Northern Natural Gas Company; Notice of Intent to Prepare an Environmental Assessment for the Proposed Redfield Expansion 2008 Project and Request for Comments on Environmental Issues, 19922-19923 [E7-7508]

Download as PDF 19922 Federal Register / Vol. 72, No. 76 / Friday, April 20, 2007 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [ Docket No. CP07–108–000] Northern Natural Gas Company; Notice of Intent to Prepare an Environmental Assessment for the Proposed Redfield Expansion 2008 Project and Request for Comments on Environmental Issues April 16, 2007. sroberts on PROD1PC70 with NOTICES The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the Redfield Expansion 2008 Project involving construction, relocation, and operation of facilities by Northern Natural Gas Company (Northern) in and to an existing gas storage field in Dallas County, Iowa.1 This EA will be used by the Commission in its decision-making process to determine whether the project is in the public convenience and necessity. If you are a landowner receiving this notice, you may be contacted by a pipeline company representative about the acquisition of an easement to construct, operate, and maintain the proposed facilities. The pipeline company would seek to negotiate a mutually acceptable agreement. However, if the project is approved by the Commission, that approval conveys with it the right of eminent domain. Therefore, if easement negotiations fail to produce an agreement, the pipeline company could initiate condemnation proceedings in accordance with state law. A fact sheet prepared by the FERC entitled ‘‘An Interstate Natural Gas Facility On My Land? What Do I Need To Know?’’ was attached to the project notice that Northern provided to landowners. This fact sheet addresses a number of typically asked questions, including the use of eminent domain and how to participate in the Commission’s proceedings. It is available for viewing on the FERC Internet Web site (https://www.ferc.gov). Summary of the Proposed Project Northern is proposing to expand its firm cycle capacity at the existing Redfield Storage Field by 8.0 billion cubic feet (Bcf) of storage capacity, supported by about 17.95 Bcf of cushion gas capacity, and be capable of injecting gas at maximum rate of 1.0 Bcf per day 1 Northern’s application was filed with the Commission under Section 7 of the Natural Gas Act. VerDate Aug<31>2005 18:52 Apr 19, 2007 Jkt 211001 and withdrawing and delivering gas at a maximum rate of 2.5 Bcf per day. Northern seeks authority to undertake the following construction-related activities in Dallas County, Iowa: • Drill and complete five new injection/withdrawal wells; • Convert eight existing wells from single completion to dual completion; • Install new separators, water pump valves, drain lines, line heaters, surface piping, and buildings at the thirteen (above) wells, and install about 2,400 feet of 6-inch-diameter pipeline to connect those wells to existing storage field pipelines; • Install a new 16-inch control valve, dehydration tower, filter separator, and appurtenant facilities on the Mt. Simon system; • Install a new dehydration tower and appurtenant facilities on the St. Peter system; • Install additional gas treatment facilities at the existing Redfield Compressor Station to remove hydrogen sulfide; • Abandon a 6,960-horsepower (hp) Solar Taurus 60S–T7000 simple cycle gas turbine driving a C–33 compressor and a 1,400-hp Waukesha L7042GSI engine driving an Ariel reciprocating compressor, as well as suction scrubbers, suction/discharge headers, valves, coolers, mufflers, and filters from the Sublette Compressor Station in Seward County, Kansas, and reinstall those facilities at the Redfield Compressor Station along with associated controls; • Use two staging areas within the Redfield Compressor Station property; and • Install three new access roads totaling about 2,200 feet. The location of the project facilities is shown in Appendix 1.2 Land Requirements for Construction Construction of the proposed facilities would require about 259.1 acres of land. Following construction, about 3.5 acres would be maintained as new aboveground facility sites and permanent rights-of-way. The remaining 255.6 acres of land would be restored and allowed to revert to its former use. 2 The appendices referenced in this notice are not being printed in the Federal Register. Copies of all appendices, other than Appendix 1 (maps), are available on the Commission’s Web site at the ‘‘eLibrary’’ link or from the Commission’s Public Reference Room, 888 First Street, NE., Washington, DC 20426, or call (202) 502–8371. For instructions on connecting to eLibrary refer to the last page of this notice. Copies of the appendices were sent to all those receiving this notice in the mail. PO 00000 Frm 00047 Fmt 4703 Sfmt 4703 The EA Process The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental impacts that could result from an action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. NEPA also requires us to discover and address concerns the public may have about proposals. This process is referred to as ‘‘scoping’’. The main goal of the scoping process is to focus the analysis in the EA on the important environmental issues. By this Notice of Intent, the Commission staff requests public comments on the scope of the issues to address in the EA. All comments received are considered during the preparation of the EA. State and local government representatives are encouraged to notify their constituents of this proposed action and encourage them to comment on their areas of concern. In the EA we 3 will discuss impacts that could occur as a result of the construction and operation of the proposed project under these general headings: • geology and soils • land use • water resources, fisheries, and wetlands • cultural resources • vegetation and wildlife • air quality and noise • endangered and threatened species • hazardous waste • public safety We will also evaluate possible alternatives to the proposed project or portions of the project, and make recommendations on how to lessen or avoid impacts on the various resource areas. Our independent analysis of the issues will be in the EA. Depending on the comments received during the scoping process, the EA may be published and mailed to federal, state, and local agencies, public interest groups, interested individuals, affected landowners, newspapers, libraries, and the Commission’s official service list for this proceeding. A comment period will be allotted for review if the EA is published. We will consider all comments on the EA before we make our recommendations to the Commission. To ensure your comments are considered, please carefully follow the instructions in the public participation section below. 