Download as PDF 18470 Federal Register / Vol. 72, No. 70 / Thursday, April 12, 2007 / Notices Trout Unlimited’s motion for late intervention is rejected.3 Philis J. Posey, Acting Secretary. [FR Doc. E7–6916 Filed 4–11–07; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Notice of Application Accepted for Filing and Soliciting Motions To Intervene, Protests, and Comments rmajette on PROD1PC67 with NOTICES April 6, 2007. Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Type of Application: Preliminary Permit. b. Project No.: 12770–000. c. Date Filed: January 30, 2007. d. Applicant: Lockhart Power Company. e. Name of Project: Upper Pacolet Project. f. Location: On the Pacolet River, in Spartanburg County, South Carolina. g. Filed Pursuant to: Federal Power Act, 16 USC. 791(a)–825(r). h. Applicant Contact: Bryan Stone, Lockhart Power Company, P.O. Box 10, 420 River Street, Lockhart, SC 29364, (864) 545–2211. i. FERC Contact: Robert Bell, (202) 502–6062. j. Deadline for filing comments, protests, and motions to intervene: 60 days from the issuance date of this notice. All documents (original and eight copies) should be filed with: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. Comments, protests, and interventions may be filed electronically via the Internet in lieu of paper; see 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. The Commission strongly encourages electronic filings. Please include the project number (P– 12770–000) on any comments or motions filed. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person in the official service list 3 If the Moriah files a license application, public notice will be issued; and Trout Unlimited will have an opportunity to intervene and comment on the proposed project. VerDate Aug<31>2005 15:49 Apr 11, 2007 Jkt 211001 for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. Description of Project: The proposed project would consist of: (1) An existing 370-foot-long, 22-foot-high Upper Pacolet Dam, (2) an existing impoundment having a surface area of 25 acres, with a storage capacity of 220 acre-feet and normal water surface elevation of 520.5 feet mean sea level, (3) a proposed power house containing two generating units having a total installed capacity of 850 kilowatts, (4) a proposed 1000-foot-long, 34.5 kilovolt transmission line, and (5) appurtenant facilities. The proposed project would have an estimated average annual generation of 5.07 gigawatt-hours, which would be sold to a local utility. l. Location of Application: This filing is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, call toll-free 1–866–208– 3676 or e-mail FERCOnlineSupport@ferc.gov. For TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item h above. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Competing Preliminary Permit: Anyone desiring to file a competing application for preliminary permit for a proposed project must submit the competing application itself, or a notice of intent to file such an application, to the Commission on or before the specified comment date for the particular application (see 18 CFR 4.36). Submission of a timely notice of intent allows an interested person to file the competing preliminary permit application no later than 30 days after the specified comment date for the particular application. A competing preliminary permit application must conform with 18 CFR 4.30(b) and 4.36. o. Competing Development Application: Any qualified development applicant desiring to file a competing development application must submit to the Commission, on or before a specified comment date for the particular application, either a competing development application or a PO 00000 Frm 00014 Fmt 4703 Sfmt 4703 notice of intent to file such an application. Submission of a timely notice of intent to file a development application allows an interested person to file the competing application no later than 120 days after the specified comment date for the particular application. A competing license application must conform with 18 CFR 4.30(b) and 4.36. p. Notice of Intent: A notice of intent must specify the exact name, business address, and telephone number of the prospective applicant, and must include an unequivocal statement of intent to submit, if such an application may be filed, either a preliminary permit application or a development application (specify which type of application). A notice of intent must be served on the applicant(s) named in this public notice. q. Proposed Scope of Studies Under Permit: A preliminary permit, if issued, does not authorize construction. The term of the proposed preliminary permit would be 36 months. The work proposed under the preliminary permit would include economic analysis, preparation of preliminary engineering plans, and a study of environmental impacts. Based on the results of these studies, the Applicant would decide whether to proceed with the preparation of a development application to construct and operate the project. r. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, 385.211, 385.214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. s. Filing and Service of Responsive Documents: Any filings must bear in all capital letters the title ‘‘COMMENTS’’, ‘‘NOTICE OF INTENT TO FILE COMPETING APPLICATION’’, ‘‘COMPETING APPLICATION’’, ‘‘PROTEST’’, and ‘‘MOTION TO INTERVENE’’, as applicable, and the Project Number of the particular application to which the filing refers. Any of the above-named documents must be filed by providing the original and the number of copies provided by the Commission’s regulations to: The Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., E:\FR\FM\12APN1.SGM 12APN1 Federal Register / Vol. 72, No. 70 / Thursday, April 12, 2007 / Notices Washington, DC 20426. An additional copy must be sent to Director, Division of Hydropower Administration and Compliance, Federal Energy Regulatory Commission, at the above-mentioned address. A copy of any notice of intent, competing application or motion to intervene must also be served upon each representative of the Applicant specified in the particular application. t. Agency Comments: Federal, state, and local agencies are invited to file comments on the described application. A copy of the application may be obtained by agencies directly from the Applicant. If an agency does not file comments within the time specified for filing comments, it will be presumed to have no comments. One copy of an agency’s comments must also be sent to the Applicant’s representatives. Philis J. Posey, Acting Secretary. [FR Doc. E7–6918 Filed 4–11–07; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Notice of Application Accepted for Filing and Soliciting Motions To Intervene, Protests, and Comments rmajette on PROD1PC67 with NOTICES April 6, 2007. Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Type of Application: Preliminary Permit. b. Project No.: 12777–000. c. Date Filed: February 13, 2007. d. Applicant: Maine Maritime Academy. e. Name of Project: Castine Harbor and Bagaduce Narrows Project. f. Location: The project would be located on the Atlantic Ocean and Bagaduce Narrows, in Hancock County, Maine. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Mr. James E. Adamson, Maine Maritime Academy, c/o Mainus Power LLC, 440 Louisiana Street, Suite 625, Houston, TX 77002, Phone (713) 236–0037, ext. 109. i. FERC Contact: Robert Bell, (202) 502–6062. j. Deadline for filing comments, protests, and motions to intervene: 60 days from the issuance date of this notice. All documents (original and eight copies) should be filed with: Kimberly D. Bose, Secretary, Federal Energy VerDate Aug<31>2005 15:49 Apr 11, 2007 Jkt 211001 Regulatory Commission, 888 First Street, NE., Washington, DC 20426. Comments, protests, and interventions may be filed electronically via the Internet in lieu of paper; see 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. The Commission strongly encourages electronic filings. Please include the project number (P– 12770–000) on any comments or motions filed. The Commission’s Rules of Practice and Procedure require all interveners filing documents with the Commission to serve a copy of that document on each person in the official service list for the project. Further, if an intervener files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. Description of Project: The proposed project consists of the following two developments: Castine Harbor Development. Would consist of: (1) From 3 to 50 proposed TESEC generating units having a total installed capacity of 1.3 MW, (2) a proposed short 12.5 kV transmission line, and (3) appurtenant facilities. Bagaduce Narrows Development. Would consist of: (1) From 1 to 21 proposed TESEC generating units having a total installed capacity of 11.5 MW, (2) a proposed 16-mile-long 34.5kV transmission line, and (3) appurtenant facilities. The project would have a maximum average annual generation of 8 gigawatt hours, which would be sold to a local utility. l. Locations of Applications: A copy of the application is available for inspection and reproduction at the Commission in the Public Reference Room, located at 888 First Street, NE., Room 2A, Washington, DC 20426, or by calling (202) 502–8371. This filing may also be viewed on the Commission’s Web site at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, call toll-free 1–866–208–3676 or e-mail FERCOnlineSupport@ferc.gov. For TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item h above. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Competing Preliminary Permit: Anyone desiring to file a competing PO 00000 Frm 00015 Fmt 4703 Sfmt 4703 18471 application for preliminary permit for a proposed project must submit the competing application itself, or a notice of intent to file such an application, to the Commission on or before the specified comment date for the particular application (see 18 CFR 4.36). Submission of a timely notice of intent allows an interested person to file the competing preliminary permit application no later than 30 days after the specified comment date for the particular application. A competing preliminary permit application must conform with 18 CFR 4.30(b) and 4.36. o. Competing Development Application: Any qualified development applicant desiring to file a competing development application must submit to the Commission, on or before a specified comment date for the particular application, either a competing development application or a notice of intent to file such an application. Submission of a timely notice of intent to file a development application allows an interested person to file the competing application no later than 120 days after the specified comment date for the particular application. A competing license application must conform with 18 CFR 4.30(b) and 4.36. p. Notice of Intent: A notice of intent must specify the exact name, business address, and telephone number of the prospective applicant, and must include an unequivocal statement of intent to submit, if such an application may be filed, either a preliminary permit application or a development application (specify which type of application). A notice of intent must be served on the applicant(s) named in this public notice. q. Proposed Scope of Studies Under Permit: A preliminary permit, if issued, does not authorize construction. The term of the proposed preliminary permit would be 36 months. The work proposed under the preliminary permit would include economic analysis, preparation of preliminary engineering plans, and a study of environmental impacts. Based on the results of these studies, the Applicant would decide whether to proceed with the preparation of a development application to construct and operate the project. r. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, 385.211, 385.214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion E:\FR\FM\12APN1.SGM 12APN1

