Bost2 Hydroelectric LLC; Notice of Application Accepted for Filing and Soliciting Motions To Intervene, Protests and Comments, 29140-29141 [E7-9995]
Download as PDF
29140
Federal Register / Vol. 72, No. 100 / Thursday, May 24, 2007 / Notices
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
May 18, 2007.
For assistance, contact FERC Online
Support.
Kimberly D. Bose,
Secretary.
[FR Doc. E7–9999 Filed 5–23–07; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Kimberly D. Bose,
Secretary.
[FR Doc. E7–10002 Filed 5–23–07; 8:45 am]
[Docket Nos. RP07–436–000]
ANR Pipeline Company; Notice of
Tariff Filing
BILLING CODE 6717–01–P
rmajette on PROD1PC67 with NOTICES
May 17, 2007.
Take notice that on May 1, 2007, ANR
Pipeline Company (ANR) tendered for
filing as part of its FERC Gas Tariff,
Second Revised Volume No. 1, FortySeventh Revised Sheet No. 17, to be
effective June 1, 2007.
ANR states that the filing is being
filed to implement its annual cashout
surcharge pursuant to the provisions
contained in Sections 15.5 and 15.8 of
the General Terms & Conditions of its
FERC Gas Tariff, Second Revised
Volume No. 1.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practices and
Procedure (18 CFR 385.211 and
385.214). Protests will be considered by
the Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed in accordance
with the provisions of Section 154.210
of the Commission’s regulations (18 CFR
154.210). Anyone filing an intervention
or protest must serve a copy of that
document on the Applicant. Anyone
filing an intervention or protest on or
before the intervention or protest date
need not serve motions to intervene or
protests on persons other than the
Applicant.
The Commission encourages
electronic submission of protests in lieu
of paper using the ‘‘eFiling’’ link at
https://www.ferc.gov. Persons unable to
file electronically should submit an
original and 14 copies of the protest to
the Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington, DC 20426.
The filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
VerDate Aug<31>2005
15:52 May 23, 2007
Jkt 211001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. P–12755–000]
Bost2 Hydroelectric LLC; Notice of
Application Accepted for Filing and
Soliciting Motions To Intervene,
Protests and Comments
May 17, 2007.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Preliminary
Permit.
b. Project No.: 12755–000.
c. Date filed: December 12, 2006.
d. Applicant: Bost2 Hydroelectric
LLC.
e. Name of Project: Red River Lock &
Dam #2 Hydroelectric Project.
f. Location: The proposed project
would utilize the existing U.S. Army
Corps of Engineers’ Red River Lock &
Dam #2 and would be located on the
Red River, in Rapides Parish, Louisiana.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r.
h. Applicant Contact: Mr. Robert
Larson, Bost2 Hydroelectric LLC, c/o
Gray, Plant, Mooty, Mooty, & Bennett,
80 South 8th Street, Suite 500,
Minneapolis, MN 55402, (612) 632–
3355.
i. FERC Contact: Patricia W. Gillis at
(202) 502–8735.
j. Deadline for filing comments,
protests, and motions to intervene: 60
days from the issuance date of this
notice.
k. All documents (original and eight
copies) should be filed with: The
Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington, DC 20426. Please include
the project number (P–12755–000) on
any comments, protests, or motions
filed.
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person whose name appears on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency. A copy of any
motion to intervene must also be served
upon each representative of the
Applicant specified in the particular
application.
l. Description of Project: The proposed
project would use the existing U.S.
Army Corps of Engineers’ Red River
Lock and Dam No. 2 and consist of: (1)
Five proposed penstocks; (2) a proposed
powerhouse containing 5 generating
units with a total installed capacity of
23-megawatts; (3) a proposed 500-footlong, 14.7-kilovolt transmission line;
and (4) appurtenant facilities. The
proposed project would have an
estimated annual generation of
approximately 141-gigawatt hours. The
applicant plans to sell the generated
energy.
m. Locations of Application: A copy
of the application is available for
inspection and reproduction at the
Commission in the Public Reference
Room, located at 888 First Street, NE.,
Room 2A, Washington, DC 20426, or by
calling (202) 502–8371. This filing may
also be viewed on the Commission’s
Web site at https://www.ferc.gov using
the ‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. You may also register online
at https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, call 1–866–208–3676 or
e-mail FERCOnlineSupport@ferc.gov.
For TTY, call (202) 502–8659. A copy is
also available for inspection and
reproduction at the address in item h
above.
n. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
o. Competing Preliminary Permit—
Anyone desiring to file a competing
application for preliminary permit for a
proposed project must submit the
competing application itself, or a notice
of intent to file such an application, to
the Commission on or before the
specified comment date for the
particular application (see 18 CFR 4.36).
