Chugach Electric Association; Notice of Authorization for Continued Project Operation, 26348 [E7-8839]
Download as PDF
26348
Federal Register / Vol. 72, No. 89 / Wednesday, May 9, 2007 / Notices
Washington, DC 20202–4700. Requests
may also be electronically mailed to
ICDocketMgr@ed.gov or faxed to 202–
245–6623. Please specify the complete
title of the information collection when
making your request.
Comments regarding burden and/or
the collection activity requirements
should be electronically mailed to
ICDocketMgr@ed.gov. Individuals who
use a telecommunications device for the
deaf (TDD) may call the Federal
Information Relay Service (FIRS) at
1–800–877–8339.
[FR Doc. E7–8879 Filed 5–8–07; 8:45 am]
BILLING CODE 4000–01–P
DEPARTMENT OF EDUCATION
Notice of Proposed Information
Collection Requests
Department of Education.
Correction notice.
AGENCY:
ACTION:
SUMMARY: On April 27, 2007, the
Department of Education published a
notice in the Federal Register (Page
20998, Column 1) for the information
collection, ‘‘The Effect of Connected
Mathematics 2 (CM2) on the Math
Achievement of Middle School
Students’’. This notice hereby corrects
the reporting and recordkeeping hour
burden to 15,383 responses and 6,407
hours. The IC Clearance Official,
Regulatory Information Management
Services, Office of Management, hereby
issues a correction notice as required by
the Paperwork Reduction Act of 1995.
Dated: May 2, 2007.
Angela C. Arrington,
IC Clearance Official, Regulatory Information
Management Services, Office of Management.
[FR Doc. E7–8877 Filed 5–8–07; 8:45 am]
BILLING CODE 4000–01–P
Procedure (18 CFR 385.211 and
385.214). Protests will be considered by
the Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
date as indicated below. Anyone filing
an intervention or protest must serve a
copy of that document on the Applicant.
Anyone filing an intervention or protest
on or before the intervention or protest
date need not serve motions to intervene
or protests on persons other than the
Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time,
May 9, 2007.
Kimberly D. Bose,
Secretary.
[FR Doc. E7–8841 Filed 5–8–07; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Federal Energy Regulatory
Commission
[Docket No. RP07–409–000]
Black Marlin Pipeline Company; Notice
of Cash-Out Report
sroberts on PROD1PC70 with NOTICES
May 2, 2007.
Take notice that on April 27, 2007,
Black Marlin Pipeline Company (Black
Marlin) tendered for filing its annual
cash-out report for the calendar year
ended December 31, 2006.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
VerDate Aug<31>2005
18:12 May 08, 2007
Jkt 211001
[Project No. 2170]
Chugach Electric Association; Notice
of Authorization for Continued Project
Operation
May 2, 2007.
On April 22, 2005, Chugach Electric
Association, licensee for the Cooper
Lake Hydroelectric Project, filed an
application for a new or subsequent
license pursuant to the Federal Power
Act (FPA) and the Commission’s
regulations thereunder. The Cooper
PO 00000
Frm 00016
Fmt 4703
Sfmt 4703
Lake Project is located on the Cooper
Lake in South Central Alaska near
Anchorage, AK.
The license for Project No. 2170 was
issued for a period ending April 30,
2007. Section 15(a)(1) of the FPA, 16
U.S.C. 808(a)(1), requires the
Commission, at the expiration of a
license term, to issue from year-to-year
an annual license to the then licensee
under the terms and conditions of the
prior license until a new license is
issued, or the project is otherwise
disposed of as provided in section 15 or
any other applicable section of the FPA.
If the project’s prior license waived the
applicability of section 15 of the FPA,
then, based on section 9(b) of the
Administrative Procedure Act, 5 U.S.C.
558(c), and as set forth at 18 CFR
16.21(a), if the licensee of such project
has filed an application for a subsequent
license, the licensee may continue to
operate the project in accordance with
the terms and conditions of the license
after the minor or minor part license
expires, until the Commission acts on
its application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 2170
is issued to Chugach Electric
Association, for a period effective May
1, 2007 through April 30, 2008, or until
the issuance of a new license for the
project or other disposition under the
FPA, whichever comes first. If issuance
of a new license (or other disposition)
does not take place on or before April
30, 2008, notice is hereby given that,
pursuant to 18 CFR 16.18(c), an annual
license under section 15(a)(1) of the
FPA is renewed automatically without
further order or notice by the
Commission, unless the Commission
orders otherwise. If the project is not
subject to section 15 of the FPA, notice
is hereby given that Chugach Electric
Association, is authorized to continue
operation of the Cooper Lake Project
until such time as the Commission acts
on its application for a subsequent
license.
Kimberly D. Bose,
Secretary.
[FR Doc. E7–8839 Filed 5–8–07; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\09MYN1.SGM
09MYN1
Agencies
[Federal Register Volume 72, Number 89 (Wednesday, May 9, 2007)]
[Notices]
[Page 26348]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-8839]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2170]
Chugach Electric Association; Notice of Authorization for
Continued Project Operation
May 2, 2007.
On April 22, 2005, Chugach Electric Association, licensee for the
Cooper Lake Hydroelectric Project, filed an application for a new or
subsequent license pursuant to the Federal Power Act (FPA) and the
Commission's regulations thereunder. The Cooper Lake Project is located
on the Cooper Lake in South Central Alaska near Anchorage, AK.
The license for Project No. 2170 was issued for a period ending
April 30, 2007. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1),
requires the Commission, at the expiration of a license term, to issue
from year-to-year an annual license to the then licensee under the
terms and conditions of the prior license until a new license is
issued, or the project is otherwise disposed of as provided in section
15 or any other applicable section of the FPA. If the project's prior
license waived the applicability of section 15 of the FPA, then, based
on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c),
and as set forth at 18 CFR 16.21(a), if the licensee of such project
has filed an application for a subsequent license, the licensee may
continue to operate the project in accordance with the terms and
conditions of the license after the minor or minor part license
expires, until the Commission acts on its application. If the licensee
of such a project has not filed an application for a subsequent
license, then it may be required, pursuant to 18 CFR 16.21(b), to
continue project operations until the Commission issues someone else a
license for the project or otherwise orders disposition of the project.
If the project is subject to section 15 of the FPA, notice is
hereby given that an annual license for Project No. 2170 is issued to
Chugach Electric Association, for a period effective May 1, 2007
through April 30, 2008, or until the issuance of a new license for the
project or other disposition under the FPA, whichever comes first. If
issuance of a new license (or other disposition) does not take place on
or before April 30, 2008, notice is hereby given that, pursuant to 18
CFR 16.18(c), an annual license under section 15(a)(1) of the FPA is
renewed automatically without further order or notice by the
Commission, unless the Commission orders otherwise. If the project is
not subject to section 15 of the FPA, notice is hereby given that
Chugach Electric Association, is authorized to continue operation of
the Cooper Lake Project until such time as the Commission acts on its
application for a subsequent license.
Kimberly D. Bose,
Secretary.
[FR Doc. E7-8839 Filed 5-8-07; 8:45 am]