternatives available for reducing or
avoiding adverse environmental effects.
An environmental report prepared at the
early site permit stage under § 51.50(b),
construction permit stage under
§ 51.50(a), or combined license stage
under § 51.50(c) must include a
description of impacts of the
preconstruction activities performed by
the applicant (i.e., those activities listed
in paragraph (b)(1) through (b)(8) in the
definition of construction contained in
§ 51.4) necessary to support the
construction and operation of the
facility which is the subject of the
limited work authorization,
construction permit, or combined
license application. The environmental
report must also contain an analysis of
the cumulative impacts of the activities
to be authorized by the limited work
authorization, construction permit, or
combined license in light of the
preconstruction impacts described in
the environmental report. Except for an
environmental report prepared at the
early site permit stage, or an
environmental report prepared at the
E:\FR\FM\09OCR2.SGM
09OCR2
57444
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
license renewal stage under § 51.53(c),
the analysis in the environmental report
should also include consideration of the
economic, technical, and other benefits
and costs of the proposed action and its
alternatives. Environmental reports
prepared at the license renewal stage
under § 51.53(c) need not discuss the
economic or technical benefits and costs
of either the proposed action or
alternatives except if these benefits and
costs are either essential for a
determination regarding the inclusion of
an alternative in the range of
alternatives considered or relevant to
mitigation. In addition, environmental
reports prepared under § 51.53(c) need
not discuss issues not related to the
environmental effects of the proposed
action and its alternatives. The analyses
for environmental reports shall, to the
fullest extent practicable, quantify the
various factors considered. To the extent
that there are important qualitative
considerations or factors that cannot be
quantified, those considerations or
factors shall be discussed in qualitative
terms. The environmental report should
contain sufficient data to aid the
Commission in its development of an
independent analysis.
*
*
*
*
*
I 15. A new § 51.49 is added under the
heading Environmental ReportsProduction and Utilization Facilities to
read as follows:
rwilkins on PROD1PC63 with RULES_2
§ 51.49 Environmental report—limited
work authorization.
(a) Limited work authorization
submitted as part of complete
construction permit or combined license
application. Each applicant for a
construction permit or combined license
applying for a limited work
authorization under § 50.10(d) of this
chapter in a complete application under
10 CFR 2.101(a)(1) through (a)(4), shall
submit with its application a separate
document, entitled, ‘‘Applicant’s
Environmental Report—Limited Work
Authorization Stage,’’ which is in
addition to the environmental report
required by § 51.50 of this part. Each
environmental report must also contain
the following information:
(1) A description of the activities
proposed to be conducted under the
limited work authorization;
(2) A statement of the need for the
activities; and
(3) A description of the environmental
impacts that may reasonably be
expected to result from the activities,
the mitigation measures that the
applicant proposes to implement to
achieve the level of environmental
impacts described, and a discussion of
the reasons for rejecting mitigation
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
measures that could be employed by the
applicant to further reduce
environmental impacts.
(b) Phased application for limited
work authorization and construction
permit or combined license. If the
construction permit or combined license
application is filed in accordance with
§ 2.101(a)(9) of this chapter, then the
environmental report for part one of the
application may be limited to a
discussion of the activities proposed to
be conducted under the limited work
authorization. If the scope of the
environmental report for part one is so
limited, then part two of the application
must include the information required
by § 51.50, as applicable.
(c) Limited work authorization
submitted as part of an early site permit
application. Each applicant for an early
site permit under subpart A of part 52
of this chapter requesting a limited work
authorization shall submit with its
application the environmental report
required by § 51.50(b). Each
environmental report must contain the
following information:
(1) A description of the activities
proposed to be conducted under the
limited work authorization;
(2) A statement of the need for the
activities; and
(3) A description of the environmental
impacts that may reasonably be
expected to result from the activities,
the mitigation measures that the
applicant proposes to implement to
achieve the level of environmental
impacts described, and a discussion of
the reasons for rejecting mitigation
measures that could be employed by the
applicant to further reduce
environmental impacts.
(d) Limited work authorization
request submitted by early site permit
holder. Each holder of an early site
permit requesting a limited work
authorization shall submit with its
application a document entitled,
‘‘Applicant’s Environmental Report—
Limited Work Authorization under
Early Site Permit,’’ containing the
following information:
(1) A description of the activities
proposed to be conducted under the
limited work authorization;
(2) A statement of the need for the
activities;
(3) A description of the environmental
impacts that may reasonably be
expected to result from the activities,
the mitigation measures that the
applicant proposes to implement to
achieve the level of environmental
impacts described, and a discussion of
the reasons for rejecting mitigation
measures that could be employed by the
PO 00000
Frm 00030
Fmt 4701
Sfmt 4700
applicant to further reduce
environmental impacts; and
(4) Any new and significant
information for issues related to the
impacts of construction of the facility
that were resolved in the early site
permit proceeding with respect to the
environmental impacts of the activities
to be conducted under the limited work
authorization.
(5) A description of the process used
to identify new and significant
information regarding NRC’s
conclusions in the early site permit
environmental impact statement. The
process must be a reasonable
methodology for identifying this new
and significant information.
(e) Limited work authorization for a
site where an environmental impact
statement was prepared, but the facility
construction was not completed. If the
limited work authorization is for
activities to be conducted at a site for
which the Commission has previously
prepared an environmental impact
statement for the construction and
operation of a nuclear power plant, and
a construction permit was issued but
construction of the plant was never
completed, then the applicant’s
environmental report may incorporate
by reference the earlier environmental
impact statement. In the event of such
referencing, the environmental report
must identify:
(1) Any new and significant
information material to issues related to
the impacts of construction of the
facility that were resolved in the
construction permit proceeding for the
matters required to be addressed in
paragraph (a) of this section; and
(2) A description of the process used
to identify new and significant
information regarding the NRC’s
conclusions in the construction permit
environmental impact statement. The
process must use a reasonable
methodology for identifying this new
and significant information.
(f) Environmental Report. An
environmental report submitted in
accordance with this section must
separately evaluate the environmental
impacts and proposed alternatives
attributable to the activities proposed to
be conducted under the limited work
authorization. At the option of the
applicant, the ‘‘Applicant’s
Environmental Report—Limited Work
Authorization Stage,’’ may contain the
information required to be submitted in
the environmental report required under
§ 51.50, which addresses the impacts of
construction and operation for the
proposed facility (including the
environmental impacts attributable to
the limited work authorization), and
E:\FR\FM\09OCR2.SGM
09OCR2
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
discusses the overall costs and benefits
balancing for the proposed action.
I 16. In § 51.71, paragraph (e) is
redesignated as paragraph (f), and a new
paragraph (e) is added to read as
follows:
§ 51.71 Draft environmental impact
statement—contents.
*
*
*
*
*
(e) Effect of limited work
authorization. If a limited work
authorization was issued either in
connection with or subsequent to an
early site permit, or in connection with
a construction permit or combined
license application, then the
environmental impact statement for the
construction permit or combined license
application will not address or consider
the sunk costs associated with the
limited work authorization.
*
*
*
*
*
I 17. Section 51.76 is added to read as
follows:
rwilkins on PROD1PC63 with RULES_2
§ 51.76 Draft environmental impact
statement—limited work authorization.
The NRC will prepare a draft
environmental impact statement relating
to issuance of a limited work
authorization in accordance with the
procedures and measures described in
§§ 51.70, 51.71, and 51.73, as further
supplemented or modified in the
following paragraphs.
(a) Limited work authorization
submitted as part of complete
construction permit or combined license
application. If the application for a
limited work authorization is submitted
as part of a complete construction
permit or combined license application,
then the NRC may prepare a partial draft
environmental impact statement. The
analysis called for by § 51.71(d) must be
limited to the activities proposed to be
conducted under the limited work
authorization. Alternatively, the NRC
may prepare a complete draft
environmental impact statement
prepared in accordance with § 51.75(a)
or (c), as applicable.
(b) Phased application for limited
work authorization under § 2.101(a)(9)
of this chapter. If the application for a
limited work authorization is submitted
in accordance with § 2.101(a)(9) of this
chapter, then the draft environmental
impact statement for part one of the
application may be limited to
consideration of the activities proposed
to be conducted under the limited work
authorization, and the proposed redress
plan. However, if the environmental
report contains the full set of
information required to be submitted
under § 51.50(a) or (c), then a draft
environmental impact statement must
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
be prepared in accordance with
§ 51.75(a) or (c), as applicable. Siting
issues, including whether there is an
obviously superior alternative site, or
issues related to operation of the
proposed nuclear power plant at the
site, including need for power, may not
be considered. After part two of the
application is docketed, the NRC will
prepare a draft supplement to the final
environmental impact statement for part
two of the application under § 51.72. No
updating of the information contained
in the final environmental impact
statement prepared for part one is
necessary in preparation of the
supplemental environmental impact
statement. The draft supplement must
consider all environmental impacts
associated with the prior issuance of the
limited work authorization, but may not
address or consider the sunk costs
associated with the limited work
authorization.
(c) Limited work authorization
submitted as part of an early site permit
application. If the application for a
limited work authorization is submitted
as part of an application for an early site
permit, then the NRC will prepare an
environmental impact statement in
accordance with § 51.75(b). However,
the analysis called for by § 51.71(d)
must also address the activities
proposed to be conducted under the
limited work authorization.
