Georgia Power Company; Notice of Application Tendered for Filing With the Commission and Establishing Procedural Schedule for Licensing and Deadline for Submission of Final Amendments, 12793-12794 [E7-4993]
Download as PDF
ycherry on PROD1PC64 with NOTICES
Federal Register / Vol. 72, No. 52 / Monday, March 19, 2007 / Notices
i. FERC Contact: Stephen Bowler,
(202) 502–6861; or
stephen.bowler@ferc.gov.
j. The deadline for filing comments,
recommendations, terms and
conditions, and prescriptions is 60 days
from the issuance of this notice; reply
comments are due 105 days from the
issuance date of this notice.
All documents (original and eight
copies) should be filed with: Philis J.
Posey, Acting Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
Comments, recommendations, terms
and conditions, and prescriptions may
be filed electronically via the Internet in
lieu of paper. The Commission strongly
encourages electronic filings. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site (https://www.ferc.gov) under the ‘‘eFiling’’ link.
k. This application has been accepted
and is ready for environmental analysis
at this time.
l. The existing Yadkin-Pee Dee Project
consists of the Tillery development on
the Yadkin and Pee Dee Rivers and the
Blewett Falls development on the Pee
Dee River. The Yadkin Pee Dee project
has an installed capacity of 108.6
megawatts (MW). The project produces
an average annual generation of 326,000
megawatt-hours (MWh).
The Tillery development (at River
Mile[RM] 218) includes the following
existing facilities: (1) A 2,753-foot-long,
62-foot-maximum height dam with (i) A
1,200-foot-long earth dike, (ii) a 184foot-long concrete west abutment, (iii) a
731-foot-long gated concrete gravity
spillway with eighteen 34-foot-wide by
24-foot-high Tainter gates, (iv) a 14-footlong by 10-foot-high trash sluice gate,
(v) a 310-foot-long powerhouse integral
with the dam containing three vertical
Francis turbine-generators, one
modified Kaplin-type turbine-generator,
and one vertical Francis auxiliary
turbine-generator with a total generating
capacity of 84 MW, and (vi) a 310-footlong concrete east abutment; (2) a 5,697acre reservoir at normal pool elevation
of 277.3 feet North American Vertical
Datum of 1988 (NAVD 88), with 84,150
acre-feet of usable storage capacity; and
VerDate Aug<31>2005
15:50 Mar 16, 2007
Jkt 211001
(3) appurtenant facilities. The Tillery
development would continue to be
operated as a peaking facility with a
typical drawdown of not more than 4
feet under normal conditions.
The Blewett Falls development (at RM
188.2) includes the following existing
facilities: (1) A 3,168-foot-long dam with
a 870-foot-long easterly earthen
embankment, (i) 1,468-foot-long, 47 foot
average height concrete ogee gravity
spillway topped with four feet wooden
flashboards, (ii) a 850-foot-long westerly
earthen embankment, (iii) a 300-footlong, approximately 100-foot-high
concrete powerhouse containing six
generating units (each unit driven by
two horizontal shaft turbines with each
turbine consisting of two runners) with
a total generating capacity of 24.6 MW;
(2) a 2,866-acre reservoir at normal pool
elevation of 177.2 feet NAVD 88, with
30,893 acre-feet of usable storage
capacity; (3) a 900-foot-long tailrace
channel which reconnects to the Pee
Dee River; and (4) appurtenant facilities.
There is a 1,750-foot-long bypassed
reach between the dam and where the
tailrace channel enters the Pee Dee
River.
Progress Energy proposes to continue
operating the projects in the same
operational mode. Several proposed
modifications to the project include: (1)
Making minor changes in reservoir
elevations during the winter, under
maintenance conditions, and during the
largemouth bass spawning period; (2)
increasing the minimum flow releases
from the Tillery and Blewett Falls
developments and using flow-shaping
releases during fish spawning periods;
(3) implementing fish passage measures,
including trap and truck procedures and
constructing eel passage facilities at the
Blewett Falls development; (4) adopting
a shoreline management policy for the
Blewett Falls development; (5)
improving recreational access, facilities,
and trails, and closing the informal
boating area below the Tillery
development powerhouse and
relocating it; and (6) constructing a new
public boating access site on the east
side of Blewett Falls reservoir.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659. A copy is also available
PO 00000
Frm 00042
Fmt 4703
Sfmt 4703
12793
for inspection and reproduction at the
address in item h above.
