Intent To Prepare a Draft Supplement No. 1 to the Final Environmental Impact Statement for the Upper Trinity River, Central City Project, Fort Worth, TX, 7622-7623 [07-724]

Download as PDF sroberts on PROD1PC70 with NOTICES 7622 Federal Register / Vol. 72, No. 32 / Friday, February 16, 2007 / Notices Helena, and St. John Parishes. The Amite River and its tributaries flow southward from the state of Mississippi through the western ‘‘Florida’’ parishes of southeast Louisiana into Lake Maurepas, an oligohaline lake that drains into Lake Pontchartrain. The Amite River is used for recreation, propagation of fish and wildlife, and to a lesser extent, for water supply, navigation, and waste disposal. The Amite River has a large drainage area and an average flow of about 2,000 cubic feet per second (CFS) at Denham Springs. A section of the Amite River in East Feliciana Parish, from the Louisiana/Mississippi state line to Louisiana Highway 37 (LA 37) is included in Louisiana’s Natural and Scenic Rivers System. The major urban areas in this watershed are Baton Rouge, Denham Springs, and Gonzales, which are situated along the lower third of the river. FOR FURTHER INFORMATION CONTACT: Questions concerning the Environmental Impact Statement (EIS) should be addressed to Ms. Bonnie S. Obiol at U.S. Army Corps of Engineers, PM–RS, P.O. Box 60267, New Orleans, LA 70160–0267, phone (504) 862–2280, fax number (504) 862–2088 or by E-mail at bonnie.s.obiol@mvn02.usace. army.mil. SUPPLEMENTARY INFORMATION: 1. Proposed Action. An ecological restoration project will be designed to maximize environmental benefits within the study area. The proposed action includes all or portions of several alternatives, identified below, that would improve the ecosystem and possibly reduce storm water flood stages as an ancillary benefit. Design features will be fully evaluated with respect to the latest engineering, economic, and environmental regulations for acceptability under current Federal laws and regulations. The results of the feasibility study will determine the preferred alternative. 2. Alternatives. The Amite River and Tributaries Ecosystem Restoration reconnaissance study considered several alternative plans for restoring the ecosystem in the study area. Four plans were determined to be economically justified and environmentally acceptable. The plans include: (1) Recontouring and re-vegetating sterile and unstable abandoned tailing piles and un-vegetated abandoned mined areas in the immediate vicinity of the stream corridor, (2) as an increment to Alternative 1, including an additional 4,500 to 6,000 acres not immediately adjacent to the river by re-contouring and re-vegetating a total area of VerDate Aug<31>2005 19:03 Feb 15, 2007 Jkt 211001 approximately 6,000 to 7,500 acres, (3) re-meandering abandoned bendways and loops of the Amite River in appropriate areas to recreate some of the historical meander loops or create new loops that would serve the same purpose, and (4) investigate recommendations of Best Management Practices (BMPs) for the sand and gravel industry, as well as other affected industries and urban areas in the study area for more stewardship for future habitat areas. The objective of the enactment of the BMPs would be to protect the restoration efforts undertaken by this project and other restorative measures by others and prevent reoccurrence of the degradation. 3. Scoping. Scoping is the process for determining the scope of alternatives and significant issues to be addressed in the EIS. For this analysis, a letter will be sent to all parties believed to have an interest in the analysis, requesting their input on alternatives and issues to be evaluated. The letter will also notify interested parties of public scoping meetings that will be held in the local area. Notices will also be sent to local news media. All interested parties are invited to comment at this time, and anyone interested in this study should request to be included in the study mailing list. A public scoping meeting will be held in the spring of 2007. The meeting will be held in the vicinity of Baton Rouge, LA. Additional meetings could be held, depending upon interest and if it is determined that further public coordination is warranted. 4. Significant Issues. The tentative list of resources and issues to be evaluated in the EIS includes wetlands (marshes and swamps), aquatic resources, commercial and recreational fisheries, wildlife resources, essential fish habitat, water quality, air quality, threatened and endangered species, recreation and aesthetic resources, and cultural resources. Socioeconomic items to be evaluated in the EIS include navigation, flood protection, business and industrial activity, employment, land use, property values, public/community facilities and services, tax revenues, population, community and regional growth, transportation, housing, community cohesion, and noise. 