(d) Limited work authorization
request submitted by an early site
permit holder. If the application for a
limited work authorization is submitted
by a holder of an early site permit, then
the NRC will prepare a draft supplement
to the environmental impact statement
for the early site permit. The
supplement is limited to consideration
of the activities proposed to be
conducted under the limited work
authorization, the adequacy of the
proposed redress plan, and whether
there is new and significant information
identified with respect to issues related
to the impacts of construction of the
facility that were resolved in the early
site permit proceeding with respect to
the environmental impacts of the
activities to be conducted under the
limited work authorization. No other
updating of the information contained
in the final environmental impact
statement prepared for the early site
permit is required.
(e) Limited work authorization for a
site where an environmental impact
statement was prepared, but the facility
construction was not completed. If the
limited work authorization is for
activities to be conducted at a site for
which the Commission has previously
prepared an environmental impact
PO 00000
Frm 00031
Fmt 4701
Sfmt 4700
57445
statement for the construction and
operation of a nuclear power plant, and
a construction permit was issued but
construction of the plant was not
completed, then the draft environmental
impact statement shall incorporate by
reference the earlier environmental
impact statement. The draft
environmental impact statement must
be limited to a consideration of whether
there is significant new information
with respect to the environmental
impacts of construction, relevant to the
activities to be conducted under the
limited work authority, so that the
conclusion of the referenced
environmental impact statement on the
impacts of construction would, when
analyzed in accordance with § 51.71,
lead to the conclusion that the limited
work authorization should not be issued
or should be issued with appropriate
conditions.
(f) Draft environmental impact
statement. A draft environmental
impact statement prepared under this
section must separately evaluate the
environmental impacts and proposed
alternatives attributable to the activities
proposed to be conducted under the
limited work authorization. However, if
the ‘‘Applicant’s Environmental
Report—Limited Work Authorization
Stage,’’ also contains the information
required to be submitted in the
environmental report required under
§ 51.50, then the environmental impact
statement must address the impacts of
construction and operation for the
proposed facility (including the
environmental impacts attributable to
the limited work authorization), and
discuss the overall costs and benefits
balancing for the underlying proposed
action, in accordance with § 51.71, and
§ 51.75(a) or (c), as applicable.
I 18. In § 51.103, a new paragraph (a)(6)
is added to read as follows:
§ 51.103
Record of decision—general.
(a) * * *
(6) In a construction permit or a
combined license proceeding where a
limited work authorization under 10
CFR 50.10 was issued, the
Commission’s decision on the
construction permit or combined license
application will not address or consider
the sunk costs associated with the
limited work authorization in
determining the proposed action.
*
*
*
*
*
I 19. In § 51.104, a new paragraph (c) is
added to read as follows:
§ 51.104 NRC proceeding using public
hearings; consideration of environmental
impact statement.
*
E:\FR\FM\09OCR2.SGM
*
*
09OCR2
*
*
57446
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
(c) In any proceeding in which a
limited work authorization is requested,
unless the Commission orders
otherwise, a party to the proceeding
may take a position and offer evidence
only on the aspects of the proposed
action within the scope of NEPA and
this subpart which are within the scope
of that party’s admitted contention, in
accordance with the provisions of part
2 of this chapter applicable to the
limited work authorization or in
accordance with the terms of any notice
of hearing applicable to the limited
work authorization. In the proceeding,
the presiding officer will decide all
matters in controversy among the
parties.
I 20. The heading of § 51.105 is revised,
and a new paragraph (c) is added to read
as follows:
§ 51.105 Public hearings in proceedings
for issuance of construction permits or
early site permits; limited work
authorizations.
rwilkins on PROD1PC63 with RULES_2
*
*
*
*
*
(c)(1) In addition to complying with
the applicable provisions of § 51.104, in
any proceeding for the issuance of a
construction permit for a nuclear power
plant or an early site permit under part
52 of this chapter, where the applicant
requests a limited work authorization
under § 50.10(d) of this chapter, the
presiding officer shall—
(i) Determine whether the
requirements of Section 102(2)(A), (C),
and (E) of NEPA and the regulations in
the subpart have been met, with respect
to the activities to be conducted under
the limited work authorization;
(ii) Independently consider the
balance among conflicting factors with
respect to the limited work
authorization which is contained in the
record of the proceeding, with a view to
determining the appropriate action to be
taken;
(iii) Determine whether the redress
plan will adequately redress the
activities performed under the limited
work authorization, should limited
work activities be terminated by the
holder or the limited work authorization
be revoked by the NRC, or upon
effectiveness of the Commission’s final
decision denying the associated
construction permit or early site permit,
as applicable;
(iv) In an uncontested proceeding,
determine whether the NEPA review
conducted by the NRC staff for the
limited work authorization has been
adequate; and
(v) In a contested proceeding,
determine whether, in accordance with
the regulations in this subpart, the
VerDate Aug<31>2005
17:31 Oct 05, 2007
Jkt 211001
limited work authorization should be
issued as proposed.
(2) If the limited work authorization is
for activities to be conducted at a site for
which the Commission has previously
prepared an environmental impact
statement for the construction and
operation of a nuclear power plant, and
a construction permit was issued but
construction of the plant was never
completed, then in making the
determinations in paragraph (c)(1) of
this section, the presiding officer shall
be limited to a consideration whether
there is, with respect to construction
activities encompassed by the
environmental impact statement which
are analogous to the activities to be
conducted under the limited work
authorization, new and significant
information on the environmental
impacts of those activities, such that the
limited work authorization should not
be issued as proposed.
(3) The presiding officer’s
determination in this paragraph shall be
made in a partial initial decision to be
issued separately from, and in advance
of, the presiding officer’s decision in
paragraph (a) of this section.
I 21. In § 51.107, the heading is revised,
and a new paragraph (d) is added to
read as follows:
§ 51.107 Public hearings in proceedings
for issuance of combined licenses; limited
work authorizations.
*
*
*
*
*
(d)(1) In any proceeding for the
issuance of a combined license where
the applicant requests a limited work
authorization under § 50.10(d) of this
chapter, the presiding officer, in
addition to complying with any
applicable provision of § 51.104, shall:
(i) Determine whether the
requirements of Section 102(2)(A), (C),
and (E) of NEPA and the regulations in
this subpart have been met, with respect
to the activities to be conducted under
the limited work authorization;
(ii) Independently consider the
balance among conflicting factors with
respect to the limited work
authorization which is contained in the
record of the proceeding, with a view to
determining the appropriate action to be
taken;
(iii) Determine whether the redress
plan will adequately redress the
activities performed under the limited
work authorization, should limited
work activities be terminated by the
holder or the limited work authorization
be revoked by the NRC, or upon
effectiveness of the Commission’s final
decision denying the combined license
application;
PO 00000
Frm 00032
Fmt 4701
Sfmt 4700
(iv) In an uncontested proceeding,
determine whether the NEPA review
conducted by the NRC staff for the
limited work authorization has been
adequate; and
(v) In a contested proceeding,
determine whether, in accordance with
the regulations in this subpart, the
limited work authorization should be
issued as proposed by the Director of
New Reactors or the Director of Nuclear
Reactor Regulation, as applicable.
(2) If the limited work authorization is
for activities to be conducted at a site for
which the Commission has previously
prepared an environmental impact
statement for the construction and
operation of a nuclear power plant, and
a construction permit was issued but
construction of the plant was never
completed, then in making the
determinations in paragraph (c)(1) of
this section, the presiding officer shall
be limited to a consideration whether
there is, with respect to construction
activities encompassed by the
environmental impact statement which
are analogous to the activities to be
conducted under the limited work
authorization, new and significant
information on the environmental
impacts of those activities, so that the
limited work authorization should not
be issued as proposed by the Director of
New Reactors or the Director of Nuclear
Reactor Regulation, as applicable.
(3) In making the determination
required by this section, the presiding
officer may not address or consider the
sunk costs associated with the limited
work authorization.
(4) The presiding officer’s
determination in this paragraph shall be
made in a partial initial decision to be
issued separately from, and in advance
of, the presiding officer’s decision in
paragraph (a) of this section on the
combined license.
PART 52—LICENSES,
CERTIFICATIONS, AND APPROVALS
FOR NUCLEAR POWER PLANTS
22. The authority citation for part 52
continues to read as follows:
I
Authority: Secs. 103, 104, 161, 182, 183,
185, 186, 189, 68 Stat. 936, 948, 953, 954,
955, 956, as amended, sec. 234, 83 Stat. 444,
as amended (42 U.S.C. 2133, 2201, 2232,
2233, 2235, 2236, 2239, 2282); secs. 201, 202,
206, 88 Stat. 1242, 1244, 1246, as amended
(42 U.S.C. 5841, 5842, 5846); sec. 1704, 112
Stat. 2750 (44 U.S.C. 3504 note).
23. In § 52.1(a), the definition for
‘‘Limited work authorization’’ is added
to read as follows:
I
§ 52.1
Definitions.
(a) * * *
E:\FR\FM\09OCR2.SGM
09OCR2
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 / Rules and Regulations
Limited work authorization means the
authorization provided by the Director
of New Reactors or the Director of
Nuclear Reactor Regulation under
§ 50.10 of this chapter.
*
*
*
*
*
I 24. In § 52.17, paragraph (c) is revised
to read as follows:
§ 52.17 Contents of applications; technical
information.
*
*
*
*
*
(c) An applicant may request that a
limited work authorization under 10
CFR 50.10 be issued in conjunction with
the early site permit. The application
must include the information otherwise
required by 10 CFR 50.10(d)(3).
