Colorado Interstate Gas Company; Notice of Availability of the Draft Environmental Impact Statement and Public Comment Meeting for the Proposed High Plains Expansion Project, 46455-46456 [E7-16246]
Download as PDF
Federal Register / Vol. 72, No. 160 / Monday, August 20, 2007 / Notices
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries and direct links to
these documents. To learn more about
eSubscription and to sign-up for this
service please go to https://www.ferc.gov/
esubscribenow.htm.
Kimberly D. Bose,
Secretary .
[FR Doc. E7–16252 Filed 8–17–07; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP07–207–000]
Colorado Interstate Gas Company;
Notice of Availability of the Draft
Environmental Impact Statement and
Public Comment Meeting for the
Proposed High Plains Expansion
Project
pwalker on PROD1PC71 with NOTICES
August 10, 2007.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) has prepared this Draft
Environmental Impact Statement (EIS)
for the natural gas pipeline facilities
proposed by Colorado Interstate Gas
Company’s (CIG) under the abovereferenced docket. CIG’s High Plains
Expansion Project (Project) would be
located in Weld, Morgan, and Adams
Counties, Colorado.
The Draft EIS was prepared to satisfy
the requirements of the National
Environmental Policy Act. The FERC
staff concludes that the proposed
Project, with the appropriate mitigation
measures as recommended, would have
limited adverse environmental impact.
The purpose of the Project is to
expand CIG’s existing pipeline system
along Colorado’s Front Range in order to
provide additional transportation
services to this rapidly growing market.
CIG is proposing to construct about
163.7 miles of 24-inch and 30-inchdiameter pipeline in four separate
pipeline segments and associated
ancillary facilities.
The Draft EIS addresses the potential
environmental impacts resulting from
the construction and operation of the
following facilities:
• Line 250A: 64.5 miles of 30-inchdiameter pipeline and 20.3 miles of 24inch-diameter pipeline that would
VerDate Aug<31>2005
16:53 Aug 17, 2007
Jkt 211001
extend from CIG’s existing Cheyenne
Compressor Station to an interconnect
point on the proposed Line 251A in
northeast Adams County;
• Line 251A: 57.9 miles of 24-inchdiameter pipeline between CIG’s
existing Watkins and Fort Morgan
Compressor Stations;
• Line 252A: 14.9 miles of 30-inchdiameter pipeline extending westward
from a point on the proposed Line 250A
about one mile north of the existing
Hudson Power Plant in the Town of
Hudson, Colorado, to a new
interconnect with Public Service
Company of Colorado’s existing TriTown facilities in Weld County,
Colorado;
• Line 253A: 6.1 miles of 24-inchdiameter pipeline extending westward
from the Watkins Compressor Station to
CIG’s existing East Denver measurement
facility in Adams County, Colorado;
• Ten new meter stations and 19 new
block valves; and
• Twelve pig launcher/receivers.
The entire project would be capable of
transporting about 899,000 decatherms
of gas per day. CIG proposes to begin
construction in January 2008. It would
put each pipeline segment into service
as it is completed, and the entire Project
would be in service by October 2008.
Any person wishing to comment on
the Draft EIS may do so. To ensure that
your comments are timely and properly
recorded so that they may be considered
in the Final EIS, please carefully follow
these instructions:
• Send an original and two copies of
your letter to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE.,
Room 1A, Washington, DC 20426.
• Label one copy of your comments to
the attention of Gas Branch 2, DG2E;
• Reference Docket No. CP07–207–
000 on the original and both copies; and
• Mail your comments so that they
will be received in Washington, DC, on
or before October 1, 2007.
Please note that the Commission
strongly encourages electronic filing of
any comments to this proceeding.
Instructions on ‘‘eFiling’’ comments can
be found on the Commission’s Web site
at https://www.ferc.gov under the
‘‘Documents and Filings’’ link and the
link to the User’s Guide. Before you can
file comments, you will need to open a
free account which can be created online.
In lieu of or in addition to sending
written comments, we invite you to
attend a public comment meetings the
FERC will conduct in the Project area to
receive comments on the Draft EIS.
FERC staff will be in attendance. The
meeting is scheduled for 6:30 pm (MST)
PO 00000
Frm 00019
Fmt 4703
Sfmt 4703
46455
on August 28, 2007, at the following
location: Best Western Hotel, 701 8th
Street, Greeley, CO 80631, (970) 353–
8444.
The public comment meetings will be
posted on the FERC’s calendar located
at https://www.ferc.gov/EventCalendar/
EventsList.aspx. Interested groups and
individuals are encouraged to attend
and present oral comments on the Draft
EIS. Transcripts of the meetings will be
prepared. This notice is being mailed to
parties who are on the mail list for the
Draft EIS.
