Entergy Nuclear Fitzpatrick, LLC, and Entergy Nuclear Operations, Inc.; James A. Fitzpatrick Nuclear Power Plant; Notice of Availability of the Draft Supplement 31 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants, and Public Meeting for the License Renewal of James A. Fitzpatrick, 32924 [E7-11508]
Download as PDF
32924
Federal Register / Vol. 72, No. 114 / Thursday, June 14, 2007 / Notices
For the Nuclear Regulatory Commission.
Daniel Collins,
Branch Chief, Research and Test Reactors
Branch A, Division of Policy and Rulemaking,
Office of Nuclear Reactor Regulation.
[FR Doc. E7–11515 Filed 6–13–07; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket No. 50–333]
jlentini on PROD1PC65 with NOTICES
Entergy Nuclear Fitzpatrick, LLC, and
Entergy Nuclear Operations, Inc.;
James A. Fitzpatrick Nuclear Power
Plant; Notice of Availability of the Draft
Supplement 31 to the Generic
Environmental Impact Statement for
License Renewal of Nuclear Plants,
and Public Meeting for the License
Renewal of James A. Fitzpatrick
Notice is hereby given that the U.S.
Nuclear Regulatory Commission (NRC,
Commission) has published a draft
plant-specific supplement to the
Generic Environmental Impact
Statement for License Renewal of
Nuclear Plants (GEIS), NUREG–1437,
regarding the renewal of operating
license DPR–59 for an additional 20
years of operation for the James A.
FitzPatrick Nuclear Power Plant
(JAFNPP). JAFNPP is located on Lake
Ontario in Oswego County,
approximately seven miles northeast of
the City of Oswego, New York. Possible
alternatives to the proposed action
(license renewal) include no action and
reasonable alternative energy sources.
The draft Supplement 31 to the GEIS
is publicly available at the NRC Public
Document Room (PDR), located at One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852, or
from the NRC’s Agencywide Documents
Access and Management System
(ADAMS). The ADAMS Public
Electronic Reading Room is accessible at
https://adamswebsearch.nrc.gov/
dologin.htm. The Accession Number for
the draft Supplement 31 to the GEIS is
ML071420019. Persons who do not have
access to ADAMS, or who encounter
problems in accessing the documents
located in ADAMS, should contact the
NRC’s PDR reference staff by telephone
at 1–800–397–4209, or 301–415–4737,
or by e-mail at pdr@nrc.gov. In addition,
the libraries: Penfield Library SUNY,
7060 State Route 104, Oswego, NY
13126 and Oswego Public Library, 140–
142 East Second Street, Oswego, NY
13126 have agreed to make the draft
supplement to the GEIS available for
public inspection.
Any interested party may submit
comments on the draft supplement to
VerDate Aug<31>2005
17:22 Jun 13, 2007
Jkt 211001
the GEIS for consideration by the NRC
staff. To be considered, comments on
the draft supplement to the GEIS and
the proposed action must be received by
September 5, 2007; the NRC staff is able
to assure consideration only for
comments received on or before this
date. Comments received after the due
date will be considered only if it is
practical to do so. Written comments on
the draft supplement to the GEIS should
be sent to: Chief, Rulemaking,
Directives, and Editing Branch, Division
of Administrative Services, Office of
Administration, Mailstop T–6D59, U.S.
Nuclear Regulatory Commission,
Washington, DC 20555–0001.
Comments may be hand-delivered to the
NRC at 11545 Rockville Pike, Room T–
6D59, Rockville, Maryland, between
7:30 a.m. and 4:15 p.m. on Federal
workdays. Electronic comments may be
submitted to the NRC by e-mail at
FitzPatrickEIS@nrc.gov. All comments
received by the Commission, including
those made by Federal, State, local
agencies, Native American Tribes, or
other interested persons, will be made
available electronically at the
Commission’s PDR in Rockville,
Maryland, and through ADAMS.
