White Wind Farm Project (DOE/ EIS-0376), 37525-37527 [E7-13328]
Download as PDF
Federal Register / Vol. 72, No. 131 / Tuesday, July 10, 2007 / Notices
Act of 1973. For accessibility
accommodations please send an e-mail
to accessibility@ferc.gov or call toll free
(866) 208–3372 (voice) or 202–502–8659
(TTY), or send a fax to 202–208–2106
with the required accommodations.
All interested parties and staff are
permitted to attend. For further
information please contact Katie
Williams at (202) 502–8246 or e-mail
kathleen.williams@ferc.gov.
Kimberly D. Bose,
Secretary.
[FR Doc. E7–13307 Filed 7–9–07; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Western Area Power Administration
White Wind Farm Project (DOE/ EIS–
0376)
Western Area Power
Administration, DOE.
ACTION: Record of decision.
jlentini on PROD1PC65 with NOTICES
AGENCY:
SUMMARY: White Wind Farm, LLC
(Applicant), a wholly-owned subsidiary
of Navitas Energy, Inc., has applied to
the U.S. Department of Energy (DOE),
Western Area Power Administration
(Western), to interconnect its proposed
White Wind Farm Project (Project) to
Western’s transmission system at the
existing White Substation, near
Brookings, South Dakota. The project
would involve building up to 103 2megawatt (MW) wind turbine generators
(WTG or Turbine) with a net capacity of
up to 200 MW. Western considered the
environmental impacts of the Project
and has decided to grant the Applicant’s
request to interconnect to the White
Substation. Taking into consideration
the mitigation measures the Applicant
has incorporated into the Project,
Western expects no significant longterm or short-term impacts to resources
from construction, operation, and
maintenance of the proposed Project.
FOR FURTHER INFORMATION CONTACT: Ms.
Catherine Cunningham, Western Area
Power Administration, P.O. Box 281213,
Lakewood, CO 80228, telephone (720)
962–7000, e-mail cunningh@wapa.gov.
For information about DOE’s National
Environmental Policy Act (NEPA)
process, contact Ms. Carol M.
Borgstrom, Director, NEPA Policy and
Compliance, GC–20, U.S. Department of
Energy, 1000 Independence Avenue
SW., Washington, DC 20585, telephone
(202) 586–4600 or (800) 472–2756.
SUPPLEMENTARY INFORMATION: The
Applicant’s objective for the proposed
Project is to develop a technically
feasible and economically viable, wind-
VerDate Aug<31>2005
16:17 Jul 09, 2007
Jkt 211001
powered, electrical generation resource.
The Applicant has identified the Project
Area, near the White Substation, as
suitable to meet the required criteria for
developing a large, utility-scale wind
energy project and has applied to
Western for interconnection there. The
White Substation is located near
Brookings, South Dakota. The Project
Area encompasses approximately 28
square miles (17,920 acres). It is
bisected by a 345-kilovolt (kV)
transmission line owned by Western.
The location and land availability
would enable the economic viability of
the proposed Project. The Applicant
expects the proposed Project to meet a
portion of the projected regional
demand for electricity produced from
wind resources.
The Federal action associated with
the proposed Project is approval or
denial of the Applicant’s
interconnection request. Western needs
to respond to the interconnection
request, provide transmission service
under its Notice of Final Open Access
Transmission Service Tariff, protect
transmission system reliability and
service to its customers, ensure
compliance with applicable
environmental laws, and consider the
Applicant’s objective.
A Notice of Intent to prepare an
environmental impact statement (EIS)
was published in the Federal Register
on February 18, 2005. Western held a
scoping meeting to solicit public
comments on the proposed Project in
Hendricks, Minnesota, on March 1,
2005. In addition, the Applicant has
been communicating and meeting with
area landowners throughout
development of the proposed Project, as
part of lease negotiations. On August 18,
2006, the U.S. Environmental Protection
Agency published a notice in the
Federal Register, announcing the
availability of the Draft EIS. Western
held an Open House and Public Hearing
on September 14, 2006, to solicit public
comments on the Draft EIS. For both the
initial scoping meeting and subsequent
Open House/Public Hearing, Western
provided notice of the meetings to
Federal, State, and local agencies,
Tribes, and the public, with print
media, local newspapers
announcements, and direct mailings.