5. Environmental Consultation and Review. The U.S. Fish and Wildlife Service (USFWS) will be assisting in the documentation of existing conditions and assessment of effects of project alternatives through Fish and Wildlife Coordination Act consultation procedures. The USFWS will provide a Fish and Wildlife Coordination Act report. Consultation will be PO 00000 Frm 00032 Fmt 4703 Sfmt 4703 accomplished with the USFWS and the National marine Fisheries Service (NMFS) concerning threatened and endangered species and their critical habitat. The NMFS will be consulted on the effects of this proposed action on Essential Fish Habitat. The draft EIS (DEIS) or a notice of its availability will be distributed to all interested agencies, organizations, and individuals. 6. Estimated Date of Availability. Funding levels will dictate the date when the DEIS is available. The earliest that the DEIS is expected to be available is in the summer of 2009. Brenda S. Bowen, Army Federal Register Liaison Officer. [FR Doc. 07–719 Filed 2–15–07; 8:45 am] BILLING CODE 3810–84–M DEPARTMENT OF DEFENSE Department of the Army; Corps of Engineers Intent To Prepare a Draft Supplement No. 1 to the Final Environmental Impact Statement for the Upper Trinity River, Central City Project, Fort Worth, TX Department of the Army, U.S. Army Corps of Engineers, DoD. ACTION: Notice of intent. AGENCY: SUMMARY: Section 116 of Pub. L. 108– 447, dated December 8, 2004, authorized the U.S. Army Corps of Engineers’ (Corps) participation in construction of the Central City project. A Final Environmental Impact Statement (FEIS) was completed for the Central City Project in Janauary 2006. A Record of Decision (ROD) recommending the Community-Based Alternative and determining it was technically sound and environmentally acceptable was signed by the Assistant Secretary of the Army for Civil Works (ASA (CW)) on April 7, 2006. An Interim Feasibility Report with Integrated Environmental Assessment (with signed Finding of No Significant Impact) for the Riverside Oxbow Project was approved by the Chief of Engineers on May 29, 2003. An addendum, dated April 2005, was prepared to address comments from the ASA (CW); however, neither construction funding nor authority for implementation of this project has been provided by Congress to date. By letter dated June 22, 2006, the City of Fort Worth requested the Corps to evaluate the potential benefits of merging the Central City Project with the Riverside Oxbow project. They identified potential benefits including E:\FR\FM\16FEN1.SGM 16FEN1 sroberts on PROD1PC70 with NOTICES Federal Register / Vol. 72, No. 32 / Friday, February 16, 2007 / Notices greater opportunity for valley storage requirements, increased restoration opportunities, and cost savings. After an initial evaluation, the Corps determined that alternative areas along the West Fork of the Trinity River including areas within the Riverside Oxbow project had the potential to provide the required hydraulic mitigation, provide comparable ecosystem restoration outputs, reduce habitat mitigation requirements, and lower overall project costs. These potential modifications to the projects may be substantial and a supplement to the Central City environmental impact statement should be prepared concurrently with a more detailed analysis. Therefore, this Notice of Intent to prepare Supplement No. 1 to the FEIS for the Central City project is being issued in accordance with the Council on Environmental Quality’s NEPA implementing regulations at 40 CFR Parts 1500–1508. FOR FURTHER INFORMATION CONTACT: Questions and scoping comments pertaining to this analysis and Draft Supplement to the EIS should be directed to Mr. Saji Puthenpurayel, Project Manager, CESWF–EC–D, U.S. Army Corps of Engineers, Fort Worth District, P.O. Box 17300, Fort Worth, TX 76102–0300, (817) 886–1764. SUPPLEMENTARY INFORMATION: The Central City project as authorized includes a flood bypass channel and flood gates to divert flood flows around a segment of the existing Trinity River channel adjacent to downtown Fort Worth, Samuels Avenue Dam to create an interior water feature, and hydraulic and ecological mitigation areas. The bypass channel is approximately 8,400 feet long, 300–400 feet wide, and would be approximately 30 feet below the existing grade. The bypass channel would begin at the Clear Fork downstream of West Seventh Street, interest the West Fork approximately 2,600 feet upstream of the existing confluence with the Clear Fork, and continue to the northeast terminating at the West Fork about 8,500 feet downstream of the existing confluence. The Corps component of the Central City Project was authorized for construction by Section 116 of Public Law 108–447, dated December 8, 2004. Under that authority, Corps participation is limited to $110 million with a total project cost $220 million for that portion of the infrastructure plan in which the Corps can participate. Without hydraulic mitigation, the Central City project would result in a loss of valley storage due to the bypass channel being shorter and more efficient VerDate Aug<31>2005 19:03 Feb 15, 