Download as PDF 1716 Federal Register / Vol. 72, No. 9 / Tuesday, January 16, 2007 / Notices for filing a protest, the instant request shall be treated as an application for authorization pursuant to section 7 of the Natural Gas Act. Magalie R. Salas, Secretary. [FR Doc. E7–431 Filed 1–12–07; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. OR07–4–000] BP West Coast Products LLC, Chevron Products Company, and ExxonMobil Oil Corporation Complainants, v. SFPP, L.P., Kinder Morgan GP, Inc., and Kinder Morgan Inc., Respondent; Notice of Complaint sroberts on PROD1PC70 with NOTICES January 9, 2007. Take notice that on January 5, 2007, BP West Coast Products LLC (BPWCP) and ExxonMobil Oil Corporation (ExxonMobil) (together, Complainants) hereby submit both jointly and severally, a Fifth Original Complaint against SFPP, L.P. (SFPP), Kinder Morgan GP, Inc. (KMGP Inc) and Kinder Morgan Inc. (KIM) and First Amended Fourth Complaint, challenging the justness and reasonableness of rates on SFPP’s West Line, Sepulveda Line, North Line, Oregon Line and East Line, and (conditionally only), the Watson Vapor Recovery Facilities rate. Chevron Products Company joins in this complaint as a complainant, tendering its Fifth Original Complaint, supplementing all prior Chevron and Texaco Refining & Marketing Inc. complaints. On January 8, 2007, the Complainants and Chevron Products Company filed a revised Table of Contents and Table of Authorities with corrected page references, and a transmittal letter to the Secretary that was inadvertently omitted from the January 5, 2007 filing. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. The Respondent’s answer and all interventions, or protests must be filed on or before the comment date. The Respondent’s answer, motions to VerDate Aug<31>2005 15:23 Jan 12, 2007 Jkt 211001 intervene, and protests must be served on the Complainants. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5 p.m. Eastern Time on February 5, 2007. Magalie R. Salas, Secretary. [FR Doc. E7–448 Filed 1–12–07; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. EL07–30–000] Notice of Complaint; Newark Bay Cogeneration Partnership, L.P. Complainant v. PJM Interconnection, L.L.C., Public Service Electric and Gas Company, Respondent. January 9, 2007. Take notice that on January 8, 2007, Newark Bay Cogeneration Partnership, L.P. (Newark Bay) filed a formal complaint, pursuant to sections 205 and 306 of the Federal Power Act and Rule 206 of the Commission’s Rules of Practice and Procedure, against PJM Interconnection, L.L.C. (PJM) and Public Service Electric and Gas Company (PSE&G) relating to the outage of the 230KV transmission line connecting Newark Bay to PSE&G’s Essex Switching Station and alleging that PJM and PSE&G failed to comply with applicable tariff provisions in scheduling and conducting the outage. Newark Bay certifies that copies of the complaint were served simultaneously with its filing on the contacts for PJM and PSE&G as listed on the Commission’s list of Corporate Officials. PO 00000 Frm 00014 Fmt 4703 Sfmt 4703 Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. The Respondent’s answer and all interventions, or protests must be filed on or before the comment date. The Respondent’s answer, motions to intervene, and protests must be served on the Complainants. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5 p.m. Eastern Time on January 29, 2007. Magalie R. Salas, Secretary. [FR Doc. E7–447 Filed 1–12–07; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. EL07–28–000] Xcel Energy Services Inc., Complainant v. Southwest Power Pool, Inc., Respondent; Notice of Complaint January 9, 2007. Take notice that on January 4, 2007, pursuant to sections 206 and 306 of the Federal Power Act, 16 U.S.C. 824e and 825e and Rule 206 of the Rules and Practice and Procedure of the Federal Energy Regulatory Commission (Commission), 18 CFR 385.206, Xcel E:\FR\FM\16JAN1.SGM 16JAN1

Agencies

[Federal Register Volume 72, Number 9 (Tuesday, January 16, 2007)]
[Notices]
[Page 1716]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-447]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. EL07-30-000]


Notice of Complaint; Newark Bay Cogeneration Partnership, L.P. 
Complainant v. PJM Interconnection, L.L.C., Public Service Electric and 
Gas Company, Respondent.

January 9, 2007.
    Take notice that on January 8, 2007, Newark Bay Cogeneration 
Partnership, L.P. (Newark Bay) filed a formal complaint, pursuant to 
sections 205 and 306 of the Federal Power Act and Rule 206 of the 
Commission's Rules of Practice and Procedure, against PJM 
Interconnection, L.L.C. (PJM) and Public Service Electric and Gas 
Company (PSE&G) relating to the outage of the 230KV transmission line 
connecting Newark Bay to PSE&G's Essex Switching Station and alleging 
that PJM and PSE&G failed to comply with applicable tariff provisions 
in scheduling and conducting the outage.
    Newark Bay certifies that copies of the complaint were served 
simultaneously with its filing on the contacts for PJM and PSE&G as 
listed on the Commission's list of Corporate Officials.
    Any person desiring to intervene or to protest this filing must 
file in accordance with Rules 211 and 214 of the Commission's Rules of 
Practice and Procedure (18 CFR 385.211, 385.214). Protests will be 
considered by the Commission in determining the appropriate action to 
be taken, but will not serve to make protestants parties to the 
proceeding. Any person wishing to become a party must file a notice of 
intervention or motion to intervene, as appropriate. The Respondent's 
answer and all interventions, or protests must be filed on or before 
the comment date. The Respondent's answer, motions to intervene, and 
protests must be served on the Complainants.
    The Commission encourages electronic submission of protests and 
interventions in lieu of paper using the ``eFiling'' link at https://
www.ferc.gov. Persons unable to file electronically should submit an 
original and 14 copies of the protest or intervention to the Federal 
Energy Regulatory Commission, 888 First Street, NE., Washington, DC 
20426.
    This filing is accessible on-line at https://www.ferc.gov, using the 
``eLibrary'' link and is available for review in the Commission's 
Public Reference Room in Washington, DC. There is an ``eSubscription'' 
link on the Web site that enables subscribers to receive e-mail 
notification when a document is added to a subscribed docket(s). For 
assistance with any FERC Online service, please e-mail 
FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll free). For 
TTY, call (202) 502-8659.
    Comment Date: 5 p.m. Eastern Time on January 29, 2007.

Magalie R. Salas,
Secretary.
 [FR Doc. E7-447 Filed 1-12-07; 8:45 am]
BILLING CODE 6717-01-P