Combined Notice of Filings # 1, 46988-46989 [E7-16536]
Download as PDF
46988
Federal Register / Vol. 72, No. 162 / Wednesday, August 22, 2007 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings # 1
jlentini on PROD1PC65 with NOTICES
August 16, 2007.
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC07–125–000.
Applicants: Calpine Acadia Holdings,
LLC; Acadia Power Partners, LLC; Cajun
Gas Energy, LLC.
Description: Acadia Power Partners,
LLC et al submits a Joint Application for
approval of Calpine Acadia Holdings,
LLC submit indirect transfer of its
existing interest in Acadia Power
Partners, LLC to Cajun Gas Energy, LLC.
Filed Date: 08/08/2007.
Accession Number: 20070814–0050.
Comment Date: 5 p.m. Eastern Time
on Wednesday, August 29, 2007.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER04–839–002.
Applicants: MAG Energy Solutions,
Inc.
Description: MAG Energy Solutions
Inc submits its Triennial Updated
Market Power Analysis and Revised
Market-Based Rate Tariff.
Filed Date: 08/14/2007.
Accession Number: 20070815–0177.
Comment Date: 5 p.m. Eastern Time
on Tuesday, September 04, 2007.
Docket Numbers: ER07–809–002.
Applicants: Florida Power
Corporation.
Description: Florida Power Corp d/b/
a Progress Energy Florida, Inc submits
corrections to its 8/2/07 response to
FERC’s 6/21/07 deficiency letter.
Filed Date: 08/14/2007.
Accession Number: 20070815–0157.
Comment Date: 5 p.m. Eastern Time
on Tuesday, September 04, 2007.
Docket Numbers: ER07–1161–001.
Applicants: Public Power & Utility,
Inc.
Description: Public Power & Utility,
Inc submits a petition for acceptance of
FERC Electric Tariff, Original Volume 1.
Filed Date: 08/08/2007.
Accession Number: 20070813–0075.
Comment Date: 5 p.m. Eastern Time
on Wednesday, August 29, 2007.
Docket Numbers: ER07–1180–001.
Applicants: California Independent
System Operator Corporation.
Description: California Independent
System Operator Corp submits an errata
to their 7/20/07 filing of a petition to
waive sanctions for violation of Section
31.1.4.1 of its Tariff through 10/18/06.
VerDate Aug<31>2005
16:26 Aug 21, 2007
Jkt 211001
Filed Date: 08/09/2007.
Accession Number: 20070813–0082.
Comment Date: 5 p.m. Eastern Time
on Thursday, August 30, 2007.
Docket Numbers: ER07–1207–001.
Applicants: Premier Energy Marketing
LLC.
Description: Application of Premier
Energy Marketing LLC for acceptance of
Initial Rate Schedule, Waiver and
Blanket Authority.
Filed Date: 08/14/2007.
Accession Number: 20070815–0176.
Comment Date: 5 p.m. Eastern Time
on Tuesday, September 04, 2007.
Docket Numbers: ER07–1234–001.
Applicants: Upper Peninsula Power
Company.
Description: Upper Peninsula Power
Company submits an executed letter
agreement with Escanaba Municipal
Electric Utility memorializing the
parties’ understanding concerning sale
to Escanaba of capacity on an
emergency basis.
Filed Date: 08/10/2007.
Accession Number: 20070813–0165.
Comment Date: 5 p.m. Eastern Time
on Friday, August 31, 2007.
Docket Numbers: ER07–1261–000.
Applicants: Midwest Stand-Alone
Transmission Company.
Description: Post Transaction Period
Compliance Filing and Superseding
Rate Design Proposal of the Midwest
Stand-Alone Transmission Companies
and Wolverine Power Supply Coop, Inc.
Filed Date: 08/01/2007.
Accession Number: 20070814–0150.
Comment Date: 5 p.m. Eastern Time
on Wednesday, August 22, 2007.
Docket Numbers: ER07–1281–000.
Applicants: CL Power Sales One, LLC.
Description: CL Power Sales One, LLC
submits Notice of Cancellation of its
FERC Electric Tariff, effective 10/13/07.