Applications submitted before, and
pending as of November 8, 2007, must
include the information required by
§ 52.17(c) effective on the date of
docketing.
I 25. In § 52.24, paragraph (c) is revised
to read as follows:
§ 52.24
Issuance of early site permit.
*
*
*
*
*
(c) The early site permit shall specify
those 10 CFR 50.10 activities requested
under § 52.17(c) that the permit holder
is authorized to perform.
I 26. Section 52.27 is redesignated as
§ 52.26, and a new § 52.27 is added to
read as follows:
§ 52.27 Limited work authorization after
issuance of early site permit.
A holder of an early site permit may
request a limited work authorization in
accordance with § 50.10 of this chapter.
I 27. In § 52.80, paragraphs (b) and (c)
are revised to read as follows:
§ 52.80 Contents of applications;
additional technical information.
*
*
*
*
(b) An environmental report, either in
accordance with 10 CFR 51.50(c) if a
rwilkins on PROD1PC63 with RULES_2
*
VerDate Aug<31>2005
18:52 Oct 05, 2007
Jkt 211001
limited work authorization under 10
CFR 50.10 is not requested in
conjunction with the combined license
application, or in accordance with
§§ 51.49 and 51.50(c) of this chapter if
a limited work authorization is
requested in conjunction with the
combined license application.
(c) If the applicant wishes to request
that a limited work authorization under
10 CFR 50.10 be issued before issuance
of the combined license, the application
must include the information otherwise
required by 10 CFR 50.10, in accordance
with either 10 CFR 2.101(a)(1) through
(a)(4), or 10 CFR 2.101(a)(9).
28. Section 52.91 is revised to read as
follows:
I
§ 52.99
57447
Inspection during construction.
(a) The licensee shall submit to the
NRC, no later that 1 year after issuance
of the combined license or at the start
of construction as defined in 10 CFR
50.10(a), whichever is later, its schedule
for completing the inspections, tests, or
analyses in the ITAAC. The licensee
shall submit updates to the ITAAC
schedules every 6 months thereafter
and, within 1 year of its scheduled date
for initial loading of fuel, the licensee
shall submit updates to the ITAAC
schedule every 30 days until the final
notification is provided to the NRC
under paragraph (c)(1) of this section.
*
*
*
*
*
PART 100—REACTOR SITE CRITERIA
§ 52.91 Authorization to conduct limited
work authorization activities.
I
(a) If the application does not
reference an early site permit which
authorizes the holder to perform the
activities under 10 CFR 50.10(d), the
applicant may not perform those
activities without obtaining the separate
authorization required by 10 CFR
50.10(d). Authorization may be granted
only after the presiding officer in the
proceeding on the application has made
the findings and determination required
by 10 CFR 50.10(e), and the Director of
New Reactors or the Director of Nuclear
Reactor Regulation makes the
determination required by 10 CFR
50.10(e).
(b) If, after an applicant has performed
the activities permitted by paragraph (a)
of this section, the application for the
combined license is withdrawn or
denied, then the applicant shall
implement the approved site redress
plan.
Authority: Secs. 103, 104, 161, 182, 68
Stat. 936, 937, 948, 953, as amended (42
U.S.C. 2133, 2134, 2201, 2232); secs. 201, as
amended, 202, 88 Stat. 1242, as amended,
1244 (42 U.S.C. 5841, 5842); sec. 1704, 112
Stat. 2750 (44 U.S.C. 3504 note).
29. In § 52.99, paragraph (a) is revised
to read as follows:
I
PO 00000
Frm 00033
Fmt 4701
Sfmt 4700
30. The authority citation for part 100
continues to read as follows:
31. In § 100.23, paragraph (b) is
revised to read as follows:
I
§ 100.23
criteria.
Geologic and seismic siting
*
*
*
*
*
(b) Commencement of construction.
The investigations required in
paragraph (c) of this section are not
considered ‘‘construction’’ as defined in
10 CFR 50.10(a).
*
*
*
*
*
Dated at Rockville, Maryland, this 25th day
of September 2007.
For the Nuclear Regulatory Commission.
Annette L. Vietti-Cook,
Secretary of the Commission.
[FR Doc. E7–19312 Filed 10–5–07; 8:45 am]
BILLING CODE 7590–01–P
E:\FR\FM\09OCR2.SGM
09OCR2
Agencies
[Federal Register Volume 72, Number 194 (Tuesday, October 9, 2007)]
[Rules and Regulations]
[Pages 57416-57447]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-19312]
[[Page 57415]]
-----------------------------------------------------------------------
Part III
Nuclear Regulatory Commission
-----------------------------------------------------------------------
10 CFR Parts 2, 50, 51, 52, and 100
Limited Work Authorizations for Nuclear Power Plants; Final Rule
Federal Register / Vol. 72, No. 194 / Tuesday, October 9, 2007 /
Rules and Regulations
[[Page 57416]]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
10 CFR Parts 2, 50, 51, 52, and 100
RIN 3150-AI05
Limited Work Authorizations for Nuclear Power Plants
AGENCY: Nuclear Regulatory Commission.
ACTION: Final rule.
-----------------------------------------------------------------------
SUMMARY: The Nuclear Regulatory Commission (NRC) is amending its
regulations applicable to limited work authorizations (LWAs), which
allow certain construction activities on production and utilization
facilities to commence before a construction permit or combined license
is issued. This final rule modifies the scope of activities that are
considered construction for which a construction permit, combined
license, or LWA is necessary, specifies the scope of construction
activities that may be performed under an LWA, and changes the review
and approval process for LWA requests. The NRC is adopting these
changes to enhance the efficiency of its licensing and approval process
for production and utilization facilities, including new nuclear power
reactors.
DATES: The effective date is November 8, 2007.
FOR FURTHER INFORMATION CONTACT: Nanette V. Gilles, Office of New
Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555-
0001; telephone 301-415-1180; e-mail: NVG@nrc.gov or Geary Mizuno,
Office of the General Counsel, U.S. Nuclear Regulatory Commission,
Washington, DC 20555-0001; telephone 301-415-1639; e-mail: GSM@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Background
A. Development of the Supplemental Proposed LWA Rule
1. 10 CFR Part 52 Rulemaking
2. Industry Stakeholder Comments Seeking Changes to LWA Process
B. Publication of Supplemental Proposed LWA Rule and External
Stakeholder Interactions During the Public Comment Period
C. Description of Supplemental Proposed LWA Rule
II. Public Comments
A. Overview of Public Comments
B. NRC Response to Public Comments
1. Commission Questions
2. LWA Process
3. SSCs Within Scope of ``Construction''
4. Excavation
5. Compliance With NEPA
6. LWA Application Process
7. Other Topics
III. Discussion
A. History of the NRC's Concept of Construction and the LWA
B. NRC's Concept of Construction and the AEA
C. NRC's LWA Rule Complies With NEPA
1. NRC's Concept of Construction Is Consistent With the Legal
Effect of NEPA
2. NRC's Concept of the ``Major Federal Action'' Is Consistent
With NEPA Law
3. NRC's Phased Approval Approach Is Not Illegal Segmentation
Under NEPA
D. Consideration of Activities as ``Construction.''
1. Driving of Piles
2. Excavation
3. Temporary Structures and Activities in the Excavation
4. Construction SSCs
E. Phased Application and Approval Process
F. EIS Prepared, but Facility Construction Was Not Completed
G. Commission Action on PRM-50-82
IV. Section-by-Section Analysis
V. Availability of Documents
VI. Agreement State Compatibility
VII. Voluntary Consensus Standards
VIII. Environmental Impact--Categorical Exclusion
IX. Paperwork Reduction Act Statement
X. Regulatory Analysis
XI. Regulatory Flexibility Act Certification
XII. Backfit Analysis
XIII. Congressional Review Act
I. Background
A. Development of the Supplemental Proposed LWA Rule
1. 10 CFR Part 52 Rulemaking
This LWA rulemaking originated as a supplement to an NRC rulemaking
effort to revise 10 CFR part 52. The NRC issued 10 CFR part 52 on April
18, 1989 (54 FR 15372), to reform its licensing process for future
nuclear power plants. 10 CFR part 52 added alternative licensing
processes in 10 CFR part 52 for early site permits (ESPs), standard
design certifications, and combined licenses. These were additions to
the two-step licensing process that already existed in 10 CFR part 50.
The processes in 10 CFR part 52 allow for resolving safety and
environmental issues early in the licensing proceedings and were
intended to enhance the safety and reliability of nuclear power plants
through standardization.
The NRC had planned to update 10 CFR part 52 after using the
standard design certification process. The proposed rulemaking action
began with the issuance of SECY-98-282, ``Part 52 Rulemaking Plan,'' on
December 4, 1998. The Commission issued a staff requirements memorandum
(SRM) on January 14, 1999 (SRM on SECY-98-282), approving the NRC
staff's plan for revising 10 CFR part 52. Subsequently, the NRC
obtained considerable stakeholder comments on its planned action,
conducted three public meetings on the proposed rulemaking, and twice
posted draft rule language on the NRC's rulemaking Web site before
issuance of the initial proposed rule on July 3, 2003 (68 FR 40026).