Western accepted public comments on
the Draft EIS August 18 through October
2, 2006. The Notice of Availability of
the Final EIS was published in the
Federal Register on April 13, 2007.
Western decided to grant the
Applicant’s request to interconnect to
its transmission system at the White
Substation. This decision is based on a
review of the potential environmental
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
37525
impacts of the Project. Western
considered proposed mitigation
measures as part of the proposed Project
to determine impacts.
Alternatives
Western analyzed the Proposed
Action and No Action alternatives in the
EIS. Western considered alternative
sites for the Project but dismissed them
from consideration, as no viable
alternative locations were identified.
Therefore, Western limited its analysis
to the proposal the Applicant submitted
for approval.
Proposed Action
Under the Proposed Action, the
Applicant would construct up to 103 2–
MW WTGs with a net capacity of 200
MW. The Applicant would also
construct underground and overhead
electrical collector lines; a new Project
substation; a line interconnecting its
Project substation to Western’s White
Substation; and associated facilities.
The Applicant proposes to construct or
improve approximately 22 miles of
roads for access to the WTGs and
electrical collector lines.
The Project would temporarily disturb
approximately 626 acres of land during
construction of the proposed Project. It
would permanently disturb about 93
acres for installation of Project
components (access roads, turbine and
crane pads, overhead poles, and new
substation). The disturbed areas would
be dispersed throughout the Project
Area.
The Applicant would mount each
WTG on a single steel self-supporting
tower, approximately 255 feet high. The
towers would be approximately 16 feet
in diameter at the base and secured to
concrete foundations. The housing,
mounted at the top of each tower, would
enclose the electric generator, a voltage
step-up transformer, and a gearbox.
Each WTG rotor would have three
blades made of laminated glass and
carbon fiber. The full WTG height at its
tallest point would be approximately
400 feet from the ground to the tip of the
turbine blade. The Applicant would
paint the towers a flat neutral color to
blend into the natural environment.
The Applicant proposes to construct
the new Project substation adjacent to
Western’s existing White Substation.
The substation would have a footprint
of no more than 1 acre. The Applicant
would construct the substation on
private land immediately north of White
Substation.
The network of underground and
overhead 34.5-kV collector lines would
interconnect the WTGs. Approximately
45 miles of underground 34.5-kV sub-
E:\FR\FM\10JYN1.SGM
10JYN1
jlentini on PROD1PC65 with NOTICES
37526
Federal Register / Vol. 72, No. 131 / Tuesday, July 10, 2007 / Notices
transmission collection line and
approximately nine miles of overhead
34.5-kV collector line would be needed.
The Applicant would bury the
underground electric collection line at
least four feet below grade. The
underground collection line would link
each turbine to the next one or to the
overhead lines, which would in turn,
connect to the substation. The
Applicant would construct the overhead
lines within public road rights-of-way.
The overhead lines would be supported
on wooden single-pole structures,
approximately 25 to 30 feet tall and
spaced approximately 150 feet apart
along road rights of way.
A temporary staging area would be
developed on approximately eight acres
of tilled farmland. While the location of
the staging area is not final, the
Applicant expects that it would be
located near the proposed Project
substation. This staging area would be
used by the Applicant for construction
safety meetings, office trailers, parking
for equipment and vehicles, and staging
for some project components.
To accommodate interconnection of
the proposed Project to Western’s
substation, the Applicant would
construct a 345-kV overhead connection
line from the proposed Project
substation to the White Substation. The
new overhead line would terminate on
a steel structure inside the White
Substation. Western would install a
sulfur hexafluoride (SF6), gas-insulated
power circuit breaker; two high-voltage
disconnect switches; and other
miscellaneous equipment at the White
Substation. Western would monitor the
use, storage, and replacement of SF6 to
minimize releases to the environment.
The Applicant anticipates an 8-month
construction schedule. This schedule is
subject to negotiations with regulatory
agencies and utilities and may change.
With the exception of the overhead lines
within public road right of way, the
Applicant would construct the proposed
Project on privately-owned lands,
according to landowner agreements and
in compliance with county, State, and
Federal requirements. The Applicant
has obtained all necessary leases from
private landowners to construct and
operate the proposed Project up to 20
years. The Applicant would have the
option to renew leases at the end of the
20-year agreements. Depending on wind
turbine technology and market
conditions at the end of the lease
period, the Applicant may
decommission the project or update it
with more efficient components and
renew lease agreements.