After the comments received are
reviewed, any significant new issues are
investigated, and modifications are
made to the Draft EIS, a Final EIS will
be published and distributed by the
FERC staff. The Final EIS will contain
the staff’s responses to timely comments
received on the Draft EIS.
Comments will be considered by the
Commission but will not serve to make
the commentor a party to the
proceeding. Any person seeking to
become a party to the proceeding must
file a motion to intervene pursuant to
Rule 214 of the Commission’s Rules of
Practice and Procedures (18 CFR
385.214). Anyone may intervene in this
proceeding based on this Draft EIS. You
must file your request to intervene as
specified above.1 You do not need
intervenor status to have your
comments considered.
The Draft EIS has been placed in the
public files of the FERC and is available
for public inspection at: Federal Energy
Regulatory Commission, Public
Reference Room, 888 First Street, NE.,
Room 2A, Washington, DC 20426, (202)
502–8371.
A limited number of copies of the
Draft EIS are available from the Public
Reference Room identified above. In
addition, CD copies of the Draft EIS
have been mailed to affected
landowners; various federal, state, and
local government agencies; elected
officials; environmental and public
interest groups; Native American tribes;
local libraries and newspapers;
intervenors; and other individuals that
expressed an interest in the proposed
Project. Hard-copies of the Draft EIS
have also been mailed to those who
requested that format during the scoping
and comment periods for the proposed
Project.
Additional information about the
proposed Project is available from the
Commission’s Office of External Affairs,
at 1–866–208-FERC or on the FERC
Internet Web site (https://www.ferc.gov).
1 Interventions may also be filed electronically via
the Internet in lieu of paper. See the previous
discussion on filing comments electronically.
E:\FR\FM\20AUN1.SGM
20AUN1
46456
Federal Register / Vol. 72, No. 160 / Monday, August 20, 2007 / Notices
To access information via the FERC
website click on the ‘‘eLibrary’’ link
then click on ‘‘General Search’’ and
enter the docket number excluding the
last three digits in the Docket Number
field. Be sure you have selected an
appropriate date range. The ‘‘eLibrary’’
link provides access to the texts of
formal documents issued by the
Commission, such as orders, notices,
and rulemakings. For assistance with
‘‘eLibrary’’, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or toll free at 1–866–208–3676, or for
TTY, contact (202)502–8659.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries and direct links to
these documents. To learn more about
eSubscription and to sign-up for this
service please go to https://www.ferc.gov/
esubscribenow.htm.
Kimberly D. Bose,
Secretary.
[FR Doc. E7–16246 Filed 8–17–07; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. CP07–44–000; CP07–45–000]
Southeast Supply Header, LLC; Notice
of Availability of the Final
Environmental Impact Statement for
the Proposed Southeast Supply
Header Project
pwalker on PROD1PC71 with NOTICES
August 10, 2007.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) has prepared this Final
Environmental Impact Statement (EIS)
for the natural gas pipeline facilities
proposed by Southeast Supply Header,
LLC (SESH) under the above-referenced
dockets. SESH’s Southeast Supply
Header Project (Project) would be
located in various counties and parishes
in Louisiana, Mississippi, and Alabama.
The Final EIS was prepared to satisfy
the requirements of the National
Environmental Policy Act. The FERC
staff concludes that the proposed
Project, with the appropriate mitigation
measures as recommended, would have
limited adverse environmental impact.
The U.S. Fish and Wildlife Service
(FWS), National Park Service (NPS),
U.S. Environmental Protection Agency
VerDate Aug<31>2005
16:53 Aug 17, 2007
Jkt 211001
(EPA), the U.S. Army Corps of Engineers
(COE), and the Natural Resource
Conservation Service (NRCS) are federal
cooperating agencies for the
development of this EIS. A federal
cooperating agency has jurisdiction by
law or special expertise with respect to
any environmental impact involved
with the proposal and is involved in the
NEPA analysis.
The purpose of the Project is to
provide new transportation capacity
that significantly enhances access to
reliable, onshore gas supplies to serve
growing demand in the Southeast. To
provide this service, SESH proposes to
construct and operate approximately
270 miles of natural gas pipeline and
associated ancillary facilities capable of
transporting up to approximately 1.14
billion cubic feet per day of natural gas.
