PPL Montana; Notice of Application Tendered for Filing with the Commission and Establishing Procedural Schedule for Licensing and Deadline for Submission of Final Amendments, 78184-78185 [E6-22212]
Download as PDF
78184
Federal Register / Vol. 71, No. 249 / Thursday, December 28, 2006 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No.: P–2301–022]
PPL Montana; Notice of Application
Tendered for Filing with the
Commission and Establishing
Procedural Schedule for Licensing and
Deadline for Submission of Final
Amendments
December 19, 2006.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: P–2301–022.
c. Date Filed: December 15, 2006.
d. Applicant: PPL Montana.
e. Name of Project: Mystic Lake
Hydroelectric Project.
f. Location: The existing project is
located on West Rosebud Creek in
Stillwater and Carbon Counties,
Montana. The project occupies about
674 acres of federal lands in the Custard
National Forest managed by the U.S.
Forest Service.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: Jon
Jourdonnais, PPL Montana, 45 Basin
Creek Road, Butte, MT 59701;
Telephone (406) 533–3443; email
jhjourdonnais@pplweb.com. Additional
information on this project is available
on the applicant’s web site: https://
www.mysticlakeproject.com.
i. FERC Contact: Steve Hocking,
Telephone (202) 502–8753; email
steve.hocking@ferc.gov Additional
information on Federal Energy
Regulatory Commission (FERC)
hydroelectric projects is available on
FERC’s web site: https://www.ferc.gov/
industries/hydropower.asp.
j. This application is not ready for
environmental analysis at this time.
k. Project Description: The existing
project consists of the following: (1) a
368-foot-long, 45-foot-high, concrete
arch dam/spillway; (2) 42-inch high
timber flashboards on top of the arch
spillway; (3) a 145-foot-long, 15-foothigh concrete core and earthfill dike
with 1-foot-high flashboards; (4) Mystic
Lake with a storage capacity of 47,000
acre-feet and a surface area of 446.7
acres at its normal maximum surface
elevation of 7,673.5 feet above msl; (5)
a 33-foot-long, 7-foot-high, by 9-footwide concrete intake structure at the left
abutment of the dike; (6) a conduit from
the intake structure to the powerhouse
consisting of a 1,005-foot-long rock
tunnel, a 9,012-foot-long, 57-inch steel
pipeline with an inverted siphon near
the mid-point of the pipeline, a surge
tank, and a 2,566-foot-long by 42 to 48inch diameter steel penstock; (7) a 60foot-wide by 85-foot-long concrete
powerhouse with two turbine-generator
units with a total installed capacity of
11.25 megawatts; (8) two concrete
tunnels that extend from the
powerhouse into West Rosebud Creek;
(9) a re-regulation dam about 1.5 miles
downstream from the Mystic Lake
powerhouse consisting of a 19-foot-high,
420-foot-long earthfill dike with a
concrete spillway with flashboards; (10)
West Rosebud Lake with a storage
capacity of 470 acre-feet and a surface
area of 49 acres at its normal maximum
surface elevation of 6,397.4 feet above
msl; (11) two 5.3-mile-long, 50-kilovolt
transmission lines; (12) a 9,363-footlong distribution line from the
powerhouse to the arch dam and a
2,068-foot-long distribution line from
the powerhouse to the surge tank; (13)
an operator village adjacent to the
powerhouse with four homes and three
maintenance buildings; and (14)
appurtenant facilities.
PPL Montana currently operates the
project in both base load and peaking
modes depending on water availability,
electric demands, and existing license
constraints. Typically, from mid-May to
mid-August, inflows exceed the
project’s hydraulic capacity and the
project is operated as a base load plant,
continuously generating at maximum
capacity. During this time, flows above
the project’s hydraulic capacity are
captured in Mystic Lake which is
gradually raised about 15 to 20 feet per
month until it exceeds the project’s
current minimum recreation elevation
of 7,663.5 feet msl. In most years,
Mystic Lake is maintained about ten feet
higher than the minimum recreation
elevation during July and August.
After Labor Day, PPL Montana begins
to slowly draft Mystic Lake, reducing its
elevation by an average of 8 to 9 feet per
month, until the lake is at or near its
lowest elevation of 6,512.0 feet msl by
the end of March. Drafting the lake
permits PPL Montana to release more
water into West Rosebud Creek than
otherwise would be available from
inflows from August through March.
