Verde Renewable Energy, Inc.; Notice of Issuance of Order, 3828 [E7-1241]
Download as PDF
3828
Federal Register / Vol. 72, No. 17 / Friday, January 26, 2007 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. ER07–48–000 and ER07–48–
001]
Verde Renewable Energy, Inc.; Notice
of Issuance of Order
sroberts on PROD1PC70 with NOTICES
January 22, 2006.
Verde Renewable Energy, Inc. (Verde)
filed an application for market-based
rate authority, with an accompanying
rate tariff. The proposed market-based
rate tariff provides for the sale of energy
and capacity at market-based rates.
Verde also requested waivers of various
Commission regulations. In particular,
Verde requested that the Commission
grant blanket approval under 18 CFR
part 34 of all future issuances of
securities and assumptions of liability
by Verde.
On January 22, 2007, pursuant to
delegated authority, the Director,
Division of Tariffs and Market
Development—West, granted the
requests for blanket approval under Part
34. The Director’s order also stated that
the Commission would publish a
separate notice in the Federal Register
establishing a period of time for the
filing of protests. Accordingly, any
person desiring to be heard or to protest
the blanket approvals of issuances of
securities or assumptions of liability by
Verde should file a motion to intervene
or protest with the Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426, in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure. 18 CFR 385.211, 385.214
(2004).
Notice is hereby given that the
deadline for filing motions to intervene
or protest is February 21, 2007.
Absent a request to be heard in
opposition by the deadline above, Verde
is authorized to issue securities and
assume obligations or liabilities as a
guarantor, indorser, surety, or otherwise
in respect of any security of another
person; provided that such issuance or
assumption is for some lawful object
within the corporate purposes of Verde,
compatible with the public interest, and
is reasonably necessary or appropriate
for such purposes.
The Commission reserves the right to
require a further showing that neither
public nor private interests will be
adversely affected by continued
approvals of Verde’s issuance of
securities or assumptions of liability.
Copies of the full text of the Director’s
Order are available from the
Commission’s Public Reference Room,
VerDate Aug<31>2005
17:19 Jan 25, 2007
Jkt 211001
888 First Street, NE., Washington, DC
20426. The Order may also be viewed
on the Commission’s Web site at https://
www.ferc.gov, using the eLibrary link.
Enter the docket number excluding the
last three digits in the docket number
filed to access the document.
Comments, protests, and interventions
may be filed electronically via the
internet in lieu of paper. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under the
‘‘e-Filing’’ link. The Commission
strongly encourages electronic filings.
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on January 31, 2007.
Magalie R. Salas,
Secretary.
[FR Doc. E7–1155 Filed 1–25–07; 8:45 am]
BILLING CODE 6717–01–P
Magalie R. Salas,
Secretary.
[FR Doc. E7–1241 Filed 1–25–07; 8:45 am]
BILLING CODE 6717–01–P
Federal Energy Regulatory
Commission
DEPARTMENT OF ENERGY
Combined Notice of Filings #1
Federal Energy Regulatory
Commission
January 17, 2007.
[Docket No. AC07–61–000]
Williston Basin Interstate Pipeline
Company; Notice of Filing
January 17, 2007.
Take notice that on December 20,
2006, Williston Basin Interstate Pipeline
Company tendered for filing a request to
establish a new depreciation rate for
Account 336, Purification Equipment.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. Anyone filing a motion
to intervene or protest must serve a copy
of that document on the Applicant and
all the parties in this proceeding
The Commission encourages
electronic submission of protests in lieu
of paper using the ‘‘eFiling’’ link at
https://www.ferc.gov. Persons unable to
file electronically should submit an
original and 14 copies of the protest to
the Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington, DC 20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
PO 00000
Frm 00050
Fmt 4703
DEPARTMENT OF ENERGY
Sfmt 4703
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER05–1420–001.
Applicants: Lehman Brothers
Commodity Services Inc.
Description: Lehman Brothers
Commodity Services Inc. submits a
Notice of Change in Status.
Filed Date: 01/16/2007.