3 ‘‘We’’, ‘‘us’’, and ‘‘our’’ refer to the environmental staff of the Office of Energy Projects (OEP). E:\FR\FM\20APN1.SGM 20APN1 Federal Register / Vol. 72, No. 76 / Friday, April 20, 2007 / Notices Public Participation You can make a difference by providing us with your specific comments or concerns about the project. By becoming a commentor, your concerns will be addressed in the EA and considered by the Commission. You should focus on the potential environmental effects of the proposal, alternatives to the proposal, and measures to avoid or lessen environmental impact. The more specific your comments, the more useful they will be. Please carefully follow these instructions to ensure that your comments are received in time and properly recorded: • Send an original and two copies of your letter to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First St., NE., Room 1A, Washington, DC 20426. • Label one copy of the comments for the attention of Gas Branch 3. • Reference Docket No. CP07–108– 000. • Mail your comments so that they will be received in Washington, DC on or before May 18, 2007. The Commission strongly encourages electronic filing of any comments or interventions or protests to this proceeding. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site at https://www.ferc.gov under the ‘‘eFiling’’ link and the link to the User’s Guide. Before you can file comments you will need to create a free account which can be created on-line. We may mail the EA for comment. If you are interested in receiving it, please return the Information Request (Appendix 3). If you do not return the Information Request, you will be taken off the mailing list. sroberts on PROD1PC70 with NOTICES Becoming an Intervenor In addition to involvement in the EA scoping process, you may want to become an official party to the proceeding, or ‘‘intervenor’’. To become an intervenor you must file a motion to intervene according to Rule 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.214). Intervenors have the right to seek rehearing of the Commission’s decision. Motions to Intervene should be electronically submitted using the Commission’s eFiling system at https://www.ferc.gov. Persons without Internet access should send an original and 14 copies of their motion to the Secretary of the Commission at the address indicated previously. Persons filing Motions to Intervene on or before the comment deadline indicated above must send a VerDate Aug<31>2005 18:52 Apr 19, 2007 Jkt 211001 copy of the motion to the Applicant. All filings, including late interventions, submitted after the comment deadline must be served on the Applicant and all other intervenors identified on the Commission’s service list for this proceeding. Persons on the service list with email addresses may be served electronically; others must be served a hard copy of the filing. Affected landowners and parties with environmental concerns may be granted intervenor status upon showing good cause by stating that they have a clear and direct interest in this proceeding which would not be adequately represented by any other parties. You do not need intervenor status to have your environmental comments considered. Environmental Mailing List An effort is being made to send this notice to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed project. This includes all landowners who are potential right-ofway grantors, whose property may be used temporarily for project purposes, or who own homes within distances defined in the Commission’s regulations of certain aboveground facilities. By this notice we are also asking governmental agencies, especially those in Appendix 2, to express their interest in becoming cooperating agencies for the preparation of the EA. Additional Information Additional information about the project is available from the Commission’s Office of External Affairs, at 1–866–208-FERC or on the FERC Internet Web site (www.ferc.gov) using the eLibrary link. Click on the eLibrary link, click on ‘‘General Search’’ and enter the docket number excluding the last three digits in the Docket Number field. Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at 1–866–208–3676, or for TTY, contact (202)502–8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission now offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries and direct links to the documents. Go to https:// www.ferc.gov/esubscribenow.htm. PO 00000 Frm 00048 Fmt 4703 Sfmt 4703 19923 Finally, public meetings or site visits will be posted on the Commission’s calendar located at https://www.ferc.gov/ EventCalendar/EventsList.aspx along with other related information. Philis J. Posey, Deputy Secretary. [FR Doc. E7–7508 Filed 4–19–07; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Notice of Application Accepted for Filing and Soliciting Comments, Protests, and Motions To Intervene April 16, 2007. Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Type of Application: Preliminary Permit. b. Project No.: 12784–000. c. Date filed: March 8, 2007. d. Applicant: Mt. Hope Waterpower Project LP. e. Name and Location of Project: The Mount Hope Pumped Storage Project would use water from the Mt. Hope Mine and would be built in the vicinity of Rockaway Township in Morris County, New Jersey. f. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)–825(r). g. Applicant contact: Mr. Sam Ramiz, Mt. Hope Waterpower Project LP, 627 Mt. Hope Road, Wharton, NJ 07885– 2837, (201) 361–1072. h. FERC Contact: Tom Papsidero, (202) 502–6002. i. Deadline for filing comments, protests, and motions to intervene: 60 days from the issuance date of this notice. All documents (original and eight copies) should be filed with Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. Comments, protests and interventions may be filed electronically via the Internet in lieu of paper; see 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. The Commission strongly encourages electronic filings. Please include the project number (P– 12784–000) on any comments or motions filed. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person in the official service list E:\FR\FM\20APN1.SGM 20APN1