Following construction, the Applicant
would reclaim areas not maintained as
VerDate Aug<31>2005
16:17 Jul 09, 2007
Jkt 211001
permanent facilities to their prior land
use. The Applicant would reseed
disturbed vegetation in non-agricultural
areas in accordance with landowner
agreements or local county extension
service protocols.
During operation and maintenance,
the Applicant would continuously
monitor the WTGs for any
abnormalities. If required, maintenance
staff would be dispatched to repair
WTGs. The Applicant would conduct
routine maintenance of the WTGs every
six months. Maintenance activities
include lubrication and inspection of
WTG components and fasteners. The
WTGs have a design life of 20 years.
Occasionally, a crane may be necessary
to remove and replace turbine
components. In this event, the
Applicant would conduct all
construction activity within previously
disturbed areas.
During operation of the proposed
Project substation, authorized personnel
would conduct periodic inspections and
service and repair equipment as needed.
Substation equipment would include a
step-up transformer, SF6 circuit
breakers, switchgears, and other
electrical equipment. Project personnel
would monitor the use, storage, and
replacement of SF6 to minimize releases
to the environment.
Within 120 days of the completion of
Project construction, the Applicant
would submit a Decommissioning Plan
to the Brookings County Planning and
Zoning Department. The
Decommissioning Plan would outline
the manner in which decommissioning
activities would be conducted. Upon
termination of operations, and if the
WTGs are not updated, the Applicant
would be obligated to dismantle and
remove all Project components. Unless
written approval is given by the affected
landowner, all Project components
would be removed to a depth of 48
inches below grade and the soil would
be restored to a condition reasonably
similar to the condition of the
surrounding soil.
Western completed wetland surveys
to determine the presence of
jurisdictional and non-jurisdictional
wetlands in the Project Area. The U.S.
Army Corps of Engineers has
determined that the majority of streams
and wetlands in the Project Area are
jurisdictional waters of the United
States. The Applicant’s final site design
would avoid all wetlands, both
jurisdictional and non-jurisdictional.
The Applicant would apply for
appropriate permits for utility line
activities, including access roads
administered under section 404 of the
Clean Water Act. These would contain
PO 00000
Frm 00023
Fmt 4703
Sfmt 4703
general and permit-specific mitigation
conditions for areas where the proposed
access roads and utility lines would
impact jurisdictional waters of the
United States. The Applicant would
employ directional boring techniques
where underground collector systems
would require a stream or wetland
crossing. The use of directional boring
would reduce erosion and/or
sedimentation impacts. The Applicant
would use Best Management Practices
such as installing silt fencing to ensure
that sediment or fill material does not
impact adjacent waterways.
No Action Alternative
Under the No Action Alternative,
Western would not grant the
Applicant’s request to interconnect to
Western’s transmission system, and the
Applicant would not build the Project.
Without the Project, existing
environmental conditions would remain
unchanged.
Environmentally Preferred Alternative
Western evaluated the alternatives to
determine which is environmentally
preferred, as required under 40 CFR
1505.2(b). The No Action Alternative is
the environmentally preferred
alternative, because no new disturbance
would result. No impacts to
environmental or social resources
would occur. The No Action Alternative
would not, however, meet the
Applicant’s objective.
Mitigation Measures
The Applicant has committed to
minimize potential short-term and longterm environmental and social impacts
of the Proposed Action through project
design, which includes implementation
of mitigation measures. These measures
are consolidated in Appendix B of the
Final EIS.
The Applicant, in consultation with
Western, developed a monitoring plan
to collect data on avian collisions with
WTGs. Western and the Applicant
would continue to coordinate with the
U.S. Fish and Wildlife Service (USFWS)
to ensure adequacy of the plan. Through
such monitoring, the Applicant and
Western would be able to identify and
implement reasonable operational
changes or additional mitigation
measures to further reduce avian and
bat mortality. Western and the
Applicant are working with the USFWS
to identify thresholds for making
appropriate changes. Surveys associated
with the monitoring plan include 1 year
prior to construction to establish
baseline data and 2 years following
operational start-up. The Applicant
would develop additional mitigation
E:\FR\FM\10JYN1.SGM
10JYN1
Federal Register / Vol. 72, No. 131 / Tuesday, July 10, 2007 / Notices
measures in consultation with the
appropriate regulatory agency, if
needed.