During the fall and early winter, PPL
Montana employs limited peaking to
maximize generation during high use
periods, generally from 8 a.m. to 4 p.m.
daily. In general, flow changes caused
by peaking do not extend further than
the project’s re-regulation dam which
creates West Rosebud Lake located
about one mile downstream of the
powerhouse.
l. Locations of the Application: A
copy of the application is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s web site at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or tollfree at (866) 208–3676, or for TTY, (202)
502–8659. A copy is also available for
inspection and reproduction at the
address in item (h) above.
m. You may also register online at
https://www.ferc.gov/esubscribenow.htm
to be notified via email of new filings
and issuances related to this or other
pending projects. For assistance, contact
FERC Online Support.
n. Procedural Schedule: The
application will be processed according
to the following Hydro Licensing
Schedule. Revisions to the schedule
may be made as appropriate.
sroberts on PROD1PC70 with NOTICES
Milestone
Target date
Notice of Acceptance/ Notice of Ready for Environmental Analysis .......................................................................................
Filing of interventions, recommendations, preliminary terms and conditions, and fishway prescriptions ...............................
Reply comments due ................................................................................................................................................................
FERC issues single EA (without a draft) .................................................................................................................................
Comments on EA due ..............................................................................................................................................................
Filing of modified terms and conditions ...................................................................................................................................
Ready for Commission decision ...............................................................................................................................................
VerDate Aug<31>2005
20:03 Dec 27, 2006
Jkt 211001
PO 00000
Frm 00057
Fmt 4703
Sfmt 4703
E:\FR\FM\28DEN1.SGM
28DEN1
January 12, 20071
March 13, 2007
April 27, 2007
July 11, 2007
August 10, 2007
October 9, 2007
November 15, 2007
Federal Register / Vol. 71, No. 249 / Thursday, December 28, 2006 / Notices
o. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
Magalie R. Salas,
Secretary.
[FR Doc. E6–22212 Filed 12–27–06; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Application Accepted for
Filing and Soliciting Motions To
Intervene, Protests, and Comments
sroberts on PROD1PC70 with NOTICES
December 20, 2006.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Preliminary
Permit.
b. Project No.: 12749–000.
c. Date Filed: November 2, 2006.
d. Applicant: Oregon Wave Energy
Partners, LLC. P≤e. Name of Project:
Coos Bay OPT Wave Park Project.
f. Location: The project would be
located in the Pacific Ocean about 2.5
miles off shore in Coos County, Oregon.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)—825(r).
h. Applicant Contacts: Charles F.
Dunleavy, Oregon Wave Energy
Partners, LLC, 1590 Reed Road,
Pennington, NJ 08534, phone: (609)730–0400.
i. FERC Contact: Robert Bell, (202)
502–6062.
j. Deadline for filing comments,
protests, and motions to intervene: 60
days from the issuance date of this
notice.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person in the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
k. Description of Project: The
proposed project would consist of: (1)
200 to 400 Power Buoys having a total
installed capacity of 100 megawatts, (2)
a proposed 13.8 kilovolt transmission
line; and (3) appurtenant facilities. The
project is estimated to have an annual
generation of 306.6 gigawatt-hours per-
VerDate Aug<31>2005
20:03 Dec 27, 2006
Jkt 211001
unit per-year, which would be sold to a
local utility.
l. Locations of Applications: A copy of
the application is available for
inspection and reproduction at the
Commission in the Public Reference
Room, located at 888 First Street NE.,
Room 2A, Washington DC 20426, or by
calling (202) 502–8371. This filing may
also be viewed on the Commission’s
Web site at https://www.ferc.gov using
the ‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, call toll-free
1–866–208–3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY,
call (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item h
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Competing Preliminary Permit:
Anyone desiring to file a competing
application for preliminary permit for a
proposed project must submit the
competing application itself, or a notice
of intent to file such an application, to
the Commission on or before the
specified comment date for the
particular application (see 18 CFR 4.36).
