Chandler Wind Partners, LLC; Notice of Issuance of Order, 52092-52093 [E7-17965]
Download as PDF
52092
Federal Register / Vol. 72, No. 176 / Wednesday, September 12, 2007 / Notices
(Director’s Order). The Director’s Order
also stated that the Commission would
publish a separate notice in the Federal
Register establishing a period of time for
the filing of protests. Accordingly, any
person desiring to be heard concerning
the blanket approvals of issuances of
securities or assumptions of liability by
Camp Grove, should file a protest with
the Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington, DC 20426, in accordance
with Rules 211 and 214 of the
Commission’s Rules of Practice and
Procedure. 18 CFR 385.211, 385.214
(2004).
Notice is hereby given that the
deadline for filing protests is October 1,
2007.
Absent a request to be heard in
opposition to such blanket approvals by
the deadline above, Camp Grove is
authorized to issue securities and
assume obligations or liabilities as a
guarantor, indorser, surety, or otherwise
in respect of any security of another
person; provided that such issuance or
assumption is for some lawful object
within the corporate purposes of Camp
Grove, compatible with the public
interest, and is reasonably necessary or
appropriate for such purposes.
The Commission reserves the right to
require a further showing that neither
public nor private interests will be
adversely affected by continued
approvals of Camp Grove’s issuance of
securities or assumptions of liability.
Copies of the full text of the Director’s
Order are available from the
Commission’s Public Reference Room,
888 First Street, NE., Washington, DC
20426. The Order may also be viewed
on the Commission’s Web site at
https://www.ferc.gov, using the eLibrary
link. Enter the docket number excluding
the last three digits in the docket
number filed to access the document.
Comments, protests, and interventions
may be filed electronically via the
internet in lieu of paper. See, 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under the
‘‘e-Filing’’ link. The Commission
strongly encourages electronic filings.
jlentini on PROD1PC65 with NOTICES
Kimberly D. Bose,
Secretary.
[FR Doc. E7–17929 Filed 9–11–07; 8:45 am]
BILLING CODE 6717–01–P
VerDate Aug<31>2005
18:43 Sep 11, 2007
Jkt 211001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER07–1194–000]
Castlebridge Energy Group LLC;
Notice of Issuance of Order
September 6, 2007.
Castlebridge Energy Group LLC
(Castlebridge Energy) filed an
application for market-based rate
authority, with an accompanying rate
schedule. The proposed market-based
rate schedule provides for the sale of
energy and capacity at market-based
rates. Castlebridge Energy also requested
waivers of various Commission
regulations. In particular, Castlebridge
Energy requested that the Commission
grant blanket approval under 18 CFR
part 34 of all future issuances of
securities and assumptions of liability
by Castlebridge Energy.
On August 31, 2007, pursuant to
delegated authority, the Director,
Division of Tariffs and Market
Development-West, granted the requests
for blanket approval under part 34
(Director’s Order). The Director’s Order
also stated that the Commission would
publish a separate notice in the Federal
Register establishing a period of time for
the filing of protests. Accordingly, any
person desiring to be heard concerning
the blanket approvals of issuances of
securities or assumptions of liability by
Castlebridge Energy, should file a
protest with the Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426, in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure. 18 CFR 385.211, 385.214
(2004).
Notice is hereby given that the
deadline for filing protests is October 1,
2007.
Absent a request to be heard in
opposition to such blanket approvals by
the deadline above, Castlebridge Energy
is authorized to issue securities and
assume obligations or liabilities as a
guarantor, indorser, surety, or otherwise
in respect of any security of another
person; provided that such issuance or
assumption is for some lawful object
within the corporate purposes of
Castlebridge Energy, compatible with
the public interest, and is reasonably
necessary or appropriate for such
purposes.
The Commission reserves the right to
require a further showing that neither
public nor private interests will be
adversely affected by continued
approvals of Castlebridge Energy’s
PO 00000
Frm 00048
Fmt 4703
Sfmt 4703
issuance of securities or assumptions of
liability.
Copies of the full text of the Director’s
Order are available from the
Commission’s Public Reference Room,
888 First Street, NE., Washington, DC
20426. The Order may also be viewed
on the Commission’s Web site at
https://www.ferc.gov, using the eLibrary
link. Enter the docket number excluding
the last three digits in the docket
number filed to access the document.
