Summit Hydro, LLC; Putnam Green Power, LLC; Notice of Application for Transfer of License and Soliciting Comments, Motions to Intervene, and Protests, 41740 [E7-14760]

Download as PDF 41740 Federal Register / Vol. 72, No. 146 / Tuesday, July 31, 2007 / Notices and issuances related to this or other pending projects. For assistance, contact FERC Online Support. p. With this notice, we are initiating consultation with the Georgia State Historic Preservation Officer, as required by § 106, National Historic Preservation Act, and the regulations of the Advisory Council on Historic Preservation, 36 CFR 800.4. q. Procedural Schedule: At this time we do not anticipate the need for preparing a draft environmental assessment (EA). Recipients will have 30 days to provide the Commission with any written comments on the EA. All comments filed with the Commission will be considered in the Order taking final action on the license application. However, should substantive comments requiring re-analysis be received on the EA document, we would consider preparing a subsequent EA document. The application will be processed according to the following Hydro Licensing Schedule. Revisions to the schedule will be made as appropriate. Milestone Issue Acceptance or Deficiency Letter. Request Additional Information. Issue Scoping Document 1 for Comments. Issue Scoping Document 2 (if necessary). Notice that application is ready for environmental analysis. Notice of the Availability of the EA. Target date October 2007. October 2007. February 2008. April 2008. April 2008. December 2008. r. Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice ready for environmental analysis. Kimberly D. Bose, Secretary. [FR Doc. E7–14759 Filed 7–30–07; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission rmajette on PROD1PC64 with NOTICES [ Project No. 11547–013] Summit Hydro, LLC; Putnam Green Power, LLC; Notice of Application for Transfer of License and Soliciting Comments, Motions to Intervene, and Protests July 24, 2007. Take notice that the following hydroelectric application has been filed VerDate Aug<31>2005 15:11 Jul 30, 2007 Jkt 211001 with the Commission and is available for public inspection: a. Application Type: Transfer of License. b. Project No.: 11547–013. c. Date Filed: July 16, 2007. d. Applicants: Summit Hydro, LLC (Transferor) and Putnam Green Power, LLC (Transferee). e. Name and Location of Project: The Hale Hydroelectric Project is located on the Quinebaug River, in Windham County, Connecticut. f. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)–825(r). g. Applicant Contacts: For Transferor and Transferee: Duncan S. Broatch, Summit Hydro, LLC, 6 Far Hills Drive, Avon, CT 06001, (806) 255–7744. h. FERC Contact: Etta L. Foster (202) 502–8769. i. Deadline for filing comments, protests, and motions to intervene: August 23, 2007. All documents (original and eight copies) should be filed with Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. Comments, protests, and interventions may be filed electronically via the Internet in lieu of paper, see 18 CFR 385.2001 (a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. The Commission strongly encourages electronic filings. Please include the project number (P– 11547–013) on any comments, protests, or motions filed. The Commission’s Rules of Practice and Procedure require all interveners filing a document with the Commission to serve a copy of that document on each person in the official service list for the project. Further, if an intervener files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the documents on that resource agency. j. Description of Application: Applicants request approval, under Section 8 of the Federal Power Act, of a transfer of license for the Hale Hydroelectric Project No. 11547 from Summit Hydro, LLC to Putnam Green Power, LLC. k. This filing is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https:// www.ferc.gov using the ‘‘e-Library’’ link. Enter the project number excluding the last three digits (P–11547) in the docket number field to access the document. For online assistance, contact FERCOnlineSupport@ferc.gov or call toll-free (866) 208–3676, for TTY, call (202) 502–8659. A copy is also available PO 00000 Frm 00039 Fmt 4703 Sfmt 4703 for inspection and reproduction at the addresses in item g. l. Individual desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. m. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, 385.211, 385.214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. n. Filing and Service of Responsive Documents: Any filings must bear in all capital letters the title ‘‘COMMENTS’’, ‘‘PROTESTS’’, OR ‘‘MOTION TO INTERVENE’’, as applicable, and the Project Number of the particular application to which the filing refers. Any of the above-named documents must be filed by providing the original and the number of copies provided by the Commission’s regulations to: The Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. A copy of any motion to intervene must also be served upon each representative of the Applicant specified in the particular application. o. Agency Comments: Federal, state, and local agencies are invited to file comments on the described application. A copy of the application may be obtained by agencies directly from the Applicant. If an agency does not file comments within the time specified for filling comments, it will be assumed to have no comments. One copy of an agency’s comments must also be sent to the Applicant’s representatives. Kimberly D. Bose, Secretary. [FR Doc. E7–14760 Filed 7–30–07; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\31JYN1.SGM 31JYN1