Submission of a timely notice of intent
allows an interested person to file the
competing preliminary permit
application no later than 30 days after
the specified comment date for the
particular application. A competing
preliminary permit application must
conform with 18 CFR 4.30(b) and 4.36.
o. Competing Development
Application: Any qualified development
applicant desiring to file a competing
development application must submit to
the Commission, on or before a
specified comment date for the
particular application, either a
competing development application or a
notice of intent to file such an
application. Submission of a timely
notice of intent to file a development
application allows an interested person
to file the competing application no
later than 120 days after the specified
comment date for the particular
application. A competing license
application must conform with 18 CFR
4.30(b) and 4.36.
p. Notice of Intent: A notice of intent
must specify the exact name, business
address, and telephone number of the
prospective applicant, and must include
an unequivocal statement of intent to
submit, if such an application may be
filed, either a preliminary permit
application or a development
application (specify which type of
PO 00000
Frm 00058
Fmt 4703
Sfmt 4703
78185
application). A notice of intent must be
served on the applicant(s) named in this
public notice.
q. Proposed Scope of Studies under
Permit: A preliminary permit, if issued,
does not authorize construction. The
term of the proposed preliminary permit
would be 36 months. The work
proposed under the preliminary permit
would include economic analysis,
preparation of preliminary engineering
plans, and a study of environmental
impacts. Based on the results of these
studies, the Applicant would decide
whether to proceed with the preparation
of a development application to
construct and operate the project.
r. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, 385.211,
385.214. In determining the appropriate
action to take, the Commission will
consider all protests or other comments
filed, but only those who file a motion
to intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
Comments, protests and interventions
may be filed electronically via the
Internet in lieu of paper; See 18 CFR
385.2001 (a)(1)(iii) and the instructions
on the Commission’s Web site under ‘‘efiling’’ link. The Commission strongly
encourages electronic filing.
s. Filing and Service of Responsive
Documents: Any filings must bear in all
capital letters the title ‘‘COMMENTS’’,
‘‘RECOMMENDATIONS FOR TERMS
AND CONDITIONS’’,
‘‘PROTEST’’,’’COMPETING
APPLICATION’’ OR ‘‘MOTION TO
INTERVENE’’, as applicable, and the
Project Number of the particular
application to which the filing refers.
Any of the above-named documents
must be filed by providing the original
and the number of copies provided by
the Commission’s regulations to: The
Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington, DC 20426. A copy of any
motion to intervene must also be served
upon each representative of the
Applicant specified in the particular
application.
t. Agency Comments: Federal, State,
and local agencies are invited to file
comments on the described application.
A copy of the application may be
obtained by agencies directly from the
Applicant. If an agency does not file
comments within the time specified for
E:\FR\FM\28DEN1.SGM
28DEN1
Agencies
[Federal Register Volume 71, Number 249 (Thursday, December 28, 2006)]
[Notices]
[Pages 78184-78185]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E6-22212]
[[Page 78184]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No.: P-2301-022]
PPL Montana; Notice of Application Tendered for Filing with the
Commission and Establishing Procedural Schedule for Licensing and
Deadline for Submission of Final Amendments
December 19, 2006.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
b. Project No.: P-2301-022.
c. Date Filed: December 15, 2006.
d. Applicant: PPL Montana.
e. Name of Project: Mystic Lake Hydroelectric Project.
f. Location: The existing project is located on West Rosebud Creek
in Stillwater and Carbon Counties, Montana. The project occupies about
674 acres of federal lands in the Custard National Forest managed by
the U.S. Forest Service.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
h. Applicant Contact: Jon Jourdonnais, PPL Montana, 45 Basin Creek
Road, Butte, MT 59701; Telephone (406) 533-3443; email
jhjourdonnais@pplweb.com. Additional information on this project is
available on the applicant's web site: https://
www.mysticlakeproject.com.
i. FERC Contact: Steve Hocking, Telephone (202) 502-8753; email
steve.hocking@ferc.gov Additional information on Federal Energy
Regulatory Commission (FERC) hydroelectric projects is available on
FERC's web site: https://www.ferc.gov/industries/hydropower.asp.
j. This application is not ready for environmental analysis at this
time.