However, a number of factors, including the experience gained in using
the 10 CFR part 52 early site permit process, led the NRC to question
whether the July 2003 proposed rule would meet the NRC's objective of
improving the effectiveness of its processes for licensing future
nuclear power plants (March 13, 2006; 71 FR 12782). As a result, the
NRC decided that a substantial rewrite and expansion of the original
proposed rulemaking was desirable so that the agency may more
effectively and efficiently implement the licensing and approval
processes for future nuclear power plants under part 52. Accordingly,
the Commission decided to revise the July 2003 proposed rule and
published the revised proposed rule for public comment on March 13,
2006 (71 FR 12782). The public comment period on the March 2006
proposed rule ended on May 30, 2006.
2. Industry Stakeholder Comments Seeking Changes to LWA Process
In a May 25, 2006 comment letter,\1\ the Nuclear Energy Institute
(NEI) suggested modifications to the NRC's LWA process including: (1)
That non-safety-related ``LWA-1'' activities, currently reflected in
Sec. Sec. 50.10(c) and 50.10(e)(1), be allowed to proceed without
prior authorization from the NRC, and (2) that the approval process for
safety-related ``LWA-2'' activities be accelerated. NEI's comment also
stated that the current definition of construction in Sec. 50.10(b)
reflects the correct interpretation of the Commission's licensing
authority under the Atomic Energy Act of 1954, as amended.
---------------------------------------------------------------------------
\1\ See Letter from Adrian P. Heymer, Nuclear Energy Institute,
to Annette L. Vietti-Cook, Secretary, U.S. Nuclear Regulatory
Commission, Pre-Licensing Construction Activity and Limited Work
Authorization Issues relating to NRC Proposed Rule, ``Licenses,
Certifications and Approvals for Nuclear Power Plants,'' 71 FR 12782
(March 13, 2006) (RIN 3150-AG24) (May 25, 2006) (ADAMS ML061510471).
---------------------------------------------------------------------------
NEI supported its suggested changes to the LWA process, stating
that the business environment requires that new plant applicants seek
to minimize the time interval between a decision to proceed with a
combined license application and the start of commercial operation. To
achieve this goal, NEI stated that non-safety-related ``LWA-1''
activities would need to be initiated up to 2 years before the
activities currently defined as ``construction'' in Sec. 50.10(b). NEI
believes that the current LWA
[[Page 57417]]
approval process would constrain the industry's ability to use modern
construction practices and needlessly add 18 months to estimated
construction schedules for new plants that did not reference an early
site permit with LWA authority. NEI's comment letter stated that ``[t]o
the extent the NRC determines that these LWA issues cannot be addressed
in the current rulemaking, we ask that the Commission initiate an
expedited rulemaking.''
The NRC determined that the changes suggested in the NEI letter
could not be incorporated into the final part 52 rule without re-
noticing, but that the NEI letter met the sufficiency requirements for
a petition for rulemaking as described in 10 CFR 2.802(c). Therefore,
the NRC elected to treat the letter as a petition for rulemaking (PRM-
50-82).
B. Publication of Supplemental Proposed LWA Rule and External
Stakeholder Interactions During the Public Comment Period
The supplemental proposed LWA rule was published in the Federal
Register on October 17, 2006 (71 FR 61330) for a 30-day public comment
period which ended November 16, 2006. During the public comment period,
the NRC held a public meeting on November 1, 2006, to answer external
stakeholder questions about the supplemental proposed LWA rule. A
transcript of the public meeting was made (Agencywide Documents Access
and Management System (ADAMS) Accession No. ML063190396), as referenced
in the meeting summary (ADAMS Accession No. ML062970517).
In addition, the NRC informally contacted several Federal agencies
that traditionally have been interested in environmental impacts
statements (EISs) prepared by the NRC before the issuance of LWAs and
construction permits, for the purpose of seeking their comments on the
supplemental proposed LWA rule. These Federal agencies were the Council
on Environmental Quality (CEQ), the U.S. Environmental Protection
Agency (EPA), the Federal Energy Regulatory Commission (FERC), and the
U.S. Department of the Interior, Fish, and Wildlife Service (FWS).
Finally, the Commission held a public meeting on November 9, 2006,
on the overall part 52 rulemaking, at which time industry stakeholders
presented additional information on the supplemental proposed LWA rule.
C. Description of Supplemental Proposed LWA Rule
The supplemental proposed LWA rule would narrow the scope of
activities requiring permission from the NRC in the form of an LWA by
eliminating the concept of ``commencement of construction'' currently
described in Sec. 50.10(c) and the authorization described in Sec.
50.10(e)(1). Instead, under the supplemental proposed rule, NRC
authorization would be required only before undertaking activities that
have a reasonable nexus to radiological health and safety and/or common
defense and security (i.e., excavation, subsurface preparation,
installation of the foundation, and on-site, in-place fabrication,
erection, integration or testing, for any structure, system, or
component of a facility required by the Commission's rules and
regulations to be described in the site safety analysis report or
preliminary or final safety analysis report). While the proposed
redefinition of ``construction'' would result in fewer activities
requiring NRC permission in the form of an LWA, it also would redefine
certain activities (such as the driving of piles) that are currently
excluded from the regulatory definition of construction given in Sec.
50.10(b), as construction requiring an LWA.
Further, the supplemental proposed LWA rule provided an optional,
phased application and approval procedure for construction permit and
combined license applicants to obtain LWAs. The supplemental proposed
rule provided for an environmental review and approval process for LWA
requests that would allow the NRC to grant an applicant permission to
engage in LWA activities after completion of an EIS addressing those
activities, but before completion of the comprehensive EIS addressing
the underlying request for a construction permit or combined license.
The supplemental proposed rule also delineated the environmental review
required in situations where the LWA activities are to be conducted at
sites for which the Commission has previously prepared an EIS for the
construction and operation of a nuclear power plant, and for which a
construction permit was issued, but construction of the plant was never
completed.
II. Public Comments
A. Overview of Public Comments
The NRC received 13 public comments \2\ on the supplemental
proposed rule. Ten comments were from external industry stakeholders,
consisting of NEI and 7 nuclear power plant licensees--including the 3
applicants for ESPs whose applications are currently pending before the
NRC, and 2 companies who have applied (or are expected to apply) for
standard design certifications (GE Nuclear and Areva NP). One
commenter, Dianne Curran, submitted a comment on behalf of Public
Citizen, a consumer advocacy organization, and the Nuclear Information
and Resource Service (NIRS), an information and networking organization
for organizations concerned about nuclear issues and energy
sustainability. One comment was received from the EPA, and one comment
was received from an NRC staff individual.
---------------------------------------------------------------------------
\2\ A public comment dated November 7, 2006, from Westinghouse
Electric Company LLC, on the main part 52 rulemaking, was
erroneously designated as comment no. 1 on the supplemental proposed
LWA rule. This number was later assigned to a comment filed by Diane
Curran on behalf of Public Citizen and the NIRS.
---------------------------------------------------------------------------
NEI supported the general approach and objective of the
supplemental proposed rule, but raised three key issues on the
supplemental proposed rule: (1) Inclusion of excavation in the
definition of ``construction;'' (2) Designation of structures, systems,
and components (SSCs) ``required to be described'' in the standard
safety analysis report or final safety analysis report (FSAR) as a key
element of the definition of ``construction;'' and (3) Limiting
submittal of LWA applications up to 12 months in advance of a combined
license application. NEI also proposed a number of changes to the
supplemental proposed rule to address three less-significant areas of
concern: (1) An LWA applicant's reliance on an earlier EIS for an
unconstructed facility; (2) LWA applicant's ability to take advantage
of the provisions of Sec. 2.101(a)(9) for an accelerated hearing
schedule when submitting an LWA application in advance of a combined
license application; and (3) The need for ``grandfathering'' of current
ESP applicants. Finally, NEI suggested that Sec. 2.101(a)(5) be
modified from the March 2006 proposed rule to allow one part of a
combined license application to precede or follow the other part of the
application by no more than 12 months. The other industry commenters,
including GE Nuclear and Areva NP, generally supported the NEI
comments, and in some cases provided additional discussion in support
of one or more of NEI's specific comments.
Public Citizen and NIRS opposed granting of an LWA in advance of
issuance of a construction permit or combined license, in general
because
[[Page 57418]]
these commenters perceived the process as introducing additional
complexity to the licensing process, and increasing the cost to
individuals who wish to participate in the licensing process. These
organizations supported the NRC's proposal to include excavation and
the driving of piles in the definition of construction.
The EPA indicated that it had no objections to the supplemental
proposed LWA rule, stating that the supplemental rule would ``enhance
the efficiency of the NRC's LWA approval process, while maintaining
appropriate consideration of environmental effects pursuant to NEPA
[National Environmental Policy Act of 1969, as amended].'' In addition,
NRC was advised by telephone that CEQ had no objection to the
supplemental proposed LWA rule, and therefore would not submit a
written comment on the rule.
The NRC staff individual provided eight numbered comments on the
supplemental proposed LWA rule. The commenter focused on compliance
with the NEPA and the potential adverse effect of the supplemental
proposed rule on the NRC staff's resources.
B. NRC Response to Public Comments
The NRC has carefully considered the stakeholder comments, and is
adopting a final LWA rule which differs in some respects from the
supplemental proposed LWA rule. The final rule is described and
discussed in more detail in Sections III. Discussion, and IV. Section-
by-Section Analysis of this document.
The NRC is adopting the LWA rule as a separate final rule, rather
than incorporating its provisions into the final part 52 rule.
Incorporating the provisions of the final LWA rule into the final part
52 rulemaking would have resulted in a delay in publication of the
final part 52 rule, because of the additional time needed for NRC
consideration and resolution of the substantial issues raised in the
public comments on the supplemental proposed LWA rule. Accordingly, the
NRC has adopted the final part 52 rulemaking in a separate action, in
advance of this final LWA rule.
