Gulf South Pipeline Company, LP; Notice of Availability of the Draft Environmental Impact Statement for the Proposed East Texas to Mississippi Expansion Project, 7646-7647 [E7-2695]
Download as PDF
7646
Federal Register / Vol. 72, No. 32 / Friday, February 16, 2007 / Notices
https://www.ferc.gov. Persons unable to
file electronically should submit an
original and 14 copies of the protest to
the Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington, DC 20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on February 23, 2007.
Magalie R. Salas,
Secretary.
[FR Doc. E7–2694 Filed 2–15–07; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP06–446–000]
Gulf South Pipeline Company, LP;
Notice of Availability of the Draft
Environmental Impact Statement for
the Proposed East Texas to
Mississippi Expansion Project
February 9, 2007.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) has prepared this Draft
Environmental Impact Statement (EIS)
for the natural gas pipeline facilities
proposed by Gulf South Pipeline
Company, LP (Gulf South) under the
above-referenced docket. Gulf South’s
East Texas to Mississippi Expansion
Project (Project) would be located in
various counties and parishes in eastern
Texas, northern Louisiana, and western
Mississippi.
The Draft EIS was prepared to satisfy
the requirements of the National
Environmental Policy Act. The FERC
staff concludes that the proposed
Project, with the appropriate mitigation
measures as recommended, would have
limited adverse environmental impact.
The U.S. Fish and Wildlife Service
(FWS), National Park Service (NPS),
U.S. Environmental Protection Agency
(EPA), and the U.S. Army Corps of
Engineers (COE) are federal cooperating
agencies for the development of this
EIS. A federal cooperating agency has
jurisdiction by law or special expertise
with respect to any environmental
impact involved with the proposal and
is involved in the NEPA analysis.
The general purpose of the proposed
Project is to transport up to 1.7 billion
cubic feet per day of natural gas from
production fields in eastern Texas to
markets in the Gulf coast, Midwestern,
Northeastern and Southeastern regions
of the United States.
The Draft EIS addresses the potential
environmental impacts resulting from
the construction and operation of the
following facilities:
• Approximately 240.0 miles of 42inch-diameter natural gas pipeline
extending easterly from DeSoto Parish,
Louisiana to Simpson County,
Mississippi;
• Approximately 3.3 miles of 36-inchdiameter natural gas pipeline extending
northward from Gulf South’s existing
Carthage Junction Compressor Station in
Panola County, Texas to interconnect
with existing natural gas facilities
within Panola County;
• Two new compressor stations, the
Vixen and the Tallulah Compressor
Stations, located in Ouachita and
Madison Parishes, Louisiana,
respectively;
• Modifications to three existing
compressor stations, the Carthage
Junction, Hall Summit, and McComb
Compressor Stations in Panola, County,
Texas, Bienville Parish, Louisiana and
Walthall County, Mississippi,
respectively; and
• Other ancillary facilities including
six meter and regulator (M/R) facilities,
eleven mainline valves, nine side
valves, and six pig launcher and/or
receiver facilities.
Project construction would be
initiated in May 2007 and completed by
September 2007, at which point Gulf
South would place the proposed Project
in-service.
Comment Procedures and Public
Meetings
Any person wishing to comment on
the Draft EIS may do so. To ensure that
your comments are timely and properly
recorded so that they may be considered
in the Final EIS, please carefully follow
these instructions:
• Send an original and two copies of
your letter to: Magalie R. Salas,
Secretary, Federal Energy Regulatory
Commission, 888 First St., NE., Room
1A, Washington, DC 20426.
• Label one copy of your comments to
the attention of Gas Branch 2, DG2E;
and Reference Docket No. CP06–446–
000 on the original and both copies.
• Mail your comments so that they
will be received in Washington, DC on
or before March 27, 2007.
Please note that the Commission
strongly encourages the electronic filing
(‘‘eFiling’’) of comments. Instructions on
how to ‘‘eFile’’ comments can be found
on the Commission’s Web site at https://
www.ferc.gov under the ‘‘Documents
and Filings’’ link.
In lieu of or in addition to sending
written comments, we invite you to
attend the public comment meetings the
FERC will conduct in the project area to
receive comments on the Draft EIS. All
meetings will begin at 6 p.m. (CDT), and
are scheduled as follows:
Date and time
Location
Monday, February 26, 6 p.m. .......................................................
Minden American Legion Hall, 119 Pine Street, Minden, LA 71055, (318) 371–
3045.
Ouachita Parish Public Library—Main Branch, 1800 Stubbs Avenue, Monroe,
LA 71201, (318) 327–1490.