Agencies

[Federal Register Volume 72, Number 70 (Thursday, April 12, 2007)]
[Notices]
[Pages 18470-18471]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-6918]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission


Notice of Application Accepted for Filing and Soliciting Motions 
To Intervene, Protests, and Comments

April 6, 2007.
    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Type of Application: Preliminary Permit.
    b. Project No.: 12770-000.
    c. Date Filed: January 30, 2007.
    d. Applicant: Lockhart Power Company.
    e. Name of Project: Upper Pacolet Project.
    f. Location: On the Pacolet River, in Spartanburg County, South 
Carolina.
    g. Filed Pursuant to: Federal Power Act, 16 USC. 791(a)-825(r).
    h. Applicant Contact: Bryan Stone, Lockhart Power Company, P.O. Box 
10, 420 River Street, Lockhart, SC 29364, (864) 545-2211.
    i. FERC Contact: Robert Bell, (202) 502-6062.
    j. Deadline for filing comments, protests, and motions to 
intervene: 60 days from the issuance date of this notice.
    All documents (original and eight copies) should be filed with: 
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 
First Street, NE., Washington, DC 20426. Comments, protests, and 
interventions may be filed electronically via the Internet in lieu of 
paper; see 18 CFR 385.2001(a)(1)(iii) and the instructions on the 
Commission's Web site under the ``e-Filing'' link. The Commission 
strongly encourages electronic filings. Please include the project 
number (P-12770-000) on any comments or motions filed.
    The Commission's Rules of Practice and Procedure require all 
intervenors filing documents with the Commission to serve a copy of 
that document on each person in the official service list for the 
project. Further, if an intervenor files comments or documents with the 
Commission relating to the merits of an issue that may affect the 
responsibilities of a particular resource agency, they must also serve 
a copy of the document on that resource agency.
    k. Description of Project: The proposed project would consist of: 
(1) An existing 370-foot-long, 22-foot-high Upper Pacolet Dam, (2) an 
existing impoundment having a surface area of 25 acres, with a storage 
capacity of 220 acre-feet and normal water surface elevation of 520.5 
feet mean sea level, (3) a proposed power house containing two 
generating units having a total installed capacity of 850 kilowatts, 
(4) a proposed 1000-foot-long, 34.5 kilovolt transmission line, and (5) 
appurtenant facilities. The proposed project would have an estimated 
average annual generation of 5.07 gigawatt-hours, which would be sold 
to a local utility.
    l. Location of Application: This filing is available for review at 
the Commission in the Public Reference Room or may be viewed on the 
Commission's Web site at https://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, call toll-
free 1-866-208-3676 or e-mail FERCOnlineSupport@ferc.gov. For TTY, call 
(202) 502-8659. A copy is also available for inspection and 
reproduction at the address in item h above.
    m. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    n. Competing Preliminary Permit: Anyone desiring to file a 
competing application for preliminary permit for a proposed project 
must submit the competing application itself, or a notice of intent to 
file such an application, to the Commission on or before the specified 
comment date for the particular application (see 18 CFR 4.36). 
Submission of a timely notice of intent allows an interested person to 
file the competing preliminary permit application no later than 30 days 