Western will develop a Mitigation
Action Plan (MAP) to provide
additional information on how
mitigation measures, associated with the
proposed Project, would be
implemented. The MAP would be
developed and made available prior to
any project activities directed by this
Record of Decision (ROD) that are
subject to a mitigation commitment.
jlentini on PROD1PC65 with NOTICES
Consultation
Western is the lead Federal agency for
compliance with Section 106 of the
National Historic Preservation Act
(NHPA) and Tribal consultation for all
components of the Project. The
Applicant would avoid all
archaeological and traditional cultural
properties determined significant in
consultation with the South Dakota
State Historic Preservation Officer
(SHPO) and interested Tribes. Western
prepared a Programmatic Agreement
(PA) in coordination with the South
Dakota SHPO. The PA was executed on
December 18, 2006. It establishes the
Area of Potential Effect for the proposed
Project, proposes a treatment plan for
identified resources, describes
procedures for unanticipated
discoveries, sets forth procedures for
Tribal consultation, and suggests
general mitigation measures. The PA
ensures that there would be no
‘‘unmitigatable’’ adverse effects on
historic properties as defined under the
NHPA. The Applicant would avoid
areas containing identified resources.
Western is also the lead for
compliance with Section 7 of the
Endangered Species Act. Western
prepared a biological assessment and
submitted it to the USFWS. Western
determined that the project may affect
but is not likely to adversely affect the
western prairie fringed orchid, the
Topeka shiner, and the bald eagle and
is not likely to affect the Dakota skipper.
The USFWS responded with a letter of
concurrence on May 30, 2006, and an email on May 31, 2007. Western
reviewed additional literature and
conducted field reconnaissance to
supplement this analysis. Western may
conduct further field studies prior to
construction as a component of the
Applicant’s monitoring study. Western
will continue to consult informally with
the USFWS.
Floodplain Statement of Findings
Western prepared a floodplain
assessment in the EIS according to 10
CFR part 1022. The assessment can be
found in the Draft EIS along with project
VerDate Aug<31>2005
16:17 Jul 09, 2007
Jkt 211001
maps. The Federal Emergency
Management Agency has not updated
the Flood Insurance Rate Maps for this
portion of South Dakota to reflect 500year floodplains. One-hundred-year
floodplains occur along Deer Creek and
along several unnamed streams in the
Project Area. The floodplains are
generally confined to the streambed and
immediately adjacent, low-lying areas.
The floodplains associated with the
ephemeral streams generally range from
200 to 500 feet in width. The Deer Creek
floodplain ranges from approximately
400 to 1,500 feet in width. On-site or
off-site flooding would not result from
construction and operation of the
proposed Project. The Applicant would
not construct WTGs in floodplains.
Implementation of county-approved
design standards for areas of
concentrated flow would ensure that onsite or off-site flooding does not occur.
Decision
Western decided to grant the
Applicant’s request to interconnect with
Western’s transmission system at the
White Substation. The Proposed Action
would meet the Applicant’s objectives
for the Project. Construction, operation,
and maintenance of the proposed
Project would not result in significant,
short-or long-term environmental
impacts. The Applicant would employ
all practical means to avoid or minimize
environmental harm as a result of the
proposed Project.
This ROD meets the requirements of
NEPA as well as the Council on
Environmental Quality and DOE’s
NEPA implementing regulations.
Additional analyses may affect this
decision and result in subsequent
analysis or decisions. Western will
notify the public of any additional
activities necessary to meet Western’s
NEPA and other public involvement
requirements.
Dated: June 22, 2007.
Timothy J. Meeks,
Administrator.
[FR Doc. E7–13328 Filed 7–9–07; 8:45 am]
BILLING CODE 6450–01–P
ENVIRONMENTAL PROTECTION
AGENCY
[FRL–8337–7]
Coastal Elevations and Sea Level Rise
Advisory Committee Meeting
Environmental Protection
Agency (EPA).
ACTION: Notice of meeting.
AGENCY:
PO 00000
Frm 00024
Fmt 4703
Sfmt 4703
37527
SUMMARY: Under the Federal Advisory
Committee Act (Pub. L. 92–463), EPA
gives notice of a public meeting of the
Coastal Elevations and Sea Level Rise
Advisory Committee (CESLAC).