Vicksburg Convention Center, Room 4, 1600 Mulberry Street, Vicksburg, MS
39180, (866) 822–6338.
Tuesday, February 27, 6 p.m. ......................................................
sroberts on PROD1PC70 with NOTICES
Thursday, March 1, 6 p.m. ...........................................................
The public comment meetings will be
posted on the FERC’s calendar located
at https://www.ferc.gov/EventCalendar/
EventsList.aspx. Interested groups and
individuals are encouraged to attend
and present oral comments on the Draft
VerDate Aug<31>2005
19:03 Feb 15, 2007
Jkt 211001
EIS. Transcripts of the meetings will be
prepared.
After the comments received are
reviewed, any significant new issues are
investigated, and modifications are
made to the Draft EIS, a Final EIS will
be published and distributed by the
PO 00000
Frm 00056
Fmt 4703
Sfmt 4703
FERC staff. The Final EIS will contain
the staff’s responses to timely comments
received on the Draft EIS.
Comments will be considered by the
Commission but will not serve to make
the commentor a party to the
proceeding. Any person seeking to
E:\FR\FM\16FEN1.SGM
16FEN1
sroberts on PROD1PC70 with NOTICES
Federal Register / Vol. 72, No. 32 / Friday, February 16, 2007 / Notices
service please go to https://www.ferc.gov/
esubscribenow.htm.
become a party to the proceeding must
file a motion to intervene pursuant to
Rule 214 of the Commission’s Rules of
Practice and Procedures (18 CFR
385.214). Anyone may intervene in this
proceeding based on this Draft EIS. You
must file your request to intervene as
specified above.1 You do not need
intervenor status to have your
comments considered.
The Draft EIS has been placed in the
public files of the FERC and is available
for public inspection at: Federal Energy
Regulatory Commission, Public
Reference Room, 888 First Street N.E.,
Room 2A, Washington, DC 20426, (202)
502–8371.
A limited number of copies of the
Draft EIS are available from the Public
Reference Room identified above. In
addition, CD copies of the Draft EIS
have been mailed to affected
landowners; various Federal, State, and
local government agencies; elected
officials; environmental and public
interest groups; Native American tribes;
local libraries and newspapers;
intervenors; and other individuals that
expressed an interest in the proposed
Project. Hard-copies of the Draft EIS
have also been mailed to those who
requested that format during the scoping
and comment periods for the proposed
Project.
Additional information about the
proposed Project is available from the
Commission’s Office of External Affairs,
at 1–866–208–FERC or on the FERC
Internet Web site (https://www.ferc.gov).
To access information via the FERC
Web site click on the ‘‘eLibrary’’ link
then click on ‘‘General Search’’ and
enter the docket number excluding the
last three digits in the Docket Number
field. Be sure you have selected an
appropriate date range. The ‘‘eLibrary’’
link provides access to the texts of
formal documents issued by the
Commission, such as orders, notices,
and rulemakings. For assistance with
‘‘eLibrary’’, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or toll free at 1–866–208–3676, or for
TTY, contact (202) 502–8659.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries and direct links to
these documents. To learn more about
eSubscription and to sign-up for this
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Ellisburg Replacement Well Project
involving the installation and operation
of two new injection/withdrawal wells
by Dominion Transmission, Inc. (DTI)
within its Ellisburg Storage Field
located in Potter County, Pennsylvania.1
This EA will be used by the
Commission in its decision-making
process to determine whether the
project is in the public convenience and
necessity.
This notice announces the opening of
the public comment period that will be
used to gather environmental input from
the public and interested agencies on
the project. Comments are requested by
March 9, 2007.
If you are a landowner receiving this
notice, you may be contacted by a
company representative about the
acquisition of an easement to construct,
operate, and maintain the proposed
facilities. The company would seek to
negotiate a mutually acceptable
agreement. However, if the project is
approved by the Commission, that
approval conveys with it the right of
eminent domain. Therefore, if easement
negotiations fail to produce an
agreement, the company could initiate
condemnation proceedings in
accordance with state law.
A brochure prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ is available for viewing on
the FERC Web site at https://
www.ferc.gov. This fact sheet addresses
1 Interventions may also be filed electronically via
the Internet in lieu of paper. See the previous
discussion on filing comments electronically.
1 DTI’s application was filed with the
Commission under section 7 of the Natural Gas Act
and Part 157 of the Commission’s regulations.
VerDate Aug<31>2005
19:03 Feb 15, 2007
Jkt 211001
Magalie R. Salas,
Secretary.