1. Commission Questions
In the statement of considerations (SOC) for the supplementary
proposed LWA rule, the Commission posed three questions, as follows
(October 17, 2006; 71 FR 61340, second column):
As explained above, this supplemental proposed rule would impact
the types of activities that could be undertaken without prior
approval from the NRC, with NRC approval in the form of an LWA, and
with NRC approval in the form of a construction permit or combined
license. Therefore, in addition to the general invitation to submit
comments on the proposed rule, the NRC also requests comments on the
following questions:
1. What types of activities should be permitted without prior
NRC approval?
2. What types of activities should be permitted under an LWA?
3. What types of activities should only be permitted after
issuance of a construction permit or combined license?
Only one commenter provided separate responses to these three
Commission questions; but the responses were simply an abbreviated
version of the comments. The remaining commenters addressed the issues
raised in these questions in the course of the commenters' discussion
on the supplementary proposed LWA rule. Accordingly, the NRC is not
providing a separate discussion of these questions and commenters'
responses. Instead, the NRC is responding to these issues in the NRC's
responses to specific comments.
2. LWA Process
Comment: The Commission should adopt the LWA final rule as a
necessary improvement to the existing LWA process. (NEI, Dominion
Nuclear North Anna, Duke Energy, Florida Power and Light, Progress
Energy, Southern Company, Unistar, Areva, and GE Nuclear)
NRC Response: The NRC agrees with the commenters that the former
NRC provisions on LWAs should be amended to improve the LWA process.
Comment: The Commission should not adopt regulations that allow
approval of LWA activities in advance of the issuance of a construction
permit or combined license. Allowing LWA activities before a plant is
licensed would confirm to the public that the licensing process is a
sham. The LWA process represents a further segmentation of the
licensing process, which will add complexity to the licensing process,
and result in further disenfranchisement of the public. (Public
Citizen/NIRS 1)
NRC Response: The NRC disagrees with these commenters. The
commenters' position fails to recognize that the LWA process has been
used by the agency for over 30 years, and therefore the proposed
changes to the LWA process would not add to complexity, or otherwise
represent further segmentation. The agency's rules include several
longstanding requirements directed at avoiding NEPA segmentation. These
requirements are retained in their essential form in the final LWA
rulemaking.
The NRC does not believe that the final LWA rule adds any further
complexity to the licensing process, or otherwise results in further
``disenfranchisement'' of the public. As stated above, the NRC's
regulatory regime already includes the LWA process, and the rule does
not modify or change the public's ability to participate in the
licensing process. Indeed, rather than ``disenfranchising'' the public,
the LWA rule may have the effect of enhancing the ability of external
stakeholders to participate in a hearing to resolve their issues with
respect to a particular nuclear power plant. Because of resource
limitations, many public stakeholders have expressed their concern
that, because of the broad range of issues addressed by the NRC at each
stage of licensing, it is difficult for them to seek resolution in an
NRC hearing for the full range of issues that they are interested in.
For these stakeholders, the LWA process--by separating out a defined
set of issues to be resolved in advance of the underlying combined
license or construction permit proceeding--allows public stakeholders
to focus their resources on the relevant issues in an LWA hearing. The
``complexity'' of the process provides an orderly sequencing of the
overall set of issues that must be resolved, without introducing
unlawful segmentation. The NRC believes that if these public
stakeholders consider the revised process in this light, they should
conclude that the LWA process enhances, rather than detracts from,
participation in the licensing process by interested members of the
public who are resource-limited.
The NRC does not believe that the NRC's proposed redefinition of
``construction'' constitutes unlawful ``segmentation'' which results in
non-compliance with NEPA. Segmentation, as discussed elsewhere in this
SOC, embraces the situation where a Federal agency divides what would
otherwise be regarded as a single, integrated Federal action into
separate, smaller Federal actions, for the purpose of avoiding
compliance with NEPA, or otherwise minimizing the apparent impact of
the single, integrated Federal action. The NRC's redefinition of
construction is not motivated by a desire to avoid compliance with
NEPA, nor will it result in a single Federal action being divided into
smaller, sequential Federal actions. Rather, the NRC's redefinition
reflects its reconsideration of the proper regulatory jurisdiction of
the agency, and properly divides what was considered a single Federal
action into private action for
[[Page 57419]]
which the NRC has no statutory basis for regulation, and the Federal
action (licensing of construction activities with a reasonable nexus to
radiological health and safety or common defense and security, for
which no other regulatory approach is acceptable) which will require
compliance with NEPA.
3. SSCs Within Scope of ``Construction''
Comment: The scope of SSCs that must be described in the FSAR is
not always clear, even under the words of existing NRC regulations
(e.g., 10 CFR 50.34(b)(2)(i)), which requires discussion of certain
systems ``insofar as they are pertinent.'' (Areva 1, 2)
NRC Response: The NRC agrees, in part, with these comments and has
revised the scope of SSCs that fall within the definition of
construction to clearly identify the SSCs that have a reasonable nexus
to radiological health and safety, or the common defense and security.
Comment: The NRC's description of activities constituting
``construction,'' which require a combined license or construction
permit (October 17, 2006; 71 FR 61337), should be modified to refer to
the ``installation or integration of that structure, system, or
component into its final plant location and elevation * * *.''
(Progress Energy 4)
NRC Response: The NRC agrees in part with the commenter, and the
corresponding language of this SOC has been modified to state ``into
its final plant location would require * * *.''
4. Excavation
Comment: It is not necessary to define construction as including
excavation of portions of the nuclear power plant facility having a
``reasonable nexus to radiological health and safety.'' Problems
identified during excavation should be identified as part of the site
characterization and investigation required for preparing a combined
license or construction permit. NRC Regulatory Guide (RG) 1.165,
``Identification and Characterization of Seismic Sources and
Determination of Safe-Shutdown Earthquake Ground Motion,'' was updated
in 1997 to provide that combined license (COL) applicants' FSARs should
include a commitment to geologically map all excavations and notify the
NRC when excavations are open for inspection. For safety-related SSCs,
these excavations and characterization/investigation activities would
be conducted under the applicant's quality assurance (QA) program. This
could result in relocation of such SSCs. This provides a better process
for ensuring safety and would better support an effective licensing
process. In addition, NRC will be involved in pre-application
activities and may elect to conduct oversight of any activity involving
site characterization and site preparation. The examples cited by the
NRC in the public meeting as a basis for including excavation within
the definition of ``construction'' did not involve questions about the
safety of the excavation activities themselves, but rather the
conditions that were identified as the result of excavation. In these
cases, the commitments to geologic mapping and notification of the NRC
are sufficient to meet the NRC's regulatory interests. Accordingly,
Sec. Sec. 50.10(b) and 51.4 should be revised in the final rule to
exclude excavation from the definition of construction, provided that
the entity conducting excavation geologically maps the excavations and
the NRC staff is notified when the excavations are opened for
inspection. (NEI 1; GE Nuclear; Progress Energy 1)
NRC Response: The NRC agrees, in part, with this comment and has
deleted excavation from the definition of construction in 10 CFR
50.10(a). A construction permit or combined license applicant is
responsible, under the current regulations, to demonstrate that the
site conditions are acceptable for the proposed facility design. This
responsibility exists regardless of whether or not the NRC reviews and
approves the proposed excavation activities and inspects the excavation
activities as they are accomplished. Inasmuch as NRC inspection and
regulatory oversight of the excavation are not necessary for reasonable
assurance of adequate protection to public health and safety or common
defense and security, and because the applicant bears the burden for
accurately characterizing the parent material, the NRC concludes that
excavation may be excluded from the definition of construction.
Comment: Excavation and the driving of piles should be considered
``construction.'' Prior agency experience has shown that safety issues
have been identified during excavation, citing to the experience of
North Anna nuclear power plant, as well as a nuclear power plant in the
Midwest where soil conditions identified during excavation necessitated
a change in foundation design. Neither the public nor a reviewing court
would think that the NRC would be able to make the underlying licensing
decision (i.e., granting a construction permit or a combined license)
in an unbiased fashion if excavation proceeded in advance of the
underlying licensing decision. (Public Citizen/NIRS 2)
NRC Response: The NRC disagrees, in part, with this comment. As
discussed in the response immediately above, the NRC concludes that
excavation may be excluded from the definition of construction.
However, the driving of piles and any other foundation work is defined
as construction.
Comment: The SOC for the final rule should specify that excavation
includes appropriate erosion control measures necessary to stabilize
site excavations pending LWA or license (i.e., combined license or
construction permit) approval of construction activities. (NEI 1.5)
NRC Response: The NRC agrees, in part, with this comment. The NRC's
definition of construction in the final LWA rule includes: (1) Any
change made to the parent material in which the excavation occurs
(e.g., soil compaction, rock grouting); and (2) The placement of
permanent SSCs that are put into the excavation during or after the
excavation (e.g., installation of permanent drainage systems, or
placement of mudmats). If the erosion control measures are conducted
outside of the excavated hole and do not cover up the exposed soil
conditions, then those activities would be allowed under Sec.
50.10(a). However, under the final LWA rule, the placement of temporary
SSCs in the excavation, such as retaining walls, drainage systems, and
erosion control barriers, all of which are to be removed before fuel
load, would not be considered construction.