The Final EIS addresses the potential
environmental impacts resulting from
the construction and operation of the
following facilities:
• Approximately 104 miles of 42inch-diameter natural gas pipeline
extending southeasterly from Richland
Parish, Louisiana to Lawrence County,
Mississippi;
• Approximately 165 miles of 36inch-diameter natural gas pipeline
extending southeasterly from Lawrence
County, Mississippi to Mobile County,
Alabama;
• Approximately 1.7 miles of 6-,
16-, 20-, 24- and 42-inch-diameter
laterals in Jefferson Davis, Covington,
and Forrest counties, Mississippi and
Mobile County, Alabama;
• Three new compressor stations, the
Delhi, Gwinville, and the Lucedale
Compressor Stations, located in
Richland Parish, Louisiana, and
Jefferson Davis and George counties,
Mississippi, respectively;
• Two natural gas booster stations,
the Collins Booster Station and Petal
Booster Station in Covington and
Forrest counties, Mississippi,
respectively; and
• Other ancillary facilities including
13 meter and regulator facilities, 18
mainline valves, 2 tap valves, and 3 pig
launcher and/or receiver facilities.
Dependent upon Commission
approval, SESH proposes to commence
construction of the proposed Project in
November 2007.
The Final EIS has been placed in the
public files of the FERC and is available
for public inspection at: Federal Energy
Regulatory Commission, Public
Reference Room, 888 First Street NE.,
Room 2–A, Washington, DC 20426,
(202) 502–8371.
A limited number of copies of the
Final EIS are available from the Public
Reference Room identified above. In
PO 00000
Frm 00020
Fmt 4703
Sfmt 4703
addition, CD copies of the Final EIS
have been mailed to affected
landowners; various federal, state, and
local government agencies; elected
officials; environmental and public
interest groups; Native American tribes;
local libraries and newspapers;
intervenors; and other individuals that
expressed an interest in the proposed
Project. Hard copies of the Final EIS
have been mailed to those who
requested that format during the scoping
and comment periods for the proposed
Project.
In accordance with the Council on
Environmental Quality’s (CEQ)
regulations implementing NEPA, no
agency decision on a proposed action
may be made until 30 days after the U.S.
Environmental Protection Agency (EPA)
publishes a notice of availability of a
Final EIS. However, the CEQ regulations
provide an exception to this rule when
an agency decision is subject to a formal
internal process that allows other
agencies or the public to make their
views known. In such cases, the agency
decision may be made at the same time
the notice of the Final EIS is published,
allowing both periods to run
concurrently. Should the FERC issue
SESH authorizations for the proposed
Project, it would be subject to a 30-day
rehearing period. Therefore, the
Commission could issue its decision
concurrently with the EPA’s notice of
availability.
Additional information about the
proposed Project is available from the
Commission’s Office of External Affairs,
at 1–866–208–FERC or on the FERC
Internet Web site (https://www.ferc.gov).
To access information via the FERC Web
site click on the ‘‘eLibrary’’ link then
click on ‘‘General Search’’ and enter the
docket number (i.e., CP07–44) excluding
the last three digits in the Docket
Number field. Be sure you have selected
an appropriate date range. The
‘‘eLibrary’’ link provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rulemakings. For assistance with
‘‘eLibrary,’’ please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or toll free at 1–866–208–3676, or for
TTY, contact (202) 502–8659.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries and direct links to
these documents. To learn more about
eSubscription and to sign up for this
E:\FR\FM\20AUN1.SGM
20AUN1
Agencies
[Federal Register Volume 72, Number 160 (Monday, August 20, 2007)]
[Notices]
[Pages 46455-46456]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-16246]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP07-207-000]
Colorado Interstate Gas Company; Notice of Availability of the
Draft Environmental Impact Statement and Public Comment Meeting for the
Proposed High Plains Expansion Project
August 10, 2007.
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) has prepared this Draft Environmental Impact Statement
(EIS) for the natural gas pipeline facilities proposed by Colorado
Interstate Gas Company's (CIG) under the above-referenced docket. CIG's
High Plains Expansion Project (Project) would be located in Weld,
Morgan, and Adams Counties, Colorado.
The Draft EIS was prepared to satisfy the requirements of the
National Environmental Policy Act. The FERC staff concludes that the
proposed Project, with the appropriate mitigation measures as
recommended, would have limited adverse environmental impact.
The purpose of the Project is to expand CIG's existing pipeline
system along Colorado's Front Range in order to provide additional
transportation services to this rapidly growing market. CIG is
proposing to construct about 163.7 miles of 24-inch and 30-inch-
diameter pipeline in four separate pipeline segments and associated
ancillary facilities.