Filed Date: 08/14/2007.
Accession Number: 20070815–0030.
Comment Date: 5 p.m. Eastern Time
on Tuesday, September 04, 2007.
Docket Numbers: ER07–1282–000.
Applicants: ISO New England, Inc.
Description: ISO New England, Inc
submits Markets and Services Tariff,
FERC Electric Tariff 3, Second Quarter
of 2007, effective 7/1/07.
Filed Date: 08/14/2007.
Accession Number: 20070815–0029.
Comment Date: 5 p.m. Eastern Time
on Tuesday, September 04, 2007.
Docket Numbers: ER07–1283–000.
Applicants: ISO New England, Inc.
Description: ISO New England and
the New England Power Pool (NEPOOL)
Participants Committee submit revised
tariff sheets and supporting testimony of
Marc Montalvo reflecting proposed
revisions to Market Rule 1.
PO 00000
Frm 00037
Fmt 4703
Sfmt 4703
Filed Date: 08/14/2007.
Accession Number: 20070815–0028.
Comment Date: 5 p.m. Eastern Time
on Tuesday, September 04, 2007.
Docket Numbers: ER07–1284–000.
Applicants: ISO New England Inc. &
New England Power.
Description: ISO New England, Inc &
New England Power Pool Participants
Committee submits 2nd Revised Sheet
332 et al. and supporting affidavit of
Shannon L Hann reflecting proposed
revisions to Market Rule 1.
Filed Date: 08/14/2007.
Accession Number: 20070815–0156.
Comment Date: 5 p.m. Eastern Time
on Tuesday, September 04, 2007.
Docket Numbers: ER07–1285–000.
Applicants: Niagara Mohawk Power
Corporation.
Description: Niagara Mohawk Power
Corp, d/b/a National Grid submits an
interconnection agreement dated 10/31/
91 with American Ref-Fuel Company of
Niagara, LP.
Filed Date: 08/14/2007.
Accession Number: 20070815–0158.
Comment Date: 5 p.m. Eastern Time
on Tuesday, September 04, 2007.
Any person desiring to intervene or to
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s Rules of
Practice and Procedure (18 CFR 385.211
and 385.214) on or before 5 p.m. Eastern
time on the specified comment date. It
is not necessary to separately intervene
again in a subdocket related to a
compliance filing if you have previously
intervened in the same docket. Protests
will be considered by the Commission
in determining the appropriate action to
be taken, but will not serve to make
protestants parties to the proceeding.
Anyone filing a motion to intervene or
protest must serve a copy of that
document on the Applicant. In reference
to filings initiating a new proceeding,
interventions or protests submitted on
or before the comment deadline need
not be served on persons other than the
Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 14 copies
of the intervention or protest to the
E:\FR\FM\22AUN1.SGM
22AUN1
Federal Register / Vol. 72, No. 162 / Wednesday, August 22, 2007 / Notices
Federal Energy Regulatory Commission,
888 First St., NE., Washington, DC
20426.
The filings in the above proceedings
are accessible in the Commission’s
eLibrary system by clicking on the
appropriate link in the above list. They
are also available for review in the
Commission’s Public Reference Room in
Washington, DC. There is an
eSubscription link on the Web site that
enables subscribers to receive e-mail
notification when a document is added
to a subscribed docket(s). For assistance
with any FERC Online service, please email FERCOnlineSupport@ferc.gov, or
call (866) 208–3676 (toll free). For TTY,
call (202) 502–8659.
construction of any facilities at this
time. Any future proposal to construct
jurisdictional facilities at the
Cunningham Storage Field would be
subject to an appropriate environmental
review by the Commission.
A fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility on My Land? What Do I Need
To Know?’’ was attached to the project
notice that Northern provided to
landowners. This fact sheet addresses a
number of typically asked questions,
including the use of eminent domain
and how to participate in the
Commission’s proceedings. It is
available for viewing on the FERC
Internet Web site (https://www.ferc.gov).
Nathaniel J. Davis, Sr.,
Acting Deputy Secretary.