The NRC staff will hold a public
meeting to present an overview of the
draft plant-specific supplement to the
GEIS and to accept public comments on
the document. The public meeting will
be held on August 1, 2007, at the Scriba
Town Municipal Building, 42 Creamery
Road, Oswego, New York 13126. There
will be two sessions to accommodate
interested parties. The first session will
convene at 1:30 p.m. and will continue
until 4:30 p.m., as necessary. The
second session will convene at 7 p.m.
with a repeat of the overview portions
of the meeting and will continue until
10 p.m., as necessary. Both meetings
will be transcribed and will include: (1)
A presentation of the contents of the
draft plant-specific supplement to the
GEIS, and (2) the opportunity for
interested government agencies,
organizations, and individuals to
provide comments on the draft report.
Additionally, the NRC staff will host
informal discussions one hour prior to
the start of each session at the same
location. No comments on the draft
supplement to the GEIS will be accepted
during the informal discussions. To be
considered, comments must be provided
either at the transcribed public meeting
or in writing. Persons may pre-register
to attend or present oral comments at
the meeting by contacting Ms. Jessie M.
Muir, the NRC Environmental Project
Manager at 1–800–368–5642, extension
0491, or by e-mail at
PO 00000
Frm 00092
Fmt 4703
Sfmt 4703
FitzPatrickEIS@nrc.gov no later than
July 18, 2007. Members of the public
may also register to provide oral
comments before the start of each
session. Individual, oral comments may
be limited by the time available,
depending on the number of persons
who register. If special equipment or
accommodations are needed to attend or
present information at the public
meeting, the need should be brought to
Ms. Muir’s attention no later than July
18, 2007, to provide the NRC staff
adequate notice to determine whether
the request can be accommodated.
For Further Information, Contact: Ms.
Jessie M. Muir, Environmental Branch
B, Division of License Renewal, Office
of Nuclear Reactor Regulation, U.S.
Nuclear Regulatory Commission, Mail
Stop O–11F1, Washington, DC 20555–
0001. Ms. Muir may be contacted at the
aforementioned telephone number or
e-mail address.
Dated at Rockville, Maryland, this 8th day
of June, 2007.
For the Nuclear Regulatory Commission.
Rani L. Franovich,
Branch Chief, Environmental Branch B,
Division of License Renewal, Office of Nuclear
Reactor Regulation.
[FR Doc. E7–11508 Filed 6–13–07; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket Nos. 50–498 and 50–499]
STP Nuclear Operating Company;
South Texas Project, Units 1 and 2,
Environmental Assessment and
Finding of No Significant Impact
The U.S. Nuclear Regulatory
Commission (NRC) is considering
issuance of amendments to Title 10 of
the Code of Federal Regulations (10
CFR) Part 50, Section 50.92, for Facility
Operating Licenses numbered NPF–76
and NPF–80, issued to STP Nuclear
Operating Company (the licensee), for
operation of the South Texas Project,
Units 1 and 2, located in Matagorda
County. Therefore, as required by 10
CFR 51.21, the NRC is issuing this
environmental assessment and finding
of no significant impact.
Environmental Assessment
Identification of the Proposed Action
The proposed action would change
the name of one licensee Texas Genco
LP (Texas Genco), to NRG South Texas
LP.
The proposed action is in accordance
with the licensee’s application dated
April 4, 2006.
E:\FR\FM\14JNN1.SGM
14JNN1
Agencies
[Federal Register Volume 72, Number 114 (Thursday, June 14, 2007)]
[Notices]
[Page 32924]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-11508]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 50-333]
Entergy Nuclear Fitzpatrick, LLC, and Entergy Nuclear Operations,
Inc.; James A. Fitzpatrick Nuclear Power Plant; Notice of Availability
of the Draft Supplement 31 to the Generic Environmental Impact
Statement for License Renewal of Nuclear Plants, and Public Meeting for
the License Renewal of James A. Fitzpatrick
Notice is hereby given that the U.S. Nuclear Regulatory Commission
(NRC, Commission) has published a draft plant-specific supplement to
the Generic Environmental Impact Statement for License Renewal of
Nuclear Plants (GEIS), NUREG-1437, regarding the renewal of operating
license DPR-59 for an additional 20 years of operation for the James A.
FitzPatrick Nuclear Power Plant (JAFNPP). JAFNPP is located on Lake
Ontario in Oswego County, approximately seven miles northeast of the
City of Oswego, New York. Possible alternatives to the proposed action
(license renewal) include no action and reasonable alternative energy
sources.
