Jordan Cove Energy Project, L.P.; Pacific Connector Gas Pipeline, L.P.; Notice of Informational Meetings for the Proposed Jordan Cove LNG and Pacific Connector Gas Pipeline Projects, 1719 [E7-437]
Download as PDF
Federal Register / Vol. 72, No. 9 / Tuesday, January 16, 2007 / Notices
sroberts on PROD1PC70 with NOTICES
Authorization Under Section 204(A) to
Issue Short Term Debt and Request for
Shortened Notice Period and Expedited
Action.
Filed Date: 01/08/2007.
Accession Number: 20070108–5036.
Comment Date: 5 p.m. Eastern Time
on Monday, January 22, 2007.
Any person desiring to intervene or to
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s Rules of
Practice and Procedure (18 CFR 385.211
and 385.214) on or before 5 p.m. Eastern
time on the specified comment date. It
is not necessary to separately intervene
again in a subdocket related to a
compliance filing if you have previously
intervened in the same docket. Protests
will be considered by the Commission
in determining the appropriate action to
be taken, but will not serve to make
protestants parties to the proceeding.
Anyone filing a motion to intervene or
protest must serve a copy of that
document on the Applicant. In reference
to filings initiating a new proceeding,
interventions or protests submitted on
or before the comment deadline need
not be served on persons other than the
Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 14 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First St. NE., Washington, DC
20426.
The filings in the above proceedings
are accessible in the Commission’s
eLibrary system by clicking on the
appropriate link in the above list. They
are also available for review in the
Commission’s Public Reference Room in
Washington, DC. There is an
eSubscription link on the Web site that
enables subscribers to receive e-mail
notification when a document is added
to a subscribed dockets(s). For
assistance with any FERC Online
service, please e-mail
FERCOnlineSupport@ferc.gov. or call
VerDate Aug<31>2005
15:23 Jan 12, 2007
Jkt 211001
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Magalie R. Salas,
Secretary.
[FR Doc. E7–450 Filed 1–12–07; 8:45 am]
BILLING CODE 6717–01–P
1719
along with other related information. For
additional information, please contact the
Commission’s Office of External Affairs at
(202) 502–8004.
Magalie R. Salas,
Secretary.
[FR Doc. E7–437 Filed 1–12–07; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Federal Energy Regulatory
[Docket No. PF06–25–000; Docket No.
PF06–26–000]
[Docket No. CP07–10–000]
Jordan Cove Energy Project, L.P.;
Pacific Connector Gas Pipeline, L.P.;
Notice of Informational Meetings for
the Proposed Jordan Cove LNG and
Pacific Connector Gas Pipeline
Projects
Dominion Transmission, Inc.; Notice of
Intent To Prepare an Environmental
Assessment for the Proposed TL–263
Expansion Project and Request for
Comments on Environmental Issues
January 8, 2007.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) is preparing an
environmental assessment (EA) that will
describe the impacts of constructing and
operating the proposed natural gas
pipeline TL–263 Expansion Project
(Project) sponsored by Dominion
Transmission Inc. (DTI).1
The proposed Project would include
the construction, replacement,
installation, modification and operation
of natural gas pipeline facilities in
Boone and Wyoming Counties, West
Virginia to increase the capacity,
improve the efficiency and maintain the
integrity of DTI’s existing natural gas
delivery system. Specifically, DTI is
seeking authority to undertake the
following activities:
• Construct approximately 6.43 miles
of 12-inch-diameter natural gas pipeline
and associated facilities (TL–570);
• Replace six 12-inch-diameter
pipeline sections along the existing TL–
263 natural gas pipeline (a total of
approximately 601 feet of pipeline);
• Install overpressure protection; and
• Modify the existing Loup Creek
Compressor Station.