Agencies

[Federal Register Volume 72, Number 76 (Friday, April 20, 2007)]
[Notices]
[Pages 19922-19923]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-7508]



[[Page 19922]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[ Docket No. CP07-108-000]


Northern Natural Gas Company; Notice of Intent to Prepare an 
Environmental Assessment for the Proposed Redfield Expansion 2008 
Project and Request for Comments on Environmental Issues

April 16, 2007.
    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the Redfield Expansion 2008 
Project involving construction, relocation, and operation of facilities 
by Northern Natural Gas Company (Northern) in and to an existing gas 
storage field in Dallas County, Iowa.\1\ This EA will be used by the 
Commission in its decision-making process to determine whether the 
project is in the public convenience and necessity.
---------------------------------------------------------------------------

    \1\ Northern's application was filed with the Commission under 
Section 7 of the Natural Gas Act.
---------------------------------------------------------------------------

    If you are a landowner receiving this notice, you may be contacted 
by a pipeline company representative about the acquisition of an 
easement to construct, operate, and maintain the proposed facilities. 
The pipeline company would seek to negotiate a mutually acceptable 
agreement. However, if the project is approved by the Commission, that 
approval conveys with it the right of eminent domain. Therefore, if 
easement negotiations fail to produce an agreement, the pipeline 
company could initiate condemnation proceedings in accordance with 
state law.
    A fact sheet prepared by the FERC entitled ``An Interstate Natural 
Gas Facility On My Land? What Do I Need To Know?'' was attached to the 
project notice that Northern provided to landowners. This fact sheet 
addresses a number of typically asked questions, including the use of 
eminent domain and how to participate in the Commission's proceedings. 
It is available for viewing on the FERC Internet Web site (https://
www.ferc.gov).