Comments, protests, and interventions
may be filed electronically via the
Internet in lieu of paper. See, 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under the
‘‘e-Filing’’ link. The Commission
strongly encourages electronic filings.
Kimberly D. Bose,
Secretary.
[FR Doc. E7–17964 Filed 9–11–07; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER01–390–000]
Chandler Wind Partners, LLC; Notice
of Issuance of Order
September 6, 2007.
Chandler Wind Partners, LLC
(Chandler) filed an application for
market-based rate authority, with an
accompanying rate schedule. The
proposed market-based rate schedule
provides for the sale of energy and
capacity at market-based rates. Chandler
also requested waivers of various
Commission regulations. In particular,
Chandler requested that the
Commission grant blanket approval
under 18 CFR part 34 of all future
issuances of securities and assumptions
of liability by Chandler.
On December 7, 2000, pursuant to
delegated authority, the Director,
Division of Corporate Applications,
granted the requests for blanket
approval under part 34 (Director’s
Order). The Director’s Order also stated
that the Commission would publish a
separate notice in the Federal Register
establishing a period of time for the
filing of protests. Accordingly, any
person desiring to be heard concerning
the blanket approvals of issuances of
securities or assumptions of liability by
Chandler, should file a protest with the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426, in accordance with Rules 211
and 214 of the Commission’s Rules of
E:\FR\FM\12SEN1.SGM
12SEN1
Federal Register / Vol. 72, No. 176 / Wednesday, September 12, 2007 / Notices
Practice and Procedure. 18 CFR 385.211,
385.214 (2004).
Notice is hereby given that the
deadline for filing protests is September
20, 2007.
Absent a request to be heard in
opposition to such blanket approvals by
the deadline above, Chandler is
authorized to issue securities and
assume obligations or liabilities as a
guarantor, indorser, surety, or otherwise
in respect of any security of another
person; provided that such issuance or
assumption is for some lawful object
within the corporate purposes of
Chandler, compatible with the public
interest, and is reasonably necessary or
appropriate for such purposes.
The Commission reserves the right to
require a further showing that neither
public nor private interests will be
adversely affected by continued
approvals of Chandler’s issuance of
securities or assumptions of liability.
Copies of the full text of the Director’s
Order are available from the
Commission’s Public Reference Room,
888 First Street, NE., Washington, DC
20426. The Order may also be viewed
on the Commission’s Web site at
https://www.ferc.gov, using the eLibrary
link. Enter the docket number excluding
the last three digits in the docket
number filed to access the document.
Comments, protests, and interventions
may be filed electronically via the
Internet in lieu of paper. See, 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under the
‘‘e-Filing’’ link. The Commission
strongly encourages electronic filings.
Kimberly D. Bose,
Secretary.
[FR Doc. E7–17965 Filed 9–11–07; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. ER07–939–000; ER07–939–
001]
Columbia Utilities Power, LLC; Notice
of Issuance of Order
jlentini on PROD1PC65 with NOTICES
August 31, 2007.
Columbia Utilities Power, LLC
(Columbia Utilities) filed an application
for market-based rate authority, with an
accompanying rate schedule. The
proposed market-based rate schedule
provides for the sale of energy and
capacity at market-based rates.
Columbia Utilities also requested
waivers of various Commission
regulations. In particular, Columbia
VerDate Aug<31>2005
18:43 Sep 11, 2007
Jkt 211001
Utilities requested that the Commission
grant blanket approval under 18 CFR
part 34 of all future issuances of
securities and assumptions of liability
by Columbia Utilities.
On August 30, 2007, pursuant to
delegated authority, the Director,
Division of Tariffs and Market
Development-West, granted the requests
for blanket approval under part 34
(Director’s Order). The Director’s Order
also stated that the Commission would
publish a separate notice in the Federal
Register establishing a period of time for
the filing of protests. Accordingly, any
person desiring to be heard concerning
the blanket approvals of issuances of
securities or assumptions of liability by
Columbia Utilities, should file a protest
with the Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington, DC 20426, in accordance
with Rules 211 and 214 of the
Commission’s Rules of Practice and
Procedure. 18 CFR 385.211, 385.214
(2004).
Notice is hereby given that the
deadline for filing protests is October 1,
2007.