[FR Doc. E7–16536 Filed 8–21–07; 8:45 am]
Summary of the Proposed Project
Northern is proposing to extend its
existing Cunningham Gas Storage Field
by 4,800 acres in order to protect the
integrity of the storage field. Northern
believes that third party operators
outside of the storage field boundaries
are producing storage gas. The location
of the proposed storage field extension
is shown in Appendix 1.2
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP07–107–000]
Northern Natural Gas Company; Notice
of Intent To Prepare an Environmental
Assessment for the Proposed
Cunningham Storage Boundary
Extension Project and Request for
Comments on Environmental Issues
jlentini on PROD1PC65 with NOTICES
August 15, 2007.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Cunningham Storage Boundary
Extension Project involving Northern
Natural Gas Company’s (Northern)
extension of the certificated boundary of
the Cunningham Gas Storage Field in
Pratt and Kingman Counties, Kansas.1
This EA will be used by the
Commission in its decision-making
process to determine whether the
project is in the public convenience and
necessity.
If you are a landowner receiving this
notice, you may be contacted by a gas
storage company representative about
the acquisition of natural gas storage
rights beneath your property. The gas
storage company would seek to
negotiate a mutually acceptable
agreement for the rights to operate a
natural gas storage field beneath your
property. It should be noted that the
current proposal does not involve the
1 Northern’s
application was filed with the
Commission under Section 7 of the Natural Gas Act.
VerDate Aug<31>2005
16:26 Aug 21, 2007
Jkt 211001
Land Requirements
No facilities would be constructed.
Northern’s proposal is for extension of
the certificated Cunningham Storage
Field boundary by an additional 4,800
acres. This area is located due north and
adjacent to the northern boundary of the
storage field.
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us to
discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping’’. The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
Notice of Intent, the Commission staff
requests public comments on the scope
of the issues to address in the EA. All
comments received are considered
during the preparation of the EA. State
and local government representatives
are encouraged to notify their
2 The appendices referenced in this notice are not
being printed in the Federal Register. Copies of all
appendices, other than Appendix 1 (map), are
available on the Commission’s Web site at the
‘‘eLibrary’’ link or from the Commission’s Public
Reference Room, 888 First Street, NE., Washington,
DC 20426, or call (202) 502–8371. For instructions
on connecting to eLibrary refer to the last page of
this notice. Copies of the appendices were sent to
all those receiving this notice in the mail.
PO 00000
Frm 00038
Fmt 4703
Sfmt 4703
46989
constituents of this proposed action and
encourage them to comment on their
areas of concern.
In the EA we 3 will discuss impacts
that could occur as a result of the
storage field extension. We will also
evaluate possible alternatives to the
proposed project or portions of the
project, and make recommendations on
how to lessen or avoid impacts on the
various resource areas.
Our independent analysis of the
issues will be in the EA. Depending on
the comments received during the
scoping process, the EA may be
published and mailed to federal, state,
and local agencies, public interest
groups, interested individuals, affected
landowners, newspapers, libraries, and
the Commission’s official service list for
this proceeding. A comment period will
be allotted for review if the EA is
published. We will consider all
comments on the EA before we make
our recommendations to the
Commission.
To ensure your comments are
considered, please carefully follow the
instructions in the public participation
section below.
Public Participation
You can make a difference by
providing us with your specific
comments or concerns about the project.
By becoming a commentor, your
concerns will be addressed in the EA
and considered by the Commission. You
should focus on the potential
environmental effects of the proposal,
alternatives to the proposal, and
measures to avoid or lessen
environmental impact. The more
specific your comments, the more useful
they will be. Please carefully follow
these instructions to ensure that your
comments are received in time and
properly recorded:
• Send an original and two copies of
your letter to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First St., NE., Room
1A, Washington, DC 20426.
• Label one copy of the comments for
the attention of Gas Branch 3.
• Reference Docket No. CP07–107–
000.
• Mail your comments so that they
will be received in Washington, DC on
or before September 17, 2007.
