Texas Eastern Transmission, LP; Notice of Intent To Prepare an Environmental Assessment for the Proposed Cedar Bayou Lateral Project and Request for Comments on Environmental Issues, 46457-46458 [E7-16236]
Download as PDF
Federal Register / Vol. 72, No. 160 / Monday, August 20, 2007 / Notices
service, please go to https://
www.ferc.gov/esubscribenow.htm.
Kimberly D. Bose,
Secretary.
[FR Doc. E7–16247 Filed 8–17–07; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP07–411–000]
Texas Eastern Transmission, LP;
Notice of Intent To Prepare an
Environmental Assessment for the
Proposed Cedar Bayou Lateral Project
and Request for Comments on
Environmental Issues
pwalker on PROD1PC71 with NOTICES
August 13, 2007.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Cedar Bayou Lateral Project
involving construction and operation of
natural gas pipeline facilities by Texas
Eastern Transmission, LP (Texas
Eastern) in Chambers County, Texas.
The EA will be used by the Commission
in its decision-making process to
determine whether the project is in the
public convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the project.
Your input will help determine which
issues need to be evaluated in the EA.
Please note that the scoping period will
close on September 14, 2007. Details on
how to submit comments are provided
in the Public Participation section of
this notice.
If you are a landowner receiving this
notice, you may be contacted by a
pipeline company representative about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. Texas Eastern would
seek to negotiate a mutually acceptable
agreement. However, if the project is
approved by the Commission, that
approval conveys with it the right of
eminent domain. Therefore, if easement
negotiations fail to produce an
agreement, Texas Eastern could initiate
condemnation proceedings in
accordance with Texas state law.
This notice is being sent to affected
landowners; federal, state, and local
government agencies; elected officials;
Native American tribes; other interested
parties; and local libraries and
newspapers. State and local government
VerDate Aug<31>2005
16:53 Aug 17, 2007
Jkt 211001
representatives are asked to notify their
constituents of this proposed project
and to encourage them to comment on
their areas of concern.
A fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ addresses a number of
typically asked questions, including the
use of eminent domain and how to
participate in the Commission’s
proceedings. It is available for viewing
on the FERC Internet Web site (https://
www.ferc.gov).
Summary of the Proposed Project
Texas Eastern proposes to construct
about 3.79 miles of 20-inch-diameter
pipeline in Chambers County to provide
up to 360,000 dekatherms per day of
firm lateral line service to the existing
Cedar Bayou Power Plant. Texas Eastern
would also construct a metering and
regulating station and other ancillary
facilities (i.e., a pig launcher, pig
receiver, and several valves) as a part of
its Cedar Bayou Lateral Project.
The general location of the proposed
facilities is shown in Appendix 1.1
Land Requirements for Construction
The proposed pipeline would be
located almost entirely within an
existing utility corridor. Construction of
the project, including the aboveground
facilities, would affect about 29.4 acres
of land. About 28 acres of this would be
temporary disturbance, as the land
would be allowed to revert to existing
condition after construction.
The EA Process
We 2 are preparing this EA to comply
with the National Environmental Policy
Act (NEPA) which requires the
Commission to take into account the
environmental impact that could result
if it authorizes Texas Eastern’s proposal.
By this notice, we are also asking
federal, state, and local agencies with
jurisdiction and/or special expertise
with respect to environmental issues to
formally cooperate with us in the
preparation of the EA. Agencies that
would like to request cooperating status
1 The appendices referenced in this notice are not
being printed in the Federal Register. Copies are
available on the Commission’s Internet Web site
(https://www.ferc.gov) at the ‘‘eLibrary’’ link or from
the Commission’s Public Reference Room at (202)
502–8371. For instructions on connecting to
eLibrary, refer to the ‘‘Additional Information’’
section at the end of this notice. Copies of the
appendices were sent to all those receiving this
notice in the mail. Requests for detailed maps of the
proposed facilities should be made directly to Texas
Eastern.
2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the
environmental staff of the FERC’s Office of Energy
Projects.
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
46457
should follow the instructions for filing
comments provided below.
NEPA also requires the FERC to
discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping.’’ The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
Notice of Intent, we are requesting
public comments on the scope of the
issues to address in the EA. All
comments received are considered
during the preparation of the EA.