[FR Doc. E7–2695 Filed 2–15–07; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP07–067–000]
Dominion Transmission, Inc.; Notice of
Intent To Prepare an Environmental
Assessment for the Proposed
Ellisburg Replacement Well Project
and Request for Comments on
Environmental Issues
February 9, 2007.
PO 00000
Frm 00057
Fmt 4703
Sfmt 4703
7647
a number of typically asked questions,
including the use of eminent domain
and how to participate in the
Commission’s proceedings.
Summary of the Proposed Project
DTI seeks authority to install and
operate two new wells, EW–210 and
EW–326, located in its Ellisburg Storage
Field. The new wells would replace two
previously abandoned wells, EW–203
and EW–313. The previous well
abandonments were completed under
DTI’s blanket certificate authorization in
Docket No. CP06–419–000.
The new well EW–210 would be
installed approximately 32 feet
northwest of EW–203, and the new EW–
326 well would be located
approximately 49 feet northeast of EW–
313. In addition, DTI would connect the
new wells to the existing storage
pipeline network by installing
approximately 230 feet of new well
pipeline. The construction and
operation of the new pipeline would be
performed under DTI’s existing blanket
certificate authorization in Docket No.
CP82–537–000. The new wells are
required to maintain the overall
deliverability of the Ellisburg Storage
Field.
The general locations of the new wells
are shown in Appendix 1.2
Land Requirements
Construction of the new wells would
require about 3.31 acres of land and
includes access roads, staging areas and
extra work areas. Each well site would
require approximately 1.62 acres.
Following construction, about 1.26 acres
would be permanently maintained. The
remaining 2.05 acres of land would be
restored and allowed to revert to its
former use.
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us to
discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping’’. The
main goal of the scoping process is to
focus the analysis in the EA on the
2 The appendices referenced in this notice are not
being printed in the Federal Register. Copies of all
appendices, other than Appendix 2 (map), are
available on the Commission’s website at the
‘‘eLibrary’’ link or from the Commission’s Public
Reference Room, 888 First Street, NE., Washington,
DC 20426, or call (202) 502–8371. For instructions
on connecting to eLibrary refer to the last page of
this notice. Copies of the appendices were sent to
all those receiving this notice in the mail.
E:\FR\FM\16FEN1.SGM
16FEN1
Agencies
[Federal Register Volume 72, Number 32 (Friday, February 16, 2007)]
[Notices]
[Pages 7646-7647]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-2695]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP06-446-000]
Gulf South Pipeline Company, LP; Notice of Availability of the
Draft Environmental Impact Statement for the Proposed East Texas to
Mississippi Expansion Project
February 9, 2007.
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) has prepared this Draft Environmental Impact Statement
(EIS) for the natural gas pipeline facilities proposed by Gulf South
Pipeline Company, LP (Gulf South) under the above-referenced docket.
Gulf South's East Texas to Mississippi Expansion Project (Project)
would be located in various counties and parishes in eastern Texas,
northern Louisiana, and western Mississippi.
The Draft EIS was prepared to satisfy the requirements of the
National Environmental Policy Act. The FERC staff concludes that the
proposed Project, with the appropriate mitigation measures as
recommended, would have limited adverse environmental impact.
The U.S. Fish and Wildlife Service (FWS), National Park Service
(NPS), U.S. Environmental Protection Agency (EPA), and the U.S. Army
Corps of Engineers (COE) are federal cooperating agencies for the
development of this EIS. A federal cooperating agency has jurisdiction
by law or special expertise with respect to any environmental impact
involved with the proposal and is involved in the NEPA analysis.
The general purpose of the proposed Project is to transport up to
1.7 billion cubic feet per day of natural gas from production fields in
eastern Texas to markets in the Gulf coast, Midwestern, Northeastern
and Southeastern regions of the United States.
The Draft EIS addresses the potential environmental impacts
resulting from the construction and operation of the following
facilities:
Approximately 240.0 miles of 42-inch-diameter natural gas
pipeline extending easterly from DeSoto Parish, Louisiana to Simpson
County, Mississippi;
Approximately 3.3 miles of 36-inch-diameter natural gas
pipeline extending northward from Gulf South's existing Carthage
Junction Compressor Station in Panola County, Texas to interconnect
with existing natural gas facilities within Panola County;
Two new compressor stations, the Vixen and the Tallulah
Compressor Stations, located in Ouachita and Madison Parishes,
Louisiana, respectively;
Modifications to three existing compressor stations, the
Carthage Junction, Hall Summit, and McComb Compressor Stations in
Panola, County, Texas, Bienville Parish, Louisiana and Walthall County,
Mississippi, respectively; and
Other ancillary facilities including six meter and
regulator (M/R) facilities, eleven mainline valves, nine side valves,
and six pig launcher and/or receiver facilities.