Submission of a timely notice of intent
E:\FR\FM\24MYN1.SGM
24MYN1
rmajette on PROD1PC67 with NOTICES
Federal Register / Vol. 72, No. 100 / Thursday, May 24, 2007 / Notices
allows an interested person to file the
competing preliminary permit
application no later than 30 days after
the specified comment date for the
particular application. A competing
preliminary permit application must
conform with 18 CFR 4.30(b) and 4.36.
p. Competing Development
Application—Any qualified
development applicant desiring to file a
competing development application
must submit to the Commission, on or
before a specified comment date for the
particular application, either a
competing development application or a
notice of intent to file such an
application. Submission of a timely
notice of intent to file a development
application allows an interested person
to file the competing application no
later than 120 days after the specified
comment date for the particular
application. A competing license
application must conform with 18 CFR
4.30(b) and 4.36.
q. Notice of Intent—a notice of intent
must specify the exact name, business
address, and telephone number of the
prospective applicant, and must include
an unequivocal statement of intent to
submit, if such an application may be
filed, either a preliminary permit
application or a development
application (specify which type of
application). A notice of intent must be
served on the applicant(s) named in this
public notice.
r. Proposed Scope of Studies under
Permit—A preliminary permit, if issued,
does not authorize construction. The
term of the proposed preliminary permit
would be 36 months. The work
proposed under the preliminary permit
would include economic analysis,
preparation of preliminary engineering
plans, and a study of environmental
impacts. Based on the results of these
studies, the Applicant would decide
whether to proceed with the preparation
of a development application to
construct and operate the project.
s. Comments, Protests, or Motions to
Intervene—Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
VerDate Aug<31>2005
15:52 May 23, 2007
Jkt 211001
t. Filing and Service of Responsive
Documents—Any filings must bear in
all capital letters the title
‘‘COMMENTS’’, ‘‘PROTEST’’,
‘‘MOTION TO INTERVENE’’, ‘‘NOTICE
OF INTENT’’, or ‘‘COMPETING
APPLICATION’’, as applicable, and the
Project Number of the particular
application to which the filing refers.
Any of the above-named documents
must be filed by providing the original
and the number of copies provided by
the Commission’s regulations to: The
Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington, DC 20426. A copy of any
motion to intervene must also be served
upon each representative of the
Applicant specified in the particular
application.
u. Agency Comments—Federal, state,
and local agencies are invited to file
comments on the described application.
A copy of the application may be
obtained by agencies directly from the
applicant. If an agency does not file
comments within the time specified for
filing comments, it will be presumed to
have no comments. One copy of an
agency’s comments must also be sent to
the Applicant’s representatives.
v. Comments, protests and
interventions may be filed electronically
via the Internet in lieu of paper. See, 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site at https://www.ferc.gov under the
‘‘e-Filing’’ link.
Kimberly D. Bose,
Secretary.
[FR Doc. E7–9995 Filed 5–23–07; 8:45 am]
BILLING CODE 6717–01–P
29141
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. On or before the
comment date, it is not necessary to
serve motions to intervene or protests
on persons other than the Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on June 11, 2007.
Kimberly D. Bose,
Secretary.
[FR Doc. E7–9990 Filed 5–23–07; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
DEPARTMENT OF ENERGY
[Docket No. ER06–615–000]
Federal Energy Regulatory
Commission
California Independent System
Operator Corporation; Notice of FERC
Staff Attendance
[Docket No. ID–5302–000]
Bryant, Robert W.; Notice of Filing
May 17, 2007.
Take notice that on May 11, 2007,
Robert W. Bryant filed an Application
for Authorization to Hold Interlocking
Positions, pursuant to section 305(b) of
the Federal Power Act.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
May 17, 2007.
The Federal Energy Regulatory
Commission (Commission) hereby gives
notice that on May 23–25, 2007
members of its staff will attend the
California Independent System
Operator’s (CAISO) training program
entitled, ‘‘Market Redesign and
Technology Upgrade (MRTU) Bid-to-Bill
Training.’’ This training covers the
MRTU market process timeline, bids,
settlements, and billing, and will be
held at the CAISO, 151 Blue Ravine
Road, Folsom, CA. The agenda and
other documents for the training are
available on the CAISO’s Web site,
https://www.caiso.com.
E:\FR\FM\24MYN1.SGM
24MYN1
Agencies
[Federal Register Volume 72, Number 100 (Thursday, May 24, 2007)]
[Notices]
[Pages 29140-29141]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-9995]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. P-12755-000]
Bost2 Hydroelectric LLC; Notice of Application Accepted for
Filing and Soliciting Motions To Intervene, Protests and Comments
May 17, 2007.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Application: Preliminary Permit.
b. Project No.: 12755-000.
c. Date filed: December 12, 2006.
d. Applicant: Bost2 Hydroelectric LLC.
e. Name of Project: Red River Lock & Dam 2 Hydroelectric
Project.
f. Location: The proposed project would utilize the existing U.S.
Army Corps of Engineers' Red River Lock & Dam 2 and would be
located on the Red River, in Rapides Parish, Louisiana.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
h. Applicant Contact: Mr. Robert Larson, Bost2 Hydroelectric LLC,
c/o Gray, Plant, Mooty, Mooty, & Bennett, 80 South 8th Street, Suite
500, Minneapolis, MN 55402, (612) 632-3355.
i. FERC Contact: Patricia W. Gillis at (202) 502-8735.
j. Deadline for filing comments, protests, and motions to
intervene: 60 days from the issuance date of this notice.
k. All documents (original and eight copies) should be filed with:
The Secretary, Federal Energy Regulatory Commission, 888 First Street,
NE., Washington, DC 20426. Please include the project number (P-12755-
000) on any comments, protests, or motions filed.
