Combined Notice of Filings #1, 36696-36697 [E7-13064]

Download as PDF 36696 Federal Register / Vol. 72, No. 128 / Thursday, July 5, 2007 / Notices should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, N.E., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, D.C. There is an ‘‘eSubscription’’ link on the web site that enables subscribers to receive email notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5 p.m. Eastern Time on July 23, 2007 Kimberly D. Bose, Secretary. [FR Doc. E7–12935 Filed 7–3–07; 8:45 am] BILLING CODE 6717–01–P The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5 p.m. Eastern Time on July 12, 2007. Kimberly D. Bose, Secretary. [FR Doc. E7–12934 Filed 7–3–07; 8:45 am] Federal Energy Regulatory Commission BILLING CODE 6717–01–P [Docket No. EL07–67–000] DEPARTMENT OF ENERGY DC Energy, LLC Complainant, v. H.Q. Energy Services (U.S.) Inc. Respondent; Notice of Amended Complaint Federal Energy Regulatory Commission June 27, 2007. sroberts on PROD1PC70 with NOTICES DEPARTMENT OF ENERGY June 29, 2007. Take notice that on June 22, 2007, DC Energy, LLC (DC Energy) pursuant to Rule 215 of the Rules of Practice and Procedure of the Commission’s Regulations, 18 CFR 385.215, filed an amendment to its June 12, 2007, Complaint. DC Energy states that it has discovered new facts which are directly relevant to the issues raised in its original Complaint. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. The Respondent’s answer and all interventions, or protests must be filed on or before the comment date. The Respondent’s answer, motions to intervene, and protests must be served on the Complainants. VerDate Aug<31>2005 18:43 Jul 03, 2007 Jkt 211001 Combined Notice of Filings #1 Take notice that the Commission received the following electric rate filings: Docket Numbers: ER05–1065–010. Applicants: Entergy Services, Inc. Description: Entergy Operating Companies submits its compliance filing in accordance with Commission’s May 25, 2007 Order. Filed Date: 06/25/2007. Accession Number: 20070627–0102. Comment Date: 5 p.m. Eastern Time on Monday, July 16, 2007. Docket Numbers: ER07–157–001, ER06–398–002, ER06–399–002, ER04– 268–005, ER98–4159–008. Applicants: Macquarie Cook Power, Inc.; Duquesne Keystone LLC; Duquesne Conemaugh LLC; Duquesne Power, LLC; Duquesne Light Company. Description: Macquarie Cook Power, Inc et al submit their notice of change in status related to the 5/31/07 acquisition of Duquesne Light Holdings, Inc. Filed Date: 06/25/2007. Accession Number: 20070627–0101. Comment Date: 5 p.m. Eastern Time on Monday, July 16, 2007. PO 00000 Frm 00050 Fmt 4703 Sfmt 4703 Docket Numbers: ER07–613–004, ER07–1077–000. Applicants: California Independent System Operator Corporation. Description: California Independent System Operator Corp submits amendments to the ISO Tariff 2007 Congestion Revenue Rights Credit Policy Amendment. Filed Date: 06/22/2007. Accession Number: 20070627–0104. Comment Date: 5 p.m. Eastern Time on Friday, July 13, 2007. Docket Numbers: ER07–1076–000. Applicants: Upper Peninsula Power Company. Description: Upper Peninsula Power Co submits a letter of understanding with the City of Escanaba, Michigan, will begin on 6/25/07. Filed Date: 06/25/2007. Accession Number: 20070627–0108. Comment Date: 5 p.m. Eastern Time on Monday, July 16, 2007. Docket Numbers: ER07–1078–000. Applicants: American Electric Power Service Corporation. Description: AEP Operating Companies submit an Interconnection and Local Delivery Service Agreement with the Village of Glouster, Ohio. Filed Date: 06/26/2007. Accession Number: 20070628–0084. Comment Date: 5 p.m. Eastern Time on Tuesday, July 17, 2007. Docket Numbers: ER07–1079–000. Applicants: American Electric Power Service Corporation. Description: Ohio Power Co and Columbus Southern Power Company submit their eighth revision to the Interconnection and Local Delivery Service Agreement with Buckeye Power, Inc. Filed Date: 06/26/2007. Accession Number: 20070628–0085. Comment Date: 5 p.m. Eastern Time on Tuesday, July 17, 2007. Docket Numbers: ER07–1080–000. Applicants: American Electric Power Service Corporation. Description: AEP Operating Companies submits an Interconnection and Local Delivery Service Agreement with the Village of Woodsfield, Woodsfield, Ohio. Filed Date: 06/26/2007. Accession Number: 20070628–0086. Comment Date: 5 p.m. Eastern Time on Tuesday, July 17, 2007. Docket Numbers: ER07–1081–000. Applicants: Southern California Edison Company. Description: Southern California Edison submits a Large Generator Interconnection Agreement etc for Wholesale Distribution Service between the Transmission and Distribution E:\FR\FM\05JYN1.SGM 05JYN1 sroberts on PROD1PC70 with NOTICES Federal Register / Vol. 72, No. 128 / Thursday, July 5, 2007 / Notices Business Unit of SCE et al for the Mira Loma Peaker Project. Filed Date: 06/26/2007. Accession Number: 20070628–0221. Comment Date: 5 p.m. Eastern Time on Tuesday, July 17, 2007. Docket Numbers: ER07–1082–000. Applicants: Southern California Edison Company. Description: Southern California Edison submits a Large Generator Interconnection Agreement etc for Wholesale Distribution Service between the