A map indicating the general
locations of the proposed Project
facilities is provided in Appendix 1.2
Construction of the new 12-inchdiameter natural gas pipeline which
would be known as TL–570 would be
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) is issuing this notice to
announce the time, dates, and locations
of a series of public informational
meetings to discuss the environmental
review process for the liquefied natural
gas (LNG) import terminal proposed by
Jordan Cove Energy Project, L.P. in Coos
County, Oregon, and the associated 223mile-long 36-inch-diameter sendout
pipeline proposed by Pacific Connector
Gas Pipeline, L.P. extending from the
LNG terminal, across Coos, Douglas,
Jackson, and Klamath Counties, to an
interconnection with Pacific Gas and
Electric Company facilities near Malin,
Oregon. Also participating in the
meetings will be staff from agencies that
are cooperating with the FERC in the
production of an environmental impact
statement for the projects, including the
U.S. Department of Agriculture Forest
Service and the U.S. Department of the
Interior Bureau of Land Management.
The meetings will all begin promptly at
6:30 p.m., (PST) (doors will open at about 6
p.m. for sign-in), on the dates below at the
following locations:
Tuesday, January 23, 2007
Umpqua Community College, Campus
Center Dining Room/Timber Room, 1140
Umpqua College Rd., Roseburg, OR 97470.
541–440–4600.
Wednesday, January 24, 2007
North Bend Community Center, 2222
Broadway St., North Bend, OR 97459. 541–
756–8500.
Thursday, January 25, 2007
Red Lion Inn, 200 N. Riverside Ave.,
Medford, OR 97501. 541–779–5811.
These events are posted on the
Commission’s calendar located at https://
www.ferc.gov/EventCalendar/EventsList.aspx
PO 00000
Frm 00017
Fmt 4703
Sfmt 4703
January 9, 2007.
1 DTI’s application was filed with the
Commission under section 7 of the Natural Gas Act
and Part 157 of the Commission’s regulations.
2 The appendices referenced in this notice are not
being printed in the Federal Register. Copies of all
appendices, other than Appendix 1 (maps), are
available on the Commission’s website at the
‘‘eLibrary’’ link or from the Commission’s Public
Reference Room, 888 First Street, NE., Washington,
DC 20426, or call (202) 502–8371. For instructions
on connecting to eLibrary refer to the last page of
this notice.
E:\FR\FM\16JAN1.SGM
16JAN1
Agencies
[Federal Register Volume 72, Number 9 (Tuesday, January 16, 2007)]
[Notices]
[Page 1719]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E7-437]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. PF06-25-000; Docket No. PF06-26-000]
Jordan Cove Energy Project, L.P.; Pacific Connector Gas Pipeline,
L.P.; Notice of Informational Meetings for the Proposed Jordan Cove LNG
and Pacific Connector Gas Pipeline Projects
January 8, 2007.
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) is issuing this notice to announce the time, dates, and
locations of a series of public informational meetings to discuss the
environmental review process for the liquefied natural gas (LNG) import
terminal proposed by Jordan Cove Energy Project, L.P. in Coos County,
Oregon, and the associated 223-mile-long 36-inch-diameter sendout
pipeline proposed by Pacific Connector Gas Pipeline, L.P. extending
from the LNG terminal, across Coos, Douglas, Jackson, and Klamath
Counties, to an interconnection with Pacific Gas and Electric Company
facilities near Malin, Oregon. Also participating in the meetings will
be staff from agencies that are cooperating with the FERC in the
production of an environmental impact statement for the projects,
including the U.S. Department of Agriculture Forest Service and the
U.S. Department of the Interior Bureau of Land Management.
The meetings will all begin promptly at 6:30 p.m., (PST) (doors
will open at about 6 p.m. for sign-in), on the dates below at the
following locations:
Tuesday, January 23, 2007
Umpqua Community College, Campus Center Dining Room/Timber Room,
1140 Umpqua College Rd., Roseburg, OR 97470. 541-440-4600.
Wednesday, January 24, 2007
North Bend Community Center, 2222 Broadway St., North Bend, OR
97459. 541-756-8500.
Thursday, January 25, 2007
Red Lion Inn, 200 N. Riverside Ave., Medford, OR 97501. 541-779-
5811.
These events are posted on the Commission's calendar located at
https://www.ferc.gov/EventCalendar/EventsList.aspx along with other
related information. For additional information, please contact the
Commission's Office of External Affairs at (202) 502-8004.
Magalie R. Salas,
Secretary.
[FR Doc. E7-437 Filed 1-12-07; 8:45 am]