Agencies

[Federal Register Volume 72, Number 146 (Tuesday, July 31, 2007)]
[Notices]
[Page 41740]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-14760]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[ Project No. 11547-013]


Summit Hydro, LLC; Putnam Green Power, LLC; Notice of Application 
for Transfer of License and Soliciting Comments, Motions to Intervene, 
and Protests

July 24, 2007.
    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Application Type: Transfer of License.
    b. Project No.: 11547-013.
    c. Date Filed: July 16, 2007.
    d. Applicants: Summit Hydro, LLC (Transferor) and Putnam Green 
Power, LLC (Transferee).
    e. Name and Location of Project: The Hale Hydroelectric Project is 
located on the Quinebaug River, in Windham County, Connecticut.
    f. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
    g. Applicant Contacts: For Transferor and Transferee: Duncan S. 
Broatch, Summit Hydro, LLC, 6 Far Hills Drive, Avon, CT 06001, (806) 
255-7744.
    h. FERC Contact: Etta L. Foster (202) 502-8769.
    i. Deadline for filing comments, protests, and motions to 
intervene: August 23, 2007.
    All documents (original and eight copies) should be filed with 
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 
First Street, NE., Washington, DC 20426. Comments, protests, and 
interventions may be filed electronically via the Internet in lieu of 
paper, see 18 CFR 385.2001 (a)(1)(iii) and the instructions on the 
Commission's Web site under the ``e-Filing'' link. The Commission 
strongly encourages electronic filings. Please include the project 
number (P-11547-013) on any comments, protests, or motions filed. The 
Commission's Rules of Practice and Procedure require all interveners 
filing a document with the Commission to serve a copy of that document 
on each person in the official service list for the project. Further, 
if an intervener files comments or documents with the Commission 
relating to the merits of an issue that may affect the responsibilities 
of a particular resource agency, they must also serve a copy of the 
documents on that resource agency.
    j. Description of Application: Applicants request approval, under 
Section 8 of the Federal Power Act, of a transfer of license for the 
Hale Hydroelectric Project No. 11547 from Summit Hydro, LLC to Putnam 
Green Power, LLC.
    k. This filing is available for review at the Commission in the 
Public Reference Room or may be viewed on the Commission's Web site at 
https://www.ferc.gov using the ``e-Library'' link. Enter the project 
number excluding the last three digits (P-11547) in the docket number 
field to access the document. For online assistance, contact 
FERCOnlineSupport@ferc.gov or call toll-free (866) 208-3676, for TTY, 
call (202) 502-8659. A copy is also available for inspection and 
reproduction at the addresses in item g.
    l. Individual desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    m. Comments, Protests, or Motions to Intervene: Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, 
385.211, 385.214. In determining the appropriate action to take, the 
Commission will consider all protests or other comments filed, but only 
those who file a motion to intervene in accordance with the 
Commission's Rules may become a party to the proceeding. Any comments, 
protests, or motions to intervene must be received on or before the 
specified comment date for the particular application.
    n. Filing and Service of Responsive Documents: Any filings must 
bear in all capital letters the title ``COMMENTS'', ``PROTESTS'', OR 
``MOTION TO INTERVENE'', as applicable, and the Project Number of the 
particular application to which the filing refers. Any of the above-
named documents must be filed by providing the original and the number 
of copies provided by the Commission's regulations to: The Secretary, 
Federal Energy Regulatory Commission, 888 First Street, NE., 
Washington, DC 20426. A copy of any motion to intervene must also be 
served upon each representative of the Applicant specified in the 
particular application.
    o. Agency Comments: Federal, state, and local agencies are invited 
to file comments on the described application. A copy of the 
application may be obtained by agencies directly from the Applicant. If 
an agency does not file comments within the time specified for filling 
comments, it will be assumed to have no comments. One copy of an 
agency's comments must also be sent to the Applicant's representatives.

Kimberly D. Bose,
Secretary.
 [FR Doc. E7-14760 Filed 7-30-07; 8:45 am]
BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.