Comment: ``Construction'' should be limited to above-ground
installation of certain SSCs. (Areva 1)
NRC Response: The NRC disagrees. Even under the former provisions
of Sec. 50.10(e)(3), construction included the setting of foundations
and other work accomplished below grade. The commenter provided no
basis for limiting the definition of construction to the above-grade
installation of SSCs of interest. No change was made in the final rule
as the result of this comment.
Comment: Temporary buildings, structures, and roads, may be located
in the eventual location of SSCs for which an LWA is required for
excavation under the supplemental proposed LWA rule. If excavation is
required for the temporary buildings, structures, and roads, the
supplemental proposed rule would appear to prohibit such excavation.
The final rule should make clear that excavation for SSCs outside the
scope of an LWA, such as temporary buildings, structures, and roads,
should be excluded from the definition of construction. (Areva 3)
[[Page 57420]]
NRC Response: As discussed previously, the NRC has decided to
exclude all excavation from the definition of construction. In
addition, the NRC notes that under the final LWA rule, SSCs that are
not within the scope of construction may be installed before receipt of
an LWA, construction permit, or combined license. Accordingly, the
final rule resolves the commenter's issue.
5. Compliance With NEPA
Comment: The impacts of the construction activities that the NRC
proposes to exclude from its regulations have been part of the NRC
regulations since 1972. What has changed causing the NRC to decided
that these activities will not longer be part of the environmental
review? Has NRC been doing it wrong for more than 30 years (including
the 3 early site permits that are either completed or near completion)?
(Kugler 1)
NRC Response: As discussed in the ``Discussion'' section of this
final rule (as well as the supplemental proposed rule), the 1972
amendment to the definition of construction in 10 CFR 50.10 was made
early in the Federal government's implementation of then-new NEPA.
Since that time, the Federal case law on NEPA has evolved, with several
U.S. Supreme Court decisions on the requirements of NEPA. In addition,
in preparing for the expected next generation of nuclear power plant
construction applications, the nuclear power industry has reviewed the
overall construction process based upon lessons learned from the
construction and licensing process used for currently operating
reactors. The industry submitted what is essentially a petition for
rulemaking seeking changes to the LWA process, reflecting those lessons
learned and their understanding of the current state of NEPA law. The
NRC has reviewed the applicable law, and for the reasons stated
elsewhere in this SOC, agrees with the petitioner that the current
definition of construction and the current LWA requirements in Sec.
50.10 are not compelled by NEPA or the Atomic Energy Act (AEA) of 1954,
as amended. While the agency's regulations on construction and LWAs
were a reasonable implementation of NEPA as understood in 1972, the NRC
believes that, with more than 30 years experience in implementing NEPA
and the evolving jurisprudence, the time is appropriate for
reconsideration and revamping of these NRC requirements.
Comment: The impacts of the construction of a nuclear power plant
that NRC now proposes to exclude from NRC regulations are probably 90
percent of the true environmental impacts of construction. Before even
talking to the NRC, a power company can clear and grade the land, build
roads and railroad spurs, erect permanent and temporary buildings,
build numerous plant structures (e.g., cooling water intake and
discharge, cooling towers), and build switchyards and transmission
lines. After potentially doing all of that, THEN the company would come
to the NRC and ask permission to build the power plant for which all of
this work was done. How does this comply with NEPA? The commenter
asserts that the NRC is going to ignore almost all of the construction
impacts of the proposed action. (Kugler 2)
NRC Response: The commenter assumes that, if a private action is
preparatory to Federal action, then NEPA provides a statutory basis for
the agency to extend its otherwise limited jurisdiction under the AEA
to those private, preparatory actions, solely for the purpose of agency
consideration of the environmental impacts under NEPA. The commenter
has not pointed to, and the NRC has not identified, Federal case law
that supports such a position. Indeed, even in a case where the Federal
agency had unequivocal statutory authority to grant or deny a Federal
permit, the U.S. Supreme Court specifically held that the Federal
agency was not compelled to require mitigation based upon environmental
considerations identified in the NEPA review. Robertson v. Methow
Valley Citizens Council, 490 U.S. 332 (1989).
The commenter also asserts that the NRC is going to ``ignore all
the [pre-]construction impacts of the proposed action.'' On the
contrary, as stated elsewhere in this SOC, the pre-construction private
actions of clearing, grading, access road construction, etc., will be
considered in the cumulative impacts analysis in the LWA EIS as the
baseline for analyzing the environmental impacts associated with the
Federal action authorizing LWA activities. This information will be
used when evaluating the environmental impacts of construction and
operation of the proposed nuclear power plant.
Comment: The commenter states that the final rule says NRC won't
consider the sunk costs of all of this work in your decision whether to
approve the request to build the plant. The commenter asserts that NRC
has allowed the company to do most of the environmental damage. Who
cleans up the mess if the NRC says no? The commenter states that
because the NRC has excluded from its review all of this work that's
specifically for the purpose of building the plant, the NRC also can't
require any redress plan for the site for those impacts. (Kugler 2.a)
NRC Response: The commenter appears to believe that the NRC has
authority to exercise its regulatory jurisdiction in an area where it
does not otherwise possess regulatory authority under its organic
statute, solely for the purpose of ensuring environmental redress of
private activities with significant environmental impacts. The NRC does
not agree with the commenter's implicit suggestion. As discussed in the
response to the previous comment as well as elsewhere in this SOC, the
NRC does not possess statutory authority to regulate activities that do
not have an impact upon radiological health and safety or common
defense and security, and NEPA does not provide independent statutory
authority to extend the agency's jurisdiction solely for the purpose of
assuring that adverse environmental impacts are considered and
mitigated. While this may be a worthy goal, the NRC may not lawfully
act in such a manner, absent additional statutory authority which is
not currently provided by either NEPA or the AEA.
Comment: The commenter asserts that NRC won't consider the sunk
costs in its review. The commenter also asserts that it sounds like the
``baseline'' for the environmental review will include the
environmental damage done by a company in terms of ``pre-application''
activities. In other words, if an applicant for an LWA, CP, or COL has
done all of the things NRC now allows without NRC review, the condition
of the cleared and partially built site is now the starting point for
the environmental review. The commenter states that in terms of
comparing this partially built site to any alternative site, NRC has
essentially ``pre-selected'' the site chosen by the applicant. The
commenter states there will be less environmental impacts at a site
that has already had most of the damage done to it as compared to any
other site. The commenter believes the NRC has handed its
responsibility for the site suitability determination over to the
applicant. (Kugler 2.b)
NRC Response: The commenter makes two incorrect assumptions. First,
the commenter implicitly assumes that environmental matters are the key
determinants of site suitability. The NRC believes that, as a practical
matter and as borne out by the history of site suitability
determinations in the past, other factors, such as seismic activity and
intensity, geological structures, meteorological factors, impediments
to development of emergency plans,
[[Page 57421]]
security issues, and demographics (population density and distance)
from a safety perspective are at least as important, if not more
important, than ``environmental'' matters as a key determinant of site
suitability.
Second, the commenter assumes that clearing of a site will always
tilt the environmental balance in favor of the applicant's ``pre-
selected site.'' This may not be true in most cases. For example, even
an ``obviously superior'' site from the standpoint of environmental
impacts on water--which is likely to be the determining
``environmental'' impact--will require grading and clearing in order to
be used. If construction were to be abandoned at the applicant's ``pre-
selected site'' and commenced at the ``obviously superior site,'' the
environmental impacts of pre-construction activities such as clearing
and grading would still have to be performed at the ``obviously
superior'' site. In essence, the ``sunk environmental impacts''
associated with preconstruction at the pre-selected site are balanced
out by the ``future'' environmental impacts associated with
preconstruction at the ``obviously superior'' site. Thus, pre-
construction at a ``pre-selected'' site could not, in and of itself,
lead to automatic dismissal of otherwise ``obviously superior'' sites.
In any event, the issue of the ``baseline'' for purposes of
alternative sites is not addressed directly in the final LWA rule and
will be resolved in the development of NRC guidance on implementation
of the final LWA rule. Furthermore, the NRC notes that pre-construction
impacts will be evaluated as part of the cumulative impacts analysis,
which may render moot some aspects of the commenter's concerns in this
area.
Comment: How can NRC tell the world in an EIS that the only real
impacts of construction of a nuclear power plant will be related to
digging a big hole and a few other straggling items that will occur
while the structures described in the FSAR are being built? (Kugler
2.c)
NRC Response: The commenter appears to assert that the NRC's EIS
for a combined license must attribute to the NRC's Federal action all
of the environmental impacts of constructing a nuclear power facility,
including the private, pre-construction activities that may be
accomplished by the applicant without any NRC approval. The commenter's
implicit assertion is incorrect. The NRC's EIS need only describe the
environmental impacts of the Federal action as those construction
activities, as defined under Sec. 50.10, which can only be
accomplished under an LWA and combined license or construction permit.
The environmental impacts of pre-construction activities will also
be described in the NRC's EIS because such description is necessary to
evaluate the cumulative impacts of the Federal action, in light of the
pre-existing impacts of the private, pre-construction action. The
cumulative impacts discussion should provide information on the total
environmental impacts of constructing the nuclear power plant to both
the NRC decisionmaker and the general public.
The NRC notes that, under the final LWA rule, excavation for SSCs
that are important from a radiological health and safety or common
defense and security standpoint will not be treated as
``construction.'' Therefore, the environmental effects of excavation
would not be evaluated as an impact attributable to the Federal
licensing action, but instead be added to the environmental baseline
for a site.