The EA will discuss impacts that
could occur as a result of the
construction and operation of the
proposed project under these general
headings:
• Geology and soils
• water resources
• wetlands
• land use and visual quality
• cultural resources
• vegetation, fisheries, and wildlife
(including threatened and endangered
species)
• air quality and noise
• reliability and safety
We will also evaluate possible
alternatives to the proposed project or
portions of the project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
Our independent analysis of the
issues will be in the EA. Depending on
the comments received during the
scoping process, the EA may be
published and mailed to federal, state,
and local agencies, public interest
groups, interested individuals, affected
landowners, newspapers, libraries, and
the Commission’s official service list for
this proceeding. A comment period will
be allotted for review if the EA is
published. We will consider all
comments on the EA before we make
our recommendations to the
Commission.
To ensure your comments are
considered, please carefully follow the
instructions in the public participation
section below.
Public Participation
You can make a difference by
providing us with your specific
comments or concerns about the project.
By becoming a commentor, your
concerns will be addressed in the EA
and considered by the Commission. You
should focus on the potential
environmental effects of the proposal,
alternatives to the proposal including
alternative berthing alignments, and
measures to avoid or lessen
environmental impact. The more
specific your comments, the more useful
E:\FR\FM\20AUN1.SGM
20AUN1
46458
Federal Register / Vol. 72, No. 160 / Monday, August 20, 2007 / Notices
they will be. Please carefully follow
these instructions to ensure that your
comments are received in time and
properly recorded:
• Send an original and two copies of
your letter to: Kimberley D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First St., NE.; Room
1A, Washington, DC 20426.
• Label one copy of the comments for
the attention of Gas Branch 1.
• Reference Docket No. CP07–411–
000.
• Mail your comments so that they
will be received in Washington, DC on
or before September 14, 2007.
The Commission encourages
electronic filing of comments. See 18
Code of Federal Regulations
385.2001(a)(1)(iii) and the instructions
on the Commission’s Internet Web site
at https://www.ferc.gov under the
‘‘eFiling’’ link and the link to the User’s
Guide. Prepare your submission in the
same manner as you would if filing on
paper and save it to a file on your hard
drive. Before you can file comments you
will need to create an account by
clicking on ‘‘Login to File’’ and then
‘‘New User Account.’’ You will be asked
to select the type of filing you are
making. This filing is considered a
‘‘Comment on Filing.’’
We may mail the EA for comment. If
you are interested in receiving it, please
return the Information Request
(Appendix 3). If you do not return the
Information Request, you will be taken
off the mailing list.
pwalker on PROD1PC71 with NOTICES
Becoming an Intervenor
In addition to involvement in the EA
scoping process, you may want to
become an official party to the
proceeding known as an ‘‘intervenor.’’
Intervenors play a more formal role in
the process. Among other things,
intervenors have the right to receive
copies of case-related Commission
documents and filings by other
intervenors. Likewise, each intervenor
must send one electronic copy (using
the Commission’s eFiling system) or 14
paper copies of its filings to the
Secretary of the Commission and must
send a copy of its filings to all other
parties on the Commission’s service list
for this proceeding. If you want to
become an intervenor you must file a
motion to intervene according to Rule
214 of the Commission’s Rules of
Practice and Procedure (18 CFR
385.214) (see Appendix 2).3 Only
intervenors have the right to seek
rehearing of the Commission’s decision.
Affected landowners and parties with
environmental concerns may be granted
intervenor status upon showing good
cause by stating that they have a clear
and direct interest in this proceeding
which would not be adequately
represented by any other parties. You do
not need intervenor status to have your
environmental comments considered.
DEPARTMENT OF ENERGY
Additional Information
Take notice that the following
hydroelectric application has been filed
with Commission and is available for
public inspection:
a. Type of Application: New Major
License.
b. Project No.: 2242–078.
c. Date filed: November 24, 2006.
d. Applicant: Eugene Water and
Electric Board.
e. Name of Project: Carmen-Smith
Hydroelectric Project.
f. Location: On the McKenzie River in
Lane and Linn Counties, near McKenzie
Bridge, Oregon. The project occupies
approximately 560 acres of the
Willamette National Forest.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)—825(r).
h. Applicant Contact: Randy L.
Berggren, General Manager, Eugene
Water and Electric Board, 500 East 4th
Avenue, P.O. Box 10148, Eugene, OR
97440, (541) 484–2411.
i. FERC Contact: Bob Easton, (202)
502–6045 or robert.easton@ferc.gov.
j. Deadline for filing scoping
comments: October 12, 2007.