DATE AND TIME: The meeting will be held
on Friday, July 27, 2007, from 12:30
p.m. until 3:30 p.m.
ADDRESSES: The meeting will take place
via teleconference. Interested parties
can access the teleconference as follows.
First, dial the following toll free
number: (866) 299–3188. Second, enter
the following conference code:
2023439719#. The leader will begin the
conference call.
FOR FURTHER INFORMATION CONTACT: Jack
Fitzgerald, Designated Federal Officer,
Climate Change Division, Mail Code
6207J, Office of Atmospheric Programs,
Environmental Protection Agency, 1200
Pennsylvania Avenue, NW.,
Washington, DC 20460; e-mail address:
Fitzgerald.jack@epa.gov, telephone
number (202) 343–9336, fax: (202) 343–
2337.
SUPPLEMENTARY INFORMATION: The
purpose of CESLAC is to provide advice
on the conduct of a study titled Coastal
Elevations and Sensitivity to Sea Level
Rise which is being conducted as part
of the U.S. Climate Change Science
Program (CCSP). The study pays
particular attention to the coastal area of
the U.S. from the state of New York
through North Carolina. A copy of the
study prospectus is available at: https://
www.climatescience.gov/Library/sap/
sap4–1/default.php. A copy of the
Committee Charter is available at
https://www.fido.gov/facadatabase/. This
is the third meeting of CESLAC. The
meeting will focus on consideration of
a draft of the study. Draft materials that
will be considered in the meeting can be
found at: https://
www.environmentalinformation.net/
CESLAC/ as of Friday, July 13, 2007. If
a printed copy of the material is needed,
please contact Ms. Beth Scherer by: (1)
E-mail at
BScherer@stratusconsulting.com; (2)
phone at (202) 466–3731, ext. 20; (3)
mail at Stratus Consulting, 1920 L St.,
NW., Suite 420, Washington, DC 20036.
Based on the extent of public
participation in the first two meetings of
CESLAC, thirty minutes of this third
meeting will be allocated for statements
by members of the public. Individuals
who are interested in making statements
should inform Jack Fitzgerald of their
interest by Tuesday, July 24, and
provide a copy of their statements for
the record. Individuals will be
scheduled in the order that their
statements of intent to present are
received. A minimum of three minutes
E:\FR\FM\10JYN1.SGM
10JYN1
Agencies
[Federal Register Volume 72, Number 131 (Tuesday, July 10, 2007)]
[Notices]
[Pages 37525-37527]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-13328]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Western Area Power Administration
White Wind Farm Project (DOE/ EIS-0376)
AGENCY: Western Area Power Administration, DOE.
ACTION: Record of decision.
-----------------------------------------------------------------------
SUMMARY: White Wind Farm, LLC (Applicant), a wholly-owned subsidiary of
Navitas Energy, Inc., has applied to the U.S. Department of Energy
(DOE), Western Area Power Administration (Western), to interconnect its
proposed White Wind Farm Project (Project) to Western's transmission
system at the existing White Substation, near Brookings, South Dakota.
The project would involve building up to 103 2-megawatt (MW) wind
turbine generators (WTG or Turbine) with a net capacity of up to 200
MW. Western considered the environmental impacts of the Project and has
decided to grant the Applicant's request to interconnect to the White
Substation. Taking into consideration the mitigation measures the
Applicant has incorporated into the Project, Western expects no
significant long-term or short-term impacts to resources from
construction, operation, and maintenance of the proposed Project.
FOR FURTHER INFORMATION CONTACT: Ms. Catherine Cunningham, Western Area
Power Administration, P.O. Box 281213, Lakewood, CO 80228, telephone
(720) 962-7000, e-mail cunningh@wapa.gov. For information about DOE's
National Environmental Policy Act (NEPA) process, contact Ms. Carol M.
Borgstrom, Director, NEPA Policy and Compliance, GC-20, U.S. Department
of Energy, 1000 Independence Avenue SW., Washington, DC 20585,
telephone (202) 586-4600 or (800) 472-2756.
SUPPLEMENTARY INFORMATION: The Applicant's objective for the proposed
Project is to develop a technically feasible and economically viable,
wind-powered, electrical generation resource. The Applicant has
identified the Project Area, near the White Substation, as suitable to
meet the required criteria for developing a large, utility-scale wind
energy project and has applied to Western for interconnection there.
