Download as PDF cprice-sewell on PROD1PC66 with NOTICES 18972 Federal Register / Vol. 72, No. 72 / Monday, April 16, 2007 / Notices c. Date Filed: March 30, 2007. d. Applicant: Pacific Gas and Electric Company. e. Name of Project: Sly Creek Transmission Line Project. f. Location: The Sly Creek Transmission Line Project is located in the Sierra Nevada Range, Butte County, California. The project is located about 15 miles east of Oroville, California and is not located within any designated cities, towns, subdivisions or Indian reservations. The project affects less than 2 acres of federal lands administered by the Plumas National Forest. g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Forrest Sullivan, Project Manager, Pacific Gas and Electric Company, 5555 FlorinPerkins Road, Building 500, Sacramento, CA, 95826. Tel: (916) 386– 5580. i. FERC Contact: John Mudre, (202) 502–8902, or john.mudre@ferc.gov. j. Cooperating Agencies: We are asking Federal, state, local, and tribal agencies with jurisdiction and/or special expertise with respect to environmental issues to cooperate with us in the preparation of the environmental document. Agencies who would like to request cooperating status should follow the instructions for filing such requests described in item l below. Cooperating agencies should note the Commission’s policy that agencies that cooperate in the preparation of the environmental document cannot also intervene. See, 94 FERC ¶ 61,076 (2001). k. Study Request Deadline: Pursuant to Section 4.32(b)(7) of 18 CFR of the Commission’s regulations, if any resource agency, Indian Tribe, or person believes that an additional scientific study should be conducted in order to form an adequate factual basis for a complete analysis of the application on its merit, the resource agency, Indian Tribe, or person must file a request for a study with the Commission not later than 60 days from the date of filing of the application, and serve a copy of the request on the applicant. l. Deadline for filing requests for cooperating agency status and additional study requests: May 29, 2007. All documents (original and eight copies) should be filed with: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. Additional study requests and requests for cooperating agency status may be filed electronically via the Internet in lieu of paper. The Commission strongly encourages electronic filings. See 18 CFR VerDate Aug<31>2005 15:24 Apr 13, 2007 Jkt 211001 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site (https:// www.ferc.gov) under the ‘‘e-Filing’’ link. m. Status: This application has not been accepted for filing and is not ready for environmental analysis. We are not soliciting motions to intervene, protests, or final terms and conditions at this time. n. Project Description: The Sly Creek Transmission Line Project is a constructed transmission line only project that transmits electricity 5.4 miles from the Sly Creek Powerhouse (owned and operated by the South Feather Water and Power Agency under FERC Project No. 2088) to Pacific Gas and Electric Company’s WoodleafKanaka Junction Transmission Line Project (FERC Project No. 2281). The Sly Creek Powerhouse is a component of the South Feather Power Project which is a water supply/power project constructed in the late 1950s/early 1960s. The transmission line project consists of an existing single-circuit, 115 kV transmission line, supported primarily on wood-pole, H-frame structures within a 75-foot right-of-way, and appurtenant facilities. o. Application Availability: A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY, (202) 502–8659. A copy is also available for inspection and reproduction at the address in item h above. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. p. Consultation: With this notice, we are initiating consultation with the California State Historic Preservation Officer (SHPO), as required by § 106, National Historic Preservation Act, and the regulations of the Advisory Council on Historic Preservation, 36, CFR, at § 800.4. q. Procedural schedule and final amendments: The application will be processed according to the following schedule. Revisions to the schedule will be made as appropriate. Issue Deficiency or Acceptance letter: May 2007. PO 00000 Frm 00026 Fmt 4703 Sfmt 4703 Issue Scoping Document for comments: June 2007. Hold Scoping Meetings/Site Visit: June 2007. Request Additional Information, if needed: July 2007. Notice of application ready for environmental analysis: August 2007. Notice of the availability of the EA: February 2008. Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis. Kimberly D. Bose, Secretary. [FR Doc. E7–7162 Filed 4–13–07; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 606–000] Pacific Gas and Electric Company (PG&E); Notice of Authorization for Continued Project Operation April 10, 2007. On March 23, 2007, the Pacific Gas and Electric Company, licensee for the Kilarc-Cow Creek Hydroelectric Project, filed a Proposed License Surrender Application Schedule. The Kilarc-Cow Creek Project is located on the Old Cow Creek and South Cow Creek in Shasta County, California. The license for Project No. 606 was issued for a period ending March 27, 2007. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), requires the Commission, at the expiration of a license term, to issue from year-to-year an annual license to the then licensee under the terms and conditions of the prior license until a new license is issued, or the project is otherwise disposed of as provided in section 15 or any other applicable section of the FPA. Notice is hereby given that an annual license for Project No. 606 is issued to the Pacific Gas and Electric Company for a period effective April 2, 2007 through March 31, 2008, or until the issuance of a new license for the project or other disposition under the FPA, whichever comes first. If issuance of a new license (or other disposition) does not take place on or before March 31, 2008, notice is hereby given that, pursuant to 18 CFR 16.18(c), an annual license under section 15(a)(1) of the FPA is renewed automatically without further order or notice by the E:\FR\FM\16APN1.SGM 16APN1 Federal Register / Vol. 72, No. 72 / Monday, April 16, 2007 / Notices Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Intervention and Protest Date: 5 p.m. Eastern Time April 17, 2007. Commission, unless the Commission orders otherwise. Kimberly D. Bose, Secretary. [FR Doc. E7–7163 Filed 4–13–07; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Kimberly D. Bose, Secretary. [FR Doc. E7–7168 Filed 4–13–07; 8:45 am] [Docket No. RP07–394–000] Panther Interstate Pipeline Energy, LLC; Notice of Cost and Revenue Study BILLING CODE 6717–01–P DEPARTMENT OF ENERGY cprice-sewell on PROD1PC66 with NOTICES April 10, 2007. Take notice that on April 2, 2007, Panther Interstate Pipeline Energy, LLC, (Panther Interstate) tendered for filing its cost and revenue study in compliance with the Commission order issued on December 24, 2003 in this docket. Panther Interstate states that the cost and revenue study follows the Commission’s regulations at 18 CFR 154.313 and is based on the twelve months ending December 31, 2006. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the date as indicated below. Anyone filing an intervention or protest must serve a copy of that document on the Applicant. Anyone filing an intervention or protest on or before the intervention or protest date need not serve motions to intervene or protests on persons other than the Applicant. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. This filing is accessible online at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the VerDate Aug<31>2005 15:24 Apr 13, 2007 Jkt 211001 Federal Energy Regulatory Commission [Docket No. RP07–339–000] Texas Gas Transmission, LLC; Notice of Technical Conference April 10, 2007. The Commission’s Order issued March 29, 2007,1 directed that a technical conference be held to investigate all aspects of Texas Gas Transmission, LLC’s proposal to amend its tariff with respect to the capacity allocation method for its supply laterals. Take notice that a technical conference will be held on Tuesday, April 17, 2007 at 10 a.m., in a room to be designated at the offices of the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC. 20426. FERC conferences are accessible under section 508 of the Rehabilitation Act of 1973. For accessibility accommodations please send an e-mail to accessibility@ferc.gov or call toll free (866) 208–3372 (voice) or 202–502–8659 (TTY), or send a fax to 202–208–2106 with the required accommodations. All interested persons are permitted to attend. For further information please contact Jacob Silverman at (202) 502– 8445 or e-mail Jacob silverman@ferc.gov. All interested parties and staff are permitted to attend. Kimberly D. Bose, Secretary. [FR Doc. E7–7166 Filed 4–13–07; 8:45 am] BILLING CODE 6717–01–P 1 Texas Gas Transmission, LLC, 118 FERC ¶ 61,259 (2007). PO 00000 Frm 00027 Fmt 4703 Sfmt 4703 18973 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. RP07–178–001] Transcontinental Gas Pipe Line Corporation; Notice of Compliance Filing April 10, 2007. Take notice that, on March 28, 2007, Transcontinental Gas Pipe Line Corporation (Transco) submitted a compliance filing pursuant to the Commission’s Order Accepting Tariff Sheets Subject to Conditions issued on March 22, 2007 in Docket No. RP07– 178–000. Transco states that copies of the filing were served on parties on the official service list in the above-captioned proceeding. Any person desiring to protest this filing must file in accordance with Rule 211 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211). Protests to this filing will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Such protests must be filed in accordance with the provisions of Section 154.210 of the Commission’s regulations (18 CFR 154.210). Anyone filing a protest must serve a copy of that document on all the parties to the proceeding. The Commission encourages electronic submission of protests in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. This filing is accessible online at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Kimberly D. Bose, Secretary. [FR Doc. E7–7165 Filed 4–13–07; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\16APN1.SGM 16APN1