All documents (original and eight
copies) should be filed with: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person on the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
Scoping comments may be filed
electronically via the Internet in lieu of
paper. The Commission strongly
encourages electronic filings. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site (https://www.ferc.gov) under the ‘‘eFiling’’ link.
k. This application is not ready for
environmental analysis at this time.
l. The Carmen-Smith Hydroelectric
Project consists of two developments,
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at 1–866–208–FERC or on the FERC
Internet Web site (https://www.ferc.gov)
using the ‘‘eLibrary’’ link. Click on the
eLibrary link, click on ‘‘General Search’’
and enter the docket number excluding
the last three digits in the Docket
Number field. Be sure you have selected
an appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or toll free at 1–866–208–3676, or for
TTY, contact (202) 502–8659. The
eLibrary link also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries and direct links to
the documents. Go to https://
www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at https://www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information. You can
also request additional information by
calling Texas Eastern at 713–627–5415.
Kimberly D. Bose,
Secretary.
[FR Doc. E7–16236 Filed 8–17–07; 8:45 am]
BILLING CODE 6717–01–P
3 Interventions may also be filed electronically via
the Internet in lieu of paper. See the previous
discussion on filing comments electronically.
VerDate Aug<31>2005
16:53 Aug 17, 2007
Jkt 211001
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
Federal Energy Regulatory
Commission
[P–2242–078]
Eugene West and Electric Board;
Carmen-Smith Hydroelectric Project;
Notice of Scoping Meetings and Site
Visit and Soliciting Scoping Comments
August 10, 2007.
E:\FR\FM\20AUN1.SGM
20AUN1
Agencies
[Federal Register Volume 72, Number 160 (Monday, August 20, 2007)]
[Notices]
[Pages 46457-46458]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-16236]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP07-411-000]
Texas Eastern Transmission, LP; Notice of Intent To Prepare an
Environmental Assessment for the Proposed Cedar Bayou Lateral Project
and Request for Comments on Environmental Issues
August 13, 2007.
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Cedar Bayou Lateral Project
involving construction and operation of natural gas pipeline facilities
by Texas Eastern Transmission, LP (Texas Eastern) in Chambers County,
Texas. The EA will be used by the Commission in its decision-making
process to determine whether the project is in the public convenience
and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the project. Your input will help determine which issues
need to be evaluated in the EA. Please note that the scoping period
will close on September 14, 2007. Details on how to submit comments are
provided in the Public Participation section of this notice.
If you are a landowner receiving this notice, you may be contacted
by a pipeline company representative about the acquisition of an
easement to construct, operate, and maintain the proposed facilities.
Texas Eastern would seek to negotiate a mutually acceptable agreement.
However, if the project is approved by the Commission, that approval
conveys with it the right of eminent domain. Therefore, if easement
negotiations fail to produce an agreement, Texas Eastern could initiate
condemnation proceedings in accordance with Texas state law.
This notice is being sent to affected landowners; federal, state,
and local government agencies; elected officials; Native American
tribes; other interested parties; and local libraries and newspapers.
State and local government representatives are asked to notify their
constituents of this proposed project and to encourage them to comment
on their areas of concern.
A fact sheet prepared by the FERC entitled ``An Interstate Natural
Gas Facility On My Land? What Do I Need To Know?'' addresses a number
of typically asked questions, including the use of eminent domain and
how to participate in the Commission's proceedings. It is available for
viewing on the FERC Internet Web site (https://www.ferc.gov).
Summary of the Proposed Project
Texas Eastern proposes to construct about 3.79 miles of 20-inch-
diameter pipeline in Chambers County to provide up to 360,000
dekatherms per day of firm lateral line service to the existing Cedar
Bayou Power Plant. Texas Eastern would also construct a metering and
regulating station and other ancillary facilities (i.e., a pig
launcher, pig receiver, and several valves) as a part of its Cedar
Bayou Lateral Project.
The general location of the proposed facilities is shown in
Appendix 1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice are not being
printed in the Federal Register. Copies are available on the
Commission's Internet Web site (https://www.ferc.gov) at the
``eLibrary'' link or from the Commission's Public Reference Room at
(202) 502-8371. For instructions on connecting to eLibrary, refer to
the ``Additional Information'' section at the end of this notice.
Copies of the appendices were sent to all those receiving this
notice in the mail. Requests for detailed maps of the proposed
facilities should be made directly to Texas Eastern.
---------------------------------------------------------------------------
Land Requirements for Construction
The proposed pipeline would be located almost entirely within an
existing utility corridor. Construction of the project, including the
aboveground facilities, would affect about 29.4 acres of land. About 28
acres of this would be temporary disturbance, as the land would be
allowed to revert to existing condition after construction.
The EA Process
We \2\ are preparing this EA to comply with the National
Environmental Policy Act (NEPA) which requires the Commission to take
into account the environmental impact that could result if it
authorizes Texas Eastern's proposal. By this notice, we are also asking
federal, state, and local agencies with jurisdiction and/or special
expertise with respect to environmental issues to formally cooperate
with us in the preparation of the EA. Agencies that would like to
request cooperating status should follow the instructions for filing
comments provided below.