All filings must: (1) Bear in all capital
letters the title ‘‘COMMENTS,’’ ‘‘REPLY
COMMENTS,’’
‘‘RECOMMENDATIONS,’’ ‘‘TERMS
AND CONDITIONS,’’ or
‘‘PRESCRIPTIONS;’’ (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person submitting the
filing; and (4) otherwise comply with
the requirements of 18 CFR 385.2001
through 385.2005. All comments,
recommendations, terms and conditions
or prescriptions must set forth their
evidentiary basis and otherwise comply
with the requirements of 18 CFR 4.34(b).
Agencies may obtain copies of the
application directly from the applicant.
Each filing must be accompanied by
proof of service on all persons listed on
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b), and
385.2010.
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. A license applicant must file no
later than 60 days following the date of
issuance of this notice: (1) A copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification.
Philis J. Posey,
Acting Secretary.
[FR Doc. E7–4992 Filed 3–16–07; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No.: P–2237–017]
Georgia Power Company; Notice of
Application Tendered for Filing With
the Commission and Establishing
Procedural Schedule for Licensing and
Deadline for Submission of Final
Amendments
March 13, 2007.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
E:\FR\FM\19MRN1.SGM
19MRN1
12794
Federal Register / Vol. 72, No. 52 / Monday, March 19, 2007 / Notices
a. Type of Application: New Major
License.
b. Project No.: P–2237–017.
c. Date Filed: February 27, 2007.
d. Applicant: Georgia Power
Company.
e. Name of Project: Morgan Falls
Hydroelectric Project.
f. Location: The existing project is
located in the metropolitan city of
Atlanta area on the Chattahoochee
River, at river mile 312.6, and about 36
miles downstream from the U.S. Corps
of Engineers’ Buford dam (Lake Sidney
Lanier) in Cobb and Fulton Counties,
Georgia. The project occupies about 14.4
acres of federal lands within the
Chattahoochee River National
Recreation Area managed by the
National Park Service.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Douglas E.
Jones, Senior Vice-President, Southern
Company Generation, 241 Ralph McGill
Boulevard NE., Bin 10240, Atlanta,
Georgia 30308–3374; Telephone (404)
506–7328; or George A. Martin, Project
Manager, at (404) 506–1357 or e-mail at
gamartin@southernco.com. Additional
information on this project is available
on the applicant’s Web site: https://
www.southerncompany.com/gapower/
hydro/.
i. FERC Contact: Janet Hutzel,
Telephone (202) 502–8675, or e-mail
janet.hutzel@ferc.gov. Additional
information on Federal Energy
Regulatory Commission (FERC)
hydroelectric projects is available on
FERC’s Web site: https://www.ferc.gov/
industries/hydropower.asp.
j. This application is not ready for
environmental analysis at this time.
k. Project Description: The existing
project consists of the following: (1) A
1,031-foot-long, 56-foot-maximum
height concrete gravity dam consisting
of a 46-foot-long non-overflow westerly
abutment; a 680-foot-long gated
spillway with sixteen 40-foot-wide by 8foot-tall Tainter gates; a 21-foot-long
trash gate section containing one 8-footwide by 4-foot-tall trash gate; a 195-footlong, 73-foot-high combined
powerhouse and intake section integral
with the dam containing seven
horizontal double runner Francis
turbines coupled to seven generating
units with a total generating capacity of
16.8 megawatt; and an 89-foot-long nonoverflow easterly abutment; (2) a 684acre reservoir (Bull Sluice Lake) at
normal full pool elevation of 866.0 feet
using plant datum,1 with 2,239 acre-feet
of usable storage; and (3) appurtenant
facilities. The average annual generation
at the project is about 15,221 megawatthours. The applicant has no plans to
modify the existing project facilities or
the current modified run-of-river mode
of operation.