2007 Jkt 211001 than the existing river channel. Valley storage sites are included in the existing authorized plan to compensate for this potential loss of storage. Four areas would provide the required valley storage; along the West Fork of the Trinity River upstream of the bypass channel (Riverbend/Rockwood), adjacent to University Drive, in the vicinity of the Samuels Avenue Dam, and slightly downstream of the proposed dam site in proximity to Riverside Park. Construction of the bypass channel and associated valley storage sites would not increase downstream water surface elevations or downstream flow. Reestablishment of vegetation and habitat at the Riverbend/Rockwood site following construction activities were included in the authorized plan, partially for mitigation of project impacts to wetland, riparian, and terrestrial resources and partially for ecosystem restoration. Additional habitat mitigation measures were included along Ham Branch, a tributary of the West Fork of the Trinity River, which enters the system a short distance downstream of Highway 121. Approximately 305 feet of the existing channel would be relocated to provide adequate width for riparian forest development and existing riparian habitat would be improved along the remainder of the channel. The Riverside Oxbow project area is adjacent to and immediately downstream of the Central City Project. The focus of the project is to restore the ecological integrity of aquatic and riparian systems along a portion of the natural Trinity River channel that was severed by construction of a realignment and enlargement of the West Fork of the Trinity River channel by non-Federal interests. The Interim Feasibility Report recommends implementation of the Locally Preferred Plan, which consists of the National Ecosystem Restoration (NER) Plan along with additional local features. The NER plan for the Riverside Oxbow will restore the biological integrity of the wetland and bottomland hardwood communities through a combination of measures directed at either specific habitat types or specific problems within the existing ecosystem. The City’s request to merge these projects recognized that each project is moving forward independently but they are located adjacent to one another. The City and the Tarrant Regional Water District expressed their opinion that based on their adjacency, there might be merit in combining the two projects. In their letter, the City of Forth Worth identified potential benefits of combining the two projects that would PO 00000 Frm 00033 Fmt 4703 Sfmt 4703 7623 not be achieved if they proceed independently. These potential benefits included greater flexibility in selecting sites for the required valley storage mitigation, opportunity to increase restoration benefits, and cost savings. In addition, during detailed design investigations it was determined that alternative locations of the proposed Samuel Avenue Dam should be evaluated due to geotechnical considerations. The amount of aquatic habitat impacted in marine and Lebow Creeks is affected by the location of Samuels Avenue Dam and will be considered during further site analysis. In response to the City’s letter request, the corps performed an initial evaluation and determined that alternative areas along the West Fork of the Trinity River including areas within the Riverside Oxbow project had the potential to provide the required hydraulic mitigation, provide comparable ecosystem restoration outputs, reduce habitat mitigation requirements, and lower project costs. Following review of this initial evaluation, Corps Headquarters directed that a detailed analysis be undertaken that evaluates the total hydraulic system including the Central City and Riveside Oxbow project areas. The Corps’ approving offices acknowledged that to determine if and how either project should be modified, additional study, reporting, and environmental compliance would be required. All affected Federal, State, and local agencies, affected Indian tribes, and other interested private local organizations and parties are hereby invited to participate in the development of the Draft SEIS. No Public Meetings have been scheduled at this time, however all agencies and other known interested entities will be informed by public notice to request their comments regarding the potential modifications. Coordination will continue with the U.S. Fish and Wildlife Service and Texas Parks and Wildlife Department in accordance with the Fish and Wildlife Coordination Act. The Texas State Historic Preservation Office will be consulted as required by Section 106 of the National Historic Preservation Act. Potential modifications to the project will also be coordinated with the Texas Council on Environmental Quality to ensure any changes are in compliance with Section 401 of the Clean Water Act. Dated: February 7, 2007. Christopher W. Martin, Colonel, Corps of Engineers, District Engineer. [FR Doc. 07–724 Filed 2–15–07; 8:45 am] BILLING CODE 3710–20–M E:\FR\FM\16FEN1.SGM 16FEN1