after the specified comment date for the particular application. A 
competing preliminary permit application must conform with 18 CFR 
4.30(b) and 4.36.
    o. Competing Development Application: Any qualified development 
applicant desiring to file a competing development application must 
submit to the Commission, on or before a specified comment date for the 
particular application, either a competing development application or a 
notice of intent to file such an application. Submission of a timely 
notice of intent to file a development application allows an interested 
person to file the competing application no later than 120 days after 
the specified comment date for the particular application. A competing 
license application must conform with 18 CFR 4.30(b) and 4.36.
    p. Notice of Intent: A notice of intent must specify the exact 
name, business address, and telephone number of the prospective 
applicant, and must include an unequivocal statement of intent to 
submit, if such an application may be filed, either a preliminary 
permit application or a development application (specify which type of 
application). A notice of intent must be served on the applicant(s) 
named in this public notice.
    q. Proposed Scope of Studies Under Permit: A preliminary permit, if 
issued, does not authorize construction. The term of the proposed 
preliminary permit would be 36 months. The work proposed under the 
preliminary permit would include economic analysis, preparation of 
preliminary engineering plans, and a study of environmental impacts. 
Based on the results of these studies, the Applicant would decide 
whether to proceed with the preparation of a development application to 
construct and operate the project.
    r. Comments, Protests, or Motions to Intervene: Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, 
385.211, 385.214. In determining the appropriate action to take, the 
Commission will consider all protests or other comments filed, but only 
those who file a motion to intervene in accordance with the 
Commission's Rules may become a party to the proceeding. Any comments, 
protests, or motions to intervene must be received on or before the 
specified comment date for the particular application.
    s. Filing and Service of Responsive Documents: Any filings must 
bear in all capital letters the title ``COMMENTS'', ``NOTICE OF INTENT 
TO FILE COMPETING APPLICATION'', ``COMPETING APPLICATION'', 
``PROTEST'', and ``MOTION TO INTERVENE'', as applicable, and the 
Project Number of the particular application to which the filing 
refers. Any of the above-named documents must be filed by providing the 
original and the number of copies provided by the Commission's 
regulations to: The Secretary, Federal Energy Regulatory Commission, 
888 First Street, NE.,

[[Page 18471]]

Washington, DC 20426. An additional copy must be sent to Director, 
Division of Hydropower Administration and Compliance, Federal Energy 
Regulatory Commission, at the above-mentioned address. A copy of any 
notice of intent, competing application or motion to intervene must 
also be served upon each representative of the Applicant specified in 
the particular application.
    t. Agency Comments: Federal, state, and local agencies are invited 
to file comments on the described application. A copy of the 
application may be obtained by agencies directly from the Applicant. If 
an agency does not file comments within the time specified for filing 
comments, it will be presumed to have no comments. One copy of an 
agency's comments must also be sent to the Applicant's representatives.

Philis J. Posey,
Acting Secretary.
 [FR Doc. E7-6918 Filed 4-11-07; 8:45 am]