Comment: How are applicants and NRC going to divide impacts if some
of the construction activities now out side (sic.) the NRC's scope are
going on at the same time as activities inside NRC's scope? For
example, traffic impacts of the construction workforce are often an
issue. But how does the NRC deal with it if part of the workforce is
building cooling towers and intake systems, and part is building FSAR-
listed structures? Another case is property taxes. The property taxes
paid by the company are a significant item in the socioeconomic review.
Are the applicant and the NRC now going to have to differentiate
between taxes paid for FSAR-related facilities and taxes paid for other
facilities? (Kugler 2.d)
NRC Response: The commenter raises a number of detailed issues with
respect to NRC implementation of the final rule in the course of
preparing EISs. None of these matters appear to raise issues that are
insurmountable or would be unusually difficult to resolve. For example,
the need to apportion the taxes for FSAR-related SSCs, versus taxes on
other portions of the facility whose construction does not require NRC
approval could be resolved by simply treating all the taxes paid as a
benefit of operation, and the impacts from all portions of the plant as
an impact of operation. The NRC expects that the staff will develop
supplemental guidance to the environmental standard review plan on
these and other implementation matters.
Comment: The commenter states that the rule says that if an LWA is
issued, the EIS to build and operate a nuclear power plant will be a
supplement to the EIS for the LWA. The commenter believes this means
that the EIS that evaluates the impacts of building and operating a
large commercial power plant will be a supplement to the EIS for
digging a big hole. The commenter states that assuming the EIS for the
big hole ignores all of the other impacts of construction that may
already have taken place, it's going to be pretty limited in scope. The
commenter states that this EIS of very limited scope will now become
the base document, and the EIS that considers ALL of the impacts of
operations will be a supplement to it. (Kugler 3)
NRC Response: The NRC believes that the proposed rule is consistent
with NEPA. The commenter presented no rationale why the NRC's proposal
violates either NEPA or CEQ's implementing regulations. NEPA itself
only requires that a statement be prepared addressing the environmental
impacts and alternatives of major Federal actions significantly
affecting the environment. The statute does not contain any language
specifically constraining the manner in which each EIS for two
sequential Federal actions must be prepared. Hence, the NRC is free to
select a manner of NEPA compliance which best meets the agency's needs.
The commenter appears to be concerned that, if the LWA applicant
chooses to submit an environmental report limited to LWA activities,
then the LWA EIS would be a relatively narrow document which cannot be
the basis for a supplemental EIS with a greatly expanded scope of
subject matters addressed. The NRC does not believe that the
commenter's concern is well-founded. First, the CEQ's regulations
specifically permit ``tiering'' of EISs to ``eliminate repetitive
discussions of the same issues and to focus on the actual issue ripe
for consideration at each level of the environmental review * * *'' (40
CFR 1502.20). Although most of the tiering discussion refers to a broad
initial EIS followed by more specific EIS tiering on the earlier EIS,
40 CFR 1502.20 also states, ``Tiering may also be appropriate for
different stages of actions (emphasis added).'' The NRC believes that
the LWA is a stage in the overall Federal action of issuing a license
for construction (and, in the case of a combined license under part 52,
operation) of a nuclear power plant. It is logical to evaluate the
environmental impacts of the activities that occur first (i.e., LWA
activities), followed by evaluation of the impacts of activities that
occur thereafter (i.e., main construction and operation). The
[[Page 57422]]
potential for segmentation of the Federal impacts is minimized, as
discussed previously, by various provisions of the rule which, inter
alia, prohibit NRC consideration of sunk costs, require consideration
of all environmental impacts and benefits attributable to LWA
activities in the supplemental EIS prepared for the underlying combined
license or construction permit application, and require the applicant/
licensee to develop and, if necessary, implement a redress plan.
Second, the CEQ regulations also encourage agencies to incorporate by
reference material into an EIS to cut down on bulk without impeding
agency and public review of the action. Nothing in the CEQ regulations
suggests that incorporation by reference is precluded where the
material being incorporated is smaller in bulk than the EIS into which
the material is being incorporated. The NRC believes the purpose of
incorporation by reference is served by incorporating the LWA EIS into
the supplemental EIS prepared at the combined license or construction
permit stage.
Comment: The commenter states the LWA EIS will only be looking at
the impacts of digging the big hole and pouring the foundation. At what
point does the NRC staff evaluate the impacts of construction and
operation to determine whether the site is SUITABLE for the
construction and operation of a nuclear power plant? Is that done
later? Does that mean that NRC could authorize digging the hole at a
site that could later be determined by NRC to be unsuitable? (Kugler 4)
NRC Response: The NRC has decided that excavation should not be
considered ``construction,'' and that NRC permission is not required to
undertake excavation activities. Accordingly, a response to this
comment, to the extent that it is focused on NRC consideration of the
impacts of excavation as an impact of the issuance of the LWA,
construction permit, or combined license, is unnecessary. As discussed
elsewhere in this document, the impacts of preconstruction activities
performed by the ESP holder, construction permit, or combined license
applicant must be described by the applicant in its environmental
report, and must be considered in the cumulative impacts analysis.
Under the final LWA rule, the NRC's evaluation of site suitability
must be made when it issues a construction permit or combined license,
unless the applicant seeks, either as part of an LWA or in advance of
the issuance of the construction permit or combined license under
subpart F of part 2, an early decision on site suitability and/or the
environmental impacts of construction and operation.
Comment: Has the NRC discussed these changes with key stakeholders
like EPA, CEQ, and FERC? What do they think of this change? The
commenter states that this is a major shift by the NRC away from its
NEPA responsibilities, and believes that other agencies may have real
problems with it beyond the basic NEPA issues. For example, will FERC
commence a review for transmission lines if the power company hasn't
submitted an application to the NRC to build the plant for which it's
needed? Similarly, will the Corps of Engineers issue Section 404
permits to damage wetlands and dredge if there's no request to build a
plant yet? Has anybody talked to them? (Kugler 5)
NRC Response: The NRC sought comments on the proposed rule from
four Federal agencies who have historically been interested in NRC
construction licensing from an environmental standpoint. Advance copies
of the proposed rule as approved by the Commission were provided to the
CEQ, the EPA, FERC, and the U.S. Department of the Interior, FWS, and
copies of the proposed rule as published in the Federal Register were
electronically transmitted to cognizant individuals in these agencies
on the date of publication of the proposed rule in the Federal Register
(ADAMS Accession Nos. ML062840445, ML062910051, and ML062910049).
Additional telephone calls were made to describe the proposed rule and
to answer any questions from these agency officials. As discussed
earlier in this document, the NRC has received comments from the EPA,
which has no objection to the change. NRC was advised by telephone that
CEQ had no objection to the supplemental proposed LWA rule. The NRC has
been advised by FERC that it ordinarily would not review transmission
line routings for lines commencing at nuclear power facilities. The NRC
believes that it has made reasonable efforts to obtain input from other
cognizant Federal agencies, and none appear to share the concerns of
the commenter. No change from the supplemental proposed LWA rule has
been made as the result of this comment.
Comment: How does this change affect the current early site permit
applicants? The commenter states that, for example, Exelon and Dominion
submitted redress plans for all of the impacts of construction they'd
be allowed to carry out before receiving a license to build and operate
a plant. The petitioner also believes Southern submitted redress plans.
Future applicants won't have to do this. What happens to the Exelon and
Dominion redress plans? Do they get out of them now? If so, how does
NRC explain that to all of the folks involved in those reviews who
relied on the NRC's representations that a redress plan was required
(e.g., the public, Federal and State environmental regulatory
agencies)? What happens to Southern, which is early in its review?
(Kugler 6)
NRC Response: The final rule does not affect the NRC staff's
approval of a full-scope redress plan to support LWA activities under
the former LWA provisions in Sec. Sec. 50.10 and 52.17. The three
applicants for ESP which are currently before the NRC are required to
meet the NRC's requirements in effect at the time of the application,
with respect to the content of the application. If the final rule is
adopted before ESPs are issued to the current ESP applicants, then the
applicant may (but is not required to seek to revise its redress plan
and seek NRC approval of a (narrowed) redress plan that meets the
requirements of the final LWA rule. In such a case, the NRC would
advise other Federal and State agencies of the change in NRC's
regulatory requirements and any change in the scope of the approved
redress plan which may be requested by the ESP applicant.
Alternatively, upon issuance of the ESP, the ESP holder may request an
amendment to its ESP, consistent with the recently-adopted revisions to
10 CFR part 52, to seek NRC approval of a (narrowed) redress plan which
is consistent with the requirements of the final LWA rule. In such an
event, the NRC would--as part of its routine procedures--consult with
relevant Federal agencies. No change from the supplemental proposed LWA
rule was made as a result of this comment.
Comment: Section 51.49(a)(2) should be revised to delete the
requirement for an LWA applicant to state the need for an LWA.
(Progress Energy 5)
NRC Response: The NRC disagrees with the commenter's proposal. An
EIS should state the purpose and need for a proposed action. 10 CFR
part 51, appendix A, paragraph 4; 40 CFR 1502.13. Inasmuch as the NRC
is acting on a private entity's request in a licensing action, the
purpose and need should be, in the first instance, determined by the
applicant and be adopted by the NRC. No change was made to the final
rule as a result of this comment.
Comment: Sections 51.20(b)(1) and (5), and 51.76(b) and (e) should
be revised to allow the NRC staff the option of preparing and issuing
an
[[Page 57423]]
environmental assessment (EA) if the environmental report shows no
significant environmental impacts associated with LWA activities.