The draft Supplement 31 to the GEIS is publicly available at the
NRC Public Document Room (PDR), located at One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852, or from the NRC's Agencywide
Documents Access and Management System (ADAMS). The ADAMS Public
Electronic Reading Room is accessible at https://adamswebsearch.nrc.gov/
dologin.htm. The Accession Number for the draft Supplement 31 to the
GEIS is ML071420019. Persons who do not have access to ADAMS, or who
encounter problems in accessing the documents located in ADAMS, should
contact the NRC's PDR reference staff by telephone at 1-800-397-4209,
or 301-415-4737, or by e-mail at pdr@nrc.gov. In addition, the
libraries: Penfield Library SUNY, 7060 State Route 104, Oswego, NY
13126 and Oswego Public Library, 140-142 East Second Street, Oswego, NY
13126 have agreed to make the draft supplement to the GEIS available
for public inspection.
Any interested party may submit comments on the draft supplement to
the GEIS for consideration by the NRC staff. To be considered, comments
on the draft supplement to the GEIS and the proposed action must be
received by September 5, 2007; the NRC staff is able to assure
consideration only for comments received on or before this date.
Comments received after the due date will be considered only if it is
practical to do so. Written comments on the draft supplement to the
GEIS should be sent to: Chief, Rulemaking, Directives, and Editing
Branch, Division of Administrative Services, Office of Administration,
Mailstop T-6D59, U.S. Nuclear Regulatory Commission, Washington, DC
20555-0001. Comments may be hand-delivered to the NRC at 11545
Rockville Pike, Room T-6D59, Rockville, Maryland, between 7:30 a.m. and
4:15 p.m. on Federal workdays. Electronic comments may be submitted to
the NRC by e-mail at FitzPatrickEIS@nrc.gov. All comments received by
the Commission, including those made by Federal, State, local agencies,
Native American Tribes, or other interested persons, will be made
available electronically at the Commission's PDR in Rockville,
Maryland, and through ADAMS.
The NRC staff will hold a public meeting to present an overview of
the draft plant-specific supplement to the GEIS and to accept public
comments on the document. The public meeting will be held on August 1,
2007, at the Scriba Town Municipal Building, 42 Creamery Road, Oswego,
New York 13126. There will be two sessions to accommodate interested
parties. The first session will convene at 1:30 p.m. and will continue
until 4:30 p.m., as necessary. The second session will convene at 7
p.m. with a repeat of the overview portions of the meeting and will
continue until 10 p.m., as necessary. Both meetings will be transcribed
and will include: (1) A presentation of the contents of the draft
plant-specific supplement to the GEIS, and (2) the opportunity for
interested government agencies, organizations, and individuals to
provide comments on the draft report. Additionally, the NRC staff will
host informal discussions one hour prior to the start of each session
at the same location. No comments on the draft supplement to the GEIS
will be accepted during the informal discussions. To be considered,
comments must be provided either at the transcribed public meeting or
in writing. Persons may pre-register to attend or present oral comments
at the meeting by contacting Ms. Jessie M. Muir, the NRC Environmental
Project Manager at 1-800-368-5642, extension 0491, or by e-mail at
FitzPatrickEIS@nrc.gov no later than July 18, 2007. Members of the
public may also register to provide oral comments before the start of
each session. Individual, oral comments may be limited by the time
available, depending on the number of persons who register. If special
equipment or accommodations are needed to attend or present information
at the public meeting, the need should be brought to Ms. Muir's
attention no later than July 18, 2007, to provide the NRC staff
adequate notice to determine whether the request can be accommodated.
For Further Information, Contact: Ms. Jessie M. Muir, Environmental
Branch B, Division of License Renewal, Office of Nuclear Reactor
Regulation, U.S. Nuclear Regulatory Commission, Mail Stop O-11F1,
Washington, DC 20555-0001. Ms. Muir may be contacted at the
aforementioned telephone number or e-mail address.
Dated at Rockville, Maryland, this 8th day of June, 2007.
For the Nuclear Regulatory Commission.
Rani L. Franovich,
Branch Chief, Environmental Branch B, Division of License Renewal,
Office of Nuclear Reactor Regulation.
[FR Doc. E7-11508 Filed 6-13-07; 8:45 am]
BILLING CODE 7590-01-P