The Draft EIS addresses the potential environmental impacts
resulting from the construction and operation of the following
facilities:
Line 250A: 64.5 miles of 30-inch-diameter pipeline and
20.3 miles of 24-inch-diameter pipeline that would extend from CIG's
existing Cheyenne Compressor Station to an interconnect point on the
proposed Line 251A in northeast Adams County;
Line 251A: 57.9 miles of 24-inch-diameter pipeline between
CIG's existing Watkins and Fort Morgan Compressor Stations;
Line 252A: 14.9 miles of 30-inch-diameter pipeline
extending westward from a point on the proposed Line 250A about one
mile north of the existing Hudson Power Plant in the Town of Hudson,
Colorado, to a new interconnect with Public Service Company of
Colorado's existing Tri-Town facilities in Weld County, Colorado;
Line 253A: 6.1 miles of 24-inch-diameter pipeline
extending westward from the Watkins Compressor Station to CIG's
existing East Denver measurement facility in Adams County, Colorado;
Ten new meter stations and 19 new block valves; and
Twelve pig launcher/receivers.
The entire project would be capable of transporting about 899,000
decatherms of gas per day. CIG proposes to begin construction in
January 2008. It would put each pipeline segment into service as it is
completed, and the entire Project would be in service by October 2008.
Any person wishing to comment on the Draft EIS may do so. To ensure
that your comments are timely and properly recorded so that they may be
considered in the Final EIS, please carefully follow these
instructions:
Send an original and two copies of your letter to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Room 1A, Washington, DC 20426.
Label one copy of your comments to the attention of Gas
Branch 2, DG2E;
Reference Docket No. CP07-207-000 on the original and both
copies; and
Mail your comments so that they will be received in
Washington, DC, on or before October 1, 2007.
Please note that the Commission strongly encourages electronic
filing of any comments to this proceeding. Instructions on ``eFiling''
comments can be found on the Commission's Web site at https://
www.ferc.gov under the ``Documents and Filings'' link and the link to
the User's Guide. Before you can file comments, you will need to open a
free account which can be created on-line.
In lieu of or in addition to sending written comments, we invite
you to attend a public comment meetings the FERC will conduct in the
Project area to receive comments on the Draft EIS. FERC staff will be
in attendance. The meeting is scheduled for 6:30 pm (MST) on August 28,
2007, at the following location: Best Western Hotel, 701 8th Street,
Greeley, CO 80631, (970) 353-8444.
The public comment meetings will be posted on the FERC's calendar
located at https://www.ferc.gov/EventCalendar/EventsList.aspx.
Interested groups and individuals are encouraged to attend and present
oral comments on the Draft EIS. Transcripts of the meetings will be
prepared. This notice is being mailed to parties who are on the mail
list for the Draft EIS.
After the comments received are reviewed, any significant new
issues are investigated, and modifications are made to the Draft EIS, a
Final EIS will be published and distributed by the FERC staff. The
Final EIS will contain the staff's responses to timely comments
received on the Draft EIS.
Comments will be considered by the Commission but will not serve to
make the commentor a party to the proceeding. Any person seeking to
become a party to the proceeding must file a motion to intervene
pursuant to Rule 214 of the Commission's Rules of Practice and
Procedures (18 CFR 385.214). Anyone may intervene in this proceeding
based on this Draft EIS. You must file your request to intervene as
specified above.\1\ You do not need intervenor status to have your
comments considered.
---------------------------------------------------------------------------
\1\ Interventions may also be filed electronically via the
Internet in lieu of paper. See the previous discussion on filing
comments electronically.
---------------------------------------------------------------------------
The Draft EIS has been placed in the public files of the FERC and
is available for public inspection at: Federal Energy Regulatory
Commission, Public Reference Room, 888 First Street, NE., Room 2A,
Washington, DC 20426, (202) 502-8371.
A limited number of copies of the Draft EIS are available from the
Public Reference Room identified above. In addition, CD copies of the
Draft EIS have been mailed to affected landowners; various federal,
state, and local government agencies; elected officials; environmental
and public interest groups; Native American tribes; local libraries and
newspapers; intervenors; and other individuals that expressed an
interest in the proposed Project. Hard-copies of the Draft EIS have
also been mailed to those who requested that format during the scoping
and comment periods for the proposed Project.
Additional information about the proposed Project is available from
the Commission's Office of External Affairs, at 1-866-208-FERC or on
the FERC Internet Web site (https://www.ferc.gov).
[[Page 46456]]
To access information via the FERC website click on the
``eLibrary'' link then click on ``General Search'' and enter the docket
number excluding the last three digits in the Docket Number field. Be
sure you have selected an appropriate date range. The ``eLibrary'' link
provides access to the texts of formal documents issued by the
Commission, such as orders, notices, and rulemakings. For assistance
with ``eLibrary'', please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at 1-866-208-3676, or for TTY,
contact (202)502-8659.
In addition, the Commission now offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries and direct links to
these documents. To learn more about eSubscription and to sign-up for
this service please go to https://www.ferc.gov/esubscribenow.htm.
Kimberly D. Bose,
Secretary.
[FR Doc. E7-16246 Filed 8-17-07; 8:45 am]
BILLING CODE 6717-01-P