(Progress Energy 6, 7, 8)
NRC Response: The NRC disagrees with the commenter's proposal. In
preparing the supplementary proposed rule, the NRC considered the
approach recommended by the commenter. However, the NRC rejected
proposing such an approach because it would increase the perception of
Federal segmentation, without any significant countervailing benefits,
in terms of resources or time necessary to complete the NEPA process.
Furthermore, the tiering concept, under CEQ regulations, involves
sequential EISs rather than an EA followed by an EIS. The NRC believes
that it would not be prudent to pursue a new approach to NEPA
compliance, which may result in legal instability in an area of
critical interest to industry stakeholders. The commenter presented no
information in favor of its proposal. Accordingly, in the absence of
new information suggesting that the Commission's initial determination
should be revisited, the Commission declines to adopt the commenter's
proposal. No change was made to the final rule as a result of this
comment.
6. LWA Application Process
Comment: The commenter states that the NRC expects over 15
applications for COLs in the next 3 years or so. Perhaps it can staff
up to meet the challenge of preparing those 15 EISs. But can it
possibly handle 30? If most or all of the COL applicants choose to
submit an LWA application too, which would seem likely, the NRC staff
will have to prepare two EISs for each site. Has the NRC considered the
resource implications? (And if an applicant chooses to go the ESP route
for some reason, there will be three EISs.) (Kugler 7)
NRC Response: The commenter appears to believe that, under a
revised LWA rule, the overall resources expended by the NRC in
preparing EISs would increase over the current regulatory regime in a
time frame that would exacerbate any problems that may be caused by
limited NRC staff resources. The NRC disagrees with the commenter. The
final LWA rule merely governs the timing of the NRC's environmental
review of the overall action of licensing the construction and
operation of a nuclear power plant, consistent with NEPA.
Taking the specific example identified by the commenter of a
combined license applicant, who both seeks an LWA and references an
ESP, it is possible--as the commenter correctly points out--that three
EISs may be prepared in the worst case of a less than complete ESP EIS.
However, the final LWA rule does not require the NRC staff to prepare
entirely new, full-scope EISs at either the LWA or the combined license
issuance stages. Instead, the EIS at the LWA stage would be limited to
considering the environmental impacts of LWA activities only (assuming
that the LWA ER is limited to providing information on the
environmental impacts of LWA activities). This is consistent with NRC
and CEQ regulations that allow incorporation by reference. Preparation
of an LWA EIS limited to those subjects would not be redundant of the
ESP EIS, inasmuch as the impacts of construction under this scenario
were not addressed in the ESP EIS. Accordingly, there is no unnecessary
expenditure of NRC resources attributable to anything in the LWA rule.
When the combined license supplemental EIS is prepared, that EIS will
be limited to considering new and significant information related to
matters concerning construction and operation of the facility which was
not addressed in the ESP EIS, unless the matter was discussed in the
LWA EIS. In that limited case, the nature and description of the LWA
construction impacts are deemed to be resolved, and these impacts would
be considered in the overall balancing and decisionmaking on issuance
of a combined license without the need to re-examine the nature and
description of those LWA impacts. Again, the final LWA rule avoids
redundant NRC review to the maximum extent practicable, inasmuch as the
combined license EIS relies upon the determinations regarding the
nature and impacts of construction and operation which were made at
both the ESP and LWA stages. The overall scope of the NRC environmental
review is not changed; it is merely the timing of the review for
individual issues that is affected by the final LWA rule.
In sum, the NRC does not agree with the commenter that the LWA rule
will, as the consequence of its provisions, result in an adverse impact
upon the amount and timing of expenditure of NRC resources that cannot
be managed in an effective manner. No change from the supplemental
proposed LWA rule was made in response to this comment.
Comment: One commenter states that it appears that this new process
will require major changes to NRC guidance documents such as RGs and
the environmental standard review plan. Almost everything related to
the impacts of construction will have to be completely rewritten. Can
this be done before the first applicant uses the new rule? (Kugler 8)
NRC Response: The NRC agrees with the commenter that changes to the
NRC RGs and the environmental standard review plan will be necessary to
provide complete guidance to potential applicants and the NRC review
staff with respect to implementation of the new LWA process in the
final LWA rule. However, the NRC does not agree with the commenter's
implicit assertion that the guidance must be finalized before the first
applicant (or several applicants) can use the new LWA process in an
effective manner. The NRC has, in many other instances, adopted rules
containing substantial changes to its technical and regulatory
requirements applicable to nuclear power reactors. Although the NRC
does not wish to understate the challenge of implementing new rules, it
is confident that the NRC working level technical staff, under careful
and timely oversight by NRC staff management, will be able to implement
the final LWA rule in a timely, consistent, and effective manner.
Comment: One commenter states that the supplemental proposed rule
does not appear to allow an applicant to use both a phased LWA process
and the hearing process for early partial decision on site suitability
issues, thereby allowing an applicant who wishes to apply for an LWA to
also submit the environmental information under Sec. 2.101(a)(5) and
proceed with an accelerated hearing on the full scope of environmental
matters. The Commission should adopt changes in Sec. Sec. 50.10(c)(2)
and 2.101(a)(5) to allow an applicant to use both processes
simultaneously. (NEI 5; Unistar 1)
NRC Response: The NRC believes that the commenter misunderstood the
provisions of the supplemental proposed rule. The NRC's intent is that:
Applicants may submit a two-part (phased) application for
an LWA in advance of the application for the underlying combined
license or construction permit, see Sec. 2.101(a)(9).
The environmental information submitted in the LWA portion
of the application may either be limited to the LWA activities
requested, or the full scope of construction and operation impacts, see
Sec. 51.49(b) and (f).
An LWA applicant may seek an early decision on siting and
environmental matters. If the LWA is submitted in advance of the
underlying construction permit or combined license application, the
procedures in 10 CFR part 2, subpart F, Sec. Sec. 2.641 through 2.649
apply. If the LWA is submitted as part of (or after) the construction
permit or
[[Page 57424]]
combined license application, then the procedures in subpart F,
Sec. Sec. 2.601 through 2.629 would apply because this is the ordinary
procedure for obtaining an early decision on siting and environmental
matters under the existing provisions of subpart F.
The NRC does not believe the specific language changes to the
proposed rule described by the commenter are necessary to accomplish
these three objectives. Accordingly, the Commission declines to adopt
the changes proposed by the commenter, and no change from the
supplemental proposed LWA rule was made in response to this comment.
Comment: One commenter proposed that the timing provisions in 10
CFR 2.101(a)(5), requiring that each part of a two-part combined
license application be submitted within 6 months of each other, should
be revised to be consistent with 10 CFR 2.101(a)(9) of the supplemental
proposed rule, which permits the LWA application to be submitted up to
12 months in advance of the underlying combined license or construction
permit. The commenter believes that additional conforming changes
should be made to implement this concept, including changes in Sec.
50.10(c)(2). (Unistar 2) Another commenter made the same proposal, but
separately suggested that the overall time between parts of
applications be lengthened to 18 months. (NEI 6)
NRC Response: The NRC agrees with the commenters that the timing
provisions should be consistent. Furthermore, the NRC agrees with the
second commenter (NEI) that the overall time between parts of
applications may be lengthened to 18 months. The 6 month limitation in
former Sec. 2.101(a)(5) for two-part applications was set many years
ago and reflected internal NRC administrative considerations, including
maximizing efficiency and ensuring continuity of review oversight. The
12-month limitation between submission of the LWA application and the
underlying combined license or construction permit application, as
proposed in the supplemental proposed LWA rule, was based upon the same
considerations, as well as environmental/NEPA considerations. The NRC
did not want the time between the initial submission of LWA
environmental information and the subsequent consideration of the
overall environmental impacts to be lengthened to the point that there
would be a substantial likelihood of new and significant information
that would require updating. A 12-month limitation was established as a
reasonable limitation. No consideration was given to having a
consistent limitation in both existing paragraph (a)(5) and proposed
paragraph (a)(9).
However, after further consideration based upon public comments,
the NRC concludes that the 6-month limitation in paragraph (a)(5) and
the proposed 12-month limitation in paragraph (a)(9) are unduly
restrictive. The NRC believes that administrative efficiency can be
maintained with longer time periods between parts of applications, in
view of modern information technology, NRC's restructuring of the
licensing process in part 52, the NRC's recent adoption of changes to
part 2, subpart D and part 52, appendix N, and the NRC's projected use
of design-centered reviews. In addition, the NRC understands, in
response to informal inquiries with EPA, that 18 months is well within
the time period considered by EPA to be acceptable for referencing a
previously-prepared EIS without updating. For these reasons, the
Commission is adopting an 18-month limitation in paragraphs (a)(5) and
(a)(9) of Sec. 2.101.
7. Other Topics
Comment: The NRC should include a ``grandfathering'' provision in
the final rule to make clear that the final rule does not require any
change to ESP applications filed before the effective date of the rule,
such as supplementing the application to require a showing of technical
qualifications. The NRC should also clarify that the final rule would
not reduce or limit the authority that such applicants would be
entitled to receive upon issuance of their ESPs under the current
regulations (e.g., perform construction of non-safety-related SSCs).
(NEI 4, Dominion 1)
NRC Response: The NRC agrees with the commenters that the final LWA
rule does not require any change to ESP applications filed before the
effective date of the rule. Upon further consideration, the NRC has