k. Project Description: The existing project consists of the
following: (1) a 368-foot-long, 45-foot-high, concrete arch dam/
spillway; (2) 42-inch high timber flashboards on top of the arch
spillway; (3) a 145-foot-long, 15-foot-high concrete core and earthfill
dike with 1-foot-high flashboards; (4) Mystic Lake with a storage
capacity of 47,000 acre-feet and a surface area of 446.7 acres at its
normal maximum surface elevation of 7,673.5 feet above msl; (5) a 33-
foot-long, 7-foot-high, by 9-foot-wide concrete intake structure at the
left abutment of the dike; (6) a conduit from the intake structure to
the powerhouse consisting of a 1,005-foot-long rock tunnel, a 9,012-
foot-long, 57-inch steel pipeline with an inverted siphon near the mid-
point of the pipeline, a surge tank, and a 2,566-foot-long by 42 to 48-
inch diameter steel penstock; (7) a 60-foot-wide by 85-foot-long
concrete powerhouse with two turbine-generator units with a total
installed capacity of 11.25 megawatts; (8) two concrete tunnels that
extend from the powerhouse into West Rosebud Creek; (9) a re-regulation
dam about 1.5 miles downstream from the Mystic Lake powerhouse
consisting of a 19-foot-high, 420-foot-long earthfill dike with a
concrete spillway with flashboards; (10) West Rosebud Lake with a
storage capacity of 470 acre-feet and a surface area of 49 acres at its
normal maximum surface elevation of 6,397.4 feet above msl; (11) two
5.3-mile-long, 50-kilovolt transmission lines; (12) a 9,363-foot-long
distribution line from the powerhouse to the arch dam and a 2,068-foot-
long distribution line from the powerhouse to the surge tank; (13) an
operator village adjacent to the powerhouse with four homes and three
maintenance buildings; and (14) appurtenant facilities.
PPL Montana currently operates the project in both base load and
peaking modes depending on water availability, electric demands, and
existing license constraints. Typically, from mid-May to mid-August,
inflows exceed the project's hydraulic capacity and the project is
operated as a base load plant, continuously generating at maximum
capacity. During this time, flows above the project's hydraulic
capacity are captured in Mystic Lake which is gradually raised about 15
to 20 feet per month until it exceeds the project's current minimum
recreation elevation of 7,663.5 feet msl. In most years, Mystic Lake is
maintained about ten feet higher than the minimum recreation elevation
during July and August.
After Labor Day, PPL Montana begins to slowly draft Mystic Lake,
reducing its elevation by an average of 8 to 9 feet per month, until
the lake is at or near its lowest elevation of 6,512.0 feet msl by the
end of March. Drafting the lake permits PPL Montana to release more
water into West Rosebud Creek than otherwise would be available from
inflows from August through March. During the fall and early winter,
PPL Montana employs limited peaking to maximize generation during high
use periods, generally from 8 a.m. to 4 p.m. daily. In general, flow
changes caused by peaking do not extend further than the project's re-
regulation dam which creates West Rosebud Lake located about one mile
downstream of the powerhouse.
l. Locations of the Application: A copy of the application is
available for review at the Commission in the Public Reference Room or
may be viewed on the Commission's web site at https://www.ferc.gov using
the ``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. For
assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov
or toll-free at (866) 208-3676, or for TTY, (202) 502-8659. A copy is
also available for inspection and reproduction at the address in item
(h) above.
m. You may also register online at https://www.ferc.gov/
esubscribenow.htm to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
n. Procedural Schedule: The application will be processed according
to the following Hydro Licensing Schedule. Revisions to the schedule
may be made as appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Notice of Acceptance/ Notice of Ready for January 12, 2007\1\
Environmental Analysis.
Filing of interventions, recommendations, March 13, 2007
preliminary terms and conditions, and
fishway prescriptions.
Reply comments due........................ April 27, 2007
FERC issues single EA (without a draft)... July 11, 2007
Comments on EA due........................ August 10, 2007
Filing of modified terms and conditions... October 9, 2007
Ready for Commission decision............. November 15, 2007
------------------------------------------------------------------------
[[Page 78185]]
o. Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Magalie R. Salas,
Secretary.
[FR Doc. E6-22212 Filed 12-27-06; 8:45 am]
BILLING CODE 6717-01-P