Summary of the Proposed Project

    Northern is proposing to expand its firm cycle capacity at the 
existing Redfield Storage Field by 8.0 billion cubic feet (Bcf) of 
storage capacity, supported by about 17.95 Bcf of cushion gas capacity, 
and be capable of injecting gas at maximum rate of 1.0 Bcf per day and 
withdrawing and delivering gas at a maximum rate of 2.5 Bcf per day. 
Northern seeks authority to undertake the following construction-
related activities in Dallas County, Iowa:
     Drill and complete five new injection/withdrawal wells;
     Convert eight existing wells from single completion to 
dual completion;
     Install new separators, water pump valves, drain lines, 
line heaters, surface piping, and buildings at the thirteen (above) 
wells, and install about 2,400 feet of 6-inch-diameter pipeline to 
connect those wells to existing storage field pipelines;
     Install a new 16-inch control valve, dehydration tower, 
filter separator, and appurtenant facilities on the Mt. Simon system;
     Install a new dehydration tower and appurtenant facilities 
on the St. Peter system;
     Install additional gas treatment facilities at the 
existing Redfield Compressor Station to remove hydrogen sulfide;
     Abandon a 6,960-horsepower (hp) Solar Taurus 60S-T7000 
simple cycle gas turbine driving a C-33 compressor and a 1,400-hp 
Waukesha L7042GSI engine driving an Ariel reciprocating compressor, as 
well as suction scrubbers, suction/discharge headers, valves, coolers, 
mufflers, and filters from the Sublette Compressor Station in Seward 
County, Kansas, and reinstall those facilities at the Redfield 
Compressor Station along with associated controls;
     Use two staging areas within the Redfield Compressor 
Station property; and
     Install three new access roads totaling about 2,200 feet.
    The location of the project facilities is shown in Appendix 1.\2\
---------------------------------------------------------------------------

    \2\ The appendices referenced in this notice are not being 
printed in the Federal Register. Copies of all appendices, other 
than Appendix 1 (maps), are available on the Commission's Web site 
at the ``eLibrary'' link or from the Commission's Public Reference 
Room, 888 First Street, NE., Washington, DC 20426, or call (202) 
502-8371. For instructions on connecting to eLibrary refer to the 
last page of this notice. Copies of the appendices were sent to all 
those receiving this notice in the mail.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction of the proposed facilities would require about 259.1 
acres of land. Following construction, about 3.5 acres would be 
maintained as new aboveground facility sites and permanent rights-of-
way. The remaining 255.6 acres of land would be restored and allowed to 
revert to its former use.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and Necessity. NEPA also requires us 
to discover and address concerns the public may have about proposals. 
This process is referred to as ``scoping''. The main goal of the 
scoping process is to focus the analysis in the EA on the important 
environmental issues. By this Notice of Intent, the Commission staff 
requests public comments on the scope of the issues to address in the 
EA. All comments received are considered during the preparation of the 
EA. State and local government representatives are encouraged to notify 
their constituents of this proposed action and encourage them to 
comment on their areas of concern.
    In the EA we \3\ will discuss impacts that could occur as a result 
of the construction and operation of the proposed project under these 
general headings:
---------------------------------------------------------------------------

    \3\ ``We'', ``us'', and ``our'' refer to the environmental staff 
of the Office of Energy Projects (OEP).
---------------------------------------------------------------------------

     geology and soils
     land use
     water resources, fisheries, and wetlands
     cultural resources
     vegetation and wildlife
     air quality and noise
     endangered and threatened species
     hazardous waste
     public safety
    We will also evaluate possible alternatives to the proposed project 
or portions of the project, and make recommendations on how to lessen 
or avoid impacts on the various resource areas.
    Our independent analysis of the issues will be in the EA. Depending 
on the comments received during the scoping process, the EA may be 
published and mailed to federal, state, and local agencies, public 
interest groups, interested individuals, affected landowners, 
newspapers, libraries, and the Commission's official service list for 
this proceeding. A comment period will be allotted for review if the EA 
is published. We will consider all comments on the EA before we make 
our recommendations to the Commission.
    To ensure your comments are considered, please carefully follow the 
instructions in the public participation section below.