The White Substation is located near Brookings, South Dakota. The
Project Area encompasses approximately 28 square miles (17,920 acres).
It is bisected by a 345-kilovolt (kV) transmission line owned by
Western. The location and land availability would enable the economic
viability of the proposed Project. The Applicant expects the proposed
Project to meet a portion of the projected regional demand for
electricity produced from wind resources.
The Federal action associated with the proposed Project is approval
or denial of the Applicant's interconnection request. Western needs to
respond to the interconnection request, provide transmission service
under its Notice of Final Open Access Transmission Service Tariff,
protect transmission system reliability and service to its customers,
ensure compliance with applicable environmental laws, and consider the
Applicant's objective.
A Notice of Intent to prepare an environmental impact statement
(EIS) was published in the Federal Register on February 18, 2005.
Western held a scoping meeting to solicit public comments on the
proposed Project in Hendricks, Minnesota, on March 1, 2005. In
addition, the Applicant has been communicating and meeting with area
landowners throughout development of the proposed Project, as part of
lease negotiations. On August 18, 2006, the U.S. Environmental
Protection Agency published a notice in the Federal Register,
announcing the availability of the Draft EIS. Western held an Open
House and Public Hearing on September 14, 2006, to solicit public
comments on the Draft EIS. For both the initial scoping meeting and
subsequent Open House/Public Hearing, Western provided notice of the
meetings to Federal, State, and local agencies, Tribes, and the public,
with print media, local newspapers announcements, and direct mailings.
Western accepted public comments on the Draft EIS August 18 through
October 2, 2006. The Notice of Availability of the Final EIS was
published in the Federal Register on April 13, 2007.
Western decided to grant the Applicant's request to interconnect to
its transmission system at the White Substation. This decision is based
on a review of the potential environmental impacts of the Project.
Western considered proposed mitigation measures as part of the proposed
Project to determine impacts.
Alternatives
Western analyzed the Proposed Action and No Action alternatives in
the EIS. Western considered alternative sites for the Project but
dismissed them from consideration, as no viable alternative locations
were identified. Therefore, Western limited its analysis to the
proposal the Applicant submitted for approval.
Proposed Action
Under the Proposed Action, the Applicant would construct up to 103
2-MW WTGs with a net capacity of 200 MW. The Applicant would also
construct underground and overhead electrical collector lines; a new
Project substation; a line interconnecting its Project substation to
Western's White Substation; and associated facilities. The Applicant
proposes to construct or improve approximately 22 miles of roads for
access to the WTGs and electrical collector lines.
The Project would temporarily disturb approximately 626 acres of
land during construction of the proposed Project. It would permanently
disturb about 93 acres for installation of Project components (access
roads, turbine and crane pads, overhead poles, and new substation). The
disturbed areas would be dispersed throughout the Project Area.
The Applicant would mount each WTG on a single steel self-
supporting tower, approximately 255 feet high. The towers would be
approximately 16 feet in diameter at the base and secured to concrete
foundations. The housing, mounted at the top of each tower, would
enclose the electric generator, a voltage step-up transformer, and a
gearbox. Each WTG rotor would have three blades made of laminated glass
and carbon fiber. The full WTG height at its tallest point would be
approximately 400 feet from the ground to the tip of the turbine blade.
The Applicant would paint the towers a flat neutral color to blend into
the natural environment.
The Applicant proposes to construct the new Project substation
adjacent to Western's existing White Substation. The substation would
have a footprint of no more than 1 acre. The Applicant would construct
the substation on private land immediately north of White Substation.
The network of underground and overhead 34.5-kV collector lines
would interconnect the WTGs. Approximately 45 miles of underground
34.5-kV sub-
[[Page 37526]]
transmission collection line and approximately nine miles of overhead
34.5-kV collector line would be needed. The Applicant would bury the
underground electric collection line at least four feet below grade.
The underground collection line would link each turbine to the next one
or to the overhead lines, which would in turn, connect to the
substation. The Applicant would construct the overhead lines within
public road rights-of-way. The overhead lines would be supported on
wooden single-pole structures, approximately 25 to 30 feet tall and
spaced approximately 150 feet apart along road rights of way.