l. Locations of the Application: A
copy of the application is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s Web site at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or tollfree at (866) 208–3676, or for TTY, (202)
502–8659. A copy is also available for
inspection and reproduction at the
address in item (h) above.
m. You may also register online at
https://www.ferc.gov/esubscribenow.htm
to be notified via e-mail of new filings
and issuances related to this or other
pending projects. For assistance, contact
FERC Online Support.
n. Procedural Schedule:
The application will be processed
according to the following Hydro
Licensing Schedule. Revisions to the
schedule may be made as appropriate.
Milestone
Target Date
Notice of Acceptance/ Notice of Ready for Environmental Analysis ........................................................................................
Filing of interventions, recommendations, preliminary terms and conditions, and fishway prescriptions ................................
Reply comments due .................................................................................................................................................................
FERC issues single EA (without a draft) ..................................................................................................................................
Comments on EA due ...............................................................................................................................................................
Filing of modified terms and conditions ....................................................................................................................................
Ready for Commission decision ................................................................................................................................................
o. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
Philis J. Posey,
Acting Secretary.
[FR Doc. E7–4993 Filed 3–16–07; 8:45 am]
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER07–169–000; Docket No.
ER07–170–000]
Ameren Energy Marketing Company,
Ameren Energy, Inc.; Notice Allowing
Post-Technical Conference Comments
BILLING CODE 6717–01–P
ycherry on PROD1PC64 with NOTICES
March 13, 2007.
Pursuant to the December 26, 2006
order in this proceeding, Ameren Energy
Marketing Co., 117 FERC ¶ 61,334
(2006), a staff technical conference was
held on Tuesday, March 13, 2006 at the
offices of the Federal Energy Regulatory
Commission. The technical conference
1 Plant
datum = mean sea level (MSL) + 12.39 ft.
schedule assumes Georgia Power
Company’s license application conforms to the
2 This
VerDate Aug<31>2005
20:21 Mar 16, 2007
Jkt 211001
Commission’s regulations and has no deficiencies
under § 5.20.
2 This schedule assumes Georgia Power
Company’s license application conforms to the
PO 00000
Frm 00043
Fmt 4703
Sfmt 4703
May 13, 2007. 2
July 12, 2007.
August 26, 2007.
November 9, 2007.
December 9, 2007.
February 8, 2008.
May 8, 2008.
addressed issues related to potential
affiliate abuse in the sale of ancillary
services among Ameren affiliates.
Take notice that the Commission will
accept post-technical conference
comments. Initial comments are due no
later than 5 p.m. Eastern Time on April
3, 2007. Reply comments are due no
later than 5 p.m. Eastern Time on April
17, 2007.
For further information please contact
Zeny Magos at (202) 502–8244 or e-mail
zeny.magos@ferc.gov.
Philis J. Posey,
Acting Secretary.
[FR Doc. E7–4987 Filed 3–16–07; 8:45 am]
BILLING CODE 6717–01–P
Commission’s regulations and has no deficiencies
under § 5.20.
E:\FR\FM\19MRN1.SGM
19MRN1
Agencies
[Federal Register Volume 72, Number 52 (Monday, March 19, 2007)]
[Notices]
[Pages 12793-12794]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-4993]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No.: P-2237-017]
Georgia Power Company; Notice of Application Tendered for Filing
With the Commission and Establishing Procedural Schedule for Licensing
and Deadline for Submission of Final Amendments
March 13, 2007.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
[[Page 12794]]
a. Type of Application: New Major License.
b. Project No.: P-2237-017.
c. Date Filed: February 27, 2007.
d. Applicant: Georgia Power Company.
e. Name of Project: Morgan Falls Hydroelectric Project.
f. Location: The existing project is located in the metropolitan
city of Atlanta area on the Chattahoochee River, at river mile 312.6,
and about 36 miles downstream from the U.S. Corps of Engineers' Buford
dam (Lake Sidney Lanier) in Cobb and Fulton Counties, Georgia. The
project occupies about 14.4 acres of federal lands within the
Chattahoochee River National Recreation Area managed by the National
Park Service.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Douglas E. Jones, Senior Vice-President,
Southern Company Generation, 241 Ralph McGill Boulevard NE., Bin 10240,
Atlanta, Georgia 30308-3374; Telephone (404) 506-7328; or George A.