[[Page 19923]]

Public Participation

    You can make a difference by providing us with your specific 
comments or concerns about the project. By becoming a commentor, your 
concerns will be addressed in the EA and considered by the Commission. 
You should focus on the potential environmental effects of the 
proposal, alternatives to the proposal, and measures to avoid or lessen 
environmental impact. The more specific your comments, the more useful 
they will be. Please carefully follow these instructions to ensure that 
your comments are received in time and properly recorded:
     Send an original and two copies of your letter to: 
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 
First St., NE., Room 1A, Washington, DC 20426.
     Label one copy of the comments for the attention of Gas 
Branch 3.
     Reference Docket No. CP07-108-000.
     Mail your comments so that they will be received in 
Washington, DC on or before May 18, 2007.
    The Commission strongly encourages electronic filing of any 
comments or interventions or protests to this proceeding. See 18 CFR 
385.2001(a)(1)(iii) and the instructions on the Commission's Web site 
at https://www.ferc.gov under the ``e-Filing'' link and the link to the 
User's Guide. Before you can file comments you will need to create a 
free account which can be created on-line.
    We may mail the EA for comment. If you are interested in receiving 
it, please return the Information Request (Appendix 3). If you do not 
return the Information Request, you will be taken off the mailing list.

Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want 
to become an official party to the proceeding, or ``intervenor''. To 
become an intervenor you must file a motion to intervene according to 
Rule 214 of the Commission's Rules of Practice and Procedure (18 CFR 
385.214). Intervenors have the right to seek rehearing of the 
Commission's decision. Motions to Intervene should be electronically 
submitted using the Commission's eFiling system at https://www.ferc.gov. 
Persons without Internet access should send an original and 14 copies 
of their motion to the Secretary of the Commission at the address 
indicated previously. Persons filing Motions to Intervene on or before 
the comment deadline indicated above must send a copy of the motion to 
the Applicant. All filings, including late interventions, submitted 
after the comment deadline must be served on the Applicant and all 
other intervenors identified on the Commission's service list for this 
proceeding. Persons on the service list with email addresses may be 
served electronically; others must be served a hard copy of the filing.
    Affected landowners and parties with environmental concerns may be 
granted intervenor status upon showing good cause by stating that they 
have a clear and direct interest in this proceeding which would not be 
adequately represented by any other parties. You do not need intervenor 
status to have your environmental comments considered.

Environmental Mailing List

    An effort is being made to send this notice to all individuals, 
organizations, and government entities interested in and/or potentially 
affected by the proposed project. This includes all landowners who are 
potential right-of-way grantors, whose property may be used temporarily 
for project purposes, or who own homes within distances defined in the 
Commission's regulations of certain aboveground facilities. By this 
notice we are also asking governmental agencies, especially those in 
Appendix 2, to express their interest in becoming cooperating agencies 
for the preparation of the EA.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at 1-866-208-FERC or on the 
FERC Internet Web site (www.ferc.gov) using the eLibrary link. Click on 
the eLibrary link, click on ``General Search'' and enter the docket 
number excluding the last three digits in the Docket Number field. Be 
sure you have selected an appropriate date range. For assistance, 
please contact FERC Online Support at FercOnlineSupport@ferc.gov or 
toll free at 1-866-208-3676, or for TTY, contact (202)502-8659. The 
eLibrary link also provides access to the texts of formal documents 
issued by the Commission, such as orders, notices, and rulemakings.
    In addition, the Commission now offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries and direct links to 
the documents. Go to https://www.ferc.gov/esubscribenow.htm.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at https://www.ferc.gov/EventCalendar/
EventsList.aspx along with other related information.

Philis J. Posey,
Deputy Secretary.
[FR Doc. E7-7508 Filed 4-19-07; 8:45 am]
BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.