A temporary staging area would be developed on approximately eight
acres of tilled farmland. While the location of the staging area is not
final, the Applicant expects that it would be located near the proposed
Project substation. This staging area would be used by the Applicant
for construction safety meetings, office trailers, parking for
equipment and vehicles, and staging for some project components.
To accommodate interconnection of the proposed Project to Western's
substation, the Applicant would construct a 345-kV overhead connection
line from the proposed Project substation to the White Substation. The
new overhead line would terminate on a steel structure inside the White
Substation. Western would install a sulfur hexafluoride (SF6), gas-
insulated power circuit breaker; two high-voltage disconnect switches;
and other miscellaneous equipment at the White Substation. Western
would monitor the use, storage, and replacement of SF6 to minimize
releases to the environment.
The Applicant anticipates an 8-month construction schedule. This
schedule is subject to negotiations with regulatory agencies and
utilities and may change. With the exception of the overhead lines
within public road right of way, the Applicant would construct the
proposed Project on privately-owned lands, according to landowner
agreements and in compliance with county, State, and Federal
requirements. The Applicant has obtained all necessary leases from
private landowners to construct and operate the proposed Project up to
20 years. The Applicant would have the option to renew leases at the
end of the 20-year agreements. Depending on wind turbine technology and
market conditions at the end of the lease period, the Applicant may
decommission the project or update it with more efficient components
and renew lease agreements.
Following construction, the Applicant would reclaim areas not
maintained as permanent facilities to their prior land use. The
Applicant would reseed disturbed vegetation in non-agricultural areas
in accordance with landowner agreements or local county extension
service protocols.
During operation and maintenance, the Applicant would continuously
monitor the WTGs for any abnormalities. If required, maintenance staff
would be dispatched to repair WTGs. The Applicant would conduct routine
maintenance of the WTGs every six months. Maintenance activities
include lubrication and inspection of WTG components and fasteners. The
WTGs have a design life of 20 years. Occasionally, a crane may be
necessary to remove and replace turbine components. In this event, the
Applicant would conduct all construction activity within previously
disturbed areas.
During operation of the proposed Project substation, authorized
personnel would conduct periodic inspections and service and repair
equipment as needed. Substation equipment would include a step-up
transformer, SF6 circuit breakers, switchgears, and other
electrical equipment. Project personnel would monitor the use, storage,
and replacement of SF6 to minimize releases to the
environment.
Within 120 days of the completion of Project construction, the
Applicant would submit a Decommissioning Plan to the Brookings County
Planning and Zoning Department. The Decommissioning Plan would outline
the manner in which decommissioning activities would be conducted. Upon
termination of operations, and if the WTGs are not updated, the
Applicant would be obligated to dismantle and remove all Project
components. Unless written approval is given by the affected landowner,
all Project components would be removed to a depth of 48 inches below
grade and the soil would be restored to a condition reasonably similar
to the condition of the surrounding soil.
Western completed wetland surveys to determine the presence of
jurisdictional and non-jurisdictional wetlands in the Project Area. The
U.S. Army Corps of Engineers has determined that the majority of
streams and wetlands in the Project Area are jurisdictional waters of
the United States. The Applicant's final site design would avoid all
wetlands, both jurisdictional and non-jurisdictional. The Applicant
would apply for appropriate permits for utility line activities,
including access roads administered under section 404 of the Clean
Water Act. These would contain general and permit-specific mitigation
conditions for areas where the proposed access roads and utility lines
would impact jurisdictional waters of the United States. The Applicant
would employ directional boring techniques where underground collector
systems would require a stream or wetland crossing. The use of
directional boring would reduce erosion and/or sedimentation impacts.
The Applicant would use Best Management Practices such as installing
silt fencing to ensure that sediment or fill material does not impact
adjacent waterways.
No Action Alternative
Under the No Action Alternative, Western would not grant the
Applicant's request to interconnect to Western's transmission system,
and the Applicant would not build the Project. Without the Project,
existing environmental conditions would remain unchanged.
Environmentally Preferred Alternative
Western evaluated the alternatives to determine which is
environmentally preferred, as required under 40 CFR 1505.2(b). The No
Action Alternative is the environmentally preferred alternative,
because no new disturbance would result. No impacts to environmental or
social resources would occur. The No Action Alternative would not,
however, meet the Applicant's objective.