Agencies

[Federal Register Volume 72, Number 72 (Monday, April 16, 2007)]
[Notices]
[Pages 18972-18973]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-7163]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 606-000]


Pacific Gas and Electric Company (PG&E); Notice of Authorization 
for Continued Project Operation

April 10, 2007.
    On March 23, 2007, the Pacific Gas and Electric Company, licensee 
for the Kilarc-Cow Creek Hydroelectric Project, filed a Proposed 
License Surrender Application Schedule. The Kilarc-Cow Creek Project is 
located on the Old Cow Creek and South Cow Creek in Shasta County, 
California.
    The license for Project No. 606 was issued for a period ending 
March 27, 2007. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), 
requires the Commission, at the expiration of a license term, to issue 
from year-to-year an annual license to the then licensee under the 
terms and conditions of the prior license until a new license is 
issued, or the project is otherwise disposed of as provided in section 
15 or any other applicable section of the FPA.
    Notice is hereby given that an annual license for Project No. 606 
is issued to the Pacific Gas and Electric Company for a period 
effective April 2, 2007 through March 31, 2008, or until the issuance 
of a new license for the project or other disposition under the FPA, 
whichever comes first. If issuance of a new license (or other 
disposition) does not take place on or before March 31, 2008, notice is 
hereby given that, pursuant to 18 CFR 16.18(c), an annual license under 
section 15(a)(1) of the FPA is renewed automatically without further 
order or notice by the

[[Page 18973]]

Commission, unless the Commission orders otherwise.

Kimberly D. Bose,
Secretary.
 [FR Doc. E7-7163 Filed 4-13-07; 8:45 am]
BILLING CODE 6717-01-P