Project construction would be initiated in May 2007 and completed
by September 2007, at which point Gulf South would place the proposed
Project in-service.
Comment Procedures and Public Meetings
Any person wishing to comment on the Draft EIS may do so. To ensure
that your comments are timely and properly recorded so that they may be
considered in the Final EIS, please carefully follow these
instructions:
Send an original and two copies of your letter to: Magalie
R. Salas, Secretary, Federal Energy Regulatory Commission, 888 First
St., NE., Room 1A, Washington, DC 20426.
Label one copy of your comments to the attention of Gas
Branch 2, DG2E; and Reference Docket No. CP06-446-000 on the original
and both copies.
Mail your comments so that they will be received in
Washington, DC on or before March 27, 2007.
Please note that the Commission strongly encourages the electronic
filing (``eFiling'') of comments. Instructions on how to ``eFile''
comments can be found on the Commission's Web site at https://
www.ferc.gov under the ``Documents and Filings'' link.
In lieu of or in addition to sending written comments, we invite
you to attend the public comment meetings the FERC will conduct in the
project area to receive comments on the Draft EIS. All meetings will
begin at 6 p.m. (CDT), and are scheduled as follows:
------------------------------------------------------------------------
Date and time Location
------------------------------------------------------------------------
Monday, February 26, 6 p.m........... Minden American Legion Hall, 119
Pine Street, Minden, LA 71055,
(318) 371-3045.
Tuesday, February 27, 6 p.m.......... Ouachita Parish Public Library--
Main Branch, 1800 Stubbs Avenue,
Monroe, LA 71201, (318) 327-
1490.
Thursday, March 1, 6 p.m............. Vicksburg Convention Center, Room
4, 1600 Mulberry Street,
Vicksburg, MS 39180, (866) 822-
6338.
------------------------------------------------------------------------
The public comment meetings will be posted on the FERC's calendar
located at https://www.ferc.gov/EventCalendar/EventsList.aspx.
Interested groups and individuals are encouraged to attend and present
oral comments on the Draft EIS. Transcripts of the meetings will be
prepared.
After the comments received are reviewed, any significant new
issues are investigated, and modifications are made to the Draft EIS, a
Final EIS will be published and distributed by the FERC staff. The
Final EIS will contain the staff's responses to timely comments
received on the Draft EIS.
Comments will be considered by the Commission but will not serve to
make the commentor a party to the proceeding. Any person seeking to
[[Page 7647]]
become a party to the proceeding must file a motion to intervene
pursuant to Rule 214 of the Commission's Rules of Practice and
Procedures (18 CFR 385.214). Anyone may intervene in this proceeding
based on this Draft EIS. You must file your request to intervene as
specified above.\1\ You do not need intervenor status to have your
comments considered.
---------------------------------------------------------------------------
\1\ Interventions may also be filed electronically via the
Internet in lieu of paper. See the previous discussion on filing
comments electronically.
---------------------------------------------------------------------------
The Draft EIS has been placed in the public files of the FERC and
is available for public inspection at: Federal Energy Regulatory
Commission, Public Reference Room, 888 First Street N.E., Room 2A,
Washington, DC 20426, (202) 502-8371.
A limited number of copies of the Draft EIS are available from the
Public Reference Room identified above. In addition, CD copies of the
Draft EIS have been mailed to affected landowners; various Federal,
State, and local government agencies; elected officials; environmental
and public interest groups; Native American tribes; local libraries and
newspapers; intervenors; and other individuals that expressed an
interest in the proposed Project. Hard-copies of the Draft EIS have
also been mailed to those who requested that format during the scoping
and comment periods for the proposed Project.
Additional information about the proposed Project is available from
the Commission's Office of External Affairs, at 1-866-208-FERC or on
the FERC Internet Web site (https://www.ferc.gov).
To access information via the FERC Web site click on the
``eLibrary'' link then click on ``General Search'' and enter the docket
number excluding the last three digits in the Docket Number field. Be
sure you have selected an appropriate date range. The ``eLibrary'' link
provides access to the texts of formal documents issued by the
Commission, such as orders, notices, and rulemakings. For assistance
with ``eLibrary'', please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at 1-866-208-3676, or for TTY,
contact (202) 502-8659.
In addition, the Commission now offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries and direct links to
these documents. To learn more about eSubscription and to sign-up for
this service please go to https://www.ferc.gov/esubscribenow.htm.
Magalie R. Salas,
Secretary.
[FR Doc. E7-2695 Filed 2-15-07; 8:45 am]
BILLING CODE 6717-01-P