The Commission's Rules of Practice and Procedure require all
intervenors filing documents with the Commission to serve a copy of
that document on each person whose name appears on the official service
list for the project. Further, if an intervenor files comments or
documents with the Commission relating to the merits of an issue that
may affect the responsibilities of a particular resource agency, they
must also serve a copy of the document on that resource agency. A copy
of any motion to intervene must also be served upon each representative
of the Applicant specified in the particular application.
l. Description of Project: The proposed project would use the
existing U.S. Army Corps of Engineers' Red River Lock and Dam No. 2 and
consist of: (1) Five proposed penstocks; (2) a proposed powerhouse
containing 5 generating units with a total installed capacity of 23-
megawatts; (3) a proposed 500-foot-long, 14.7-kilovolt transmission
line; and (4) appurtenant facilities. The proposed project would have
an estimated annual generation of approximately 141-gigawatt hours. The
applicant plans to sell the generated energy.
m. Locations of Application: A copy of the application is available
for inspection and reproduction at the Commission in the Public
Reference Room, located at 888 First Street, NE., Room 2A, Washington,
DC 20426, or by calling (202) 502-8371. This filing may also be viewed
on the Commission's Web site at https://www.ferc.gov using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. You may also
register online at https://www.ferc.gov/docs-filing/esubscription.asp to
be notified via e-mail of new filings and issuances related to this or
other pending projects. For assistance, call 1-866-208-3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY, call (202) 502-8659. A copy is
also available for inspection and reproduction at the address in item h
above.
n. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
o. Competing Preliminary Permit--Anyone desiring to file a
competing application for preliminary permit for a proposed project
must submit the competing application itself, or a notice of intent to
file such an application, to the Commission on or before the specified
comment date for the particular application (see 18 CFR 4.36).
Submission of a timely notice of intent
[[Page 29141]]
allows an interested person to file the competing preliminary permit
application no later than 30 days after the specified comment date for
the particular application. A competing preliminary permit application
must conform with 18 CFR 4.30(b) and 4.36.
p. Competing Development Application--Any qualified development
applicant desiring to file a competing development application must
submit to the Commission, on or before a specified comment date for the
particular application, either a competing development application or a
notice of intent to file such an application. Submission of a timely
notice of intent to file a development application allows an interested
person to file the competing application no later than 120 days after
the specified comment date for the particular application. A competing
license application must conform with 18 CFR 4.30(b) and 4.36.
q. Notice of Intent--a notice of intent must specify the exact
name, business address, and telephone number of the prospective
applicant, and must include an unequivocal statement of intent to
submit, if such an application may be filed, either a preliminary
permit application or a development application (specify which type of
application). A notice of intent must be served on the applicant(s)
named in this public notice.
r. Proposed Scope of Studies under Permit--A preliminary permit, if
issued, does not authorize construction. The term of the proposed
preliminary permit would be 36 months. The work proposed under the
preliminary permit would include economic analysis, preparation of
preliminary engineering plans, and a study of environmental impacts.
Based on the results of these studies, the Applicant would decide
whether to proceed with the preparation of a development application to
construct and operate the project.
s. Comments, Protests, or Motions to Intervene--Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214. In determining the appropriate action to take, the Commission
will consider all protests or other comments filed, but only those who
file a motion to intervene in accordance with the Commission's Rules
may become a party to the proceeding. Any comments, protests, or
motions to intervene must be received on or before the specified
comment date for the particular application.
t. Filing and Service of Responsive Documents--Any filings must
bear in all capital letters the title ``COMMENTS'', ``PROTEST'',
``MOTION TO INTERVENE'', ``NOTICE OF INTENT'', or ``COMPETING
APPLICATION'', as applicable, and the Project Number of the particular
application to which the filing refers. Any of the above-named
documents must be filed by providing the original and the number of
copies provided by the Commission's regulations to: The Secretary,
Federal Energy Regulatory Commission, 888 First Street, NE.,
Washington, DC 20426. A copy of any motion to intervene must also be
served upon each representative of the Applicant specified in the
particular application.
u. Agency Comments--Federal, state, and local agencies are invited
to file comments on the described application. A copy of the
application may be obtained by agencies directly from the applicant. If
an agency does not file comments within the time specified for filing
comments, it will be presumed to have no comments. One copy of an
agency's comments must also be sent to the Applicant's representatives.
v. Comments, protests and interventions may be filed electronically
via the Internet in lieu of paper. See, 18 CFR 385.2001(a)(1)(iii) and
the instructions on the Commission's Web site at https://www.ferc.gov
under the ``e-Filing'' link.
Kimberly D. Bose,
Secretary.
[FR Doc. E7-9995 Filed 5-23-07; 8:45 am]