Transmission and Distribution Business Unit of SCE et al for the Grapeland Peaker Project. Filed Date: 06/26/2007. Accession Number: 20070628–0220. Comment Date: 5 p.m. Eastern Time on Tuesday, July 17, 2007. Docket Numbers: ER07–1083–000. Applicants: Southern California Edison Company. Description: Southern California Edison submits a Large Generator Interconnection Agreement etc for Wholesale Distribution Service between the Transmission and Distribution Business Unit of SCE et al for the Center Peaker Project. Filed Date: 06/26/2007. Accession Number: 20070628–0219. Comment Date: 5 p.m. Eastern Time on Tuesday, July 17, 2007. Docket Numbers: ER07–1084–000. Applicants: Southern California Edison Company. Description: Southern California Edison submits a Large Generator Interconnection Agreement etc for Wholesale Distribution Service between the Transmission and Distribution Business Unit of SCE et al for the Barre Peaker Project. Filed Date: 06/26/2007. Accession Number: 20070628–0218. Comment Date: 5 p.m. Eastern Time on Tuesday, July 17, 2007. Docket Numbers: ER07–1085–000. Applicants: Niagara Mohawk Power Corporation. Description: Niagara Mohawk Power Corp dba National Grid submits an Amended and Restated Power Sales Agreement with Fulton Cogeneration Associates, LP, designated as Service Agreement 1150. Filed Date: 06/26/2007. Accession Number: 20070628–0082. Comment Date: 5 p.m. Eastern Time on Tuesday, July 17, 2007. Any person desiring to intervene or to protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214) on or before 5 p.m. Eastern time on the specified comment date. It VerDate Aug<31>2005 18:43 Jul 03, 2007 Jkt 211001 is not necessary to separately intervene again in a subdocket related to a compliance filing if you have previously intervened in the same docket. Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. In reference to filings initiating a new proceeding, interventions or protests submitted on or before the comment deadline need not be served on persons other than the Applicant. The Commission encourages electronic submission of protests and interventions in lieu of paper, using the FERC Online links at https://www.ferc.gov. To facilitate electronic service, persons with Internet access who will eFile a document and/ or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. Persons unable to file electronically should submit an original and 14 copies of the intervention or protest to the Federal Energy Regulatory Commission, 888 First St. NE., Washington, DC 20426. The filings in the above proceedings are accessible in the Commission’s eLibrary system by clicking on the appropriate link in the above list. They are also available for review in the Commission’s Public Reference Room in Washington, DC. There is an eSubscription link on the web site that enables subscribers to receive email notification when a document is added to a subscribed dockets(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Kimberly D. Bose, Secretary, [FR Doc. E7–13064 Filed 7–3–07; 8:45 am] BILLING CODE 6717–01–P PO 00000 Frm 00051 Fmt 4703 Sfmt 4703 36697 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 11588–027—AK] Alaska Power and Telephone Company; Notice of Availability of Environmental Assessment June 28, 2007. An environmental assessment (EA) is available for public review. The EA was prepared for an application filed by Alaska Power and Telephone Company (licensee) on January 26, 2007, and supplemented on March 6 and April 5, 2007, requesting Commission approval for an Amendment of License to Modify Project Design at the Kasidaya Hydroelectric Project. The project is located on Kasidaya Creek at Taiya Inlet, 3 miles south of the City of Skagway, Alaska. The project occupies lands within the Tongass National Forest, administered by the U.S. Forest Service. The licensee has requested that in lieu of passing the penstock through a tunnel to cross Kasidaya Creek and gain access to the diversion structure, they would like to have the penstock cross over Kasidaya Creek with a modular steel bridge. The penstock would be buried adjacent to the access road, except for crossing the creek, on a small bridge adjacent to the aluminum block culvert. In addition to being significantly less expensive than the tunnel, the bridge arrangement would also provide more convenient access to the diversion site for construction and operation of the project. The Environmental Assessment (EA), which is attached to the order approving order amending license and revising annual charges, evaluates the environmental effects of the relocation and redesign of project facilities. While these changes to project facilities will impact areas not specifically evaluated in previous EA’s, the environmental effects are expected to be similar. A copy of the EA is attached to a Commission order titled ‘‘Approving Order Amending License and Revising Annual Charges,’’ issued June 27, 2007 and is available for review at the Commission or may be viewed on the Commission’s web site at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access documents. For assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll- E:\FR\FM\05JYN1.SGM 05JYN1