Absent a request to be heard in
opposition to such blanket approvals by
the deadline above, Columbia Utilities
is authorized to issue securities and
assume obligations or liabilities as a
guarantor, indorser, surety, or otherwise
in respect of any security of another
person; provided that such issuance or
assumption is for some lawful object
within the corporate purposes of
Columbia Utilities, compatible with the
public interest, and is reasonably
necessary or appropriate for such
purposes.
The Commission reserves the right to
require a further showing that neither
public nor private interests will be
adversely affected by continued
approvals of Columbia Utilities’
issuance of securities or assumptions of
liability.
Copies of the full text of the Director’s
Order are available from the
Commission’s Public Reference Room,
888 First Street, NE., Washington, DC
20426. The Order may also be viewed
on the Commission’s Web site at
https://www.ferc.gov, using the eLibrary
link. Enter the docket number excluding
the last three digits in the docket
number filed to access the document.
Comments, protests, and interventions
may be filed electronically via the
internet in lieu of paper. See, 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under the
PO 00000
Frm 00049
Fmt 4703
Sfmt 4703
52093
‘‘e-Filing’’ link. The Commission
strongly encourages electronic filings.
Kimberly D. Bose,
Secretary.
[FR Doc. E7–17927 Filed 9–11–07; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. EL07–83–000]
Electric Transmission Texas, LLC;
Notice of Compliance Filing
September 6, 2007.
Take notice that on September 4,
2007, Electric Transmission Texas, LLC,
tendered for filing a supplement to it
July 19, 2007 filing, to respond to
informal inquiries from the
Commission’s advisory staff concerning
the AEP Texas Central Company’s
Laredo interconnection with CFE.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. Anyone filing a motion
to intervene or protest must serve a copy
of that document on the Applicant and
all the parties in this proceeding.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
E:\FR\FM\12SEN1.SGM
12SEN1
Agencies
[Federal Register Volume 72, Number 176 (Wednesday, September 12, 2007)]
[Notices]
[Pages 52092-52093]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-17965]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. ER01-390-000]
Chandler Wind Partners, LLC; Notice of Issuance of Order
September 6, 2007.
Chandler Wind Partners, LLC (Chandler) filed an application for
market-based rate authority, with an accompanying rate schedule. The
proposed market-based rate schedule provides for the sale of energy and
capacity at market-based rates. Chandler also requested waivers of
various Commission regulations. In particular, Chandler requested that
the Commission grant blanket approval under 18 CFR part 34 of all
future issuances of securities and assumptions of liability by
Chandler.
On December 7, 2000, pursuant to delegated authority, the Director,
Division of Corporate Applications, granted the requests for blanket
approval under part 34 (Director's Order). The Director's Order also
stated that the Commission would publish a separate notice in the
Federal Register establishing a period of time for the filing of
protests. Accordingly, any person desiring to be heard concerning the
blanket approvals of issuances of securities or assumptions of
liability by Chandler, should file a protest with the Federal Energy
Regulatory Commission, 888 First Street, NE., Washington, DC 20426, in
accordance with Rules 211 and 214 of the Commission's Rules of
[[Page 52093]]
Practice and Procedure. 18 CFR 385.211, 385.214 (2004).
Notice is hereby given that the deadline for filing protests is
September 20, 2007.
Absent a request to be heard in opposition to such blanket
approvals by the deadline above, Chandler is authorized to issue
securities and assume obligations or liabilities as a guarantor,
indorser, surety, or otherwise in respect of any security of another
person; provided that such issuance or assumption is for some lawful
object within the corporate purposes of Chandler, compatible with the
public interest, and is reasonably necessary or appropriate for such
purposes.
The Commission reserves the right to require a further showing that
neither public nor private interests will be adversely affected by
continued approvals of Chandler's issuance of securities or assumptions
of liability.
Copies of the full text of the Director's Order are available from
the Commission's Public Reference Room, 888 First Street, NE.,
Washington, DC 20426. The Order may also be viewed on the Commission's
Web site at https://www.ferc.gov, using the eLibrary link. Enter the
docket number excluding the last three digits in the docket number
filed to access the document. Comments, protests, and interventions may
be filed electronically via the Internet in lieu of paper. See, 18 CFR
385.2001(a)(1)(iii) and the instructions on the Commission's Web site
under the ``e-Filing'' link. The Commission strongly encourages
electronic filings.
Kimberly D. Bose,
Secretary.
[FR Doc. E7-17965 Filed 9-11-07; 8:45 am]