The Commission strongly encourages
electronic filing of any comments or
interventions or protests to this
proceeding. See 18 CFR
385.2001(a)(1)(iii) and the instructions
3 ‘‘We’’, ‘‘us’’, and ‘‘our’’ refer to the
environmental staff of the Office of Energy Projects
(OEP).
E:\FR\FM\22AUN1.SGM
22AUN1
Agencies
[Federal Register Volume 72, Number 162 (Wednesday, August 22, 2007)]
[Notices]
[Pages 46988-46989]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-16536]
[[Page 46988]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings 1
August 16, 2007.
Take notice that the Commission received the following electric
corporate filings:
Docket Numbers: EC07-125-000.
Applicants: Calpine Acadia Holdings, LLC; Acadia Power Partners,
LLC; Cajun Gas Energy, LLC.
Description: Acadia Power Partners, LLC et al submits a Joint
Application for approval of Calpine Acadia Holdings, LLC submit
indirect transfer of its existing interest in Acadia Power Partners,
LLC to Cajun Gas Energy, LLC.
Filed Date: 08/08/2007.
Accession Number: 20070814-0050.
Comment Date: 5 p.m. Eastern Time on Wednesday, August 29, 2007.
Take notice that the Commission received the following electric
rate filings:
Docket Numbers: ER04-839-002.
Applicants: MAG Energy Solutions, Inc.
Description: MAG Energy Solutions Inc submits its Triennial Updated
Market Power Analysis and Revised Market-Based Rate Tariff.
Filed Date: 08/14/2007.
Accession Number: 20070815-0177.
Comment Date: 5 p.m. Eastern Time on Tuesday, September 04, 2007.
Docket Numbers: ER07-809-002.
Applicants: Florida Power Corporation.
Description: Florida Power Corp d/b/a Progress Energy Florida, Inc
submits corrections to its 8/2/07 response to FERC's 6/21/07 deficiency
letter.
Filed Date: 08/14/2007.
Accession Number: 20070815-0157.
Comment Date: 5 p.m. Eastern Time on Tuesday, September 04, 2007.
Docket Numbers: ER07-1161-001.
Applicants: Public Power & Utility, Inc.
Description: Public Power & Utility, Inc submits a petition for
acceptance of FERC Electric Tariff, Original Volume 1.
Filed Date: 08/08/2007.
Accession Number: 20070813-0075.
Comment Date: 5 p.m. Eastern Time on Wednesday, August 29, 2007.
Docket Numbers: ER07-1180-001.
Applicants: California Independent System Operator Corporation.
Description: California Independent System Operator Corp submits an
errata to their 7/20/07 filing of a petition to waive sanctions for
violation of Section 31.1.4.1 of its Tariff through 10/18/06.
Filed Date: 08/09/2007.
Accession Number: 20070813-0082.
Comment Date: 5 p.m. Eastern Time on Thursday, August 30, 2007.
Docket Numbers: ER07-1207-001.
Applicants: Premier Energy Marketing LLC.
Description: Application of Premier Energy Marketing LLC for
acceptance of Initial Rate Schedule, Waiver and Blanket Authority.
Filed Date: 08/14/2007.
Accession Number: 20070815-0176.
Comment Date: 5 p.m. Eastern Time on Tuesday, September 04, 2007.
Docket Numbers: ER07-1234-001.
Applicants: Upper Peninsula Power Company.
Description: Upper Peninsula Power Company submits an executed
letter agreement with Escanaba Municipal Electric Utility memorializing
the parties' understanding concerning sale to Escanaba of capacity on
an emergency basis.
Filed Date: 08/10/2007.
Accession Number: 20070813-0165.
Comment Date: 5 p.m. Eastern Time on Friday, August 31, 2007.
Docket Numbers: ER07-1261-000.
Applicants: Midwest Stand-Alone Transmission Company.
Description: Post Transaction Period Compliance Filing and
Superseding Rate Design Proposal of the Midwest Stand-Alone
Transmission Companies and Wolverine Power Supply Coop, Inc.
Filed Date: 08/01/2007.
Accession Number: 20070814-0150.