Martin, Project Manager, at (404) 506-1357 or e-mail at
gamartin@southernco.com. Additional information on this project is
available on the applicant's Web site: https://www.southerncompany.com/
gapower/hydro/.
i. FERC Contact: Janet Hutzel, Telephone (202) 502-8675, or e-mail
janet.hutzel@ferc.gov. Additional information on Federal Energy
Regulatory Commission (FERC) hydroelectric projects is available on
FERC's Web site: https://www.ferc.gov/industries/hydropower.asp.
j. This application is not ready for environmental analysis at this
time.
k. Project Description: The existing project consists of the
following: (1) A 1,031-foot-long, 56-foot-maximum height concrete
gravity dam consisting of a 46-foot-long non-overflow westerly
abutment; a 680-foot-long gated spillway with sixteen 40-foot-wide by
8-foot-tall Tainter gates; a 21-foot-long trash gate section containing
one 8-foot-wide by 4-foot-tall trash gate; a 195-foot-long, 73-foot-
high combined powerhouse and intake section integral with the dam
containing seven horizontal double runner Francis turbines coupled to
seven generating units with a total generating capacity of 16.8
megawatt; and an 89-foot-long non-overflow easterly abutment; (2) a
684-acre reservoir (Bull Sluice Lake) at normal full pool elevation of
866.0 feet using plant datum,\1\ with 2,239 acre-feet of usable
storage; and (3) appurtenant facilities. The average annual generation
at the project is about 15,221 megawatt-hours. The applicant has no
plans to modify the existing project facilities or the current modified
run-of-river mode of operation.
---------------------------------------------------------------------------
\1\ Plant datum = mean sea level (MSL) + 12.39 ft.
---------------------------------------------------------------------------
l. Locations of the Application: A copy of the application is
available for review at the Commission in the Public Reference Room or
may be viewed on the Commission's Web site at https://www.ferc.gov using
the ``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. For
assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov
or toll-free at (866) 208-3676, or for TTY, (202) 502-8659. A copy is
also available for inspection and reproduction at the address in item
(h) above.
m. You may also register online at https://www.ferc.gov/
esubscribenow.htm to be notified via e-mail of new filings and
issuances related to this or other pending projects. For assistance,
contact FERC Online Support.
n. Procedural Schedule:
The application will be processed according to the following Hydro
Licensing Schedule. Revisions to the schedule may be made as
appropriate.
---------------------------------------------------------------------------
\2\ This schedule assumes Georgia Power Company's license
application conforms to the Commission's regulations and has no
deficiencies under Sec. 5.20.
------------------------------------------------------------------------
Milestone Target Date
------------------------------------------------------------------------
Notice of Acceptance/ Notice of Ready May 13, 2007. \2\
for Environmental Analysis.
Filing of interventions, July 12, 2007.
recommendations, preliminary terms
and conditions, and fishway
prescriptions.
Reply comments due................... August 26, 2007.
FERC issues single EA (without a November 9, 2007.
draft).
Comments on EA due................... December 9, 2007.
Filing of modified terms and February 8, 2008.
conditions.
Ready for Commission decision........ May 8, 2008.
------------------------------------------------------------------------
o. Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
---------------------------------------------------------------------------
\2\ This schedule assumes Georgia Power Company's license
application conforms to the Commission's regulations and has no
deficiencies under Sec. 5.20.
Philis J. Posey,
Acting Secretary.
[FR Doc. E7-4993 Filed 3-16-07; 8:45 am]