Mitigation Measures
The Applicant has committed to minimize potential short-term and
long-term environmental and social impacts of the Proposed Action
through project design, which includes implementation of mitigation
measures. These measures are consolidated in Appendix B of the Final
EIS.
The Applicant, in consultation with Western, developed a monitoring
plan to collect data on avian collisions with WTGs. Western and the
Applicant would continue to coordinate with the U.S. Fish and Wildlife
Service (USFWS) to ensure adequacy of the plan. Through such
monitoring, the Applicant and Western would be able to identify and
implement reasonable operational changes or additional mitigation
measures to further reduce avian and bat mortality. Western and the
Applicant are working with the USFWS to identify thresholds for making
appropriate changes. Surveys associated with the monitoring plan
include 1 year prior to construction to establish baseline data and 2
years following operational start-up. The Applicant would develop
additional mitigation
[[Page 37527]]
measures in consultation with the appropriate regulatory agency, if
needed.
Western will develop a Mitigation Action Plan (MAP) to provide
additional information on how mitigation measures, associated with the
proposed Project, would be implemented. The MAP would be developed and
made available prior to any project activities directed by this Record
of Decision (ROD) that are subject to a mitigation commitment.
Consultation
Western is the lead Federal agency for compliance with Section 106
of the National Historic Preservation Act (NHPA) and Tribal
consultation for all components of the Project. The Applicant would
avoid all archaeological and traditional cultural properties determined
significant in consultation with the South Dakota State Historic
Preservation Officer (SHPO) and interested Tribes. Western prepared a
Programmatic Agreement (PA) in coordination with the South Dakota SHPO.
The PA was executed on December 18, 2006. It establishes the Area of
Potential Effect for the proposed Project, proposes a treatment plan
for identified resources, describes procedures for unanticipated
discoveries, sets forth procedures for Tribal consultation, and
suggests general mitigation measures. The PA ensures that there would
be no ``unmitigatable'' adverse effects on historic properties as
defined under the NHPA. The Applicant would avoid areas containing
identified resources.
Western is also the lead for compliance with Section 7 of the
Endangered Species Act. Western prepared a biological assessment and
submitted it to the USFWS. Western determined that the project may
affect but is not likely to adversely affect the western prairie
fringed orchid, the Topeka shiner, and the bald eagle and is not likely
to affect the Dakota skipper. The USFWS responded with a letter of
concurrence on May 30, 2006, and an e-mail on May 31, 2007. Western
reviewed additional literature and conducted field reconnaissance to
supplement this analysis. Western may conduct further field studies
prior to construction as a component of the Applicant's monitoring
study. Western will continue to consult informally with the USFWS.
Floodplain Statement of Findings
Western prepared a floodplain assessment in the EIS according to 10
CFR part 1022. The assessment can be found in the Draft EIS along with
project maps. The Federal Emergency Management Agency has not updated
the Flood Insurance Rate Maps for this portion of South Dakota to
reflect 500-year floodplains. One-hundred-year floodplains occur along
Deer Creek and along several unnamed streams in the Project Area. The
floodplains are generally confined to the streambed and immediately
adjacent, low-lying areas. The floodplains associated with the
ephemeral streams generally range from 200 to 500 feet in width. The
Deer Creek floodplain ranges from approximately 400 to 1,500 feet in
width. On-site or off-site flooding would not result from construction
and operation of the proposed Project. The Applicant would not
construct WTGs in floodplains. Implementation of county-approved design
standards for areas of concentrated flow would ensure that on-site or
off-site flooding does not occur.
Decision
Western decided to grant the Applicant's request to interconnect
with Western's transmission system at the White Substation. The
Proposed Action would meet the Applicant's objectives for the Project.
Construction, operation, and maintenance of the proposed Project would
not result in significant, short-or long-term environmental impacts.
The Applicant would employ all practical means to avoid or minimize
environmental harm as a result of the proposed Project.
This ROD meets the requirements of NEPA as well as the Council on
Environmental Quality and DOE's NEPA implementing regulations.
Additional analyses may affect this decision and result in subsequent
analysis or decisions. Western will notify the public of any additional
activities necessary to meet Western's NEPA and other public
involvement requirements.
Dated: June 22, 2007.
Timothy J. Meeks,
Administrator.
[FR Doc. E7-13328 Filed 7-9-07; 8:45 am]