Agencies

[Federal Register Volume 72, Number 128 (Thursday, July 5, 2007)]
[Notices]
[Pages 36696-36697]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-13064]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission


Combined Notice of Filings 1

June 29, 2007.
    Take notice that the Commission received the following electric 
rate filings:
    Docket Numbers: ER05-1065-010.
    Applicants: Entergy Services, Inc.
    Description: Entergy Operating Companies submits its compliance 
filing in accordance with Commission's May 25, 2007 Order.
    Filed Date: 06/25/2007.
    Accession Number: 20070627-0102.
    Comment Date: 5 p.m. Eastern Time on Monday, July 16, 2007.

    Docket Numbers: ER07-157-001, ER06-398-002, ER06-399-002, ER04-268-
005, ER98-4159-008.
    Applicants: Macquarie Cook Power, Inc.; Duquesne Keystone LLC; 
Duquesne Conemaugh LLC; Duquesne Power, LLC; Duquesne Light Company.
    Description: Macquarie Cook Power, Inc et al submit their notice of 
change in status related to the 5/31/07 acquisition of Duquesne Light 
Holdings, Inc.
    Filed Date: 06/25/2007.
    Accession Number: 20070627-0101.
    Comment Date: 5 p.m. Eastern Time on Monday, July 16, 2007.

    Docket Numbers: ER07-613-004, ER07-1077-000.
    Applicants: California Independent System Operator Corporation.
    Description: California Independent System Operator Corp submits 
amendments to the ISO Tariff 2007 Congestion Revenue Rights Credit 
Policy Amendment.
    Filed Date: 06/22/2007.
    Accession Number: 20070627-0104.
    Comment Date: 5 p.m. Eastern Time on Friday, July 13, 2007.

    Docket Numbers: ER07-1076-000.
    Applicants: Upper Peninsula Power Company.
    Description: Upper Peninsula Power Co submits a letter of 
understanding with the City of Escanaba, Michigan, will begin on 6/25/
07.
    Filed Date: 06/25/2007.
    Accession Number: 20070627-0108.
    Comment Date: 5 p.m. Eastern Time on Monday, July 16, 2007.

    Docket Numbers: ER07-1078-000.
    Applicants: American Electric Power Service Corporation.
    Description: AEP Operating Companies submit an Interconnection and 
Local Delivery Service Agreement with the Village of Glouster, Ohio.
    Filed Date: 06/26/2007.
    Accession Number: 20070628-0084.
    Comment Date: 5 p.m. Eastern Time on Tuesday, July 17, 2007.

    Docket Numbers: ER07-1079-000.
    Applicants: American Electric Power Service Corporation.
    Description: Ohio Power Co and Columbus Southern Power Company 
submit their eighth revision to the Interconnection and Local Delivery 
Service Agreement with Buckeye Power, Inc.
    Filed Date: 06/26/2007.
    Accession Number: 20070628-0085.
    Comment Date: 5 p.m. Eastern Time on Tuesday, July 17, 2007.

    Docket Numbers: ER07-1080-000.
    Applicants: American Electric Power Service Corporation.
    Description: AEP Operating Companies submits an Interconnection and 
Local Delivery Service Agreement with the Village of Woodsfield, 
Woodsfield, Ohio.
    Filed Date: 06/26/2007.
    Accession Number: 20070628-0086.
    Comment Date: 5 p.m. Eastern Time on Tuesday, July 17, 2007.