Comment Date: 5 p.m. Eastern Time on Wednesday, August 22, 2007.
Docket Numbers: ER07-1281-000.
Applicants: CL Power Sales One, LLC.
Description: CL Power Sales One, LLC submits Notice of Cancellation
of its FERC Electric Tariff, effective 10/13/07.
Filed Date: 08/14/2007.
Accession Number: 20070815-0030.
Comment Date: 5 p.m. Eastern Time on Tuesday, September 04, 2007.
Docket Numbers: ER07-1282-000.
Applicants: ISO New England, Inc.
Description: ISO New England, Inc submits Markets and Services
Tariff, FERC Electric Tariff 3, Second Quarter of 2007, effective 7/1/
07.
Filed Date: 08/14/2007.
Accession Number: 20070815-0029.
Comment Date: 5 p.m. Eastern Time on Tuesday, September 04, 2007.
Docket Numbers: ER07-1283-000.
Applicants: ISO New England, Inc.
Description: ISO New England and the New England Power Pool
(NEPOOL) Participants Committee submit revised tariff sheets and
supporting testimony of Marc Montalvo reflecting proposed revisions to
Market Rule 1.
Filed Date: 08/14/2007.
Accession Number: 20070815-0028.
Comment Date: 5 p.m. Eastern Time on Tuesday, September 04, 2007.
Docket Numbers: ER07-1284-000.
Applicants: ISO New England Inc. & New England Power.
Description: ISO New England, Inc & New England Power Pool
Participants Committee submits 2nd Revised Sheet 332 et al. and
supporting affidavit of Shannon L Hann reflecting proposed revisions to
Market Rule 1.
Filed Date: 08/14/2007.
Accession Number: 20070815-0156.
Comment Date: 5 p.m. Eastern Time on Tuesday, September 04, 2007.
Docket Numbers: ER07-1285-000.
Applicants: Niagara Mohawk Power Corporation.
Description: Niagara Mohawk Power Corp, d/b/a National Grid submits
an interconnection agreement dated 10/31/91 with American Ref-Fuel
Company of Niagara, LP.
Filed Date: 08/14/2007.
Accession Number: 20070815-0158.
Comment Date: 5 p.m. Eastern Time on Tuesday, September 04, 2007.
Any person desiring to intervene or to protest in any of the above
proceedings must file in accordance with Rules 211 and 214 of the
Commission's Rules of Practice and Procedure (18 CFR 385.211 and
385.214) on or before 5 p.m. Eastern time on the specified comment
date. It is not necessary to separately intervene again in a subdocket
related to a compliance filing if you have previously intervened in the
same docket. Protests will be considered by the Commission in
determining the appropriate action to be taken, but will not serve to
make protestants parties to the proceeding. Anyone filing a motion to
intervene or protest must serve a copy of that document on the
Applicant. In reference to filings initiating a new proceeding,
interventions or protests submitted on or before the comment deadline
need not be served on persons other than the Applicant.
The Commission encourages electronic submission of protests and
interventions in lieu of paper, using the FERC Online links at https://
www.ferc.gov. To facilitate electronic service, persons with Internet
access who will eFile a document and/or be listed as a contact for an
intervenor must create and validate an eRegistration account using the
eRegistration link. Select the eFiling link to log on and submit the
intervention or protests.
Persons unable to file electronically should submit an original and
14 copies of the intervention or protest to the
[[Page 46989]]
Federal Energy Regulatory Commission, 888 First St., NE., Washington,
DC 20426.
The filings in the above proceedings are accessible in the
Commission's eLibrary system by clicking on the appropriate link in the
above list. They are also available for review in the Commission's
Public Reference Room in Washington, DC. There is an eSubscription link
on the Web site that enables subscribers to receive e-mail notification
when a document is added to a subscribed docket(s). For assistance with
any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or
call (866) 208-3676 (toll free). For TTY, call (202) 502-8659.
Nathaniel J. Davis, Sr.,
Acting Deputy Secretary.
[FR Doc. E7-16536 Filed 8-21-07; 8:45 am]
BILLING CODE 6717-01-P