Agencies

[Federal Register Volume 72, Number 32 (Friday, February 16, 2007)]
[Notices]
[Pages 7622-7623]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 07-724]


-----------------------------------------------------------------------

DEPARTMENT OF DEFENSE

Department of the Army; Corps of Engineers


Intent To Prepare a Draft Supplement No. 1 to the Final 
Environmental Impact Statement for the Upper Trinity River, Central 
City Project, Fort Worth, TX

AGENCY: Department of the Army, U.S. Army Corps of Engineers, DoD.

ACTION: Notice of intent.

-----------------------------------------------------------------------

SUMMARY: Section 116 of Pub. L. 108-447, dated December 8, 2004, 
authorized the U.S. Army Corps of Engineers' (Corps) participation in 
construction of the Central City project. A Final Environmental Impact 
Statement (FEIS) was completed for the Central City Project in Janauary 
2006. A Record of Decision (ROD) recommending the Community-Based 
Alternative and determining it was technically sound and 
environmentally acceptable was signed by the Assistant Secretary of the 
Army for Civil Works (ASA (CW)) on April 7, 2006. An Interim 
Feasibility Report with Integrated Environmental Assessment (with 
signed Finding of No Significant Impact) for the Riverside Oxbow 
Project was approved by the Chief of Engineers on May 29, 2003. An 
addendum, dated April 2005, was prepared to address comments from the 
ASA (CW); however, neither construction funding nor authority for 
implementation of this project has been provided by Congress to date.
    By letter dated June 22, 2006, the City of Fort Worth requested the 
Corps to evaluate the potential benefits of merging the Central City 
Project with the Riverside Oxbow project. They identified potential 
benefits including

[[Page 7623]]

greater opportunity for valley storage requirements, increased 
restoration opportunities, and cost savings. After an initial 
evaluation, the Corps determined that alternative areas along the West 
Fork of the Trinity River including areas within the Riverside Oxbow 
project had the potential to provide the required hydraulic mitigation, 
provide comparable ecosystem restoration outputs, reduce habitat 
mitigation requirements, and lower overall project costs.
    These potential modifications to the projects may be substantial 
and a supplement to the Central City environmental impact statement 
should be prepared concurrently with a more detailed analysis. 
Therefore, this Notice of Intent to prepare Supplement No. 1 to the 
FEIS for the Central City project is being issued in accordance with 
the Council on Environmental Quality's NEPA implementing regulations at 
40 CFR Parts 1500-1508.

FOR FURTHER INFORMATION CONTACT: Questions and scoping comments 
pertaining to this analysis and Draft Supplement to the EIS should be 
directed to Mr. Saji Puthenpurayel, Project Manager, CESWF-EC-D, U.S. 
Army Corps of Engineers, Fort Worth District, P.O. Box 17300, Fort 
Worth, TX 76102-0300, (817) 886-1764.