Accession Number: 20070116–5163.
Comment Date: 5 p.m. Eastern Time
on Tuesday, February 06, 2007.
Docket Numbers: ER07–199–001.
Applicants: PJM Interconnection,
L.L.C.
Description: PJM Interconnection,
LLC submits a corrected version of the
Wholesale Market Participation
Agreement filed on 11/13/06.
Filed Date: 01/09/2007.
Accession Number: 20070116–0158.
Comment Date: 5 p.m. Eastern Time
on Tuesday, January 30, 2007.
Docket Numbers: ER07–426–000.
Applicants: Covanta Delaware Valley,
L.P.
Description: Covanta Delaware Valley,
LP submits First Revised Sheet 1 et al.
to FERC Electric Tariff, Original Volume
2, to be effective 1/13/07.
Filed Date: 01/12/2007.
Accession Number: 20070116–0064.
Comment Date: 5 p.m. Eastern Time
on Friday, February 02, 2007.
Docket Numbers: ER07–427–000.
Applicants: Green Mountain Power
Corporation.
Description: Green Mountain Power
Co submits a notice of cancellation of
Amended Transmission Contract with
the Village of Hardwick, VT etc.
Filed Date: 01/12/2007.
Accession Number: 20070116–0063.
E:\FR\FM\26JAN1.SGM
26JAN1
Agencies
[Federal Register Volume 72, Number 17 (Friday, January 26, 2007)]
[Notices]
[Page 3828]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-1241]
[[Page 3828]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket Nos. ER07-48-000 and ER07-48-001]
Verde Renewable Energy, Inc.; Notice of Issuance of Order
January 22, 2006.
Verde Renewable Energy, Inc. (Verde) filed an application for
market-based rate authority, with an accompanying rate tariff. The
proposed market-based rate tariff provides for the sale of energy and
capacity at market-based rates. Verde also requested waivers of various
Commission regulations. In particular, Verde requested that the
Commission grant blanket approval under 18 CFR part 34 of all future
issuances of securities and assumptions of liability by Verde.
On January 22, 2007, pursuant to delegated authority, the Director,
Division of Tariffs and Market Development--West, granted the requests
for blanket approval under Part 34. The Director's order also stated
that the Commission would publish a separate notice in the Federal
Register establishing a period of time for the filing of protests.
Accordingly, any person desiring to be heard or to protest the blanket
approvals of issuances of securities or assumptions of liability by
Verde should file a motion to intervene or protest with the Federal
Energy Regulatory Commission, 888 First Street, NE., Washington, DC
20426, in accordance with Rules 211 and 214 of the Commission's Rules
of Practice and Procedure. 18 CFR 385.211, 385.214 (2004).
Notice is hereby given that the deadline for filing motions to
intervene or protest is February 21, 2007.
Absent a request to be heard in opposition by the deadline above,
Verde is authorized to issue securities and assume obligations or
liabilities as a guarantor, indorser, surety, or otherwise in respect
of any security of another person; provided that such issuance or
assumption is for some lawful object within the corporate purposes of
Verde, compatible with the public interest, and is reasonably necessary
or appropriate for such purposes.
The Commission reserves the right to require a further showing that
neither public nor private interests will be adversely affected by
continued approvals of Verde's issuance of securities or assumptions of
liability.
Copies of the full text of the Director's Order are available from
the Commission's Public Reference Room, 888 First Street, NE.,
Washington, DC 20426. The Order may also be viewed on the Commission's
Web site at https://www.ferc.gov, using the eLibrary link. Enter the
docket number excluding the last three digits in the docket number
filed to access the document. Comments, protests, and interventions may
be filed electronically via the internet in lieu of paper. See 18 CFR
385.2001(a)(1)(iii) and the instructions on the Commission's Web site
under the ``e-Filing'' link. The Commission strongly encourages
electronic filings.
Magalie R. Salas,
Secretary.
[FR Doc. E7-1241 Filed 1-25-07; 8:45 am]
BILLING CODE 6717-01-P