---------------------------------------------------------------------------
\2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff
of the FERC's Office of Energy Projects.
---------------------------------------------------------------------------
NEPA also requires the FERC to discover and address concerns the
public may have about proposals. This process is referred to as
``scoping.'' The main goal of the scoping process is to focus the
analysis in the EA on the important environmental issues. By this
Notice of Intent, we are requesting public comments on the scope of the
issues to address in the EA. All comments received are considered
during the preparation of the EA.
The EA will discuss impacts that could occur as a result of the
construction and operation of the proposed project under these general
headings:
Geology and soils
water resources
wetlands
land use and visual quality
cultural resources
vegetation, fisheries, and wildlife (including threatened
and endangered species)
air quality and noise
reliability and safety
We will also evaluate possible alternatives to the proposed project
or portions of the project, and make recommendations on how to lessen
or avoid impacts on the various resource areas.
Our independent analysis of the issues will be in the EA. Depending
on the comments received during the scoping process, the EA may be
published and mailed to federal, state, and local agencies, public
interest groups, interested individuals, affected landowners,
newspapers, libraries, and the Commission's official service list for
this proceeding. A comment period will be allotted for review if the EA
is published. We will consider all comments on the EA before we make
our recommendations to the Commission.
To ensure your comments are considered, please carefully follow the
instructions in the public participation section below.
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the project. By becoming a commentor, your
concerns will be addressed in the EA and considered by the Commission.
You should focus on the potential environmental effects of the
proposal, alternatives to the proposal including alternative berthing
alignments, and measures to avoid or lessen environmental impact. The
more specific your comments, the more useful
[[Page 46458]]
they will be. Please carefully follow these instructions to ensure that
your comments are received in time and properly recorded:
Send an original and two copies of your letter to:
Kimberley D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First St., NE.; Room 1A, Washington, DC 20426.
Label one copy of the comments for the attention of Gas
Branch 1.
Reference Docket No. CP07-411-000.
Mail your comments so that they will be received in
Washington, DC on or before September 14, 2007.
The Commission encourages electronic filing of comments. See 18
Code of Federal Regulations 385.2001(a)(1)(iii) and the instructions on
the Commission's Internet Web site at https://www.ferc.gov under the
``eFiling'' link and the link to the User's Guide. Prepare your
submission in the same manner as you would if filing on paper and save
it to a file on your hard drive. Before you can file comments you will
need to create an account by clicking on ``Login to File'' and then
``New User Account.'' You will be asked to select the type of filing
you are making. This filing is considered a ``Comment on Filing.''
We may mail the EA for comment. If you are interested in receiving
it, please return the Information Request (Appendix 3). If you do not
return the Information Request, you will be taken off the mailing list.
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an official party to the proceeding known as an
``intervenor.'' Intervenors play a more formal role in the process.
Among other things, intervenors have the right to receive copies of
case-related Commission documents and filings by other intervenors.
Likewise, each intervenor must send one electronic copy (using the
Commission's eFiling system) or 14 paper copies of its filings to the
Secretary of the Commission and must send a copy of its filings to all
other parties on the Commission's service list for this proceeding. If
you want to become an intervenor you must file a motion to intervene
according to Rule 214 of the Commission's Rules of Practice and
Procedure (18 CFR 385.214) (see Appendix 2).\3\ Only intervenors have
the right to seek rehearing of the Commission's decision.
---------------------------------------------------------------------------
\3\ Interventions may also be filed electronically via the
Internet in lieu of paper. See the previous discussion on filing
comments electronically.
---------------------------------------------------------------------------
Affected landowners and parties with environmental concerns may be
granted intervenor status upon showing good cause by stating that they
have a clear and direct interest in this proceeding which would not be
adequately represented by any other parties. You do not need intervenor
status to have your environmental comments considered.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at 1-866-208-FERC or on the
FERC Internet Web site (https://www.ferc.gov) using the ``eLibrary''
link. Click on the eLibrary link, click on ``General Search'' and enter
the docket number excluding the last three digits in the Docket Number
field. Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at 1-866-208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission now offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries and direct links to
the documents. Go to https://www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at https://www.ferc.gov/EventCalendar/
EventsList.aspx along with other related information. You can also
request additional information by calling Texas Eastern at 713-627-
5415.
Kimberly D. Bose,
Secretary.
[FR Doc. E7-16236 Filed 8-17-07; 8:45 am]
BILLING CODE 6717-01-P