SUPPLEMENTARY INFORMATION: The Central City project as authorized 
includes a flood bypass channel and flood gates to divert flood flows 
around a segment of the existing Trinity River channel adjacent to 
downtown Fort Worth, Samuels Avenue Dam to create an interior water 
feature, and hydraulic and ecological mitigation areas. The bypass 
channel is approximately 8,400 feet long, 300-400 feet wide, and would 
be approximately 30 feet below the existing grade. The bypass channel 
would begin at the Clear Fork downstream of West Seventh Street, 
interest the West Fork approximately 2,600 feet upstream of the 
existing confluence with the Clear Fork, and continue to the northeast 
terminating at the West Fork about 8,500 feet downstream of the 
existing confluence. The Corps component of the Central City Project 
was authorized for construction by Section 116 of Public Law 108-447, 
dated December 8, 2004. Under that authority, Corps participation is 
limited to $110 million with a total project cost $220 million for that 
portion of the infrastructure plan in which the Corps can participate.
    Without hydraulic mitigation, the Central City project would result 
in a loss of valley storage due to the bypass channel being shorter and 
more efficient than the existing river channel. Valley storage sites 
are included in the existing authorized plan to compensate for this 
potential loss of storage. Four areas would provide the required valley 
storage; along the West Fork of the Trinity River upstream of the 
bypass channel (Riverbend/Rockwood), adjacent to University Drive, in 
the vicinity of the Samuels Avenue Dam, and slightly downstream of the 
proposed dam site in proximity to Riverside Park. Construction of the 
bypass channel and associated valley storage sites would not increase 
downstream water surface elevations or downstream flow.
    Reestablishment of vegetation and habitat at the Riverbend/Rockwood 
site following construction activities were included in the authorized 
plan, partially for mitigation of project impacts to wetland, riparian, 
and terrestrial resources and partially for ecosystem restoration. 
Additional habitat mitigation measures were included along Ham Branch, 
a tributary of the West Fork of the Trinity River, which enters the 
system a short distance downstream of Highway 121. Approximately 305 
feet of the existing channel would be relocated to provide adequate 
width for riparian forest development and existing riparian habitat 
would be improved along the remainder of the channel.
    The Riverside Oxbow project area is adjacent to and immediately 
downstream of the Central City Project. The focus of the project is to 
restore the ecological integrity of aquatic and riparian systems along 
a portion of the natural Trinity River channel that was severed by 
construction of a realignment and enlargement of the West Fork of the 
Trinity River channel by non-Federal interests. The Interim Feasibility 
Report recommends implementation of the Locally Preferred Plan, which 
consists of the National Ecosystem Restoration (NER) Plan along with 
additional local features. The NER plan for the Riverside Oxbow will 
restore the biological integrity of the wetland and bottomland hardwood 
communities through a combination of measures directed at either 
specific habitat types or specific problems within the existing 
ecosystem.
    The City's request to merge these projects recognized that each 
project is moving forward independently but they are located adjacent 
to one another. The City and the Tarrant Regional Water District 
expressed their opinion that based on their adjacency, there might be 
merit in combining the two projects. In their letter, the City of Forth 
Worth identified potential benefits of combining the two projects that 
would not be achieved if they proceed independently. These potential 
benefits included greater flexibility in selecting sites for the 
required valley storage mitigation, opportunity to increase restoration 
benefits, and cost savings.
    In addition, during detailed design investigations it was 
determined that alternative locations of the proposed Samuel Avenue Dam 
should be evaluated due to geotechnical considerations. The amount of 
aquatic habitat impacted in marine and Lebow Creeks is affected by the 
location of Samuels Avenue Dam and will be considered during further 
site analysis.
    In response to the City's letter request, the corps performed an 
initial evaluation and determined that alternative areas along the West 
Fork of the Trinity River including areas within the Riverside Oxbow 
project had the potential to provide the required hydraulic mitigation, 
provide comparable ecosystem restoration outputs, reduce habitat 
mitigation requirements, and lower project costs. Following review of 
this initial evaluation, Corps Headquarters directed that a detailed 
analysis be undertaken that evaluates the total hydraulic system 
including the Central City and Riveside Oxbow project areas. The Corps' 
approving offices acknowledged that to determine if and how either 
project should be modified, additional study, reporting, and 
environmental compliance would be required.
    All affected Federal, State, and local agencies, affected Indian 
tribes, and other interested private local organizations and parties 
are hereby invited to participate in the development of the Draft SEIS. 
No Public Meetings have been scheduled at this time, however all 
agencies and other known interested entities will be informed by public 
notice to request their comments regarding the potential modifications. 
Coordination will continue with the U.S. Fish and Wildlife Service and 
Texas Parks and Wildlife Department in accordance with the Fish and 
Wildlife Coordination Act. The Texas State Historic Preservation Office 
will be consulted as required by Section 106 of the National Historic 
Preservation Act. Potential modifications to the project will also be 
coordinated with the Texas Council on Environmental Quality to ensure 
any changes are in compliance with Section 401 of the Clean Water Act.

    Dated: February 7, 2007.
Christopher W. Martin,
Colonel, Corps of Engineers, District Engineer.
[FR Doc. 07-724 Filed 2-15-07; 8:45 am]
BILLING CODE 3710-20-M
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.