    Docket Numbers: ER07-1081-000.
    Applicants: Southern California Edison Company.
    Description: Southern California Edison submits a Large Generator 
Interconnection Agreement etc for Wholesale Distribution Service 
between the Transmission and Distribution

[[Page 36697]]

Business Unit of SCE et al for the Mira Loma Peaker Project.
    Filed Date: 06/26/2007.
    Accession Number: 20070628-0221.
    Comment Date: 5 p.m. Eastern Time on Tuesday, July 17, 2007.

    Docket Numbers: ER07-1082-000.
    Applicants: Southern California Edison Company.
    Description: Southern California Edison submits a Large Generator 
Interconnection Agreement etc for Wholesale Distribution Service 
between the Transmission and Distribution Business Unit of SCE et al 
for the Grapeland Peaker Project.
    Filed Date: 06/26/2007.
    Accession Number: 20070628-0220.
    Comment Date: 5 p.m. Eastern Time on Tuesday, July 17, 2007.

    Docket Numbers: ER07-1083-000.
    Applicants: Southern California Edison Company.
    Description: Southern California Edison submits a Large Generator 
Interconnection Agreement etc for Wholesale Distribution Service 
between the Transmission and Distribution Business Unit of SCE et al 
for the Center Peaker Project.
    Filed Date: 06/26/2007.
    Accession Number: 20070628-0219.
    Comment Date: 5 p.m. Eastern Time on Tuesday, July 17, 2007.

    Docket Numbers: ER07-1084-000.
    Applicants: Southern California Edison Company.
    Description: Southern California Edison submits a Large Generator 
Interconnection Agreement etc for Wholesale Distribution Service 
between the Transmission and Distribution Business Unit of SCE et al 
for the Barre Peaker Project.
    Filed Date: 06/26/2007.
    Accession Number: 20070628-0218.
    Comment Date: 5 p.m. Eastern Time on Tuesday, July 17, 2007.

    Docket Numbers: ER07-1085-000.
    Applicants: Niagara Mohawk Power Corporation.
    Description: Niagara Mohawk Power Corp dba National Grid submits an 
Amended and Restated Power Sales Agreement with Fulton Cogeneration 
Associates, LP, designated as Service Agreement 1150.
    Filed Date: 06/26/2007.
    Accession Number: 20070628-0082.
    Comment Date: 5 p.m. Eastern Time on Tuesday, July 17, 2007.

    Any person desiring to intervene or to protest in any of the above 
proceedings must file in accordance with Rules 211 and 214 of the 
Commission's Rules of Practice and Procedure (18 CFR 385.211 and 
385.214) on or before 5 p.m. Eastern time on the specified comment 
date. It is not necessary to separately intervene again in a subdocket 
related to a compliance filing if you have previously intervened in the 
same docket. Protests will be considered by the Commission in 
determining the appropriate action to be taken, but will not serve to 
make protestants parties to the proceeding. Anyone filing a motion to 
intervene or protest must serve a copy of that document on the 
Applicant. In reference to filings initiating a new proceeding, 
interventions or protests submitted on or before the comment deadline 
need not be served on persons other than the Applicant.
    The Commission encourages electronic submission of protests and 
interventions in lieu of paper, using the FERC Online links at https://
www.ferc.gov. To facilitate electronic service, persons with Internet 
access who will eFile a document and/or be listed as a contact for an 
intervenor must create and validate an eRegistration account using the 
eRegistration link. Select the eFiling link to log on and submit the 
intervention or protests.
    Persons unable to file electronically should submit an original and 
14 copies of the intervention or protest to the Federal Energy 
Regulatory Commission, 888 First St. NE., Washington, DC 20426.
    The filings in the above proceedings are accessible in the 
Commission's eLibrary system by clicking on the appropriate link in the 
above list. They are also available for review in the Commission's 
Public Reference Room in Washington, DC. There is an eSubscription link 
on the web site that enables subscribers to receive email notification 
when a document is added to a subscribed dockets(s). For assistance 
with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov 
or call (866) 208-3676 (toll free). For TTY, call (202) 502-8659.

Kimberly D. Bose,
Secretary,
[FR Doc. E7-13064 Filed 7-3-07; 8:45 am]
BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.